Legacy Evaluation Form.xlsx

XLSX spreadsheet 25 KB Posted

Attached to
RFQ-484-122126 Intermodal Transit on Call Contract
Solicitation number
PE-48401-RFQ-2027-000000640
Issued by
Georgia

About this file

This is a Local Project Evaluation Form used by the Georgia Department of Transportation (GDOT) to assess consultant performance on completed projects. The form is designed to evaluate consultant services across multiple rating factors and project phases, with evaluations conducted by agency project managers or subject matter experts. The form does not specify particular products, services, quantities, response dates, due dates, site visits, bidder meetings, award dates, or contract terms.

The evaluation form uses a three-tiered scoring system where 5 indicates exceeds requirements, 3 indicates meets requirements, and 1 indicates does not meet requirements, with an N/A option available. Rating factors are organized into two sections: Management (including resource management, independent work, scope adherence, and communication) and Prosecution and Progress (including timeliness of deliverables, quality and completeness of documentation, and budget compliance). Each factor is assigned a weighted value, with management factors weighted at 20, 15, 10, and 8 points respectively, and prosecution factors weighted at 15 and 15 points, for a maximum total score of 50 points. The form requires signatures and acknowledgment from the Agency Owner Project Manager, Consultant Project Manager, and the Agency Evaluator's Supervisor, with space for justifications of scores and consultant responses.

View the file

Other files

File Type Posted
LAP Evaluation Form.xlsx XLSX spreadsheet
RFQ 484_122126.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Local Project Evaluation Form

Local Project Evaluation Form

Evaluation Date:

Consultant:

GDOT PI No.(if applicable):

GDOT PM (if applicable):

Agency/Owner:

Agency/Owner PM:

Phone:

Email:

Project Description & Scope:

Project Phase:

Service Dates:

Ratings: 5 = Exceeds Requirement and Expectation; 3 = Meets Requirement and Expectation; 1 = Does not Meet Requirement and Expectation; or N/A Requirement and Expectation

AManagementRatingFactor
1Consultant appropriately managed resources (manpower, equipment, subconsultants, etc.)N/A- - -1
2Consultant worked independently and without significant help from Agency's staff on routine tasks.100
3Consultant remained within the scope of work as contracted.5200
4Consultant communicated well and worked cooperatively with agency staff, and Consultant promptly responded to calls, emails, correspondences, and direction given by agency staff.100
3Ratings
Sub Total:20
Agency/Owner PM/SME Justification for Scores (required):

Consultant Response to Evaluation (if applicable):

BProsecution and ProgressRatingFactor
5Consultant completed the deliverable(s) by the latest agreed upon date or within the duration contracted, as applicable.3150
6All invoices, studies, reports, design requirements, and details are complete, accurate, clear, and concise. Revisions are minimal.N/A- - -1
7Consultant completed the deliverable(s) within the assigned budget.3150
2Ratings
Sub Total:30
Agency/Owner PM/SME Justification for Scores (required):

Consultant Response to Evaluation (if applicable):

Total Score: 50

Agency/Owner PM:
Signature:Date:
Supervisor's Acknowledgement:
Consultant PM:
Signature:Date:
Agency Evaluator's
Supervisor (if applicable):
Signature:Date:

&12&A Page &P of &N

Scoring

1
3
5
N/A
Factor Table
Section Value:60531
0Ratings000
1Ratings60300
2Ratings30150
3Ratings20100
4Ratings1580

File details come from the government source that posted it. Updated .