This is a Local Administered Project (LAP) Evaluation Form used by the Georgia Department of Transportation (GDOT) to assess consultant performance on contracted projects. The form serves as a standardized evaluation instrument for GDOT Project Managers and agency staff to rate consultant performance across defined criteria and project deliverables. The evaluation captures project-specific information including the consultant name, GDOT Project Identification number, GDOT Project Manager, local agency details, project description, project phase, and service dates. The form does not establish specific response dates, due dates, site visits, bidder meetings, award dates, or contract renewal options, as it functions as a post-project performance assessment tool rather than a solicitation document.
The LAP Evaluation Form employs a standardized five-point rating scale assessing two primary categories: Management and Prosecution and Progress. The Management section evaluates resource management, consultant independence, scope adherence, and communication quality with GDOT staff. The Prosecution and Progress section rates timely deliverable completion, quality and completeness of invoices and reports, and budget compliance. Ratings are scaled as follows: 5 (Exceeds Requirement and Expectation), 3 (Meets Requirement and Expectation), 1 (Does not Meet Requirement and Expectation), or N/A. A scoring table converts individual ratings into point values based on the number of factors rated, with maximum scores of 50, 30, 15, 10, or 7.5 points depending on the quantity of rated factors. The form requires documented justifications from the GDOT Project Manager and may include consultant responses. Supervisory acknowledgements and signatures from GDOT management are mandated when any factor receives a rating of 1, ensuring quality control and documentation of substandard performance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Legacy Evaluation Form.xlsx | XLSX spreadsheet | |
| RFQ 484_122126.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LAP Evaluation Form
Local Administered Project (LAP) Evaluation Form
Evaluation Date:
Consultant:
GDOT PI No:
GDOT PM:
Agency:
Agency PM:
Phone:
Email:
Project Description & Scope:
Project Phase:
Service Dates:
Ratings: 5 = Exceeds Requirement and Expectation; 3 = Meets Requirement and Expectation; 1 = Does not Meet Requirement and Expectation; or N/A Requirement and Expectation
| A | Management | Rating | Factor | ||
| 1 | Consultant appropriately managed resources (manpower, equipment, subconsultants, etc.) | N/A | - - - | 1 | |
| 2 | Consultant worked independently and without significant help from Agency's staff on routine tasks. | N/A | - - - | 1 | |
| 3 | Consultant remained within the scope of work as contracted. | N/A | - - - | 1 | |
| 4 | Consultant communicated well and worked cooperatively with GDOT staff, and Consultant promptly responded to calls, emails, correspondences, and direction given by GDOT staff. | N/A | - - - | 1 | |
| 0 | Ratings | ||||
| Sub Total: | 0.00 | ||||
| GDOT PM/SME Justification for Scores (required): |
Consultant Response to Evaluation (if applicable):
| B | Prosecution and Progress | Rating | Factor | ||
| 5 | Consultant completed the deliverable(s) by the latest agreed upon date or within the duration contracted, as applicable. | N/A | - - - | 1 | |
| 6 | All invoices, studies, reports, design requirements, and details are complete, accurate, clear, and concise. Revisions are minimal. | N/A | - - - | 1 | |
| 7 | Consultant completed the deliverable(s) within the assigned budget. | N/A | - - - | 1 | |
| 0 | Ratings | ||||
| Sub Total: | 0.00 | ||||
| GDOT PM/SME Justification for Scores (required): |
Consultant Response to Evaluation (if applicable):
Total Score: 0
| GDOT PM: | ||
| Signature: | Date: | |
| Supervisor's Acknowledgement: |
Local's Comments:
Local's Acknowledgement:
| The GDOT Assistant Office Head (AOH) and Office Head (OH) Acknowledgements are required if a Rating of 1 is recorded for any item above. |
| AOH Acknowledgement: OH Acknowledgement: |
| Consultant PM: | ||
| Signature: | Date: |
| Agency Evaluator's | ||
| Supervisor (if applicable): | ||
| Signature: | Date: |
&12&A Page &P of &N
Scoring
| 1 | |||||
| 3 | |||||
| 5 | |||||
| N/A | |||||
| Factor Table | |||||
| Section Value: | 50 | 5 | 3 | 1 | |
| 0 | Ratings | 0.00 | 0.00 | 0.00 | |
| 1 | Ratings | 50.00 | 30.00 | 10.00 | |
| 2 | Ratings | 25.00 | 15.00 | 5.00 | |
| 3 | Ratings | 16.67 | 10.00 | 3.33 | |
| 4 | Ratings | 12.50 | 7.50 | 2.50 |