Lead Survey_Bldg-54_20120124.pdf
PDF 487 KB Posted
- Attached to
- Replace roof of Building 54, Fort Bliss, TX
- Solicitation number
- W911SG25BA033
About this file
This is a Lead-Based Paint Survey Report for Building 54 at Fort Bliss, Texas, conducted by ENCON International, Inc. on January 24, 2012. The survey was performed to identify lead-based paint (LBP) in areas scheduled for renovation or demolition, in compliance with OSHA lead regulations. Of the 108 X-ray fluorescence (XRF) readings taken, 57 tested positive for lead at or above the 0.3 mg/cm2 action level.
The survey covered both the first and second floors of the 10,250 square foot two-story fire station, which was constructed with brick and stucco walls on a concrete foundation. Positive lead readings were found on various components including casings, windows, doors, columns, walls, and sills, with lead concentrations ranging from 1.5 to 26.9 mg/cm2. The report emphasizes the need for careful handling of painted surfaces during any renovation or demolition to prevent lead dust or soil contamination, and recommends consulting the lead risk assessors for any clarifications.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
El Paso Office: 7307 Remcon Circle, Suite 103 El Paso, Texas 79912 Fax 915-581-2049 Phone 915-833-3740
Engineering, Environmental & Technical Services
LEAD PAINT SURVEY REPORT
BUILDING 54
FORT BLISS, TEXAS 79916
Prepared for:
Mr. Eddie Gardea
TEPA EC, LLC
6501 Boeing Drive Suite D-4
Fort Bliss, TX 79925
Prepared by:
ENCON International, Inc.
7307 Remcon Circle, Suite 103
El Paso, Texas 79912
Date of Inspection:
January 24, 2012
ENCON Project No. 1044-11
E
N C O N INTERNATIONAL, INC.
Engineering, Environmental & Technical Services
February 6, 2012
Mr. Eddie Gardea Phone: (915) 773-8400
Tepa EC, LLC Via email: eddie.gardea@mailhosts.com
6501 Boeing Drive Suite D-4
El Paso, TX 79925
RE: LEAD-BASED PAINT SURVEY REPORT
Building 54
Fort Bliss, TX 79916
Dear Mr. Gardea, ENCON International, Inc., (ENCON) has submitted for your review the attached Lead-
Based Paint (LBP) Survey Report. This survey was conducted at Building 54 at Fort
Bliss, Texas. This survey was performed of the entire building to address the
Occupational Safety and Health Administration (OSHA) lead regulations (29 CFR
1926.62).
This LBP Survey was performed on January 24, 2012 by Mr. Tim Jones, certified Texas
Department of State Health Services (DSHS) Lead Risk Assessor utilizing a NITON XLP
303 AW X-Ray Fluorescence analyzer (XRF) with serial No. 18451.
We appreciate the opportunity to be of service to you. Please call if you have any questions or if we may be of further assistance.
Sincerely, Alex Woelper, P.E.
Program Manager
Attachments:
Lead Survey Report
Sample Location Drawing
Technical Documentation
E
N C O N INTERNATIONAL, INC.
Lead Survey Report ENCON International. Inc.
Fort Bliss, Building 54 File Number 1044-12
El Paso Office: 7307 Remcon Circle, Suite 103 El Paso, Texas 79912 Fax 915-581-2049 Phone 915-833-3740
LEAD SURVEY REPORT
Fort Bliss, Texas Bldg. 54
SUMMARY
ENCON International, Inc, (ENCON) presents the findings of the Lead-Based Paint
(LBP) Survey performed at Building 54 at Fort Bliss, Texas. The purpose of this LBP survey was to determine if LBP was present in the areas scheduled for renovation or demolition, and if present, which building components contain LBP. This was determined by performing a surface-by-surface investigation representative of all painted components. This information is necessary in order for contractors to comply with OSHA regulation 29 CFR 1926.62 Safety and Health Regulations for Construction- Lead.
Lead-based Paint means paint or other surface coatings that contain lead equal to or in excess of 1.0 milligrams per square centimeter (mg/cm ) or more than 0.5%, or 5000 parts per million by weight as established by EPA and HUD regulations. However, for the purposes of this study, ENCON will utilize the lowest “Action Level” setting of the
NITON XRF of 0.3 milligrams per square centimeter (mg/cm ) as the detection limit for lead. Results indicate that fifty-seven (57) of the one hundred eight (108) XRF readings tested at or above the limit of 0.3 mg/cm . Positive lead results and locations are indicated in the chart below.
POSITIVE LEAD XRF READINGS (>0.3 mg/cm
No Component Substrate Cond. Color Room Area PbC
6 Casing Wood Fair Green Outside 1st Floor 26.9
7 Lintel Concrete Poor Green Outside 1st Floor 3.3
8 Casing Metal Fair Green Outside 1st Floor 3.7
9 Casing Metal Fair Green Outside 1st Floor 7.1
12 Window Metal Fair Red Outside 1st Floor 11.2
15 Window Metal Fair Red Outside 1st Floor 11.9
18 Door Wood Poor Red Outside 1st Floor 5.2
19 Casing Metal Poor Green Outside 1st Floor 17.8
22 Soffit Wood Poor Tan Outside 1st Floor 6.9
23 Soffit Wood Poor Tan Outside 1st Floor 12.2
24 Soffit Wood Poor Tan Outside 1st Floor 4.6
25 Frieze Board Wood Poor Tan Outside 1st Floor 11.8
El Paso Office: 7307 Remcon Circle, Suite 103 El Paso, Texas 79912 Fax 915-581-2049 Phone 915-833-3740
No Component Substrate Cond. Color Room Area PbC
26 Frieze Board Wood Poor Tan Outside 1st Floor 7.7
31 Casing Metal Fair Green Outside 1st Floor 9
43 Window Wood Poor White Outside 1st Floor 4.6
44 Window Wood Poor White Outside 1st Floor 5.5
45 Casing Wood Poor White Outside 1st Floor 3.8
46 Casing Wood Poor White Outside 1st Floor 11.6
47 Casing Wood Fair Black Bay 1st Floor 20.1
49 Column Wood Fair Tan Bay 1st Floor 23.7
50 Column Wood Fair Tan Bay 1st Floor 18.7
51 Column Base Concrete Fair Black Bay 1st Floor 5.9
52 Column Base Concrete Fair Black Bay 1st Floor 6.6
53 Wall Plaster Fair Tan Bay 1st Floor 2.2
54 Wall Plaster Fair Tan Bay 1st Floor 16.2
55 Riser Metal Fair Black Bay 1st Floor 5.9
56 Newel Post Metal Fair Black Bay 1st Floor 1.5
58 Casing Metal Fair Black Bay 1st Floor 8.6
59 Casing Wood Fair Black Bay 1st Floor 14.4
60 Door Wood Fair Tan Bay 1st Floor 13.4
61 Door Wood Fair Tan Bay 1st Floor 8.7
62 Door Wood Fair Tan Bay 1st Floor 4.6
63 Ladder Metal Fair Tan Bay 1st Floor 5.4
64 Wall Brick Fair Tan Bay 1st Floor 3.1
65 Wall Plaster Fair Tan Bay 1st Floor 10.6
66 Casing Wood Fair Black Bay 1st Floor 3.3
67 Casing Wood Fair Black Bay 1st Floor 11.2
68 Casing Wood Fair Black Bay 1st Floor 16.6
79 Stairs Concrete Fair Red Stairs 1st Floor 3.5
82 Casing Wood Fair Black Bay 1st Floor 6.4
83 Door Wood Fair Tan Bay 1st Floor 3.9
84 Door Wood Fair Tan Bay 1st Floor 4.1
85 SILL Wood Fair Tan Bay 1st Floor 4.4
88 Sill Plaster Fair Tan Bay 2nd Floor 4
92 Wall Plaster Fair Brown Bay 2nd Floor 3.4
93 Casing Wood Fair Tan Bay 2nd Floor 7.9
95 Paint Casing Fair Tan Bay 2nd Floor 3.1
97 Door Wood Fair Tan Bay 2nd Floor 2
98 Door Wood Fair Tan Bay 2nd Floor 7
99 Wall Plaster Fair Brown Bed Room 2nd Floor 11.2
100 Window Metal Fair Tan Bed Room 2nd Floor 7.7
101 Casing Wood Fair Tan Bed Room 2nd Floor 8
103 Casing Wood Fair Black Bed Room 2nd Floor 21.1
106 Wall Plaster Fair Brown Bath 2nd Floor 6
109 Sill Plaster Fair Brown Hall 2nd Floor 0
110 Column Wood Fair Brown Hall 2nd Floor 15.8
El Paso Office: 7307 Remcon Circle, Suite 103 El Paso, Texas 79912 Fax 915-581-2049 Phone 915-833-3740
No Component Substrate Cond. Color Room Area PbC
111 Column Wood Fair Brown Hall 2nd Floor 22.7
DESCRIPTION OF AREAS INSPECTED
Building 54 was occupied and is being used as a fire station at Fort Bliss, Texas. This facility occupied an area of approximately 10,250 SF. This building was a two-story structure which was constructed with brick and stucco walls on a concrete foundation. At the time this Lead Survey was performed, the date of construction was not known. An inventory of the affected painted surfaces was recorded as XRF testing proceeded. See the “LBP Testing Data Sheet.”
CALIBRATION OF THE XRF INSTRUMENT
Before proceeding with the investigation of painted surfaces, the XRF was calibrated in accordance to the manufacturer’s quality control procedures. The XRF utilized was a
NITON XLp 303 AW X-Ray Fluorescence analyzer (XRF) with serial No. 18451. The inspector took three calibration readings at 1.0 mg/cm and at the Action Level of 0.3 mg/cm on a lead calibration film (NIST 2579 SRM) provided by the manufacturer. The measured difference between the initial calibration test and the lead film was within the manufacturer’s acceptable calibration tolerance limit (< 0.2 mg/cm at 1.0 mg/ cm
). In accordance with the HUD XRF Performance Characteristic Sheet, the XRF instrument did not require correction for substrate bias for any substrate encountered and the instrument had no inconclusive range. Calibration of the instrument was also conducted at the conclusion of sampling for the building using the same procedures as the initial calibration check.
CONCLUSION
Care shall be taken for surfaces that contain levels of lead below the Action Level stated above for the instrument (0.3 mg/cm ), which could create lead dust or lead-contaminated soil hazards if the paint is turned into dust by abrasion, scraping, or sanding.
El Paso Office: 7307 Remcon Circle, Suite 103 El Paso, Texas 79912 Fax 915-581-2049 Phone 915-833-3740
Contact the Senior Lead Risk Assessor, or alternatively, the Lead Risk Assessor listed below with any clarifications that may be needed.
Inspected by Approved by: Report by:
Tim Jones Alicia Orrantia
Senior Lead Risk Assessor Lead Risk Assessor
Lead Sample Locations
ENCON #: 1044-11
Date: 01/24/11
Legend
# Lead Sample Location
Positive Lead Sample
Bldg. 54
First Floor
Lead Sample Location Drawing
N.T.S.
22 23
3637 383940 4345 44
50 51
53 55
63 65
12 13 1514
16 17
18 19
Lead Sample Locations
ENCON #: 1044-11
Date: 1/24/12
Legend
# Lead Sample Location
Positive Lead Sample
Bldg. 54
Second Floor
Lead Sample Location Drawing
N.T.S.
93 9594
Ft. Bliss Building 54 LEAD-BASED PAINT INSPECTION Date of inspection 1/24/2012
Reading No Type Component Substrate Condition Color Room Area Results Action Level PbC
1 SHUTTER 1.42
2 PAINT Calibrate Positive 0.3 0.3
3 PAINT Calibrate Positive 0.3 0.3
4 PAINT Calibrate Positive 0.3 0.3
5 PAINT Door Wood Fair Red Outside 1st Floor Negative 0.3 0
6 PAINT Casing Wood Fair Green Outside 1st Floor Positive 0.3 26.9
7 PAINT Lintel Concrete Poor Green Outside 1st Floor Positive 0.3 3.3
8 PAINT Casing Metal Fair Green Outside 1st Floor Positive 0.3 3.7
9 PAINT Casing Metal Fair Green Outside 1st Floor Positive 0.3 7.1
10 PAINT Door Metal Fair Red Outside 1st Floor Negative 0.3 0
11 PAINT Door Metal Fair Red Outside 1st Floor Negative 0.3 0
12 PAINT Window Metal Fair Red Outside 1st Floor Positive 0.3 11.2
13 PAINT Ext Sill Concrete Fair Green Outside 1st Floor Negative 0.3 0.01
14 PAINT Ext Sill Concrete Poor Green Outside 1st Floor Negative 0.3 0.05
15 PAINT Window Metal Fair Red Outside 1st Floor Positive 0.3 11.9
16 PAINT AC Stand Metal Poor Tan Outside 1st Floor Negative 0.3 0
17 PAINT AC Stand Metal Poor Silver Outside 1st Floor Negative 0.3 0
18 PAINT Door Wood Poor Red Outside 1st Floor Positive 0.3 5.2
19 PAINT Casing Metal Poor Green Outside 1st Floor Positive 0.3 17.8
20 PAINT AC Stand Metal Poor Tan Outside 1st Floor Negative 0.3 0
21 PAINT Out Building Wood Poor Tan Outside 1st Floor Negative 0.3 0
22 PAINT Soffit Wood Poor Tan Outside 1st Floor Positive 0.3 6.9
23 PAINT Soffit Wood Poor Tan Outside 1st Floor Positive 0.3 12.2
24 PAINT Soffit Wood Poor Tan Outside 1st Floor Positive 0.3 4.6
25 PAINT Frieze Board Wood Poor Tan Outside 1st Floor Positive 0.3 11.8
26 PAINT Frieze Board Wood Poor Tan Outside 1st Floor Positive 0.3 7.7
27 PAINT Door Wood Fair Red Outside 1st Floor Negative 0.3 0
28 PAINT Door Wood Fair Green Outside 1st Floor Negative 0.3 0.01
29 PAINT Casing Metal Fair Green Outside 1st Floor Negative 0.3 0
30 PAINT Casing Wood Fair Green Outside 1st Floor Negative 0.3 0.07
31 PAINT Casing Metal Fair Green Outside 1st Floor Positive 0.3 9
32 PAINT Casing Metal Poor White Outside 1st Floor Negative 0.3 0
33 PAINT Door Metal Fair White Outside 1st Floor Negative 0.3 0.02
34 PAINT Wall CMU Fair White Outside 1st Floor Negative 0.3 0
35 PAINT Downspout Metal Poor White Outside 1st Floor Negative 0.3 -0.2
36 PAINT Storage Tank Metal Poor White Outside 1st Floor Negative 0.3 0
37 PAINT Storage Tank Metal Poor White Outside 1st Floor Negative 0.3 0
38 PAINT Door Metal Poor White Outside 1st Floor Negative 0.3 0.04
39 PAINT Casing Metal Poor White Outside 1st Floor Negative 0.3 0.02
40 PAINT Wall Stucco Fair Tan Outside 1st Floor Negative 0.3 0.01
43 PAINT Window Wood Poor White Outside 1st Floor Positive 0.3 4.6
44 PAINT Window Wood Poor White Outside 1st Floor Positive 0.3 5.5
45 PAINT Casing Wood Poor White Outside 1st Floor Positive 0.3 3.8
46 PAINT Casing Wood Poor White Outside 1st Floor Positive 0.3 11.6
47 PAINT Casing Wood Fair Black Bay 1st Floor Positive 0.3 20.1
48 PAINT Door Wood Fair White Bay 1st Floor Negative 0.3 0
49 PAINT Column Wood Fair Tan Bay 1st Floor Positive 0.3 23.7
50 PAINT Column Wood Fair Tan Bay 1st Floor Positive 0.3 18.7
51 PAINT Column Base Concrete Fair Black Bay 1st Floor Positive 0.3 5.9
52 PAINT Column Base Concrete Fair Black Bay 1st Floor Positive 0.3 6.6
53 PAINT Wall Plaster Fair Tan Bay 1st Floor Positive 0.3 2.2
54 PAINT Wall Plaster Fair Tan Bay 1st Floor Positive 0.3 16.2
55 PAINT Riser Metal Fair Black Bay 1st Floor Positive 0.3 5.9
56 PAINT Newel Post Metal Fair Black Bay 1st Floor Positive 0.3 1.5
57 PAINT Column Metal Fair Black Bay 1st Floor Negative 0.3 0.03
58 PAINT Casing Metal Fair Black Bay 1st Floor Positive 0.3 8.6
59 PAINT Casing Wood Fair Black Bay 1st Floor Positive 0.3 14.4
60 PAINT Door Wood Fair Tan Bay 1st Floor Positive 0.3 13.4
61 PAINT Door Wood Fair Tan Bay 1st Floor Positive 0.3 8.7
62 PAINT Door Wood Fair Tan Bay 1st Floor Positive 0.3 4.6
63 PAINT Ladder Metal Fair Tan Bay 1st Floor Positive 0.3 5.4
64 PAINT Wall Brick Fair Tan Bay 1st Floor Positive 0.3 3.1
65 PAINT Wall Plaster Fair Tan Bay 1st Floor Positive 0.3 10.6
66 PAINT Casing Wood Fair Black Bay 1st Floor Positive 0.3 3.3
67 PAINT Casing Wood Fair Black Bay 1st Floor Positive 0.3 11.2
68 PAINT Casing Wood Fair Black Bay 1st Floor Positive 0.3 16.6
69 PAINT Casing Wood Fair Black Bay 1st Floor Negative 0.3 0.01
70 PAINT Casing Wood Fair White Bay 1st Floor Negative 0.3 0
71 PAINT Floor Concrete Fair Grey Bay 1st Floor Negative 0.3 0
72 PAINT Floor Concrete Fair Grey Bay 1st Floor Negative 0.3 0.03
73 PAINT Floor Concrete Fair Red Bay 1st Floor Negative 0.3 0.01
74 PAINT Floor Concrete Fair Red Bay 1st Floor Negative 0.3 0.03
75 PAINT Wall Drywall Fair Brown Office 1st Floor Negative 0.3 0.01
76 PAINT Wall Drywall Fair Brown Office 1st Floor Negative 0.3 0
77 PAINT Casing Wood Fair White Office 1st Floor Negative 0.3 0.09
78 PAINT Rail Metal Fair Black Stairs 1st Floor Negative 0.3 0.11
79 PAINT Stairs Concrete Fair Red Stairs 1st Floor Positive 0.3 3.5
80 PAINT Elec. Cabinet Metal Fair Tan Bay 1st Floor Negative 0.3 0.05
81 PAINT Cabinet Wood Fair Tan Bay 1st Floor Negative 0.3 0.02
82 PAINT Casing Wood Fair Black Bay 1st Floor Positive 0.3 6.4
83 PAINT Door Wood Fair Tan Bay 1st Floor Positive 0.3 3.9
84 PAINT Door Wood Fair Tan Bay 1st Floor Positive 0.3 4.1
85 PAINT SILL Wood Fair Tan Bay 1st Floor Positive 0.3 4.4
86 PAINT Ceiling Plaster Fair Tan Bay 1st Floor Negative 0.3 0.01
87 PAINT Wall Plaster Fair Tan Bay 1st Floor Negative 0.3 0.11
88 PAINT Sill Plaster Fair Tan Bay 2nd Floor Positive 0.3 4
89 PAINT Door Wood Fair Tan Bay 2nd Floor Negative 0.3 0
90 PAINT Casing Wood Fair Tan Bay 2nd Floor Negative 0.3 0
91 PAINT Wall Drywall Fair Brown Bay 2nd Floor Negative 0.3 0.03
92 PAINT Wall Plaster Fair Brown Bay 2nd Floor Positive 0.3 3.4
93 PAINT Casing Wood Fair Tan Bay 2nd Floor Positive 0.3 7.9
94 PAINT Baseboard Wood Fair Tan Bay 2nd Floor Negative 0.3 0.06
95 PAINT Casing Wood Fair Tan Bay 2nd Floor Positive 0.3 3.1
96 PAINT Casing Wood Fair Tan Bay 2nd Floor Negative 0.3 0
97 PAINT Door Wood Fair Tan Bay 2nd Floor Positive 0.3 2
98 PAINT Door Wood Fair Tan Bay 2nd Floor Positive 0.3 7
99 PAINT Wall Plaster Fair Brown Bed Room 2nd Floor Positive 0.3 11.2
100 PAINT Window Metal Fair Tan Bed Room 2nd Floor Positive 0.3 7.7
101 PAINT Casing Wood Fair Tan Bed Room 2nd Floor Positive 0.3 8
102 PAINT Casing Wood Fair Black Bed Room 2nd Floor Negative 0.3 0.02
103 PAINT Casing Wood Fair Black Bed Room 2nd Floor Positive 0.3 21.1
104 PAINT Casing Wood Fair Black Bed Room 2nd Floor Negative 0.3 0
105 PAINT Casing Wood Fair Black Bed Room 2nd Floor Negative 0.3 0
106 PAINT Wall Plaster Fair Brown Bath 2nd Floor Positive 0.3 6
107 PAINT Door Wood Fair Black Hall 2nd Floor Negative 0.3 0.02
108 PAINT Door Wood Fair Brown Hall 2nd Floor Negative 0.3 0.15
109 PAINT Sill Plaster Fair Brown Hall 2nd Floor Positive 0.3 0
110 PAINT Column Wood Fair Brown Hall 2nd Floor Positive 0.3 15.8
111 PAINT Column Wood Fair Brown Hall 2nd Floor Positive 0.3 22.7
112 PAINT Rail Metal Fair Brown Hall 2nd Floor Negative 0.3 0.16
113 PAINT Calibrate Positive 0.3 0.3
114 PAINT Calibrate Positive 0.3 0.3
115 PAINT Calibrate Positive 0.3 0.3
| Bldg 54 Cover page Lead |
| bldg 54 lead report |
| Bldg 54 Lead Drawing 1st Floor |
| Bldg 54 Lead Drawing 1st Floor.vsd |
| Page-1 |
| Bldg 54 Lead Drawing 2nd Floor |
| Bldg 54 Lead Drawing 2nd Floor.vsd |
| Page-1 |
XRF Final
File details come from the government source that posted it. Updated .