This is a Justification and Approval (J&A) form for other than full and open competition for the Library of Congress to award a contract to Constantine Ltd for transportation services of museum loan objects. The contract, valued at $70,000, covers the transport of 32 objects from the Royal Collection Trust and 5 objects from the Science Museum Group in the UK to the US for the exhibition "The Two Georges: Parallel Lives in an Age of Revolution."
The sole source justification is based on the Science Museum Group's requirement that Constantine Ltd must be used to transport their loan objects, while the Royal Trust specified Constantine as one of two approved contractors. The period of performance is February 25, 2025 to May 1, 2026, with objects from both museums being delivered to the Library of Congress in March 2025. The Royal Collection Trust objects will be returned in October 2025, while the Science Museum Group objects will be returned in March 2026. The final negotiated price of $78,348.80 includes additional options and was determined to be fair and reasonable based on comparison to the Independent Government Estimate of $70,000.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Justification and Approval For Other than Full and Open Competition
Plan ID Number:
Form Updated 4/14/2023
Justification & Approval
As a legislative branch agency, the Library is subject to the competition and advertising requirements of 41 U.S.C. § 6101. Like the Competition in Contracting Act and the FAR, 41 U.S.C. § 6101 does not require competition when a contracting officer certifies that only one source or brand-name item is available, when dictated by public exigency, or when otherwise authorized by law.
This document sets forth the justification and approval for award of a contract or order by means providing for other than full and open competition per 41 U.S.C. § 6101, LCR 7-210, and, as applicable, FAR 6.302, FAR 13.106-1, FAR 8.405, and FAR 16.505. Contracting without competition shall not be justified on the basis of a lack of advance planning or concerns related to availability of funds.
This form shall be used to support instances where competition will be limited to a single source, a limited number of sources, including where a brand name product is required.
Part 1 – Identification
1. Contracting Agency and Activity: Library of Congress, LBN/Center for Exhibits and Interpretation
2. Nature of Action Being Approved
Contract (or modification) LoC or Leg Branch Order (or modification) GSA Schedule or GWAC: Identify Schedule/Contract Other: Identify
Plan ID Number: 2025-CEI-0039 Contractor (or Brand Name): Constantine Ltd Estimated Value (Base and all options): $70,000 Period of Performance: 02/25/2025 – 05/01/2026
3. Description of Supplies or Services Required to Meet Library Needs
Describe the supplies or services that are required to meet the Library’s minimum needs and the delivery schedule required to meet those needs. Do not focus on a description of the program.
The Library requires the following supplies or services:
The Library of Congress (LOC) seeks a U.K. transport agent to transport loan objects from the Royal Collection Trust and the Science Museum Group in the U.K. to the U.S. for the exhibition The Two Georges: Parallel Lives in an Age of Revolution. The loans comprise thirty-two objects from the Royal Collection Trust, which will be delivered to LOC in March 2025 and returned in October 2025; and five objects from the Science Museum Group, which will be delivered to LOC in March 2025 and returned in March 2026.
Plan ID Number:
Form Updated 4/14/2023
Part 2 – Program Office Justification & Approval
4. Authority for Contracting Without Competition Over $250,000 For this requirement over $250,000, under FAR part 6, the basis for contracting without providing for full and open competition is:
There is only one responsible source and no other supplies or services will satisfy Library requirements.
41 U.S.C. § 6101(b)(2)(C); FAR 6.302-1.
Library’s minimum needs can only be satisfied by contractor’s unique capabilities or products. FAR 6.302-1(b)(1).
Source controls copyrights, patents, raw materials, or secret processes cannot be acquired otherwise, or similar circumstances. FAR 6.302- 1(b)(2).
Other exception identified in FAR 6.302-1: Identify the exception
There is such unusual & compelling urgency that the Government would be seriously injured if competition is not limited.
41 U.S.C. § 6101(b)(2)(B); FAR 6.302-2. Option years are not permitted.
Source is expressly authorized or required by statute (e.g., AbilityOne, UNICOR, GPO, GSA Public Buildings Service, Appropriations Act, etc.) per 41 U.S.C. § 6101(b)(1) and FAR 6.302-5: Identify the authority Other basis authorized in 41 U.S.C. § 6101(b) or FAR part 6.302: Identify the exception
Library’s needs can only be satisfied by a brand-name product or item which is essential to the Government’s requirement. FAR 6.302-1(c).
The Product is listed on the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable IT Standard Data Sheet)
Up to and including $250,000 For this requirement up to $250,000, using simplified acquisition procedures under FAR part 13, the basis for contracting without providing for full and open competition is:
Only one responsible source is reasonably available to meet Library requirements. 41 U.S.C. § 6101(b); FAR 13.106-1.
Product or service is reasonably available from only one source.
Source controls copyrights, patents or other exclusive licensing arrangements.
Urgent circumstances; only one source can reasonably deliver by required date. Option years are not permitted.
Source is expressly authorized or required by statute:
Other basis authorized in 41 U.S.C. § 6101(b) or FAR part 6.302-4(a)(2). The loan objects are from the Royal Collection Trust and the Science Museum Group both based in the UK and the loan agreement between the Library and the Science Museum Group states that the Library must use Constantine to transport the loan objects from the Science Museum Group.
Library’s needs can only be satisfied by a brand-name product The Product is listed the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable IT Standard Data Sheet)
GSA Schedule Order For this GSA schedule order under FAR part 8, the basis for not competing among GSA schedule-holders and/or specifying a brand name product or item is:
An urgent and compelling need exists, and following GSA procedures would result in unacceptable delays.
FAR 8.405-6(a)(1)(i)(A).
Only one GSA source is capable of fulfilling the requirement at the level of quality required because the supplies or services are unique or highly specialized. FAR 8.405-6(a)(1)(i)(B).
In the interest of economy and efficiency, the new work is a logical follow-on to an original order that was placed competitively among GSA schedule-holders (i.e., the original order was not sole-source or limited-source.) FAR 8.405-6(a)(1)(i)(C).
Library’s needs can only be satisfied by a brand-name product The Product is listed on the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable IT Standard Data Sheet)
Order Under Multiple Award Indefinite-Delivery Contract or GWAC For this order under FAR subpart 16.5, the basis for contracting without providing for full and open competition is:
The need is so urgent fair opportunity would result in unacceptable delays. 41 U.S.C. § 6101(b)(2)(C) and FAR 16.505(b)(2)(i)(A).
The Library’s minimum needs can only be satisfied by contractor’s unique capabilities or products. 41 U.S.C. § 6101(b)(1) and FAR
16.505(b)(2)(i)(B).
A logical follow-on order in the interest of economy and efficiency. 41 U.S.C. § 6101(b)(1) and FAR 16.505(b)(i)(2)(C).
To satisfy a minimum guarantee. 41 U.S.C. § 6101(b)(1) and FAR 16.505(b)(2)(D).
Authorized or required by statute. 41 U.S.C. § 6101(b)(1) and FAR 16.505(b)(2)(E).
The Library’s minimum needs can only be satisfied by a brand-name product or item which is essential to the Government’s requirement. 41 U.S.C. § 6101(b)(2)(B) and FAR 16.505(a)(4)(i).
The Product is listed on the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable
IT Standard Data Sheet)
5. Rationale for Contracting Without Competition
In supporting an action not providing for full and open competition, it is not sufficient to demonstrate that the contractor is exceptionally well qualified or even the best qualified, or that the required brand name product is well suited to the Library’s needs. The rationale must demonstrate that no one else, or no other competing product, can satisfactorily fulfill the Library’s requirement. Do not focus on the importance of the requirement; the issue is the rationale for not competing.
In supporting urgency, address the following: What are the unexpected facts or the unpredictable events that led to this situation? When is the required delivery or performance start date? Why this date? What specific harm to the Government will occur if the delivery is not made or performance not begun as scheduled? (Note that expiration of funds is not sufficient harm to justify not competing.) Demonstrate that the contract is only for items and quantities urgently needed until a competitive procurement action can be developed, or that a separate competitive follow-on is not practical.
In supporting a brand name justification, the brand name or feature must be essential to the Library’s requirements, and market research indicates that other company’s similar products or products with similar features cannot meet or be modified to meet the Library’s needs.
We are authorized to limit competition on the basis of the citation in section 4 because:
The loan agreement with the Science Museum Group states that LOC must use Constantine to transport the loan objects that are being provided by their museum. However, as the loan objects from both museums will be transported at the same time it is more cost efficient to have all the loan objects transported by the same transport agent.
6. Actions to Overcome Barriers to Competition Before Subsequent Contract Is Required
State what actions, if any, the program office can take to overcome barriers to competition before a contracting for this requirement again, such as:
using action to provide time to develop specifications for a competitive procurement by a certain date; licensing copyrights or patents so other contractors may use the works; or breaking the requirement into parts that may be purchased competitively. If this is a one-time requirement, explain that action to increase future competition is not needed. If the source is expressly required by statute, state “Source is statutory.”
To increase competition, we will:
As applicable and allowed by the loaners we will compete future requirements.
7. Program Office Certification
I certify that the description of the Government’s minimum needs, schedule requirements, and technical information that provide the basis for this justification are accurate and complete.
Name
Title
Signature
01/30/2025
Date
0BPART 3 – CONTRACTING OFFICER DETERMINATIONS & CERTIFICATION
8. Efforts to Solicit from As Many Potential Sources As Practicable Unless a justification is based on FAR 6.302-2, Unusual and compelling urgency, contracting officers shall post justifications for other than full and open competition, including brand name justifications, to the Contract Opportunities website on sam.gov (or eBuy for Brand Name Justifications under FAR Part 8) prior to requesting a proposal or otherwise entering into negotiations.
Advance notice will be published in sam.gov for 15 days before a contract is awarded. FAR 5.203(a).
Advance or concurrent notice will be published in sam.gov for a reasonable time for commercial items FAR 5.203(a) and 12.204(b).
Advance notice will not be published because the action meets the following FAR exception:
Notice would compromise national security. FAR 5.202(a)(1).
Unusual and compelling urgency; notice period would seriously injure Government. FAR 5.202(a)(2).
Expressly authorized or required to be made through another Government agency. FAR 5.202(a)(4).
Order will be placed against an IDIQ contract awarded under FAR 16.5. FAR 5.202(a)(6).
Order will be placed against GSA schedule or other competitively-awarded contract. FAR 5.202(a)(11).
Other: 13.501(a)(iii) Make publicly available the justifications (excluding brand name) required by 6.305(a) within 14 days after contract award.
Advance notice will not be published per 41 U.S.C. § 6101; see attached deviation from the FAR per LCR 7-210 § 3.A.
We made the following efforts to interest potential sources in this award:
9. Listing of Sources That Expressed Interest in Writing
The following sources expressed interest in this award:
N/A
10. Additional Information
The following additional information is relevant to this justification and approval:
None
11. Contracting Officer Determination that Price Is Fair and Reasonable As explained in detail below, I have determined that the prices for this contracting action are fair and reasonable based on comparison of the prices to the following (see FAR 15.404-1(b)(2)):
Historical prices paid by the Government Published competitive price lists Library’s Independent Government Estimate Prices obtained through market research Other: SME review of proposed prices and determination of price reasonableness
Prices obtained through competitive proposals
The following analysis (based on attached pricing information) supports my determination:
12. Contracting Officer Determination of Responsibility Checked System for Award Management (or will check in the case of competitive proposals for a brand name product) In accordance with FAR 9.104-1, Contractor Qualifications and Standards – Constantine Limited has been determined to be responsible, has no exclusions and the SAM registration is valid up till 2/6/2026.
13. Contracting Officer Determination of Best Value I have determined that this action represents the best value to the Government because:
A sole source contract is being awarded to Constantine Limited as the Science Museum, one of the museums loaning the objects specified that Constantine is the only contractor that is allowed to transport their loan objects and the Royal Trust the other museum specified Constantine as one of two contractors allowed to transport their objects. In addition, The SME, reviewed the prices proposed by Constantine and determined them to be reasonable and in line with their estimates. (See e-mail exchange with in the “Correspondence” file). Also, the proposed price of $78,348.80, which includes options not specified when the IGCE was being developed is comparable to the IGCE of $70,000 provided. The total price for the options is $13,169.56, as such the price proposed by Constantine is $4,820.76 lower than the IGCE. According to FAR 15.404-1(b)(2)(v) comparison to the IGCE ensures fair and reasonable pricing. As such awarding the contract to Constantine, presents the best value to the Library.