This document is an Amendment #1 to the Scope of Work for the Lawrence 7F Project, issued by the Ohio Department of Natural Resources' Division of Oil & Gas Resources Management for multiple orphan well sites in Lawrence County, Windsor Township. The amendment modifies the original contract terms, specifically revising the project completion timeline to eighteen (18) months after the effective date or by June 30, 2025, whichever comes first. The amendment also updates the Plan Set (Sheets 5 & 6) to show access to Donald Mootz 1 & 3 wells through the western part of the field along the tree line, with a date restriction limiting work on these wells to the months of July through October. The offer due date remains unchanged, with submissions required through OhioBuys by 12:00 PM on May 1st, 2025.

The amendment reinforces that all contractors must acknowledge receipt by submitting a revised Offer Sheet through OhioBuys, with failure to do so resulting in an unresponsive offer. Any previously submitted offers will be deleted from the system. The document is approved by Pete G. Moran, P.E. from the Division of Oil & Gas Resources Management, and signed on April 25, 2025. This amendment appears to be part of a larger orphan well plugging project that requires contractors to be active on a specific state contract (CSP900922) and meet established evaluation criteria for responsiveness and responsibility.

View the file

Other files

File Type Posted
SOW-Lawrence 7F_Amendment 1.pdf PDF
OhioBuys_Solicitation_Lawrence 7F.xlsx XLSX spreadsheet
SOW-Lawrence 7F.pdf PDF
Standard_T_C 3-1-24.pdf PDF
OWP_SORTING_ITEMS_OHIOBUYS (4).pdf PDF
SOW-Lawrence 7F.pdf PDF
OhioBuys_Solicitation_Lawrence 7F.xlsx XLSX spreadsheet
Standard_T_C 3-1-24.pdf PDF
OWP_SORTING_ITEMS_OHIOBUYS (4).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

Lawrence 7F PROJECT Multiple Orphan Well Sites

Lawrence County, Windsor Township

AMENDMENT #1

DATE OF AMENDMENT: April 25th, 2025

DIVISION OF OIL & GAS RESOURCES MANAGEMENT

OHIO DEPARTMENT OF NATURAL RESOURCES

2045 MORSE ROAD

BUILDING F-3

COLUMBUS, OHIO 43229-6693

To the Conditions and Specifications for:

Lawrence 7F PROJECT Multiple Orphan Well Sites

All contractors are reminded to acknowledge receipt of the Amendment when submitting an offer by submitting the revised Offer Sheet through OhioBuys. Failure to acknowledge this Amendment will result in submittal of an unresponsive Offer. Any offers submitted prior to this amendment shall be deleted from the OhioBuys system.

TO ALL BIDDERS:

1) This amendment shall revise the General Conditions, Part 8: Effective Date and Term.

Delete sentence three and replace with the following, “The Project must be completed eighteen (18) months after the effective date or by June 30, 2025, whichever is sooner.”

2) This amendment shall revise the Plan Set, Sheets 5 & 6 are revised to show access to Donald Mootz 1 & 3 through the western part of the field along the tree line. Additionally, a date restriction has been placed on the Donald Mootz 1 & 3, Work shall be completed in the months of July – October.

3) The Offer due date has NOT been changed for this project. "Offers must be fully submitted online through OhioBuys (https://procure.ohio.gov/bidders-and-suppliers) not later than, 12:00 PM on May 1st,2025."

APPROVED:

Pete G. Moran, P.E.

Division of Oil & Gas Resources Management