About this file
This is a Local Administered Project (LAP) Evaluation Form used by the Georgia Department of Transportation (GDOT) to assess consultant performance on contracted projects. The form evaluates consultants across two primary rating categories: Management and Prosecution and Progress. The Management section assesses resource management, consultant independence, scope adherence, and communication with GDOT staff across four factors. The Prosecution and Progress section evaluates three factors: timely completion of deliverables, quality and completeness of invoices and reports, and budget compliance. The evaluation uses a five-point scale where 5 indicates exceeding requirements, 3 indicates meeting requirements, and 1 indicates failure to meet requirements, with an N/A option where applicable. The form includes fields for the evaluation date, GDOT Project Identification Number, Project Manager information, Agency details, project description, phase, and service dates.
The scoring methodology assigns weighted point values based on the number of ratings within each section, with higher scores corresponding to better performance ratings. The form requires justification from the GDOT PM or Subject Matter Expert for all scores and includes space for consultant response. Signature blocks and acknowledgment sections are mandatory for both GDOT and consultant representatives, with additional Assistant Office Head and Office Head acknowledgment required if any factor receives a rating of 1. This evaluation instrument serves as a performance monitoring tool to document consultant compliance and quality of work delivery on GDOT-administered projects.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ 484_121825A Lighting Engineering Design S.pdf | ||
| RFQ 484_121825A_Lighting Engineering and Desi.pdf | ||
| Public Notice Of Advertisement RFQ_484_121825.pdf | ||
| Legacy Evaluation Form.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LAP Evaluation Form
Local Administered Project (LAP) Evaluation Form
Evaluation Date:
Consultant:
GDOT PI No:
GDOT PM:
Agency:
Agency PM:
Phone:
Email:
Project Description & Scope:
Project Phase:
Service Dates:
Ratings: 5 = Exceeds Requirement and Expectation; 3 = Meets Requirement and Expectation; 1 = Does not Meet Requirement and Expectation; or N/A Requirement and Expectation
| A | Management | Rating | Factor | ||
| 1 | Consultant appropriately managed resources (manpower, equipment, subconsultants, etc.) | N/A | - - - | 1 | |
| 2 | Consultant worked independently and without significant help from Agency's staff on routine tasks. | N/A | - - - | 1 | |
| 3 | Consultant remained within the scope of work as contracted. | N/A | - - - | 1 | |
| 4 | Consultant communicated well and worked cooperatively with GDOT staff, and Consultant promptly responded to calls, emails, correspondences, and direction given by GDOT staff. | N/A | - - - | 1 | |
| 0 | Ratings | ||||
| Sub Total: | 0.00 | ||||
| GDOT PM/SME Justification for Scores (required): |
Consultant Response to Evaluation (if applicable):
| B | Prosecution and Progress | Rating | Factor | ||
| 5 | Consultant completed the deliverable(s) by the latest agreed upon date or within the duration contracted, as applicable. | N/A | - - - | 1 | |
| 6 | All invoices, studies, reports, design requirements, and details are complete, accurate, clear, and concise. Revisions are minimal. | N/A | - - - | 1 | |
| 7 | Consultant completed the deliverable(s) within the assigned budget. | N/A | - - - | 1 | |
| 0 | Ratings | ||||
| Sub Total: | 0.00 | ||||
| GDOT PM/SME Justification for Scores (required): |
Consultant Response to Evaluation (if applicable):
Total Score: 0
| GDOT PM: | ||
| Signature: | Date: | |
| Supervisor's Acknowledgement: |
Local's Comments:
Local's Acknowledgement:
| The GDOT Assistant Office Head (AOH) and Office Head (OH) Acknowledgements are required if a Rating of 1 is recorded for any item above. |
| AOH Acknowledgement: OH Acknowledgement: |
| Consultant PM: | ||
| Signature: | Date: |
| Agency Evaluator's | ||
| Supervisor (if applicable): | ||
| Signature: | Date: |
&12&A Page &P of &N
Scoring
| 1 | |||||
| 3 | |||||
| 5 | |||||
| N/A | |||||
| Factor Table | |||||
| Section Value: | 50 | 5 | 3 | 1 | |
| 0 | Ratings | 0.00 | 0.00 | 0.00 | |
| 1 | Ratings | 50.00 | 30.00 | 10.00 | |
| 2 | Ratings | 25.00 | 15.00 | 5.00 | |
| 3 | Ratings | 16.67 | 10.00 | 3.33 | |
| 4 | Ratings | 12.50 | 7.50 | 2.50 |