This is a Local Administered Project (LAP) Evaluation Form used by the Georgia Department of Transportation (GDOT) to assess consultant performance on contracted projects. The form evaluates consultants across two primary categories: Management Rating and Prosecution and Progress Rating. The Management Rating section assesses resource management, consultant independence from agency staff, adherence to scope of work, and communication and cooperation with GDOT personnel. The Prosecution and Progress Rating section evaluates whether deliverables were completed by agreed-upon dates, the completeness and accuracy of invoices and reports, and budget compliance. The evaluation uses a five-point rating scale where 5 indicates exceeds requirements, 3 meets requirements, and 1 does not meet requirements, with an N/A option available. Each section produces subtotals that contribute to an overall project score.
The form includes signature and acknowledgment lines for the GDOT Project Manager, consultant Project Manager, agency evaluator's supervisor, and required acknowledgments from the GDOT Assistant Office Head and Office Head if any item receives a rating of 1. The scoring methodology applies weighted point values based on the number of rated factors, with single-factor ratings valued at 50 points for a score of 5, 10 points for a score of 1, and zero points for N/A designations. The form includes space for justifications of scores by the GDOT PM and responses from the consultant, allowing for documented feedback on performance throughout the project lifecycle.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ_484_092826 On_Call Engineering Support Se.pdf | ||
| Legacy Form.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LAP Evaluation Form
Local Administered Project (LAP) Evaluation Form
Evaluation Date:
Consultant:
GDOT PI No:
GDOT PM:
Agency:
Agency PM:
Phone:
Email:
Project Description & Scope:
Project Phase:
Service Dates:
Ratings: 5 = Exceeds Requirement and Expectation; 3 = Meets Requirement and Expectation; 1 = Does not Meet Requirement and Expectation; or N/A Requirement and Expectation
| A | Management | Rating | Factor | ||
| 1 | Consultant appropriately managed resources (manpower, equipment, subconsultants, etc.) | N/A | - - - | 1 | |
| 2 | Consultant worked independently and without significant help from Agency's staff on routine tasks. | N/A | - - - | 1 | |
| 3 | Consultant remained within the scope of work as contracted. | N/A | - - - | 1 | |
| 4 | Consultant communicated well and worked cooperatively with GDOT staff, and Consultant promptly responded to calls, emails, correspondences, and direction given by GDOT staff. | N/A | - - - | 1 | |
| 0 | Ratings | ||||
| Sub Total: | 0.00 | ||||
| GDOT PM/SME Justification for Scores (required): |
Consultant Response to Evaluation (if applicable):
| B | Prosecution and Progress | Rating | Factor | ||
| 5 | Consultant completed the deliverable(s) by the latest agreed upon date or within the duration contracted, as applicable. | N/A | - - - | 1 | |
| 6 | All invoices, studies, reports, design requirements, and details are complete, accurate, clear, and concise. Revisions are minimal. | N/A | - - - | 1 | |
| 7 | Consultant completed the deliverable(s) within the assigned budget. | N/A | - - - | 1 | |
| 0 | Ratings | ||||
| Sub Total: | 0.00 | ||||
| GDOT PM/SME Justification for Scores (required): |
Consultant Response to Evaluation (if applicable):
Total Score: 0
| GDOT PM: | ||
| Signature: | Date: | |
| Supervisor's Acknowledgement: |
Local's Comments:
Local's Acknowledgement:
| The GDOT Assistant Office Head (AOH) and Office Head (OH) Acknowledgements are required if a Rating of 1 is recorded for any item above. |
| AOH Acknowledgement: OH Acknowledgement: |
| Consultant PM: | ||
| Signature: | Date: |
| Agency Evaluator's | ||
| Supervisor (if applicable): | ||
| Signature: | Date: |
&12&A Page &P of &N
Scoring
| 1 | |||||
| 3 | |||||
| 5 | |||||
| N/A | |||||
| Factor Table | |||||
| Section Value: | 50 | 5 | 3 | 1 | |
| 0 | Ratings | 0.00 | 0.00 | 0.00 | |
| 1 | Ratings | 50.00 | 30.00 | 10.00 | |
| 2 | Ratings | 25.00 | 15.00 | 5.00 | |
| 3 | Ratings | 16.67 | 10.00 | 3.33 | |
| 4 | Ratings | 12.50 | 7.50 | 2.50 |