This Scope of Work document from the Ohio Department of Natural Resources (ODNR) outlines requirements for rigging hydraulic cylinders at Lake White State Park Dam in Waverly, Ohio. The project involves the removal and replacement of four hydraulic cylinders essential for the dam's gate control system, including rigging services, installation, and potential traffic control measures if work must be conducted from State Highway 104. Site visits are encouraged and can be scheduled Monday through Friday from 9am to 4pm by calling 740-493-2212, and the contractor must provide all labor, materials, tools, equipment, and supervision necessary for the project.

The contract will be awarded to the lowest responsive and responsible bidder based on low lot total, which will be determined by multiplying unit costs by estimated usage for all items. The contract includes F.O.B. Destination/Pre-Paid/Allowed terms, with the contractor bearing freight costs and maintaining risk of loss until title passes to the State upon acceptance of deliverables. All work must comply with OSHA safety standards and include appropriate traffic control measures if highway access is required, with ODOT notification necessary in such cases.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

The Ohio Department of Natural Resources is requesting bids for: Rigging Hydraulic Cylinders at Lake White State Park Dam Ordering Division and address: Lake White State Park Dam, 11291 St. Rt. 104 Waverly, OH 45690 Specifications

1. Introduction This Scope of Work (SOW) document outlines the requirements for the rigging, installation, and removal of hydraulic cylinders at the Lake White State Park Dam. The work includes the removal of existing cylinders, installation of new hydraulic cylinders, and coordination of traffic control to ensure safe and efficient operation if rigging is done from State highway 104. If this method is chosen, ODOT will need to be notified.

2. Project Overview The project involves the replacement of (4) hydraulic cylinders at Lake White State Park Dam, which is essential for maintaining the operation and safety of the dam's gate control system. The work will require precise rigging and careful handling of the cylinders to avoid damage to the dam structure and surrounding equipment. Additionally, traffic control measures may be necessary if cylinders are needed to be rigged from the state highway. If this is deemed necessary, ODOT will need to be notified as well.

3. Scope of Work The selected contractor shall provide all labor, materials, tools, equipment, and supervision necessary to complete the following tasks:

3.1 Rigging and Removal of Existing Hydraulic Cylinders

· Preparation:

· Mobilization of personnel, equipment, and tools required for rigging and removal.

· Survey and assessment of existing hydraulic cylinders to determine the rigging plan and removal procedures.

· Verification of existing cylinder connections, access points, and any potential hazards before removal.

· Rigging:

· Properly secure and rig the existing (4) cylinders using safe and effective rigging techniques, ensuring no damage to the dam structure, cylinders, or surrounding equipment.

· Ensure lifting equipment (e.g., cranes, hoists, etc.) is appropriately rated for the weight and size of the cylinders.

· Removal:

· Remove existing (4) cylinders without causing any damage to the surrounding infrastructure.

· Ensure that removed cylinders are carefully lowered, inspected, and prepared for either disposal or storage as per the client’s instructions.

3.2 Installation of New Hydraulic Cylinders

· Preparation:

· Inspection and confirmation of new hydraulic cylinders' specifications, alignment, and fitment requirements before installation.

· Verification of all necessary equipment and components, including seals, mounting hardware, and hydraulic connections.

· Installation:

· Rigging and carefully lifting the (4) new cylinders into position.

· Secure the new cylinders to the mounting brackets and connections per manufacturer guidelines and dam operational standards.

· Make necessary hydraulic and mechanical connections, ensuring proper alignment and tightness.

· Testing and Commissioning:

· Conduct functional tests to ensure proper operation of the new hydraulic cylinders.

3.3 Traffic Control and Site Safety if deemed necessary to rig off the Highway

· Traffic Control Plan:

· Develop and implement a traffic control plan to manage vehicle and pedestrian traffic around the worksite to ensure safety for workers and the public.

· Coordinate with local authorities, if required, to obtain necessary permits or approvals for road closures, detours, or other traffic management measures.

· Traffic Control Measures:

· Placement of appropriate signs, cones, barricades, flaggers, or other traffic control devices to manage and direct traffic around the worksite.

· Ensure that all traffic control measures comply with local and state regulations.

· Safety Protocols:

· Provide appropriate personal protective equipment (PPE) for all workers involved in the rigging, installation, and removal of cylinders.

· Implement job safety analysis (JSA) procedures to identify and mitigate potential risks, including falls, crane operations, and lifting hazards.

· Provide a site-specific safety plan that adheres to OSHA standards.

3.4 Clean-Up and Demobilization

· Upon completion of the work, remove all equipment, tools, and debris from the worksite.

· Ensure the area is restored to its original or better condition and that all traffic control measures are dismantled.

4. Safety Requirements

· All workers must adhere to OSHA guidelines and safety protocols while performing the work.

· The contractor shall maintain an active safety program, including daily toolbox talks, safety checks, and inspections of all equipment used in the project.

· Emergency procedures and contact numbers for safety personnel should be available on-site at all times.

F.O.B. DESTINATION/PRE-PAID/ALLOWED. The Contractor must provide Deliverables under this Contract F.O.B. Destination/Pre-Paid/Allowed. The place of destination will be specified by the Ordering Agency on the agency’s purchase order or other ordering document. Cost of the freight must be borne and paid by the Contractor unless otherwise stated.

All risk of loss, regardless of the cause, will remain with the Contractor until title to the Deliverable passes to the State. Unless otherwise provided in this Contract, the State will determine whether the Contractor provided each Deliverable required in this Contract and has fully met all work requirements of this Contract. Title to any Deliverables will pass to the State on Acceptance of the Deliverable.

Evaluation. The contract will be awarded to the lowest responsive and responsible bidder as determined by the State.

Contract Award. The contract will be awarded to the lowest responsive and responsible bidder by low lot total. Low lot total will be determined by multiplying the unit cost by the estimated usage listed in the bid and then adding each of the totals together to arrive at a total for all items. Failure to bid all items may result in the bidder being deemed not responsive

Site Visit & Point of Contact

· A site visit is encouraged in order to view the project site and accurately bid out work. The site at 11291 St. Rt. 104 Waverly, OH 45690

· Site visits can be scheduled Monday through Friday from 9am to 4pm by appointment.

· Call 740-493-2212 to schedule an appointment.

Once a contract is awarded, failure of the bidder to have requested a site visit to become familiar with the facility and requirements of the bid will be insufficient reason to support any request to be released from the contract.