About this file

Summary of Construction Proposal

This is a Louisiana Department of Transportation and Development (LA DOTD) construction proposal for a federal aid highway project located in St. Tammany Parish. The project involves the construction of improvements on LA 3241 from the I-12/LA 434 Interchange to LA 36, encompassing approximately 4.818 miles of work including clearing and grubbing, grading, drainage structures, lime treatment, milling asphalt concrete, pavement patching, Class II base course, asphalt concrete pavement, Portland cement concrete pavement, detour roads, precast concrete piles, precast-prestressed concrete girder spans for bridge construction, lighting, and related work. Electronic bids and bid bonds must be submitted through www.bidx.com prior to the electronic bidding deadline of Wednesday, November 18, 2026, at 10:00 a.m. Eastern Time. Bidders are required to complete online bidder registration with LA DOTD prior to submission, with no registrations accepted within 24 hours before the bid opening. The project utilizes a Cost-Plus-Time (A+B) bidding method with a daily road user cost of $10,500 per calendar day; the apparent low bidder must submit a pre-award Critical Path Method (CPM) schedule for approval within 20 calendar days of bid letting. The successful contractor must be licensed under La. R.S. 37:2150-2165 for highway, street, and bridge construction and shall comply with a 90-calendar-day assembly period before regular construction operations commence, during which time the contractor is responsible for traffic maintenance but may perform certain maintenance work with no time charges.

The estimated project cost ranges from $100,000,000 to $125,000,000, with the final award amount to be determined based on actual estimate values published at bid opening. The project is designated for payment adjustments for asphalt cements, fuels, and steel in accordance with established price indices. Mandatory electronic payroll submission using AASHTOWare Civil Rights & Labor Software is required. The contractor must maintain comprehensive insurance coverage including workers' compensation with employer liability of at least $1,000,000 for work over water with maritime exposures, commercial general liability with combined single limits ranging from $1,000,000 to $5,000,000 depending on initial contract amount, owner's and contractor's protective liability (OCP) coverage with reimbursement of direct costs only, and business automobile liability insurance; all policies must be placed with A.M. Best rated insurers at A-:VI or higher. The project includes provisions for on-the-job training with estimated trainee hours of 12,000 for up to twelve trainees, compliance with Build America Buy America (BABA) provisions requiring domestically manufactured iron, steel, and construction materials, and adherence to environmental protection standards including Storm Water Pollution Prevention Plans. The project engineer is Darrick Berner, and the project manager is Christina Brignac.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF LOUISIANA

DEPARTMENT OF TRANSPORTATION AND

DEVELOPMENT

CONSTRUCTION PROPOSAL

DOTD

LOUISIANA DEPARTMENT OF

TRANSPORTATION & DEVELOPMENT

FEDERAL AID PROJEСТ

STATE PROJECT NO. H.004957

CONTROL SECTION NO. 454-04, 852-12, 280-03 & 852-33

LA 3241: I-12/LA 434 INTERCHANGE TO LA 36

ROUTES I-12, LA 434, LA 36 & LA 3241

ST. TAMMANY PARISH

ATE OF LOUSAA

RANDAL D. SANDERS

REG. No. 21391

REGISTERED

PROFESSIONAL ENGINEER

Tandal amer

NCINER

21 ОCТOBtR 2026

A-1

10/21/2026 07:52 AM

STATE PROJECT NO. H.004957

TABLE OF CONTENTS

Page No.

Title Sheet A-1

Table of Contents B-1

Notice to Contractors C-1 thru C-4

Special Provisions D-1 thru D-162

Federal Aid Construction Project Contract Documents

Required Contract Provisions, Federal-Aid Construction Contracts (06/26) E-1 thru E-12

Female and Minority Participation in Construction (01-83) E-13 thru E-20

New Orleans Plan (01-83) E-21 thru E-22

On-The-Job Training (06-21) E-23 thru E-26

DBE/SBE Participation in Federal Aid Construction Contracts (10-25) E-27 thru E-28

Minimum Wage Determination F-1 thru F-4

Technical Specifications G-1 thru G-40

Construction Proposal Information

RET Contract Time Form (A Plus B Method No Max) (01-26) H-1

Bid Bond I-1

Schedule of Items J-1 thru J-27

Construction Proposal Signature and Execution Form K-1 thru K-2

B-1

CONTROL SECTION NOS. 454-04, 852-33, 852-12 & 280-03

FEDERAL AID PROJECT NO. H004957

DESCRIPTION: LA 3241: I-12/LA 434 INTERCHANGE TO LA 36

NHS ROUTE: I-12 & LA 3241

NON-NHS ROUTE: LOCAL ROADS, LA 434 & LA 36

PARISH: ST. TAMMANY

LENGTH: 4.818 Miles

TYPE: CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTURES, LIME

TREATMENT, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, CLASS

II BASE COURSE, ASPHALT CONCRETE PAVEMENT, PORTLAND CEMENT

CONCRETE PAVEMENT, DETOUR ROAD, PRECAST CONCRETE PILES,

PRECAST-PRESTRESSED CONCRETE GIRDER SPANS BRIDGE, LIGHTING,

AND RELATED WORK.

Electronic bids and electronic bid bonds for the following project will be downloaded by the Louisiana Department of Transportation and Development (LA DOTD) on Wednesday, November 18, 2026. Paper bids and paper bid bonds will not be accepted. Electronic bids and electronic bid bonds must be submitted through www.bidx.com prior to the electronic bidding deadline. Beginning at 10:00 a.m., all bids will be downloaded and posted online at http://wwwapps.dotd.la.gov/engineering/lettings/. No bids are accepted after 10:00 a.m. The electronic bid download process is held in LA DOTD Headquarters Building, 1201 Capitol Access Road in Baton Rouge, LA, Room 113 B, and is open to the public. Visitors must check-in with the security desk in the first floor lobby.

LOCATED ON EXISTING ROUTE LA 434 / FUTURE ROUTE LA 3241 FROM

APPROXIMATELY 600 FEET SOUTH OF ITS PLANNED ROUNDABOUT

JUNCTION WITH THE ROUTE I-12 W.B. RAMPS TO ITS PLANNED

JUNCTION WITH ROUTE LA 434, AS SHOWN IN PLANS

LIMITS:

LOCATED ON ROUTE LA 36 FOR APPROXIMATELY 0.132 MILES ON EITHER

SIDE (EAST & WEST) OF ITS PLANNED JUNCTION WITH ROUTE LA 36.

LIMITS:

LOCATED ON VORTISCH RD. FROM ITS JUNCTION WITH EXISTING

ROUTE LA 434, EXENDING ALONG ROUTE LA 434 TO ITS PLANNED

JUNCTION WITH REALIGNED ROUTE LA 434, AS SHOWN IN PLANS

LIMITS:

LOCATED ON ROUTE LA 434 AT ITS PLANNED REALIGNED JUNCTION

WITH THE ROUTE LA 3241 EXTENSION.

LIMITS:

LOCATED ON LEGENDS BLVD. AT ITS PLANNED ROUNDABOUT

JUNCTION WITH EXISTING ROUTE LA 434 / FUTURE ROUTE LA 3241, AS

SHOWN IN PLANS.

LIMITS:

LOCATED ON TAMANEND WAY AT ITS PLANNED ROUNDABOUT

JUNCTION WITH EXISTING ROUTE LA 434 / FUTURE ROUTE LA 3241, AS

SHOWN IN PLANS.

LIMITS:

LOCATED ON THE ROUTE I-12 W.B. ON AND OFF RAMPS AT THEIR

PLANNED ROUNDABOUT JUNCTION WITH EXISTING ROUTE LA 434 /

LIMITS:

NOTICE TO CONTRACTORS (01/26)

C-1

ESTIMATED COST RANGE: $100,000,000 to $125,000,000

The estimated cost range is for informational purposes only and may be subject to change.

The bid prices received from bidders will be evaluated based on the actual estimate value, which will be published at bid opening, for award determination.

PROJECT ENGINEER: Berner, Darrick; 12810 Burgess Ave., Walker, LA 70785; (225) 665- 3945.

PROJECT MANAGER: Brignac, Christina.

PROJECT CLASSIFICATION

The winning bidder shall be licensed under La. R.S. 37:2150-2165 for the classification of

Highway, Street, and Bridge Construction. before execution of the awarded contract.

SPECIAL NOTICE TO CONTRACTORS: Bidders are required to certify their intent to comply with Section 102.14 of the 2026 Louisiana Standard Specifications for Roads and Bridges.

Bids must be prepared and submitted in accordance with Section 102 of the 2026 Louisiana Standard Specifications for Roads and Bridges as amended by the project specifications, and must include all information required by the proposal.

ONLINE BIDDER REGISTRATION IS FOR ALL PROSPECTIVE BIDDERS AND FOR

OTHERS INTERESTED IN INFORMATION ONLY. Prior to the electronic bid submission deadline, ONLINE BIDDER REGISTRATION for each project bid is REQUIRED. Online Bidder Registration may be accessed via the Internet at www.dotd.la.gov. Select the following options: DOING BUSINESS, then Construction Services, then Bidder Registration.

When completed, a registration confirmation notice will be displayed and may be printed by the bidder. When approved for bidding, the bidder’s name will be placed on the “List of Prospective Bidders” located on the LA DOTD Internet website. It is the bidder’s responsibility to review the “List of Prospective Bidders” to ensure approval to bid. If a bidder does not register for a project, the bid will not be accepted by LA DOTD. As per 102.4 e) of the 2026 edition of the Louisiana Standard Specifications for Roads and Bridges, no bidders will be approved for bid registration within 24 hours before the bid opening. All bidders must register to bid before that deadline. If further information is required, please contact Mr. Alfonzo Simon, email:

Alfonzo.Simon@la.gov, (225) 379-1111, fax : (225) 379-1857.

Plans and bid proposals are available in electronic format ONLY. All Plans, Proposals, Addenda, Amendments, Letters of Clarification, and Withdrawal Notices will be posted online. Paper

PLANNED ROUNDABOUT JUNCTION WITH EXISTING ROUTE LA 434 /

FUTURE ROUTE LA 3241, AS SHOWN IN PLANS.

LOCATED ON THE PLANNED ROUTE LA 3241 EXTENSION FROM ITS

PLANNED ROUNDABOUT JUNCTION WITH ROUTE LA 434 TO ITS

PLANNED JUNCTION WITH LA 36, AS SHOWN IN PLANS.

LIMITS:

LOCATED ON KRENTEL RD & N. DIXIE RD. AT THEIR PLANNED

ROUNDABOUT JUNCTION WITH EXISTING ROUTE LA 434 / FUTURE

ROUTE LA 3241, AS SHOWN IN PLANS.

LIMITS:

C-2

Amendments, Letters of Clarification, and Withdrawal Notices will be posted online. Paper notices will not be distributed.

Construction bid proposals (includes specifications) and plans may be accessed via the Internet at www.dotd.la.gov. To receive update notifications on specific projects, ONLINE BIDDER REGISTRATION is required. From the LA DOTD home page, select the following options:

DOING BUSINESS, then Construction Services then Construction Letting Information.

Once the Construction Letting Information page appears, find the Notice to Contractors box.

From the drop down menu, select the appropriate letting date and press the “Go To” button to open the page, which provides a listing of all projects to be let and a Construction Proposal Documents link for each project. All project specific notices are found here. It will be the responsibility of the bidder to check for updates. Additionally, plans and specifications may be seen at the Project Engineer's office. Upon request, the Project Engineer will show the project site.

All questions concerning the plans shall be submitted via the Electronic Plans Distribution Center known as Falcon. All submitted questions will be forwarded by email to the Project Manager and the Project Engineer. Questions submitted within a period of 96 hours prior to the advertised time for the opening of bids, excluding Saturdays, Sundays, and any other legal holidays, may not be answered prior to bidding. Falcon may be accessed via the Internet at www.dotd.la.gov. From the home page, select DOING BUISINESS then Construction Services then select Construction Letting Info. On the Construction Letting Information page, select the link, DOTD Plans Room (Falcon); Login to Falcon (or request an ID if a first-time user). Once logged in, you will have access to view Project Information, submit a question concerning the project, and view the plans. To avoid any suggestion that a potential bidder is using the Falcon system to communicate with other potential bidders, DOTD will not post any question or any statement of fact or opinion not made for the purpose of seeking clarification of plans and/or specifications. Any non-questions posted on falcon will be limited to the statement of an issue considered unresolved by a previous DOTD response.

Bidders assume the responsibility for accessing the Apparent Bid Results and final Bid Results on the Construction Letting Information web page located at wwwapps.dotd.la.gov/engineering/lettings/ to confirm whether they are the apparent low bidder for any given project and the specific due date of Form CS-6AAA for SBE Goal Projects.

Apparent Low Bidders on Small Business Element (SBE) Goal Projects shall comply fully with the “Required Contract Provisions for SBE Participation in Federal Aid Construction Contracts (SBE Goal Project)” contained in Section “E” of the Proposal; and, in accordance therewith, Apparent Low Bidders shall submit the completed Form CS-6AAA for SBE Goal Projects and Attachments to the LA DOTD Compliance Programs Office utilizing the list of SBE Certified Contractors as posted for this letting at:

http://wwwapps.dotd.la.gov/engineering/lettings/construction.aspx.

The award of the contract will be electronically submitted to the successful low bidder on each project.

The U. S. Department of Transportation (DOT) operates a toll free "Hotline" Monday through

C-3

The U. S. Department of Transportation (DOT) operates a toll free "Hotline" Monday through Friday, 8:00 a.m. to 5:00 p.m., Eastern Time. Anyone with knowledge of possible bid rigging, bidder collusion, or other fraudulent activities should call 1-800-424-9071. All information will be treated confidentially and caller anonymity will be respected.

C-4

S.P. CONTRACT TIME (01-26):

The entire contract shall be completed in all details and ready for final acceptance in accordance with 105.17.020 within the time specified by the contractor.

Prior to assessment of contract time, the contractor will be allowed 90 calendar days from the date stipulated in the Notice to Proceed to commence with portions of the contract work including but not limited to assembly periods, preparatory work for materials fabrications such as test piles, or other activities which hinder progress in the beginning stages of construction.

Prior to issuance of the Notice to Proceed, the Department will consider extending the assembly period, upon written request from the contractor justifying the need for additional time.

The contractor shall be responsible for maintenance of traffic from the beginning of the assembly period. During the assembly period, the contractor will be allowed to do patching and other maintenance work necessary to maintain the roadway with no time charges when approved by the engineer.

If the contractor begins regular construction operations prior to expiration of the assembly period, the assessment of contract time will commence at the time construction operations are begun.

The contractor is directed to the special provisions and the plans for any restrictions that may affect work schedules.

D-1

SPECIAL PROVISIONS

S.P. GENERAL BIDDING REQUIREMENTS (01-26):

The specifications, contract and bonds governing the construction of the work are the 2026 Edition of the Louisiana Standard Specifications for Roads and Bridges, together with any supplementary specifications and special provisions attached to this proposal.

Bids shall be prepared and submitted in accordance with Section 102 of the Standard Specifications.

The plans herein referred to are the plans approved and marked with the project number, route and Parish, together with all standard or special designs that may be included in such plans.

The bidder declares that the only parties interested in this proposal as principals are those named herein; that this proposal is made without collusion or combination of any kind with any other person, firm, association, or corporation, or any member or officer thereof; that careful examination has been made of the site of the proposed work, the plans, Standard Specifications, supplementary specifications and special provisions above mentioned, and the form of contract and payment, performance, and retainage bond; that the bidder agrees, if this proposal is accepted, to provide all necessary machinery, tools, apparatus and other means of construction and will do all work and furnish all material specified in the contract, in the manner and time therein prescribed and in accordance with the requirements therein set forth; and agrees to accept as full compensation therefore, the amount of the summation of the products of the quantities of work and material incorporated in the completed project, as determined by the engineer, multiplied by the respective unit prices herein bid.

It is understood by the bidder that the quantities given in this proposal are a fair approximation of the amount of work to be done and that the sum of the products of the approximate quantities multiplied by the respective unit prices bid shall constitute gross sum bid, which sum shall be used in comparison of bids and awarding of the contract.

The bidder further agrees to perform all extra and force account work that may be required on the basis provided in the specifications.

The bidder further agrees that within 15 calendar days after the contract has been transmitted to him, he will execute the contract and furnish the Department satisfactory surety bonds.

If this proposal is accepted and the bidder fails to execute the contract and furnish bonds as above provided, the proposal guaranty shall become the property of the Department; otherwise, said proposal guaranty will be returned to the bidder; all in accordance with 103.4.

D-2

S.P. MANDATORY ELECTRONIC BIDS

AND ELECTRONIC BID BONDS SUBMISSION (01-26):

This project requires mandatory electronic bidding. All Specifications, whether Standard, Supplemental or Special Provisions, are hereby amended to delete any references regarding paper bids and the ability to submit paper bid forms.

The contractor shall register online to be placed on the Louisiana Department of Transportation and Development (LA DOTD) prospective bidders list or for information only list.

Modifications to proposal documents will be posted on the Department’s website at the following URL address: http://wwwapps.dotd.la.gov/engineering/lettings/.

LA DOTD shall not be responsible if the bidder cannot complete and submit a bid due to failure or incomplete delivery of the files submitted via the internet.

D-3

S.P. MANDATORY ELECTRONIC

PAYROLL SUBMISSION (01-26):

This project requires mandatory submission of contractor payrolls using the AASHTOWare Civil Rights & Labor Software. All Specifications, whether Standard, Supplemental or Special Provisions, are hereby amended to delete any references regarding paper payrolls and the ability to submit such paper payroll forms.

D-4

S.P. DBE/SBE PARTICIPATION

IN FEDERAL AID CONSTRUCTION CONTRACTS (01-26):

This project has not been selected for a specific DBE/SBE Goal. The contractor shall meet the obligations of the Required Contract Provisions for DBE/SBE Participation in Federal Aid Construction Contracts contained elsewhere herein.

D-5

S.P. PARTICIPATION IN JOB TRAINING (01-26):

If the contractor desires to participate in job training, as provided by the Federal Aid Construction Project Contract Document entitled On the Job Training elsewhere herein, he/she shall submit a written request to the project engineer with a copy to the Compliance Program Section. According to the design formula, the number of potential trainees has been established as twelve (12). For the purposes of reimbursement, this number of trainees has been translated into an estimated twelve thousand (12,000) trainee hours. The pay item for Trainee Reimbursement; will be established in the contract in accordance with the Federal Aid Construction Project Contract Documents for On-The-Job Training and the above hours.

Should the design formula not indicate that the contract could support training; a contractor may still train upon the approval of the Department.

D-6

S.P. BUILD AMERICA / BUY AMERICA PROVISIONS (01-26):

Section 106, Control of Materials, of the Standard Specifications for Roads and Bridges, 2026 Edition, is hereby amended to include the following:

Pursuant to the Build America Buy America ("BABA") provisions of the Infrastructure Investment and Jobs Act (“IIJA”) enacted on November 15, 2021 (Pub. L. No. 117-58), all iron and steel materials (including the application of a coating), manufactured products manufactured in the United States and having the cost of the components greater than 55 percent of the total cost of all components of the manufactured product, as well as construction materials permanently installed in the project, shall be manufactured and produced in the United States, unless a waiver of these provisions is granted.

COST CALCULATION:

Refer to Part 184 of title 2 of the Code of Federal Regulations (2 CFR) for guidance to determine the cost of components for manufactured products.

CONTRACTOR CERTIFICATION AND CERTIFICATION SUBMISSION:

The apparent low bidder shall provide certification of intent to conform to BABA with their completed contract documents, through transmittal of a completed certification document. The certification document, “DOTD’s Bidder's Build America, Buy America Certification Form”, will be provided in the federal package with the other required federal documents, and shall be the only form acceptable for use in certification of intent to conform to BABA. The contractor shall provide a separate Certification Form from the supplier for each applicable material.

WAIVER:

Minimal use of foreign steel and iron materials will be allowed without waiver provided the cost of these materials does not exceed 0.l percent of the total contract cost or $2,500, whichever is greater; however, the contractor shall make written request to the Chief Construction Division Engineer for permission to use such foreign materials and shall furnish a listing of the materials, their monetary value, and their origin and place of production.

RECORDS RETENTION:

The contractor shall retain any and all records pertaining to or relating with the contractor’s BABA certification and processes for a period of not less than five years after final acceptance of the construction project.

D-7

INSPECTION:

At the Department’s sole discretion, the department shall have the right to inspect or audit any and all records pertaining to or relating with the contractor’s BABA certification and processes.

FOR MORE INFORMATION ON BABA:

More information may be found by going to FHWA website Made in America | US Department of Transportation, https://www.fhwa.dot.gov/construction/cqit/buyam.cfm, and OMB M-24-02.

D-8

S.P. COST-PLUS-TIME BIDDING PROCEDURE

(A + B METHOD) (NO MAX TIME)(01-26):

Subsection 102 of the 2026 LSSRB is amended to include:

102.15 COST-PLUS-TIME BIDDING PROCEDURE (A + B METHOD)

102.15.010 GENERAL

The process for bidding and the award of this project will take into account not only the contract amount bid but also the bidder’s stated contract time in which the project will be completed to final acceptance. This method will only be used to determine the successful bidder. It will not be used to determine the award amount nor final payment to the contractor.

Should only one contractor bid then he will be required to turn in a Pre-Award CPM prior to Award of Contract for time verification by DOTD.

102.15.020 DEFINITION OF TERMS

For this project the following definitions apply:

Calendar Day. Refer to Subsection 101.3.

Contract Amount. The summation of the products of the quantities shown in the Schedule of Items multiplied by the unit bid prices.

Contract Time. The number of calendar days stated in the successful bidders proposal to complete the project to final acceptance as adjusted by authorized extensions.

Daily Road User Cost. The amount which represents the average daily cost of interference and inconvenience to the road user. The Department has assigned a daily road user cost of $10,500 per calendar day for this project.

Final Acceptance. Refer to Subsection 105.17.020.

102.15.030 PREPARATION OF PROPOSAL

In addition to all other bidding requirements of the project specifications, the bidder shall state his required completion time in the space provided on the “CONTRACT TIME” form contained elsewhere herein. The proposed completion time shall be based on the construction phases shown in the plans in their respective order and will be a factor used in considering bids for award. The stated number of calendar days required for completion will be the contract time for this project should the bidder be successful. Bids not including a contract time will be considered irregular and will be rejected.

D-9

102.15.040 CONSIDERATION OF BIDS

After bids are downloaded from BIDX, they will be compared based on the Total Bid Amount as determined by the following formula. In case of equal total bid amounts between qualified bidders, award will be made to the bidder proposing the lowest contract time.

Total Bid Amount = A + B

Where:

A = the contract amount as defined herein.

B = the product of the number of calendar days of contract time stated by the bidder and the daily road user cost contained herein.

102.15.050 LATE COMPLETION

Should the contractor fail to complete the project to final acceptance prior to expiration of the contract time, stipulated damages will be charged an amount equal to the daily road user cost stated herein.

D-10

S.P. CONSIDERATION OF BIDS (01-26):

Subsection 103.1.010 of the 2026 LSSRB is amended to include the following:

g) The single bidder on a Cost-Plus-Time bid fails to obtain approval from the Chief Construction Engineer of a Pre-Award CPM within 20 calendar days after the Bid Letting.

Subsection 103.1.020 of the 2026 LSSRB is amended to include the following:

g) The Contract Time submitted as part of a Cost-Plus-Time bid is found to be excessive by the Chief Construction Engineer.

D-11

S.P. INTENT OF CONTRACT (01-26):

Subsection 104.1, Intent of Contract, is amended to include the following.

104.4.010 COVENANT OF GOOD FAITH AND FAIR DEALING

This contract imposes an obligation of good faith and fair dealing in its performance and enforcement.

The contractor and the Department agree from the beginning to focus on creative cooperation, to avoid adverse confrontation, and to foster mutual respect, along with a positive commitment to honesty and integrity, and agree to the following mutual duties.

a) Each will function within the laws and statutes applicable to their duties and responsibilities.

b) Each will communicate in an open and candid manner.

c) Each will assist in the other's performance.

d) Each will avoid hindering the other's performance.

e) Each will proceed to fulfill its obligations diligently.

f) Each will cooperate in the common endeavor of the contract.

104.1.020 VOLUNTARY PARTNERING

The Louisiana Department of Transportation and Development intends to encourage the foundation of a cohesive partnership with the contractor and its principal subcontractors and suppliers. This partnership will be structured to draw on the strengths of each organization to identify and achieve reciprocal goals. The objective is a cooperative approach to contract management that will reduce costs, litigation, and "stress" while completing the project in accordance with the plans and specifications.

This partnership will be bilateral in makeup, and participation in partnering will be totally voluntary and is not a requirement of the contract.

A partnering conference is to be implemented and held prior to beginning construction. The contractor's management personnel and the Project Engineer will initiate a partnering development conference. They, working with the assistance of the District Construction Engineer, will make arrangements to determine the facilitator, the attendees at the conference, agenda of the conference, duration, and location. Persons required to be in attendance will be the Project Engineer and key project personnel; the contractor's on-site project manager and key project supervision personnel of both the prime and principal subcontractors and suppliers. The project design engineers, FHWA, key company representatives, and key local government personnel will also be invited to attend as

D-12 necessary. The contractor and DOTD will also be required to have Regional/District and Corporate/State level managers on the project team.

Any cost associated with effectuating this partnering will be agreed to by both parties and will be shared equally and will be paid for in accordance with Subsection 109.4. The contractor, DOTD, FHWA and all others invited to the partnering conference will be responsible for any expenses incurred by their respective employees which includes salaries, travel, and lodging.

Follow-up conferences may be held periodically throughout the duration of the contract as agreed by the contractor and the DOTD.

The establishment of a partnership charter on a project will not change the legal relationship of the parties to the contract nor relieve either party from any of the terms of the contract.

This partnership charter is intended only to establish an environment of cooperation and communication between all parties involved with the completion of the project.

D-13

S.P. MAINTENANCE OF TRAFFIC (01-26)

Section 104.3 of the 2026 Louisiana Standard Specifications for Roads and Bridges is amended to include the following:

In order to maintain traffic, temporary detours shall be constructed as required by the contract.

Conduct paving operations on one side of the roadway at a time. The side of the roadway, including shoulder, that is open to traffic shall be clear at all times.

When pavement layers are 2 inches or less, paving will be permitted in one lane for a full day;

the adjacent lane shall be paved the following workday.

When pavement layers are greater than 2 inches thickness, a wedged joint shall be used.

Paving will be permitted in one lane for a full day; the adjacent lane shall be paved the following day or place approximately 1/2 of each day's production in one lane and the remainder in the adjacent lane.

When asphalt concrete pavement is milled 2 inches or less, milling is permitted in one lane for a full day; the adjacent lane shall be milled no later than the following workday. When asphalt concrete pavement is milled more than 2 inches, milling shall be limited to approximately 1/2 of each day's production in one lane and the remainder in the adjacent lane.

All asphalt concrete pavement new construction, overlays, and shoulder surfacing operations open to traffic shall be conducted in accordance with the following requirements:

Shoulder Subgrade Preparation: Any required embankment widening shall be completed before placement of the asphalt concrete overlay. All vegetation shall be removed from existing shoulders before beginning temporary or final shoulder construction. When a shoulder wedge is required, the contractor shall blade and shape existing material to form a uniform surface for the placement of the wedge prior to placement of the asphalt concrete overlay.

Blading and Shaping of Material Adjacent to Pavement: Blading and shaping material adjacent to pavement described herein shall be completed at the end of each day's operations for all asphalt concrete courses. There shall be no drop-off from the pavement edge to the adjacent shoulder or foreslope. The contractor shall blade and shape existing material against, and approximately level with, the top of the pavement surfacing to form a uniform slope from the pavement edge to the adjacent existing shoulder, or to a point 10 feet from the pavement edge.

If existing materials are insufficient, the contractor shall furnish, place, and shape additional materials to form the required tie-in or temporary shoulder. Permanent materials and procedures shall be in accordance with contract documents. Existing and/or additional materials

D-14 placed temporarily shall be to the satisfaction of the Engineer. Compaction shall be by approved methods.

No direct payment will be made for temporary work; payment for permanent materials will be made using the appropriate pay items when additional materials are needed.

Direct special attention to the maintenance of traffic at entrance and exit ramps particularly when construction operations are being conducted on the adjacent travel lanes of interstate highways. Additional signs, barricades, channelizing devices, etc. shall be provided and maintained as directed by the Engineer and included in the as-bid cost of appropriate contract items, including temporary traffic control.

Lane closure and work hour restrictions shall be as follows:

No single lane closure restrictions are recommended for this project. One lane must remain open at all times.

No work shall be allowed and all lanes shall be open during New Year’s, Mardi Gras, Easter, Memorial Day, Independence Day, Labor Day, Thanksgiving, Christmas holiday periods, and other events as directed by the Engineer. No work shall be allowed and all lanes shall be open in preparation for weather events such as hurricanes, ice storms, etc, as deemed necessary, or during hurricane evacuation and contra flow operations. These periods shall be considered excusable, non-compensable.

D-15

S.P. Plans and Submittals (06-26)

Section 105.2 of the 2026 Louisiana Standard Specifications for Roads and Bridges has been amended to delete and replace the first paragraph as follows:

105.2 PLANS AND SUBMITTALS

Conform to 801.3.010 for format of plans and submittals.

D-16

S.P. PERMITS, LICENSES, TAXES AND INSURANCE (01-26)

Section 107 of the 2026 Louisiana Standard Specifications for Roads is Bridges is amended as follows:

107.2 is deleted and replaced with the following:

107.2 PERMITS, LICENSES, TAXES AND INSURANCE.

Contractors shall procure temporary permits and licenses for the work, pay charges, fees, and taxes, and give notices necessary for lawful prosecution of the work. Contractor, and its subcontractors, shall maintain all licenses and certifications necessary to accomplish the work in accordance with contract requirements and applicable law.

The contractor shall maintain, at a minimum, the following insurance coverage until final acceptance of the contract:

a) Workers Compensation in compliance with state law, with the exception that the contractor’s Employer liability is to be at least $1,000,000 when work is to be over water and involves maritime exposures. For the coverage provided in this subpart the contractor’s Insurer will have no right of recovery or subrogation against the State of Louisiana or the Louisiana Department of Transportation and Development.

b) For Commercial General Liability Insurance with a combined single limit per occurrence for bodily injury and property damage, the aggregate loss limit must be on a per project basis.

This insurance shall include coverage for bodily injury and property damage, and include coverage for Premises-Operation; Broad form Contractual Liability; Products and Completed Operation; Use of Contractors and Subcontractors; Personal Injury; Broad form Property Damage; and Explosion, Collapse and Underground (XCU) coverage. The required combined single limit amount of insurance shall be as provided in Table 107.2-1.

When a railroad is within the project limits, the combined single limit amount of Commercial General Liability Insurance shall be as required by the railroad or as provided in Table 107- 1, whichever is greater.

c) A separate Owner’s and Contractor’s Protective Liability (OCP) Policy shall be furnished by the contractor naming the Louisiana Department of Transportation and Development as the named insured. The policy period of the OCP insurance shall extend through final acceptance of the project. The required combined single OCP limit amount shall be as provided in Table 107.2-1.

d) For Business Automobile Liability Insurance with a combined single limit per occurrence for bodily injury and property damage, this insurance shall include bodily injury and property damage coverage for owned automobiles, hired automobiles and non-owned automobiles.

The required combined single limit amount of insurance shall be as provided in Table 107.2- 1 below.

D-17

Table 107.2-1 Insurance Requirements1

Initial Contract Amount

Occurrence Minimum

Aggregate Ultrahazardous

Aggregate

Up to $1 $1 $2 $3

From >$1 to $2 $2 $4 $6

Over $2 $5 $10 $15 1 $ in millions.

Aggregate coverage for projects with ultrahazardous activities shall be triple the occurrence minimum. Ultrahazardous activities include pile driving; transportation, use, storage, or removal of explosives, radioactive materials, or particularly hazardous or volatile chemicals; and asbestos or lead paint abatement; but does not include vibratory installation of sheet piles.

Each policy shall include provisions stipulating that the insurance company(ies) shall have no recourse against the State of Louisiana and the Department for payment of any premiums or for assessments under any form of the policy and that any and all deductibles in the above described insurance policy(ies) shall be assumed by and be at the sole risk of the contractor.

Insurance is to be placed with insurance companies authorized in the State of Louisiana with an A. M. Best’s rating of A-: VI or higher. This rating requirement may be waived for Workers Compensation coverage only.

Should any policies be canceled, the contractor shall immediately notify the Department.

Upon failure of the contractor to furnish, deliver and maintain such insurance for itself as required, this contract, at the election of the Department, may be immediately declared suspended, discontinued or terminated. Upon failure of the contractor to maintain OCP insurance at any time prior to final acceptance of the project, work on this contract shall be immediately suspended until proof of such insurance is presented to and accepted by the Department’s Project Control unit. During a suspension caused by the lack of any required insurance, contractual time charges will continue to be assessed against contract time, as will any assessment of stipulated damages, without interruption.

Failure of the contractor to maintain any required insurance shall not relieve the contractor from any liability under the contract, nor shall the insurance requirements be construed to conflict with the obligations of the contractor concerning indemnification under 107.17.

The contractor is responsible for requiring and verifying that all subcontractors working on the project maintain appropriate types and levels of insurance coverage.

Purchases related to work performed for this Project are exempt from sales and use taxes.

Prior to claiming the exemption, the general contractor or its subcontractor shall obtain a certificate of exemption from the secretary of the Department of Revenue at Louisiana Department of Revenue, Taxpayer Compliance - SES Division, Phone: (855) 307-3893, Email:

LDRSales.ExemptionApplications@la.gov.

D-18

107.2.010 REIMBURSEMENT OF OCP INSURANCE:

Contractor may submit the direct cost of OCP insurance (only) to the Department for reimbursement. The provisions of 109.4 shall not apply to this reimbursement. The cost of all other required insurance must be included in contractor’s overhead applied to all other bid items.

The Department will reimburse the actual cost of OCP coverage as shown on an invoice produced by the insurance company or broker issuing the invoice in the amount of the premium due for the OCP policy: a) without a markup for profit or indirect costs including indirect costs associated with procurement of the OCP insurance; and b) less charges in the amount of a tax from which the Department is exempt and other related incidental fees.

Contractor will be responsible for submitting a written request for reimbursement of the amount of the OCP policy premium invoice less all such charges including surplus lines taxes and other incidental fees. The Contractor shall contact the Louisiana Department of Insurance, ldi.la.gov, to receive additional guidance.

Contractor must also submit an original sworn affidavit from the insurance producer/agent in which that person attests that the submitted invoice is for the required OCP coverage only, and that the invoice accurately reports the cost to contractor of that coverage. The invoice and affidavit may be submitted at the preconstruction conference or thereafter for inclusion with a partial estimate.

There will be no reimbursement for any purchase of OCP insurance policy extensions necessitated by concurrent; non-excusable; or excusable, non-compensable delays in completion of the project, whenever such delays occur, or for claimed utility delays where such days were not added to Contract Time by change order. Any policy extensions necessitated by excusable, compensable delays will be reimbursed on a pro-rata monthly basis.

D-19

S.P. NAVIGABLE WATERS AND WETLANDS (01-26):

Subsection 107.9 of the Standard Specifications is amended to include the following.

In accordance with the provisions of this Subsection, the Department has obtained the required U.S. Army Corps of Engineers, permit.

Bidders shall comply with the permit requirements. Bidders may view permit(s) online via the Department’s FALCON system, or obtain a copy by contacting the Department's Environmental Section at (225) 379-1317.

D-20

S.P. ENVIRONMENTAL PROTECTION (01-26):

107.14 of the 2026 Louisiana Standard Specifications for Roads and Bridges is deleted and replaced with the following:

107.14 ENVIRONMENTAL PROTECTION

Comply with federal, state and local laws and regulations controlling pollution of the environment, including air, water and noise. Take precautions to prevent pollution of waters and wetlands with fuels, oils, asphalts, chemicals, or other harmful materials and to prevent pollution of the atmosphere from particulate and gaseous matter. Attention is directed to Section 204, Temporary Erosion Control.

Certify under penalty of law the understanding of and agreement to abide by the terms and conditions of the Storm Water Pollution Prevention Plan (SWPPP) and the Louisiana Pollution Discharge Elimination System (LPDES) General Permit. LPDES General Permit requires the discharges from construction sites be managed to prevent pollutants from entering waters of the United States in accordance with the Environmental Protection Agency's (EPA) regulations for storm water discharges with respect to 33 U.S.C. § 1342 (Sections 402 (p) and 405 of Public Law 100-4).

The use of erosion control features or methods other than those in the contract shall be as directed by the engineer.

Construction operations in rivers, streams, lakes, tidal waters, reservoirs, canals, and other impoundments are restricted to areas where it is necessary to perform filling or excavation to accomplish the work and areas which must be entered to construct temporary or permanent structures. Operations in navigable waters, wetlands, or other waters of the United States require permits. Responsible to ensure all appropriate permits are obtained prior to commencement of operations. As soon as conditions permit, streams and impoundments shall be cleared of temporary obstructions placed therein or caused by construction operations.

Frequent fording of streams with construction equipment will not be permitted.

No residue from dust collectors or washers shall be dumped into a stream. Attention is further directed to the federal, state, and local air pollution control programs and their rules and regulations regarding air pollution, especially open burning, fugitive dust and asphalt concrete plant restrictions.

Maintain and operate equipment to minimize noise and vibration as well as comply with local noise ordinances. Engines shall be equipped with properly functioning mufflers. Assure the activities near noise and vibration sensitive areas, such as churches, hospitals, and schools are not unduly disruptive.

The Master Notice of Intent (NOI) will be submitted by the Department to the Louisiana Department of Environmental Quality (LDEQ) at the end of each 5 year permit cycle of the Louisiana Pollution Discharge Elimination System (LPDES) Statewide Permit (LAR 600000) and

D-21 prior to project letting under the new permit cycle. The monthly Project List will be completed and submitted by the Department to the LDEQ by the 15th of each month, in accordance with the terms of the permit.

The Contractor will develop and post a site specific Storm Water Pollution Prevention Plan (SWPPP) for each project in accordance with the Master SWPPP Template provided to the Contractor by the Department. The Department ensures the posting of the SWPPP at the project site by the Contractor and that all site activities conform to the terms of the LPDES Statewide Permit (LAR 600000) and the Master SWPPP.

The Storm Water Pollution Prevention Plan shall be comprised of Section 204 of the standard specifications along with applicable supplemental specifications and special provisions, and Standard Plan EC-01, "Temporary Erosion Control Details."

D-22

S.P. PRE-AWARD CPM

FOR CONTRACT TIME REVIEW (01-26):

Should only one bid be received then the single bidder shall be required to gain approval from the Chief Construction Engineer, as outlined below, prior to the Award of Contract. A Pre-Award CPM shall only be used for review and justification of the contract time submitted as part of the bid.

Critical Path Methods (CPM) as described and with terms as defined in the Associated General Contractors of America (AGC) publication, Construction Planning and Scheduling, shall be used in construction scheduling and establishing the critical items of work. In case of discrepancy between these specifications and Construction Planning and Scheduling, these specifications shall govern.

The Single Bidder shall submit to the Chief Construction Engineer for approval, CPM Construction Schedules and Summary of Activities tabulations, all as described hereinafter, and altogether defined as "Construction Schedule". The Construction Schedule shall be based on the planned work, the proposed maintenance of traffic restrictions, and other design requirements given in the plans and specifications. Each sheet or page of each submittal shall be identified with the contractor's company name, state project number, project name, date prepared, revision dates, and sheet or page number. If the submittals are not prepared by the contractor's own staff, the company name of the preparer shall be shown on each sheet or page.

The critical activities as shown on the Construction Schedule will be considered in establishing the controlling item of work. If the Construction Schedule is not approved by the Chief Construction Engineer the bid will be considered irregular and will be rejected.

The sequence of work as represented on the approved Construction Schedule and approved associated data shall be interpreted as being the intention of the contractor at the time that the schedule was made.

CONSTRUCTION SCHEDULE

The Construction Schedule shall be a Critical Path Method (CPM) graphic diagram, computer prepared, utilizing the Precedence Diagramming Method (PDM). For the calendar day contract, the Gregorian calendar shall be used.

The schedule shall show and describe the various activities of work required to complete the contract in sufficient detail so that all activities are readily identifiable and progress on the activities can be readily measured. Sufficient detail in bridge work means each element of work (piles, footings, columns, caps, rebar, cure time, etc.) of individual bents; each element of work in individual spans (girders, strip seal joints, Structural Class A1, rebar, cure time, etc.); individual approach slabs; railings; rebar for all of the above as separate activities; and, miscellaneous other bridge work. Sufficient detail in road work means individual runs of pipe

D-23 in drainage structures; individual box culverts; individual detour roads; the embankment, excavation, base and paving layers within definable geometric limits (e.g., from station to station, within a single ramp, etc.). Physical locations of activities within definable geometric limits (e.g., from station to station, within a single ramp, individual bents, individual spans, etc.) shall be included in the activity description or shown in activity codes relative to each activity. It shall include submittals and approvals of critical samples, shop drawings, procedures, order lists (pilings for example), or other things that could have a significant schedule impact.

Relatively minor items of work, similar or non-similar, may be grouped together into one activity (or more). Activities to be performed by subcontractors shall be included and identified. The schedule shall show the sequence in which the activities are to be accomplished and their dependency relationships. The pay item quantities associated with each activity shall be included and shall equal the current contract amount.

The duration of activities shall be in whole calendar days and no activity shall have duration of less than one calendar day or more than 30 calendar days. The ending event of the schedule shall be a finish milestone identified as “Contract Completion Date”. Its sole predecessor shall be “Reserved Float”. The sole predecessor of “Reserved Float” shall be “Final Inspection” which shall be a finish milestone and shall have as predecessors all of the activities that must be completed prior to the Department’s final inspection of the work. The duration of “Reserved Float” is the difference between “Final Inspection” and “Contract Completion Date”. “Reserved Float” is defined as that part of the shared float reserved exclusively for the contractor’s use. The contract date for stipulated damages will be adjusted by change order to the beginning date of the activity “Reserved Float”.

The Construction Schedule shall be computer plotted on sheets not larger than 22 inches x 36 inches and shall show a continuous flow of information from left to right with no arrows from right to left and shall be drawn to a time scale of calendar days. The critical path shall be clearly identified. Resource constraints shall be identified, as shall scheduled starts or completions imposed on the schedule by the contractor.

The contractor shall submit color-coded graphics in the required multiple copies.

The contractor shall provide the Department with the means to electronically translate the Construction Schedule data into a configuration that can be read and processed by the Department or its consultants' hardware and Primavera software. If the contractor elects to use SureTrak Project Manager software, the following defaults must be placed: (1) resources shall be non-driving; (2) default activity type shall be "Task"; (3) activity type shall not be "Independent"; (4) duration display style shall be "Day (d)"; (5) float style shall be "Days";

and, (6) dates time format shall be "Don't show time". In both the SureTrak Project Manager and in the Primavera Project Planner (P3) "Back up" menu selection, the contractor will ensure that the option "Remove access list during backup" is checked. In addition, the project must be saved in SureTrak as a "Concentric P3" Type project.

D-24

SUMMARY OF ACTIVITIES

The Summary of Activities shall be a tabulation of all activities shown on the Construction Schedule, and shall accurately reflect the data used in preparation of the Construction Schedule. The summary shall be computer generated and sequenced by activity number.

Each activity shall include as a minimum the following, in calendar days:

a) Activity numbers.

b) Activity description.

c) Estimated duration of activity.

d) Early start.

e) Late start.

f) Constrained start, if constrained.

g) Early finish.

h) Late finish.

i) Constrained finish, if constrained.

j) Status (whether critical).

k) Free float.

l) Total float.

m) Remaining duration and calendar days used.

SUBMITTAL

Prior to the Award of Contract the Single Bidder shall submit to the Chief Construction engineer for approval, in triplicate, a Construction Schedule giving a proposed schedule of operations that provides for completion of the work and a Summary of Activities tabulation.

The Single Bidder shall also submit the Construction Schedule data electronically capable of being processed with the hardware and software being used by the Department or its consultants.

Within 10 calendar days after receipt of the submittal, the Chief Construction engineer and Single Bidder shall meet and review the proposed schedules and tabulations. Any revisions resulting from the review shall be submitted, in triplicate, for approval within 5 calendar days after the meeting.

Failure to have obtained approval of the Construction Schedule and tabulations within 20 calendar days after the Bid Letting, the bid will be considered irregular and will be rejected.

PAYMENT

The Pre-Award CPM Construction Schedule will be provided at no direct pay.

D-25

S.P. SUBLETTING OF CONTRACT (01/26):

Subsection 108.1 of the 2026 LSSRB is amended to include:

In accordance with 108.1 of the Standard Specifications, the following items are designated as "Specialty Items":

202-11-00100 Removal and Disposal of Electrical Equipment (Removal of Existing Service Controller)

202-12-00100 Removal and Storage of Light Pole (Ground Mount) (According to Plans)

202-13-00100 Removal…