Work_Summary_Sheet.pdf

PDF 165 KB Posted

Attached to
CRP BOARDWALK RECONSTRUCTION Federal contract opportunity
Solicitation number
L15PS00485
Issued by
Department of the Interior Bureau of Land Management California Region

About this file

Revised Work Summary Sheet

View the file

Other files for this federal contract opportunity

Other files attached to CRP BOARDWALK RECONSTRUCTION, newest first.
File Type Posted
Sol_L15PS00485_Amd_000002.pdf PDF
Specifications_(2).pdf PDF
Sol_L15PS00485_Amd_000001.pdf PDF
L15PS00485_SF_1442.pdf PDF
Sol_L15PS00485.pdf PDF
Specifications.pdf PDF
Bidschedule.pdf PDF
General_Decision_CA150029.pdf PDF
Drawings.pdf PDF
presolann.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Work Summary Sheet

Cosumnes River Preserve Boardwalk Reconstruction

LLCAC08000-01009-Amended1

Boardwalk Reconstruction Notes

Unless otherwise noted below:

1. Clear vegetative matter along boardwalk alignment per Section 02231 – Clearing and

Grubbing.

2. Establish and maintain horizontal and vertical alignment control of boardwalk, concrete trail and viewing platform.

3. Maintain the material staging area in a neat and orderly fashion.

Stationing

Location

Work

Description

Boardwalk Reconstruction

0+00 Project begins at end of existing concrete trail.

0+00 – 2+08 Demolish existing wooden boardwalk. Construct new boardwalk on existing alignment.

0+76 Centerline of existing boardwalk turnout and bench. Construct new turnout and bench of like dimensions and configuration.

0+98 Angle point in boardwalk centerline.

2+08 End section of new boardwalk construction.

2+08 – 4+15 Existing section of concrete trail. No work to be done. The portion of this concrete trail crossing levee road is 12 inches thick.

4+15 – 9+76 Demolish existing wooden boardwalk. Construct new boardwalk on existing alignment.

5+32 Centerline of existing boardwalk turnout and bench. Construct new turnout and bench of like dimensions and configuration.

5+63 Angle point in boardwalk centerline.

6+64 Angle point in boardwalk centerline.

7+29 Centerline of existing boardwalk turnout and bench. Construct new turnout and bench of like dimensions and configuration.

7+60 Angle point in boardwalk centerline.

8+69 Angle point in boardwalk centerline.

9+76 End section of new boardwalk construction.

9+76 – 12+17 Existing section of concrete trail. The portion of this concrete trail crossing levee road is 12 inches thick.

11+40(+/-) Demolish damaged concrete trail and install new concrete trail beginning at trail painted red and continuing for +/- 78 feet.

12+01 – 12+35 Demolish existing concrete trail and boardwalk. Construct new boardwalk on existing alignment and extend boardwalk an additional 20 feet to point of access to new viewing platform.

12+35 Demolish existing wooden viewing platform and concrete footings.

Construct new viewing platform and concrete footings of like octagonal shape and 50% larger dimension. Refer to Specification Section 02822 –

Boardwalk for salient features. Projects ends at new viewing platform.

Sheet 3 of 7 Total

Work Summary Sheet

LLCAC08000-01009-Amended2

New Boardwalk Construction

Stationing

Location

Work

Description

0+00 Project begins at end of existing concrete trail.

0+00 – 0+30 (+/-) Construct new boardwalk on alignment to be determined in the field. End station to be determined in the field.

0+30 (+/-) Construct new viewing platform and concrete footings of like octagonal shape and dimension as the viewing platform at Station 12+35. Refer to

Specification Section 02822 – Boardwalk for salient features. Projects ends at new viewing platform.