KSD HVAC TAB Specs.pdf

PDF 95 KB Posted

Attached to
RFB-86-24 TAB HVAC Upgrades Kentucky School for the Deaf
Solicitation number
RFB-785-2400000169-1
Issued by
Boyle County, Kentucky

About this file

This document is a specification section for the Testing, Adjusting, and Balancing (TAB) of the HVAC systems for the Kentucky School for the Deaf Acct 540-C9WW-SD09-00-E701 HVAC Renovation and Replacements project. The scope of the TAB work includes the new chiller and cooling tower, all new rooftop HVAC units, energy recovery units, exhaust fans, and terminal/direct heating units in Thomas Gym, Kerr Hall, and Brady Hall. The TAB work will be performed by a certified TAB agency contracted directly by the Owner. The Contractor is responsible for coordinating with the TAB agency, providing access, adjusting equipment as needed, and addressing any deficiencies identified by the TAB agency.

The document outlines the qualifications required of the TAB agency, the testing and balancing procedures to be followed, the reporting requirements, and the responsibilities of the various contractors. Payments for the TAB work will be contingent upon the proper submittal and approval of the final TAB report. Overall, this specification details the standards and requirements for the TAB scope of work as part of the larger HVAC renovation and replacement project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Kentucky School for the Deaf Acct 540-C9WW-SD09-00-E701

HVAC Renovation and Replacements - Thomas Gym, Kerr and Brady Halls

4968-01 TESTING, ADJUSTING AND BALANCING 239600-1

SECTION 239600 - TESTING, ADJUSTING, AND BALANCING

PART 1 – GENERAL

1.1 RELATED DOCUMENTS

A. All Division 22, 23 specification sections, drawings, and general provisions of the Contract apply to work of this section, as do other documents referred to in this section.

1.2 SCOPE OF WORK

A. The Owner will directly contract with a certified testing, adjusting, and balancing (TAB) agency to test, adjust, and balance the plumbing and HVAC systems.

B. This specification section is included herein to assist and inform the Contractor of the standards, requirements and scope of the work to be performed by the Commonwealth’s TAB Contractor.

The Contractor is not responsible for any of the technical or reporting aspects of this work, but is responsible for all coordination, scheduling and assistance required by this section, including any equipment operation, controls coordination, sheave changes, if necessary, and providing access to the work areas, as necessary.

1.3 PREPARATION AND COORDINATION REQUIREMENTS – GENERAL

A. Shop drawings, submittal data, up-to-date revisions, change orders, and other data required for planning, preparation, and execution of the TAB work shall be provided to the TAB Agency no later than 30 days prior to the start of TAB work.

B. System installation and equipment startup shall be complete prior to the TAB Agency’s being notified to begin.

C. The building control system shall be complete and operational. The Building Management

System (sub) contractor shall install all necessary computers and computer programs, and make these operational. Assistance shall be provided as required for reprogramming, coordination, and problem resolution.

D. All test points, balancing devices, identification tags, etc. shall be accessible and clear of insulation and other obstructions that would impede TAB procedures.

E. Qualified installation or startup personnel shall be readily available for the operation and adjustment of the systems. Assistance shall be provided as required for coordination and problem resolution.

1.4 PREPARATION AND COORDINATION REQUIREMENTS – HVAC CONTROLS

A. Written notice shall be submitted through the General Contractor to the Architect-Engineer stating that the Control System is operating and controlling the HVAC System.

B. The Control (sub) contractor shall have entered all data needed for the TAB Agency to begin work.

C. The Control (sub) contractor shall be available to correct any problems that the TAB Agency may encounter with the systems.

D. All costs for additional work by the TAB Agency due to the Contractor’s failure to comply with the above shall be paid by the Contractor and any subcontractor(s) for HVAC controls.

1.5 PREPARATION AND COORDINATION REQUIREMENTS – MECHANICAL

A. Written notice shall be submitted through the General Contractor to the A/E stating that the

HVAC system is operational and ready for the TAB Agency.

B. The Mechanical subcontractor shall have proved all units operational and all air outlets in the full open position.

C. The Mechanical Contractor shall be available to correct any problems that the TAB Agency might have with any equipment or systems.

D. The Mechanical Contractor shall furnish and install any replacement sheaves, pulleys and drive belts required for flow adjustments, as determined by the TAB Agency. Adjustable sheaves shall be selected so that the final adjustment position is in the middle third of the total adjustment range.

E. All costs for additional work by the TAB Agency due to the Contractor’s failure to comply with the above shall be paid by the Contractor and any subcontractor(s) for mechanical work.

1.6 WORK BY TAB AGENCY

A. The work included in the remainder of this section consists of furnishing labor, instruments, and tools required in testing, adjusting and balancing the HVAC systems, as described in these specifications or shown on accompanying drawings. Services shall include checking equipment performance, taking the specified measurements, and recording and reporting the results. This work shall be performed by the TAB Agency under direct contract to the owner. The remainder herein is also for the information of the Contractor and all subcontractors.

B. The items requiring testing, adjusting, and balancing include the

WATER SYSTEMS:

1. Kerr Hall: New chiller, CH-1

2. Brady Hall: New cooling tower CT-1

AIR SYSTEMS

1. Thomas Gym: All new rooftop HVAC units and associated new or existing circulating duct systems, grilles, register and diffusers.

2. Thomas Gym: All new energy recovery units and associated duct systems.

3. Thomas Gym: All new exhaust fans.

4. Thomas Gym: All new terminal and direct heating units.

1. 7 QUALIFICATIONS

A. Agency qualifications: The TAB Agency shall be a current member of a nationally recognized balance organization (“National Organization”). This Organization shall provide the owner with

National Guarantee document certifying the work of the TAB Agency. Acceptable organizations are Associated Air Balance Council (AABC) or National Environmental

Balancing Bureau (NEBB).

1. The selected TAB Agency must provide proof of certification for the total project (air, water, sound, vibration, etc.).

2. The selected TAB Agency shall possess computers, cables, and software needed to operate the building control system. This requires the TAB Agency to be properly licensed and/or trained to run the Control contractor’s software.

1.8 DEFINITIONS, REFERENCES AND STANDARDS

A. All work shall be in accordance with the latest edition of the National Standards, as published by the National Organization affiliated with the TAB Agency.

1.9 SUBMITTALS

A. Qualifications: The TAB Agency shall submit a company resume listing personnel and project experience in air and hydronic system balancing and a copy of the agency’s test and balance engineer (TBE) certificate. Certification in noise, vibration, and air quality shall be submitted as the job requires.

B. Procedures and agenda: The TAB Agency shall submit the TAB procedures and agenda proposed to be used, as well as the certifications for the instruments to be used.

1.10 REPORTS

A. Final TAB Report – The TAB Agency shall submit the final TAB report for review by the engineer. All outlets, devices, HVAC equipment, etc., shall be identified, along with a numbering system corresponding to report unit identification. The TAB Agency shall submit a

“National Project Performance Guaranty” assuring that the project systems were tested, adjusted and balanced in accordance with the project specifications and National Standards.

B. Submit three (3) copies of the Final TAB Report to the Architect- Engineer, and (1) copy to the

Project Manager from the Division of Engineering and Contract Administration.

C. Payments for the TAB work shall be contingent upon the proper submittal and approval of the

TAB reports.

1.11 DEFICIENCIES

A. Any deficiencies in the installation or performance of a system or component observed by the

TAB Agency shall be brought to the attention of the appropriate responsible person. Also notify the mechanical project representative from the Division of Engineering and Contract

Administration.

B. The work necessary to correct items on the deficiency listing shall be performed and verified by the affected contractor before the TAB Agency returns to retest. Unresolved deficiencies shall be noted in the final report.

PART 2 – PRODUCTS

2.1 INSTRUMENTATION

A. All instruments used for measurements shall be accurate and calibrated. Calibration and maintenance of all instruments shall be in accordance with the requirements of the National

Standards. Certifications for instruments to be used shall be submitted as indicated above.

PART 3 – EXECUTION

3.1 GENERAL

A. The specific systems shall be reviewed and inspected for conformance to design documents.

Testing, adjusting and balancing on each identified system shall be performed. The accuracy of measurements shall be in accordance with national Standards. Adjustment tolerances shall be

+10%, -0%, unless otherwise stated.

B. Equipment settings, including manual valve indicators and similar controls and devices shall be marked to show final settings.

C. All information necessary to complete a proper TAB project and report shall be per National

Organization’s standards unless otherwise noted. The descriptions for work required, as listed in this section, are guides to the minimum information needed.

3.2 AIR SYSTEMS

A. The TAB Agency shall verify that all ductwork, dampers, grilles, registers, and diffusers have been installed per design and set in the full open position. The TAB Agency shall perform the following TAB procedures in accordance with the National Standards:

For supply fans:

1. Test and record supply air temperature with space at or near design point temperature.

2. Outside Air – Test and adjust the outside air on applicable equipment using a Pitot-tube traverse. If a traverse is not practical use the mixed-air temperature method if the inside and outside temperature difference is at least 20 degrees Fahrenheit or use the difference between Pitot-tube traverses of the supply and return air ducts.

For exhaust fans:

1. Fan speeds – Test and adjust fan RPM to achieve maximum and design CFM. Confirm proper rotation direction.

2. Current and Voltage – Test and record motor voltage and amperage, and compare data with the nameplate limits to ensure motor is not in or above the service factor.

3. Pitot-tube Traverse – Perform a Pitot-tube traverse of main exhaust ducts to obtain total

CFM.

For diffusers, registers and grilles:

1. Tolerances – Test, adjust, and balance each diffuser, grille, and register to within +10%, -0% of design requirements. Minimize drafts.

2. Identification – Identify the type, location, and size of each grille, diffuser, and register.

This information shall be recorded on air outlet data sheets.

3.3 WET SYSTEMS

A. The TAB Agency shall, as applicable, confirm that all equipment, piping, and coils have been filled and purged; that strainers have been cleaned; and that all balancing valves (except bypass valves) are set full open. The TAB Agency shall perform the following testing and balancing functions in accordance with the National Standards:

For pumps:

1. Test and adjust existing chilled water pumps, existing water-source heat pump loop circulation pumps and cooling tower water circulation pump(s) to achieve maximum or design GPM. Check pumps for proper operation. Confirm proper rotation direction.

Pumps shall be free of vibration and cavitation. Record appropriate gauge readings for final TDH and Block Off/Dead head calculations.

2. Current and Voltage – Test and record motor voltage and amperage, and compare data with the nameplate limits to ensure pump motor is not in or above the service factor.

END OF SECTION 239600