C9WW TAB SPECIAL CONDITIONS.pdf
PDF 145 KB Posted
- Solicitation number
- RFB-785-2400000169-1
- Issued by
- Boyle County, Kentucky
About this file
This document is the Special Conditions for the HVAC Testing, Adjusting, and Balancing (TAB) Services related to the KSD - HVAC Upgrades RFB 97-23 in Danville, Kentucky. The project involves the replacement and upgrade of most HVAC equipment and some distribution and support systems at the KSD Physical Education Facility, Thomas Hall, and the outdoor air-cooled HVAC chiller at Kerr Hall and the closed-circuit evaporative cooler for the Brady Hall closed-loop water source heat pump system. The TAB agency is responsible for completing checkout and startup plans, participating in equipment startup, providing preliminary TAB reports, participating in owner training, and TAB verification. The substantial completion date for the general contractor is November 29, 2023, and the final completion date is December 29, 2023, though the TAB work may need to be completed at each building at different times.
The document outlines the unit prices for the TAB technician, additional trips to the job site, and use of special tools. The TAB agency may submit invoices for up to 90% of the contract amount pending acceptance of the completed work, with the remaining 10% contingent upon final acceptance. Invoicing and change orders are to be emailed to the project manager, and TAB reports are to be uploaded to the project's eCommunications platform.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HVAC TESTING, ADJUSTING & BALANCING SERVICES
KSD - HVAC Upgrades
RFB 97-23
Danville, Kentucky
Account No: 540C9WWSD0900
SPECIAL CONDITIONS 01000 A - 1
DIVISION 1 – GENERAL REQUIREMENTS
SECTION 01000 A - SPECIAL CONDITIONS for TAB Work
Re: KSD HVAC Upgrades
Account #: 540-C9WW-SD09-00
Index:
1. Project Information / Scope
2. Related Documents and Information
3. TAB – Additional Services
4. List of Unit prices
5. Coordination and Participation
6. Substantial and Final Completion Dates
7. Payment
8. Project Directory
1. PROJECT INFORMATION / SCOPE:
A. Project Description: This project involves replacement and upgrade of most HVAC equipment and some of the distribution and support systems at the KSD Physical Education Facility, Thomas Hall, with exception of the relatively new low pressure steam boiler plant. Also included are the replacement of the outdoor, air-cooled, HVAC chiller at Kerr Hall and the closed-circuit evaporative cooler for the Brady Hall closed-loop water source heat pump system. Due to equipment delivery project will be completed in phases.
2. RELATED DOCUMENTS AND INFORMATION:
A. Project Documents (plans and specifications) and related information for this project is available on DECA’s eCommunications web site hosted by Lynn Imaging.
B. After award of the TAB Contract, the successful bidder will receive a “Link” for access to the web site for the above referenced Project.
C. It is the Responsibility of the TAB Agency to review all Project Documents and coordinate their work with the GC (General Contractor), and the Commissioning Agency for the Project.
3. ADDITIONAL SERVICES:
A. The TAB Agency shall include in their Bid the following.
a) Additional Services:
Attend Project Progress Meetings as needed
Un-anticipated Services:
RFB 97-23
SPECIAL CONDITIONS 01000 A - 2
i. Work not anticipated in the Base Bid Documents. This may include repeated testing due to the equipment not being ready for/or passing the initial tests; ad-ditional services requested by the Owner or Engineer. ‘
B. Posting Daily Reports in eComm:
a) The TAB Agency shall document their time spent in Daily Reports Log.
b) TAB Agency shall post their Daily Reports Weekly under workflow “7.2 AE/ Owner Observation
Reports” in eComm (eCommunications) for this Project.
c) The TAB Agency shall indicate in their Project Log which items are repeats of work, not ready, failed, etc, as this time will be back-charged by Change Order from the GC’s Contract.
d) There are no allowances in this project.
4. LIST OF UNIT PRICES:
A. Unit Prices shall include furnishing all labor, materials, supplies, services and all items of cost, and overhead and profit for the Agency and any Subcontractor involved. Unit Prices shall be used uniformly without modification for either additions or deductions.
Description of Work Quantity Unit Price
TEST AND BALANCING TECHNICIAN 1Hour $ /Hour
Additional Trips to Job Site 1Trip $ /Trip
Special Tools 1Hour $________/Hour
5. Coordination and Participation:
C. Coordination with GC and the HVAC Contractor:
a) The TAB Agency is responsible for certain aspects for this project including, but not limited to the following:
i. Completion of Checkout and Start-up Plans
ii. Participation in equipment start-up
iii. Providing draft/pencil copies of preliminary TAB reports as systems complete TAB pro-cedures
iv. Participation in Owner Training
v. Participation in TAB Verification.
6. SUBSTANTIAL AND FINAL COMPLETION DATES:
A. Project Completion dates for the GC (General Contractor):
• Substantial Completion date 11/29/23
• Final Completion date is 12/29/23.
RFB 97-23
SPECIAL CONDITIONS 01000 A - 3
• However due to equipment deliveries TAB may be need to be completed at each building at different times.
B. Project completion date for the TAB Contractor:
• Final Completion is 12/29/23
C. The TAB Agency is responsible for coordinating their work with the project schedule through the Pro-ject’s General and Mechanical Contractors and the Commissioning Agency.
7. PAYMENT:
A. The TAB Agency may submit invoicing for partial payments up to 90% of the contract amount pending the acceptance of the completed work by the A/E Project Design Engineer.
B. The TAB Agency may submit invoicing for remaining 10% of their contract contingent upon final ac-ceptance of the completed work.
A. Invoicing and change orders should be emailed to kristi.sharp@ky.gov. Reports should be loaded in eCommunications.
a) To post a Report go to your Dashboard in eComm; find this Project by RFB #; pick “Item Logs” (from the blue bar); pick “6.12 Invoice for TAB Services” from the dropdown menu; post your report, and then pick “save and submit to next step”.
b) The TAB Report will then go to the Project Engineer for either: review, comments and revert back one step, or approval.
c) The TAB Agency will receive payment, after acceptance of the TAB Report by those in the eComm Workflow.
8. PROJECT DIRECTORY:
Agency:
Project Manager: Walter Hulett
KDE
Walter.hulett@education.ky.gov
Engineer:
GRW
Bill Brewer Phone 859 223-3999 bbrewer@grwinc.com
Commissioning Agent
FCG
Jim Magee
(859) 221-5838 jim@facomgrp.com
RFB 97-23
SPECIAL CONDITIONS 01000 A - 4
General Contractor (GC):
Marrillia Brian Stakelin Phone (859) 420-4729 bstakelin@marrillia.com
Mechanical Contractor:
Prewitt Mechanical Contractors, Inc.
David Prewitt Phone 859-255-9769 david.prewitt@prewittmechanical.com
Controls Contractor:
Trane
Owner Project Manager(s):
Tony Yates Division of Engineering and Contract Administration Bush Building 403 Wapping Street Frankfort, KY 40601 Mobile: (502) 229-9759 Tony.yates@ky.gov mailto:bstakelin@marrillia.com mailto:Tony.yates@ky.gov