This document is Addendum 1 for KEYS Bid 17-25, which pertains to Transmission Line Station Post Insulator Replacement. The addendum contains a question and answer section addressing the bid bond documentation, specifically clarifying the preferred bid bond form as AIA Document A310™–2010. No additional details about the project scope, timeline, or specifications are provided in this single-page document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
KEYS BID 17-25 SPECIFICATIONS FOR TRANSMISSION LINE STATION POST
INSULATOR REPLACEMENT
Addendum 1
Questions and Answers:
1. Is the standard form sufficient for the bid bond, or do you have a specific bid form that our bonding company needs to use?
AIA Document A310™–2010 is preferred.