JUN 2026 Equipment Only Consolidation Schedule

This document is a consolidation schedule outlining the procurement timeline for equipment-only acquisitions across all modalities. The schedule establishes a structured process beginning with requirements submission on June 30, 2026, followed by publication of a pre-solicitation notice on August 5, 2026, and posting of requirements and Request for Offers (RFO) on August 12, 2026. The National Acquisition Center (NAC) will manage vendor communications, with a deadline of August 26, 2026, for vendors to submit equipment questions, followed by published responses via amendment on September 16, 2026.

Vendor offer submission is due October 14, 2026, with customers receiving vendor offers via shared drive by October 21, 2026. Customers must submit technical evaluations and best value selections by November 12, 2026. The NAC assigns contracting officer (CO) workload on November 18, 2026, with a goal to award delivery orders by February 16, 2027, representing a 90-day window from workload assignment. All dates are identified as estimates subject to change. No specific federal contract vehicle, pricing terms, or set-asides are detailed in this schedule.

View the file

Other files

File Type Posted
Pre-Solicitation Notice - JUN 2026 EQ Only Consolidation.pdf PDF
36A79726Q0011.pdf PDF
EQ JUN 2026 CONSOLIDATION - Schedule of Line Items with QA Template-.xlsx XLSX spreadsheet
OPPORTUNITIES-DESCRIPTION 02.docx DOCX document
36A79726Q0011.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

JUN 2026 Equipment Only Consolidation Schedule

Dates* Milestone – All Modalities

6/30/2026 Requirements due to the NAC in FORCE

8/05/2026 Publish Pre-Solicitation Notice

8/12/2026 Post Requirements and Request for Offers (RFO)

8/26/2026 Vendors to submit Equipment Questions to NAC

9/16/2026 NAC Published Responses to Vendor Questions via Amendment

10/14/2026 Vendors to Submit Offers to NAC

10/21/2026 Customers Receive Vendor Offers via the Shared Drive

11/12/2026 Customers Submit Technical Evaluations (Best Value Selections)

11/18/2026 NAC Assigns CO Workload

2/16/2027 Goal to Award Delivery Orders (90 Days from Assignment)