JUN 2025 Equipment Only Consolidation Schedule.pdf

PDF 124 KB Posted

Attached to
6525--JUN 2025 Equipment Only Consolidation Federal contract opportunity
Solicitation number
36A79725Q0010
Issued by
Department of Veterans Affairs National Acquisition Center

About this file

The document is a JUN 2025 Equipment Only Consolidation Schedule from the Department of Veterans Affairs National Acquisition Center (NAC), outlining a detailed timeline for an equipment procurement process. Key milestones include requirements submission by 6/30/2025, pre-solicitation notice publication on 7/30/2025, and a Request for Offers (RFO) posting on 8/6/2025. Vendors will have opportunities to submit equipment questions by 8/20/2025, with NAC publishing responses via amendment on 9/10/2025.

The procurement schedule indicates vendors must submit offers to NAC by 10/8/2025, with customers receiving vendor offers via shared drive on 10/15/2025. Technical evaluations are due 11/5/2025, and the NAC will assign Contracting Officer (CO) workload on 11/12/2025. The goal is to award delivery orders by 2/10/2026, approximately 90 days after workload assignment. The document prominently notes that all dates are estimates and subject to change, providing flexibility in the procurement timeline.

View the file

Other files for this federal contract opportunity

Other files attached to 6525--JUN 2025 Equipment Only Consolidation, newest first.
File Type Posted
Pre-Solicitation Notice - JUN 2025 EQ Only Consolidation.docx DOCX document
688B50016-740B50040.zip ZIP file
600B40011-630B50023.zip ZIP file
Copy of JUN 2025 EQ Consolidation - Schedule of Line Items_HTM Edits.xlsx XLSX spreadsheet
632B51008-662B50021.zip ZIP file
501B50014-593B50031.zip ZIP file
36A79725Q0010.docx DOCX document
663B53008-678B52009.zip ZIP file
402B51210-499B59050.zip ZIP file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

JUN 2025 Equipment Only Consolidation Schedule

Dates* Milestone – All Modalities

6/30/2025 Requirements due to the NAC in FORCE

7/30/2025 Publish Pre-Solicitation Notice

8/6/2025 Post Requirements and Request for Offers (RFO)

8/20/2025 Vendors to submit Equipment Questions to NAC

9/10/2025 NAC Published Responses to Vendor Questions via Amendment

10/8/2025 Vendors to Submit Offers to NAC

10/15/2025 Customers Receive Vendor Offers via the Shared Drive

11/5/2025 Customers Submit Technical Evaluations (Best Value Selections)

11/12/2025 NAC Assigns CO Workload

2/10/2026 Goal to Award Delivery Orders (90 Days from Assignment)

*Dates are estimates and are subject to change