Judicial Center Temporary Generator Connections.pdf
PDF 2 MB Posted
- Attached to
- Temporary Generator Connections
- Solicitation number
- IFB 2026-075
- Issued by
- Union County, North Carolina
About this file
This is a sealed bid invitation for construction work issued by Union County, North Carolina's Department of Public Works for the Judicial Center Temporary Generator Connections project located at 400 N. Main Street, Monroe, NC 28112. The scope of work requires contractors to provide and install a Manual Transfer Switch (MTS) to interface with the existing permanent generator, enabling a trailered backup generator to connect via camlock connections and power existing loads if the permanent generator fails to start. A non-mandatory pre-bid conference and site visit is scheduled for October 13, 2026, at 11:00 AM at the project site. Sealed bids are due November 12, 2026, at 10:00 AM at Union County Procurement and Contract Management, 610 Patton Avenue, Monroe, NC 28110. The bid must be received by the specified time or will not be accepted. Bidders must complete all work within 45 calendar days from receipt of the Notice to Proceed. The contract will be awarded to a single prime contractor on a lump sum basis, with the successful bidder required to submit five original copies of the Small Construction Agreement with wet ink signatures and original corporate seals.
Bids must include 5 percent bid security in the form of a bid bond, cash, cashier's check, or certified check, and remain valid for 90 days after opening. The bidder's North Carolina contractor license number must be designated on the sealed envelope. Liquidated damages are assessed at $250 per calendar day for delays beyond the 45-day completion period. Bidders must comply with E-Verify requirements and provide non-collusion affidavits. Comprehensive insurance requirements include workers' compensation, commercial general liability ($2,000,000 aggregate), commercial automobile liability ($1,000,000), professional liability ($1,000,000), pollution liability ($1,000,000), cyber liability ($1,000,000), and abuse and molestation insurance ($300,000). Union County is eligible for sales and use tax refunds on materials becoming permanent parts of the construction, requiring contractors to submit certified tax documentation with each payment request. The project engineer is Progressive Architecture Engineering, P.C., with procurement contact Kyle Hodge at Kyle.Hodge@unioncountync.gov or (704) 283-3631. Bidding documents are available electronically or in printed form through Duncan-Parnell's bid room at https://www.bidroom.duncan-parnell.com for a $50 PDF download or $67 for printed and digital sets, plus applicable taxes and shipping.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U N IO N C OU N T Y, N OR T H C A R OL I N A
D E P A R TM E N T O F P U B L I C WO R K
Invitation for Bid No. 2026-075
Union County Judicial Center Temporary Generator Connections
RAM
Due Date: November 09, 2026 Time: 10:00 AM Local Time Receipt Location: Union County Procurement and Contract Management 610 Patton Avenue Monroe, NC 28110
Non-Mandatory Pre-Bid Conference and Site Visit
Due Date: October 13, 2026 Time: 11:00 AM Local Time Location: Union County Judicial Center
400 N. Main Street Monroe, NC 28112
Procurement Representative:
Kyle Hodge Senior Procurement Specialist Procurement and Contract Management
(704) 283-3631 Kyle.Hodge@unioncountync.gov
Prepared by:
Dane Stivers, P.E.
Progressive Architecture Engineering, P.C.
1801 N Graham St, Charlotte, NC 28206
DOCUMENT 00 01 01 – PROJECT TITLE PAGE
Progressive AE IFB 2026-075 96520013 1 Union County Judicial Center Construction Documents August 04 2026 00 01 01 Temporary Generator Connections
PROJECT MANUAL – 100% CONSTRUCTION DOCUMENTS
IFB 2026-075
Union County Judicial Center Temporary Generator Connections 400 N. Main Street
Engineer Project No. 96520013
OWNER
UNION COUNTY, NORTH CAROLINA
500 N. MAIN STREET
MONROE, NORTH CAROLINA
Engineer Progressive Architecture Engineering, P.C.
1801 N. Graham Street Charlotte, NC 28206
(616) 988-4804
CONSTRUCTION DOCUMENTS 08.04.2026
DOCUMENT 00 01 07 – SEALS PAGE
3 Union County Judicial Center
Progressive AE 96520013 Construction Documents August 04 2026 00 01 07 Temporary Generator Connections
ELECTRICAL
ENGINEER
This item has been electronically signed and sealed by Dane A. Stivers using a Digital Signature and date. Printed copies of this document are not considered signed and sealed and the signature must be verified on any electronic copies.
09/03/2026 3:52:28 PM
DOCUMENT 00 01 10 - TABLE OF CONTENTS
Construction Documents August 04 2026 00 01 10 Temporary Generator Connections
PROJECT MANUAL – 100% CONSTRUCTION DOCUMENTS
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 01 Project Title Page 00 01 07 Seals Page 00 01 10 Table of Contents 00 01 15 List of Drawing Sheets 00 11 13 Advertisement for Bids 00 11 16 Invitation to Bid 00 25 00 Pre-Bid Meetings 00 41 13 Bid Form – Stipulated Sum 00 43 13 Bid Security Form 00 43 28 Tax Rebate Form 00 45 19 Non-Collusion Affidavit 00 52 00 Agreement Forms 00 55 00 Notice to Proceed 00 62 00 Certificate of Insurance
DIVISION 01 – GENERAL REQUIREMENTS
01 10 00 Summary 01 26 00 Contract Modifications Procedures 01 29 00 Payment Procedures 01 31 00 Project Management and Coordination 01 32 00 Construction Progress Documentation 01 33 00 Submittal Procedures 01 40 00 Quality Requirements 01 42 00 References 01 50 00 Temporary Facilities and Controls 01 60 00 Product Requirements 01 73 00 Execution 01 73 29 Cutting and Patching 01 74 19 Construction Waste Management and Disposal 01 77 00 Closeout Procedures 01 78 23 Operation and Maintenance Data 01 78 39 Project Record Documents 01 79 00 Demonstration and Training
DIVISION 26 – ELECTRICAL
26 05 19 Low Voltage Electrical Power Conductors and Cables 26 05 26 Grounding and Bonding for Electrical Systems 26 05 33.13 Conduit for Electrical Systems 26 05 53 Identification for Electrical Systems 26 36 00 Transfer Switches
END OF TABLE OF CONTENTS
DOCUMENT 00 01 15 – LIST OF DRAWING SHEETS
Construction Documents August 04 2026 00 01 15 Temporary Generator Connections
1.1 LIST OF DRAWINGS
A. Drawings: Drawings consist of the drawings listed on the SHEET INDEX page of the separately bound drawing set dated 08/04/2026, as modified by subsequent Addenda and Contract modifications.
E001 Electrical Plan, Riser, Notes and Abbreviations 08-04-2026
END OF DOCUMENT 00 01 15
DOCUMENT 00 11 13 - ADVERTISEMENT FOR BID
Construction Documents August 04 2026 00 11 13 Temporary Generator Connections
UNION COUNTY, NORTH CAROLINA
Union County Judicial Center Temporary Generator Connections
ADVERTISEMENT FOR BIDS
Sealed Bids for Union County Judicial Center Temporary Generator Controls will be received by Union County Procurement and Contract Management, 610 Patton Avenue, Monroe, North Carolina 28110 until 10:00 AM local time on November 12, 2026, at which time the Bids received will be publicly opened and read. Late bids will not be accepted.
If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid shall be enclosed in a separate package plainly marked on the outside with the notation “BID ENCLOSED – 2026-075” and shall be addressed to Union County Procurement and Contract Management, Attn: Kyle Hodge, 610 Patton Avenue, Monroe, NC 28110.
A Non-Mandatory Pre-Bid meeting will be held on October 13, 2026, at 11:00 AM local time at 400 N. Main Street, Monroe, NC 28112. Attendance at this meeting is strongly encouraged.
Scope of Work: Provide and install a Manual Transfer Switch (MTS) to interface with the existing permanent generator. In the event that the permanent generator doesn’t start, a trailered generator can be brought in, hooked up to the MTS via camlock connections and power the existing generator loads.
Bids will be received for a single prime Contract. Bids shall be on a lump sum basis as set forth in the Bid Form.
All questions about the meaning or intent of the Bidding Documents are to be submitted in writing to the Procurement contact person listed on the cover page (Kyle.hodge@unioncountync.gov). Deadline for questions is 5:00 PM local time on October 20, 2026. Questions will be addressed via Addenda no later than 7 days prior to bid date.
The Issuing Office for the Bidding Documents is:
Union County Procurement and Contract Management 610 Patton Avenue Monroe NC 28110 Kyle Hodge Kyle.hodge@unioncountync.gov
(704) 283-3631
Prospective Bidders may examine the Bidding Documents at Union County Procurement and Contract Management at 610 Patton Avenue, Monroe, North Carolina on Mondays through Fridays between the hours of 8:00 AM and 5:00 PM and may obtain copies of the Bidding Documents from the Issuing Office as described below.
Bidding Documents are available in electronic or printed form from Duncan-Parnell via their bid room https://www.bidroom.duncan-parnell.com. Registration with Duncan-Parnell is required to obtain the bid documents.
There is no charge for registration. Printed hard copies of the Bidding Documents can be ordered and shipped for an additional fee, which will depend on the number of sets, size of Drawings, applicable taxes, and shipping method selected by the prospective Bidder. The approximate costs of the Bidding Documents and shipping are non-refundable, and are as follows:
• Download (PDF) $ 50.00 plus tax
• Printed Set and Digital Set $ 67.00 plus tax https://www.bidroom.duncan-parnell.com/
DOCUMENT 00 11 13 - ADVERTISEMENT FOR BID
96520013 2 Union County Judicial Center
Partial sets of Bidding Documents will not be available from the Issuing Office. Neither Owner nor Engineer will be responsible for full or partial sets of Bidding Documents, including Addenda if any, obtained from sources other than the Issuing Office or Ducan-Parnell.
Bidders must have a license to do work as a contractor in the State of North Carolina, as set forth under Article 1 chapter 87 of the North Carolina General statutes. The bidder’s North Carolina Contractor license number shall be designated on the outside of the sealed envelope containing the Bid.
Bidders are required to provide a non-collusion affidavit, as set forth in the bidding documents.
Union County reserves the right to reject any or all bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner further reserves the right to reject the Bid and Bidder whom they find, after reasonable inquiry and evaluation, to not be responsible. Owner may also reject the Bid and Bidder if the Owner believes that it would not be in the best interest of the Project to make an award to that Bidder. Owner also reserves the right to waive all informalities and technicalities not involving price, time, or changes in the Work and to negotiate, as allowed by law, contract terms with the Successful Bidder.
Union County encourages good faith effort outreach to small business entities.
END OF DOCUMENT 00 11 13
DOCUMENT 00 11 16 – INVITATION TO BID
Construction Documents August 04 2026 00 11 16 Temporary Generator Connections
1.
1.1 PROJECT INFORMATION
A. Notice to Bidders: Bidders are invited to submit bids for Project as described in this document.
1.2 Related Sections:
A. 00 11 13 Advertisement for Bids B. 00 21 00 Instructions to Bidders C. 00 25 00 Pre-Bid Meetings D. 00 41 13 Bid Form – Stipulated Sum E. 00 43 13 Bid Security Form F. 00 45 19 Non-Collusion Affidavit G. 00 45 36 E-Verify Affidavit
1.3 Project Identification:
1. Name: Union County Judicial Center Temporary Generator Connections
2. Address: 400 N. Main Street
Monroe, NC 28112
3. Designer: Progressive AE
Name: Dane Stivers Address: 1801 North Graham Street, Suite 200 Charlotte, NC 28206 Phone Number: (704) 731-8068
4. Owner: Union County, North Carolina
a. The Owner designates persona as its representative and a Point of Contact for this Bid.
Bidders shall restrict all contact and direct all questions regarding this Bid, including questions regarding terms and conditions, and technical specifications, to the Procurement Point of Contact listed below in writing (via email) no later than 10 days prior to the Bid Opening date.
b. Owner’s Point of Contact:
Kyle Hodge Senior Procurement Specialist Union County Procurement and Contract Management Department 610 Patton Avenue Monroe, NC 28110 704.283.3631 Kyle.hodge@unioncountync.gov
1.4 SUMMARY
A. Scope: Provide and install a Manual Transfer Switch (MTS) to interface with the existing permanent generator. In the event the permanent generator doesn’t start, a trailered generator can be brought in, hooked up to the MTS via camlock connections and power the existing generator loads.
B. Designer / Engineer Identification: 96520013
1. Project Designer: Progressive AE
2. Owner: Union County, North Carolina
C. The project will be constructed in one phase.
D. Construction Contract: Bids will be received for the following work:
1. November 12, 2026, at 10:00 AM
1.5 BID SUBMITTAL AND OPENING
A. Owner will receive sealed bids until the bid time and date at the location indicated within the section
00 11 13 Advertisement for Bidders for Bid IFB 2026-075.
DOCUMENT 00 11 16 – INVITATION TO BID
Construction Documents August 04 2026 00 11 16 Temporary Generator Connections
1.6 BID SECURITY
A. Bid security shall be submitted with each bid in the amount of 5 percent of the bid amount. No bids may be withdrawn for a period of 90 days after opening. Owner reserves the right to reject any and all bids to waive informalities and irregularities.
1.7 DOCUMENTS
A. Online Procurement and Contracting Documents. Complete sets of Bidding Documents can be obtained from the Issuing Office as described within the section 00 11 13 Advertisement for Bidders for Bid IFB 2026-075
1.8 Time of completion and liquidated damages
A. Bidders shall begin the Work on receipt of Notice to Proceed and shall complete the Work within
45 calendar days. Work is subject to liquidated damages of $ 250.00 per day.
1.9 BIDDERS QUALIFICATIONS
A. Bidders must be properly licensed under the laws governing their respective trades and be able to procure and maintain minimum insurances listed in Exhibit A of the Small Construction Agreement.
END OF DOCUMENT 00 11 16
DOCUMENT 00 25 00 – PRE BID MEETINGS
Construction Documents August 04 2026 00 25 00 Temporary Generator Connections
1.1 SUMMARY
A. A Pre-Bid Meeting will be held to answer questions of the designer potential bidders deem important to submitting a proposal.
1.2 PROJECT CONDITIONS
A. A non-mandatory pre-bid meeting will be held at Union County Judicial Center, 400 N. Main Street, Monroe NC 28112, on October 13, 2026, at 11:00 AM local time. Attendance is not required however it is strongly encouraged.
B. The designers for this project which comprise the scope of work will be in attendance.
1. Progressive AE
END OF DOCUMENT 00 25 00
DOCUMENT 00 41 13 – BID FORM STIPULATED SUM
BID INFORMATION
Name of Bidder:
Date:
Project Name: Union County Judicial Center Temporary Generator Connections
Owner: Union County, North Carolina
Owner Project Number: IFB 2026-075
Designer: Progressive Architecture Engineering, P.C.
Designer Project Number: 96520013
CERTIFICATIONS OF BASE BID
The undersigned Bidder hereby declares that he has carefully investigated the scope of work and having thoroughly familiarized himself with the Contract Documents relative hereto and has read all special provisions furnished prior to the opening of the bids; that he has satisfied himself relative to the work to be performed.
The bidder further declares that he and his subcontractors have fully complied with NCGS 64, Article 2 in regard to E-Verification as required by N.C. General Statute 143-129(j). The bidder agrees to hold the proposed bid price for 90 days.
The bidder proposes and agrees if this proposal is accepted, to contract with Union County Government, in the form of contract specified, to provide all necessary labor, equipment, materials, machinery, tools, apparatus, transportation, services, fees, permits, etc., to complete the construction of Union County Judicial Center Temporary Generator Connections all in accordance with the aforementioned Contract Documents to the full and entire satisfaction of Union County Government, with definite understanding that no money will be allowed for extra work except for the lump sum of:
Provide 5% of the base bid price as an Owner contingency allowance and provide a Total Base Bid Price. Any funds not used from this allowance will be returned to the Owner by deduct change order.
A) BASE BID PRICE:
________________________________________________________Dollars ($__________________).
B) OWNERS CONTINGENCY:
________________________________________________________Dollars ($__________________).
C) TOTAL BASE BID PRICE WITH OWNER CONTINGENCY (A+B=C):
Dollars ($ ).
SUB-CONTRACTOR LIST (if applicable):
The following shall execute subcontracts with the Bidder for the portion of the work indicated (if in the scope of work):
Specialty Work Sub-Contractor (Name & License No.):
License No.
TIME OF COMPLETION
The undersigned Bidder proposes and agrees hereby to commence the Work of the Contract Documents on a date specified in a written Notice to Proceed to be issues by Owner and shall fully complete the Work within Forty-Five [45] calendar days.
LIQUIDATED DAMAGES:
The undersigned further agrees, stipulates, and fixes as Liquidated Damages if delayed, but not as a penalty, the sum of Two Hundred Dollars [$250.00] per calendar day that the undersigned shall pay the Owner for each calendar day or part thereof that expires after the date specified for the substantial completion of the work and until the Work is Substantially complete. By bidding, the undersigned hereby agrees to be responsible for liquidated damages.
BID SECURITY:
Accompanying this proposal is a bid security five percent (5%) of the Total Bid Price Sum in accordance with Instructions to Bidders in the form of (check one):
⬜ Bid Bond (AIA Document A310-2010), or
⬜ Cash, or
⬜ Cashier’s Check, or Certified Check.
RECIEPT OF ADDENDA:
The undersigned acknowledges receipt of the following addenda which will be considered as part of the contract Documents:
96520013 3 Union County Judicial Center
Addendum No. Dated Addendum No. Dated
Addendum No. Dated Addendum No. Dated
CONTRACTOR’S LICENSE:
The undersigned further states that it is a duly licensed contractor for the proposed work in the State of North Carolina, and that all fees, permits, etc. pursuant to submitting this proposal have been paid in full.
ACKNOWLEDGEMENT AND REPRESENTATIONS:
If notice of acceptance of this bid is given to the undersigned within 90 days after the date of opening of bids, or any time thereafter before this bid is withdrawn, the undersigned will execute and deliver an Agreement in the prescribed form promptly after is has been presented to him for signature
The undersigned bidder certifies that neither he/she, nor any official, agent or employee has entered into any agreement, participated in any collusion, or otherwise taken any action which is in restraint of free competitive bidding in conjunction with this bid. The person signing this bid form represents that he/she has full authority and representative capacity to execute this Bid Form in the capacity indicated below.
The undersigned bidder agrees that they are expected to act as Project Expediter and coordinate work of all other contractors.
The firm signing this bid and registered under that name is legally qualified to perform all work included in the scope of the contract as determined by the State of North Carolina, in granting the registration.
PROPOSAL SIGNATURE:
Respectfully submitted this day of , 20 .
(Name of firm or corporation making bid)
By:
Signature and Typed Name Title:
Address of Bidder:
Email Address: ______________________________________________
Bidders N.C. Contractor License No.
Type of License:
Limitations:
96520013 4 Union County Judicial Center
Attest:
By:
Title:
END OF DOCUMENT 00 41 13
DOCUMENT 00 43 13 – BID SECURITY FORM
1.1 GENERAL CONDITIONS
A. The required Bid Security form for the Project is either Bid Bond (AIA Document A310-2010), Cash or Cashier’s Check, or Certified Check.
B. Copies of AIA standard forms may be obtained from:
1. American Institute of Architects, Charlotte, NC: 704.377.3610.
2. Online at https://aiacontracts.com/contract-documents/18151-bid-bond
END OF DOCUMENT 00 43 13
https://aiacontracts.com/contract-documents/18151-bid-bond
DOCUMENT 00 43 28 – TAX REBATE FORMS
Progressive AE 96520013 Construction Documents August 04 2026 00 43 28
IFB 2026-075
Union County Judicial Center
Temporary Generator Connections
Instructions for Completing Certificate for North Carolina Sales Tax Form
Union County may apply for a refund of all sales and/or use taxes paid in North Carolina by the County’s contractors on purchases of building materials, supplies, fixtures and equipment which become a part of or are annexed to any building or structure being erected, altered or repaired under contract with the County. Contractors shall include and must pay all other taxes imposed by governmental authorities which are applicable to the contract work. Examples of property on which sales and use tax has been paid by the contractor and for which the contractor will not be reimbursed by the County are scaffolding, forms for concrete, fuel for the operation of machinery and equipment, tools, equipment repair parts and equipment rentals, blueprints, etc, or any other items which do not become a part of or are not annexed to the building or structure being erected, altered, or repaired.
Please submit with this form invoices (or copies of invoices) from vendors covering the items purchased. This form should still be submitted as “0” if no sales tax was paid for the period covered.
Requests for sales tax reimbursements should be filed with each request for contract payment.
Project or Contract Number: The name of the project, or the County Contract Number.
Date: The date the form was completed.
Trade: Your trade, e.g., electrical, plumbing, concrete contractor, etc.
Contractor: The name of your company.
Invoice Date: The date the materials were purchased.
Invoice Number: The vendor's invoice number.
Name of Vendor: The vendor's name.
Description of Materials: The type of materials purchased, e.g., concrete, nails, roofing material, etc.
Item Cost: The cost of the item(s) before any taxes are added.
State Tax: The North Carolina State tax, currently 4.75% of the item cost.
County Tax: The County tax, currently 2% of the item cost.
Total Invoice: The sum of the Item Cost, State Tax, and County Tax.
County Name: County where material was purchased and sales tax paid, e.g., Mecklenburg, Union, Cabarrus, etc. The owner or an officer of the company must certify that the statement is correct. The signature should also be notarized.
Progressive AE 96520013 Construction Documents August 04 2026 00 43 28
IFB 2026-075
Union County Judicial Center
Temporary Generator Connections
Page ______ of ______.
Certificate for North Carolina Sales Tax Trade: __________________________________________________________________________
Contractor: ______________________________________________________________________
Project or Contract Number: _________________________________________________________
Date: ___________________________________________________________________________
Invoice Date
Invoice Number Name of Vendor Description of Materials Item Cost State Tax
County Tax
Total Invoice
County Name
Totals:
NOTE: Last page must be the certified page.
Page _____of _____.
Progressive AE 96520013 Construction Documents August 04 2026 00 43 28
IFB 2026-075
Union County Judicial Center
Temporary Generator Connections
Certificate for North Carolina Sales Tax Trade: __________________________________________________________________________
Contractor: ______________________________________________________________________
Project or Contract Number: _________________________________________________________
Date: ___________________________________________________________________________
Invoice Date
Invoice Number Name of Vendor Description of Materials Item Cost State Tax
County Tax
Total Invoice
County Name
Totals:
This is to certify that the above materials purchased on the invoices listed were used in the construction of the ________________________________________ and that the Sales Tax listed (State and County) is not included on the monthly estimate for contract payment or any other certificate for North Carolina sales tax.
Further, that the items listed are annexed to, affixed to, or in some manner have become a part of the building or structure being erected, altered or repaired.
Certified to be correct by: _____________________________________________________ Owner or Officer of Company
Sworn to and Subscribed before me this _______day of_________________20_______
________________________________________ (SEAL)
Notary Public
My Commission Expires:___________________
DOCUMENT 00 45 19 – NON-COLLUSION AFFIDAVIT
1 Union County Judicial Center
Progressive AE 96520013 Construction Documents August 04 2026 00 45 19 Temporary Generator Connections
NON-COLLUSION AFFIDAVIT
STATE OF NORTH CAROLINA
COUNTY OF UNION
I , being first duly sworn, deposes and says that:
1. He/She is the of , the Bidder that has submitted the attached Bid;
2. He/She is fully informed respecting the preparation and contents of the attached Bid and of all pertinent circumstances respecting such Bid;
3. Such Bid is genuine and is not a collusive or sham bid;
4. Neither the said Bidder nor any of its officers, partners, owners agents, representatives, em-ployees or parties of interest, including this affiant, has in any way colluded, conspired, con-nived or agreed, directly or indirectly, with any other bidder, firm or person to submit a col-lusive or sham bid in connection with the contract for which the attached Bid has been sub-mitted or to refrain from bidding in connection with such contract, or has in any manner, di-rectly or indirectly, sought by agreement or collusion or communication or conference with any other bidder, firm or person to fix the price or prices in the attached bid or of any other bidder, or to fix any overhead, profit or cost element of the bid price of any other bidder or to secure through collusion, conspiracy, connivance or unlawful agreement any advantage against the Owner or any person interested in the proposed contract; and
5. The price or prices quoted in the attached Bid are fair and proper and are not tainted by any collusion, conspiracy, connivance or unlawful agreement on the part of the Bidder or any of its agents, representatives, owners, employees, or parties in interest, including this affiant.
TITLE
Subscribed and sworn before me, this _______day of ________________, 20____
Notary Public
My Commission Expires _______________________________
END OF DOCUMENT 00 45 19
DOCUMENT 00 45 36 – E-VERIFY AFFIDAVIT
1 Union County Judicial Center
Progressive AE 96520013 Construction Documents August 04 2026 00 45 36 Temporary Generator Connections
STATE OF NORTH CAROLINA
AFFIDAVIT
UNION COUNTY
NOW COMES Affiant, first being sworn, deposes and says as follows:
1. I, being duly authorized by and on behalf of ______________________________ (“Contractor”), have bid on an agreement with Union County, North Carolina (“Union”)
2. As part of my duties and responsibilities pursuant to said agreement, I attest that I am aware of and in compliance with the requirements of E-Verify, Article 2 of Chapter 64 of the North Carolina General Statutes, to include (mark which applies):
___ After hiring an employee to work in North Carolina, I verify the work authorization of said employee through E-Verify and retain the record of the verification of work authorization while the employee is employed and for one year thereafter; or
___ I employ fewer than twenty-five (25) employees in the State of North Carolina.
3. As part of my duties and responsibilities pursuant to said agreement, I attest that to the best of my knowledge any subcontractors employed as a part of this agreement are in compliance with the requirements of E-Verify, Article 2 of Chapter 64 of the North Carolina General Statutes, to include (mark which applies):
___ After hiring an employee to work in North Carolina, the subcontractor verifies the work authorization of said employee through E-Verify and retains the record of the verification of work authorization while the employee is employed and for one year thereafter; or
___ The subcontractor employs fewer than twenty-five (25) employees in the State of North Carolina. Specify subcontractor: ____________________________________________
This the _____ day of ________________, 20___.
Affiant
Printed Name
Sworn to and subscribed before me, this the _____ day of ________________, 20____.
[OFFICIAL SEAL]
_____________________, Notary Public
My Commission Expires: _______________
DOCUMENT 00 45 36 – E-VERIFY AFFIDAVIT
2 Union County Judicial Center
Progressive AE 96520013 Construction Documents August 04 2026 00 45 36 Temporary Generator Connections
END OF DOCUMENT 00 45 19
DOCUMENT 00 52 00 - AGREEMENT FORMS
Construction Documents August 04 2026 00 52 00 Temporary Generator Connections
1.1 FORM OF AGREEMENT
A. The following form of Owner/Contractor Agreement shall be utilized for the Project:
1. Small Construction Agreement, sample attached at end of section.
B. By submitting a bid, the Respondent acknowledges that it has reviewed Union County’s Small Construction Agreement and has no issue with agreeing to terms.
C. Union County requires the successful bidder to submit five, (5) original agreement forms which shall be undated at the time of submission to the County. Forms will be dated by the County upon execution of the agreements.
D. Union County requires the successful bidder to submit each copy with original wet ink signature, and original wet or raised corporate seal.
END OF DOCUMENT 00 52 00
Construction Documents August 04 2026 Temporary Generator Connections
STATE OF NORTH CAROLINA
AGREEMENT
COUNTY OF UNION
1. AGREEMENT. This agreement (“Agreement”) is entered into on ___________________________, by and between UNION COUNTY, a political subdivision of the State of North Carolina (“Union”), and [Contractor’s full legal name], (“Contractor”), whose business address is _______________________________________.
2. INDEPENDENT CONTRACTOR. Contractor shall be an independent contractor in all its activities pursuant to this Agreement. Neither Contractor nor any of its employees are to be considered Union's employee or agent for any purpose including, but not limited to, the accrual of any employee benefits. Contractor is not authorized to represent Union or otherwise bind Union in any dealings between Contractor and third parties. Any employees furnished by Contractor under this Agreement shall be deemed to be Contractor's employees exclusively.
3. SCOPE OF THE WORK. Contractor shall furnish all labor, equipment, tools, materials, supplies, transportation, tests and supervision required to complete in a workmanlike manner the work described in the IFB 2026-075 Union County Judicial Center Temporary Generator Connections, which is attached hereto and incorporated herein by reference (“Work”).
Union is not financially committed by this agreement to purchase any minimum amount of services.
4. PERIOD OF PERFORMANCE. This Agreement shall commence as of the date first written above and shall continue until the earlier of the completion and acceptance of the Work or ___________ [total maximum time period from execution of the Agreement].
Contractor shall promptly commence Work and shall achieve [substantial or final (whichever is used in the solicitation/bid form)] completion of the Work within Forty-Five (45) days from Contractor’s receipt of notice to proceed from Union.
5. PAYMENT FOR WORK. Union shall pay Contractor [state the lump sum or hourly rate or unit pricing] for Work, as set forth in the Contractor’s bid, which is attached hereto and incorporated herein by reference. Payment for work satisfactorily completed shall be made within thirty (30) days of receipt of invoice by Union’s finance office. Contractor shall submit documentation supporting its entitlement to payment as required by Union, and Union shall have no obligation to pay Contractor unless and until Union has received such documentation. All payments shall be conditioned upon appropriation by the Union County Board of Commissioners of sufficient funds for each request for services.
6. LICENSING REQUIREMENTS. Contractor represents and warrants that it is and shall remain properly licensed at all times in the performance of Work.
7. PERMITS AND LICENSES. Unless otherwise agreed in writing in advance by Union, Contractor shall obtain and pay for all licenses and permits that are required for it to perform Work.
8. COMPLIANCE WITH LAWS/COMPLIANCE WITH RULES AND POLICIES
OF UNION. In performing the services pursuant to this Agreement, Contractor shall comply with all laws, rules, regulations, ordinances, codes, standards, and orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction. Contractor also shall comply with all rules and policies of Union.
9. INSURANCE. Contractor shall comply with the insurance requirements set forth in Exhibit A, attached and incorporated herein by reference.
No workers’ compensation insurance shall be obtained by Union concerning Contractor or the employees of Contractor. Contractor shall comply with the workers’ compensation law concerning Contractor and the employees of Contractor.
10. TAXES. Contractor shall be responsible for paying all taxes, fees, assessments and premiums of any kind payable on its employees and operations. Contractor shall substantiate, on demand by Union, that all taxes and other charges are being properly paid.
Pursuant to N.C.G.S. § 105-164.14, Union is eligible for sales and use tax refunds on all materials which become a permanent part of the construction. Contractor agrees to provide Union such documentation as may be necessary to meet the requirements of the North Carolina Department of Revenue regarding requests for refund of sales and use taxes. Such requirements include those described in the North Carolina Department of Revenue Sales and Use Tax Technical Bulletins § 18-2(F), outlined below:
To substantiate a refund claim for sales or use taxes paid on purchases of building materials, supplies, fixtures, and equipment by a contractor, Union must secure from a contractor certified statements setting forth the specific required information. A “certified statement” is a statement signed by a contractor’s Union, a corporate officer of a contractor, or an employee of a contractor who is authorized to provide information set forth in the statement. The certified statement must include all of the following information:
a. The date the property was purchased;
b. The type of property purchased;
c. The cost of property purchased and the amount of sales and use taxed paid thereon;
d. The vendor from whom the property was purchased;
e. The project for which the property was purchased;
f. If the property was purchased in the State of North Carolina, the county to which it was delivered, or, if the property was not purchased in the State of North Carolina, the county in which the property was used; and
g. The invoice number of the purchase.
In the event Contractor makes several purchases from the same vendor, such certified statement must indicate the invoice numbers, the inclusive dates of the invoices, the total amount of the invoices, and the State and local sales and use taxes paid thereon. Such statement must also include the cost of any tangible personal property withdrawn from Contractor’s warehouse stock and the amount of State and local sales or use tax paid thereon by Contractor. Any local sales or use taxes included in Contractor’s statements must be shown separately from the State sales or use taxes. Contractor’s statements must not contain sales or use taxes paid on purchases of tangible personal property purchased by Contractor for use in performing the Contract which does not annex to, affix to or in some manner become a part of the building or structure that is owned or leased by a governmental agency and is being erected, altered or repaired for use by a governmental entity as defined by N.C.G.S. § 105-164.14(c). Examples of property on which sales or use tax has been paid by Contractor and which shall not be included in Contractor’s certified statement are scaffolding, forms for concrete, fuel for the operation of machinery and equipment, tools, equipment, equipment repair parts and equipment rentals. Similar certified statements by Subcontractors must be obtained by Contractor and furnished to Union.
Contractor shall submit notarized sales tax certificates which meet the requirements detailed above with each Application for Payment. Payment will not be made until the sales tax certificate(s) have been submitted to Union. Union is the recipient of sales tax refunds and no such funds shall be provided to Contractor, or claim made by Contractor therefor.
11. WARRANTY OF WORK. Contractor warrants that all Work shall be new, unless otherwise agreed in this Agreement, and of good quality and performed in a good and workmanlike manner. Contractor shall, at its own expense, at the request of Union, promptly replace or repair any defective or deficient Work for a period of one year after completion of Work. The express warranty contained in this section shall not diminish any of Union's rights against Contractor with respect to the time within which proceedings may be commenced to establish Contractor's liability with respect to Contractor's obligations other than specifically to correct Work.
12. SAFETY. Contractor shall establish and enforce safe working procedures at all times during its performance of Work in accordance with all federal, state and local laws, ordinances, rules and regulations pertaining to safety.
13. AGE LIMITS. No employee of Contractor under the age of 18 shall be permitted on property owned or leased by Union.
14. CLEANUP. Contractor shall keep its work areas clean of debris and excess materials, and at the end of each day will leave its work areas in broom-clean condition. If Contractor fails to clean up as required herein, Union may clean up and deduct the cost from Contractor's payment.
15. LIABILITY. Contractor agrees to protect, defend, indemnify and hold Union County, its officers, employees and agents free and harmless from and against any and all losses, penalties, damages, settlements, costs, charges, professional fees or other expenses or liabilities of every kind and character arising out of or relating to any and all claims, liens, demands, obligations, actions, proceedings, or causes of action of every kind in connection with or arising out of this agreement and/or the performance hereof that are due, in whole or in part, to the negligence of the Contractor, its officers, employees, subcontractors or agents. Contractor further agrees to investigate, handle, respond to, provide defense for, and defend the same at its sole expense and agrees to bear all other costs and expenses related thereto.
16. “RESERVED”
17. [Include this section only if required by the IFB. If not required by IFB, delete this section and insert the word “RESERVED” in its place.] LIQUIDATED DAMAGES. Contractor and Union recognize that time is of the essence and that Union will suffer financial loss if the Work is not completed within the times specified in Section 4 herein. The parties also recognize the delays, expense, and difficulties involved in proving in a legal proceeding the actual loss suffered by Union if the Work is not completed on time. Accordingly, instead of requiring any such proof, Union and Contractor agree that as liquidated damages for delay (but not as a penalty), Contractor shall pay Union $250.00 for each day that expires after the time specified in Section 4 herein for substantial completion until the Work is substantially complete.
18. DEFAULT/TERMINATION. If Contractor fails or refuses to supply sufficient and properly skilled labor, equipment or materials, or fails in any respect to diligently prosecute Work, or otherwise is in default or breach of any term of this Agreement, Union may terminate this Agreement upon 24 hours' written notice. In the event of such termination, Contractor immediately will stop work and remove its employees from Union's property. Union may complete the Work in whatever way it determines best, and at completion of the Work shall pay Contractor for the value of the Work performed by Contractor (excluding profit) but unpaid prior to the termination, less any costs incurred by Union to correct any deficiencies or defects attributable to Contractor's work.
19. TERMINATION FOR CONVENIENCE. Union may terminate this Agreement at any time upon three (3) days’ written notice to Contractor. Such termination shall be effective in the manner specified in such written notice. Upon a termination for convenience, Union shall pay Contractor for Work performed to the date of termination. Contractor shall accept such payment in full and final payment and shall make no claim of any kind against Union, including but not limited to any claim for any additional payment.
20. ASSIGNMENT. Neither this Agreement, nor any payments to be earned pursuant to this Agreement, may be assigned by Contractor without the prior written consent of Union.
21. NO WAIVER. Union's not insisting upon strict compliance with any of the provisions of this Agreement, or not exercising any of its options provided herein, shall not be construed as a waiver of its right thereafter to require such compliance or to exercise any such options.
22. E-VERIFY. E-Verify is the federal program operated by the United States Department of Homeland Security and other federal agencies, or any successor or equivalent program, used to verify the work authorization of newly hired employees pursuant to federal law.
96520013 5 Union County Judicial Center
Contractor shall ensure that Contractor and any subcontractor performing work under this Agreement: (i) uses E-Verify if required to do so by North Carolina law; and (ii) otherwise complies with the requirements of Article 2 of Chapter 64 of the North Carolina General Statutes. A breach of this provision by Contractor will be considered a breach of this Agreement, which entitles Union to terminate this Agreement, without penalty, upon notice to Contractor.
23. ENTIRE AGREEMENT. This Agreement represents the entire agreement of the parties, and may not be modified except in writing signed by both parties.
24. GOVERNING LAW. This Agreement shall be construed and enforced in accordance with the laws of the State of North Carolina. The parties to this agreement confer exclusive jurisdiction of all disputes arising hereunder upon the General Courts of Justice of Union County, North Carolina.
25. AUTHORITY. Each signatory below warrants that it has the corporate or other organizational power and authority to execute, deliver and perform this Agreement. Each signatory further warrants that the execution, delivery and performance by it of the Agreement has been duly authorized and approved by all requisite action of the party’s management and appropriate governing body.
IN WITNESS WHEREOF, the parties hereto, acting under authority of their respective governing bodies, have hereunto set their hands and seals and caused this Agreement to be duly executed, this the day and year first above written.
UNION COUNTY [CONTRACTOR’S FULL LEGAL NAME]
By: (SEAL) By: (SEAL) Brian W. Matthews, County Manager
Approved as to Legal Form _____
This instrument has been preaudited in the manner required by The Local Government Budget and Fiscal Control Act.
Deputy Finance Officer
96520013 6 Union County Judicial Center
EXHIBIT A
INSURANCE REQUIREMENTS
I. At Contractor’s sole expense, Contractor shall procure and maintain the following minimum insurances with insurers authorized to do business in North Carolina and rated A-VII or better by A.M. Best, or as otherwise authorized by the Union County Risk Manager.
A. WORKERS’ COMPENSATION
Statutory (coverage for three or more employees) limits covering all employees, including Employer’s Liability with limits of:
$500,000 Each Accident $500,000 Disease - Each Employee $500,000 Disease - Policy Limit
B. COMMERCIAL GENERAL LIABILITY
Covering Ongoing and Completed Operations involved in this Agreement.
$2,000,000 General Aggregate $2,000,000 Products/Completed Operations Aggregate $1,000,000 Each Occurrence $1,000,000 Personal and Advertising Injury Limit
C. COMMERCIAL AUTOMOBILE LIABILITY
$1,000,000 Combined Single Limit - Any Auto
D. PROFESSIONAL LIABILITY
$1,000,000 Claims Made
Contractor shall provide evidence of continuation or renewal of Professional
Liability Insurance for a period of two (2) years following termination of the Agreement.
E. POLLUTION LIABILITY INSURANCE
$1,000,000 Claims Made
Contractor shall provide evidence of continuation or renewal of Pollution
Liability Insurance for a period of two (2) years following termination of the Agreement.
96520013 7 Union County Judicial Center
F. NETWORK SECURITY & PRIVACY LIABILITY (CYBER)
$1,000,000 Claims Made $3,000,000 Aggregate Limit
Contractor shall provide evidence of continuation or renewal of Technology Errors & Omissions Insurance for a period of two (2) years following termination of the Agreement.
G. ABUSE AND MOLESTATION INSURANCE
$300,000 Per Claim $300,000 Aggregate Limit
II. ADDITIONAL INSURANCE REQUIREMENTS
A. The Contractor’s General Liability policy shall be endorsed, specifically or generally, to include the following as Additional Insured:
UNION COUNTY, ITS OFFICERS, AGENTS AND EMPLOYEES ARE
INCLUDED AS ADDITIONAL INSURED WITH RESPECTS TO THE
GENERAL LIABILITY INSURANCE POLICY.
Additional Insured status for Completed Operations shall extend for a period of not less than three (3) years from the date of final payment.
B. Before commencement of any work or event, Contractor shall provide a
Certificate of Insurance in satisfactory form as evidence of the insurances required above.
C. Contractor shall have no right of recovery or subrogation against Union County
(including its officers, agents and employees).
D. It is the intention of the parties that the insurance policies afforded by contractor shall protect both parties and be primary and non-contributory coverage for any and all losses covered by the above-described insurance.
E. Union County shall have no liability with respect to Contractor’s personal property whether insured or not insured. Any deductible or self-insured retention is the sole responsibility of Contractor.
F. Notwithstanding the notification requirements of the Insurer, Contractor hereby agrees to notify County’s Risk Manager at 500 North Main Street, Monroe, NC 28112, within two (2) days of the cancellation or substantive change of any insurance policy set out herein. Union, in its sole discretion, may deem failure to provide such notice as a breach of this Agreement.
96520013 8 Union County Judicial Center
G. The Certificate of Insurance should note in the Description of Operations the following:
Department: Facilities & Fleet Management Contract #: _____________________
H. Insurance procured by Contractor shall not reduce nor limit Contractor’s contractual obligation to indemnify, save harmless and defend Union County for claims made or suits brought which result from or are in connection with the performance of this Agreement.
I. Certificate Holder shall be listed as follows:
Union County Attention: Risk Manager 500 North Main Street Monroe, NC 28112
J. If Contractor is authorized to assign or subcontract any of its rights or duties hereunder and in fact does so, Contractor shall ensure that the assignee or subcontractor satisfies all requirements of this Agreement, including, but not limited to, maintenance of the required insurances coverage and provision of certificate(s) of insurance and additional insured endorsement(s), in proper form prior to commencement of services.
DOCUMENT 00 55 00 – NOTICE TO PROCEED
100% Construction Documents June 07 2026 00 55 00 Temporary Generator Connections
1.1 NOTICE TO PROCEED
A. The Notice to Proceed is attached at the end of this section.
END OF DOCUMENT 00 55 00
Facilities Management 1407 Airport Road
Monroe, NC 28110 T 704.238.7768
Unioncountync.gov
NOTICE TO PROCEED
Contractor: Name address address
Owner: Union County Owners Project No. IFB # 2026-075 Union County Judicial Center Temporary Generator Connections
Date: Date sent to contractor
Architect: Progressive AE Architect’s Project No. 96520013
You are hereby notified that the Contract terms under the above Contract will commence on Date xx, xxxx considered the construction start date for Union County Judicial Center Temporary Generator Connections. In accordance with Section 4 of the Small Construction Agreement, the number of days to achieve Substantial Completion of base bid work included in this contract is no later than forty-five, [45] calendar days from the Notice to Proceed and shall be achieved by Date
Before you may start any work at the site, in accordance with Exhibit A of the Small Construction Agreement provide that you deliver to the Owner certificates of insurance which are required to be purchased and maintained in accordance with the Contract Documents.
Please acknowledge your receipt and acceptance of the Notice to Proceed by signing below and returning.
Contractor: Owner:
xxxxxxxxxx Union County
Name Eric Simpson Title Facilities Project Manager
DOCUMENT 00 62 00 – CERTIFICATE OF INSURANCE
1 Union County Judicial Center
Progressive AE 96520013 Construction Documents August 04 2026 00 62 00 Temporary Generator Connections
1.1 CERTIFICATE OF INSURANCE
Union County’s requires a Certificate of Insurance stating the required insurances and minimum limits.
END OF DOCUMENT 00 62 00
SECTION 01 10 00 - SUMMARY
Construction Documents August 04 2026 01 10 00 Temporary Generator Connections
1.
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General Conditions and Division 01
Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Type of Contract.
3. Work schedule and sequence.
4. Use of premises.
5. Work restrictions.
6. Specification formats and conventions.
1.3 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Identification: Union County Judicial Center Temporary Generator Connections
1. Address: 400 N. Main Street
2. Owner: Union County, North Carolina.
B. The Work consists of: Provide and install a Manual Transfer Switch (MTS) to interface with the existing permanent generator. In the event that the permanent generator doesn’t start, a trailered generator can be brought in, hooked up to the MTS via camlock connections and power the existing generator loads.
C. Identification:
1. Project Designer: Progressive AE
2. Owner: Union County, North Carolina
1.4 CONTRACTS
A. Project will be constructed under a Small Construction Agreement.
1.5 WORK SCHEDULE AND SEQUENCE
A. The Work shall be conducted in a single phase in coordination with the Union County Facilities and
Fleet Management Department for access, security, and shut-downs. With the date of Substantial Completion to be as indicated in the Agreement.
1.6 USE OF PREMISES
A. General: Contractor shall have full use of premises for construction operations, including use of Project site, during construction period. Contractor's use of premises is limited only by Owner's right to perform work or to retain other contractors on portions of Project.
1. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to
Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
SECTION 01 10 00 - SUMMARY
Construction Documents August 04 2026 01 10 00 Temporary Generator Connections
B. Deliveries: Provide representative to receive all materials and offload at the job site. The Owner will refuse all deliveries to other locations.
C. Personnel Identification: All construction personnel in occupied portions of the facility must wear Contractor-furnished identification badges at all times. Personnel without proper identification are subject to removal from the site by the Owner.
D. Safety and Security: Comply with Owner’s requirements related to security and fire drills and alerts.
E. Burning/Welding Operations: Comply with Owner’s…