Job Order Contract Supplementary Technical Specifications Summary
This document is a Supplementary Technical Specifications manual for a Job Order Contract (JOC PW2603) issued by California State University, Northridge (CSUN) for Facilities Planning, Design and Construction services. The contract covers various renovation and construction projects on the CSUN campus, including renovations to existing classrooms, laboratories, offices, facilities, playing fields, and roadways. Individual projects must not exceed $1,103,000.00 in value. The contract term is one year or $2,000,000.00, whichever comes first, with liquidated damages assessed for delays in completion. The contractor must submit a phasing plan and sequence of work to CSUN by the first pre-construction meeting. Special Campus Accommodation (SCA) processes must be initiated within 21 days of the Notice to Proceed to coordinate any campus impacts and utility shutdowns. Normal construction activities are permitted Monday through Friday between 7:00 a.m. and 11:00 p.m., excluding holidays, with any off-hours work requiring advance approval. Weekly project meetings are mandatory with the contractor's project manager and superintendent in attendance, and the contractor must provide a three-week look-ahead schedule updated weekly.
The contractor is responsible for all costs associated with cutting, patching, coordination, and protection of existing structures and utilities, with no additional compensation provided for the contractor's failure to survey existing conditions or review available record drawings. The contractor must employ a competent superintendent fluent in English who remains on-site during all work activities and cannot be assigned to other projects. An Environmental Protection Plan must be developed and submitted within 30 calendar days of the Notice to Proceed, addressing noise control, dust control, erosion and sediment control, and waste disposal. Construction waste diversion rates must meet a minimum of 75 percent, with an 80 percent goal, and all waste must be reported to CSUN Energy and Sustainability. The contractor must maintain safety standards including providing ANSI Class II safety vests and hard hats for all workers, with a supply of at least 10 additional vests maintained on-site at all times. The contractor may request use of an on-site trailer office at a rate of $400 per month. University keys are required for site access, with a $50 fine per lost key. All existing utilities must be located and protected, with damage repair costs borne by the contractor.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Special_Conditions_2026.pdf | ||
| Notice_to_Contractors_Rev._1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Facilities Planning, Design and Construction
Supplementary Technical Specifications
JOB ORDER CONTRACT (JOC)
PW2603
SUPPLEMENTARY
TECHNICAL SPECIFICATIONS
CSUN
BID #PW2603
JOB ORDER CONTRACT
Supplementary Technical Specifications
JOB ORDER CONTRACT (JOC)
PW2603
THIS PAGE INTENTIONALLY LEFT BLANK
Supplementary Technical Specifications Page 3 JOB ORDER CONTRACT (JOC) November 2026 PW2603 Table of Contents
Table of Contents
Section 01010 - Summary of Work
Section 01035 - Alteration Project Procedures
Section 01040 - Coordination
Section 01045 - Cutting and Patching
Section 01050 - Field Engineering
Section 01060 - Regulatory Requirements
Section 01095 - Reference Standards and Definitions
Section 01100 - Special Project Procedures
Section 01151 - Construction and Demolition
Section 01200 - Project Meetings
Supplementary Technical Specifications Page 4 JOB ORDER CONTRACT (JOC) November 2026 PW2603 Section 01010 - 1
Section 01010 - Summary of Work
Part 1 - General
1.1 Related Documents
A. Contract General Conditions.
B. Section 01035: Alteration Project Procedures C. Section 01045: Cutting and Patching.
1.2 Summary
A. The following subjects are included in this section:
1. Project Description
2. Project Phasing
3. Contractor Use of Premises
4. Superintendent/Supervisory Staff
5. Special Project Requirements
1.3 Project Description
A. General Description of the Work: Projects type will vary depending on campus requests. Projects will be less than $1,103,000.00. The projects will consist of renovating existing classrooms, laboratories, offices, facilities, playing fields, and roadways.
B. Contract Time: 1 year or $2,000,000.00 C. The Contractor will pay to the Trustees the sum of money stipulated per day in said Job Order for each day completion is delayed beyond the time prescribed, in accordance with the Contract General Conditions, Article 8.02, Delay in Completion—Liquidated Damages.
D. At the request of the contractor they can be provided an office in an onsite trailer and internet access for the contractor’s use for the duration of the contract. The rate for use of this office will be $400/month to be paid to the University.
1.4 Project Phasing
A. Phasing Plan/Sequence of Work: As required by individual projects, should be provided to CSUN by the first Pre-construction Meeting.
B. Owner Occupancy: Evaluate on a project-by-project basis.
C. Maintenance and Operation D. Work Under Separate Contract (Also refer to Contract General Conditions Article 4.19)
1. The Trustees reserve the right to award separate contracts for performance of work within or adjacent to the project site. Work may be conducted simultaneously with work under this contract. Contractor shall cooperate fully with separate contractors and coordinate work so that work under separate contract may be carried out efficiently, without interfering or delaying Contractor's work.
Supplementary Technical Specifications Page 5
PW2603 Section 01010 - 3
2. Disagreements between Contractor and entities performing work under separate contract concerning concurrent use of work areas and access to site which are not resolved by the participants shall be referred to the University Representative.
Contractor agrees to abide by the University Representative's determination as to concurrent use or priority of access, and to perform work in compliance with the University Representative's resolution at no additional cost.
1.5 Contractor Use of Premises
A. General
1. Contractor shall at all times conduct the work so as to impose no hardship on the
Trustees or others engaged in the Trustees' work nor cause any unreasonable delay or hindrance thereto.
2. Construction activities will be scheduled to minimize disruption to the University and to Campus users.
3. The Contractor may not interrupt any Campus utilities without prior written permission from the Trustees. Requests for utility shutdowns shall be submitted within 21 days of the issuance of the Notice to Proceed. Refer to the "JOC Special Campus Accommodation" form (SCA) included at the end of this section for detailed requirements and procedures for SCAs.
B. Surrounding Site Condition Survey
1. Prior to commencing the work, the Contractor and the University Representative shall tour the Project Site together to examine and record damage to existing buildings, landscape, hardscape and other improvements, both on and adjacent to the project site.
The resulting record shall serve as a basis for determination of subsequent damage due to Contractor's operations and shall be signed parties involved in the tour. Any damage to existing improvements not noted in the original survey, but subsequently discovered, shall be reported to the University Representative immediately.
C. Protection of Existing Structures and Utilities (also refer to Contract General Conditions- Article 4.08)
1. Locate all known existing utility installations before proceeding with construction operations which may cause damage to such installations. The existing utilities shall be protected and maintained in continual service at the Contractor's expense. Where existing utilities cross or are adjacent to the work of this contract, the Contractor shall notify the University Representative a minimum of 48 hours in advance of commencement of work. The Contractor shall locate the existing utility(s) by hand digging; repair of damage to existing utility(s) shall be at the Contractor's expense.
2. In the event that undocumented existing structures or utilities are encountered, the contractor shall immediately notify the University Representative and request direction concerning how to proceed with the work via a formal Request for Information (RFI).
3. Should the Contractor damage any existing structure or utility, the Contractor shall take immediate action to ensure the safety of both persons and property.
4. Contractor shall visit existing building(s) and grounds and thoroughly familiarize itself with existing conditions. Existing record drawings are available for Contractor review at
Supplementary Technical Specifications Page 6
PW2603 Section 01010 - 3 the office of Facilities Planning, Design and Construction.
5. Contractor shall include all necessary pipe offsets, fittings, etc. as required to complete the work in the base bid. No additional costs due to the Contractor's failure to survey existing conditions and review available record drawings will be allowed.
6. Contractor shall note all utility items (utility meters, junction boxes, valve boxes, post indicator valves, man-hole covers, etc.) at or above grade in the vicinity of the project site prior to commencing with trenching operations. These items indicate the presence of underground utilities in the area which shall be located and kept in continual service.
This requirement shall apply regardless of inclusion of these utilities on existing record documents.
7. When cutting, removal or alteration of existing work is required to form connections with new work or otherwise to meet the requirements of the contract documents, perform such work so as not to damage the work that will remain in place. Refer to sections 01035 and 01045 for cutting, patching and repair requirements.
8. Contractor shall provide all necessary materials, equipment and labor to adequately protect existing structures, floors, architectural finishes, utilities, landscape and hardscape which may be impacted by the work of this contract.
D. Allowable Work Schedule
1. Normal construction activities shall be performed Monday through Friday between the hours of 7:00 am and 11:00 pm, excluding holidays.
2. Shutdown of existing utilities or other activities which impact Campus operations shall be scheduled in advance with the University Representative in accordance with paragraph 1.5.A.3 above, and shall be scheduled during off-hours at the discretion of the University and at no additional cost to the University.
3. Contractor shall submit an Off-hours work Schedule Request a minimum of 72 hours prior to any anticipated after-hours, weekend, or holiday work.
E. Site Decorum
1. Contractor is to control the conduct of labor forces and prevent unwanted interaction initiated by workers with the University staff, students, or other individuals other than those associated with the project.
2. In the event that any worker initiates unwanted interaction, utilizes profanity, or (in the opinion of the University Representative) conducts him/herself in an offensive or unprofessional manner, the Contractor shall immediately remove the worker from the project and replace said worker with another of equivalent technical skill at no additional cost to the University.
3. Smoking and/or any tobacco use is strictly prohibited within the University.
4. No radios, other than 2-way communication type, shall NOT be allowed on the project site.
5. Contractor shall provide an ANSI Class II - Heavy Duty Safety Vest (Item#:SV59G-
Green/SV59O-Orange) http://www.safetygearonline.com/safety-vest/custom-screen-printing/screen-printing-service and hard hat for every employee, every subcontractor, every sub-tier subcontractor, and subcontractor employee working on-site.
Supplementary Technical Specifications Page 7
PW2603 Section 01010 - 4
6. Contractor shall maintain a supply of at least 10 additional vests on site at all times.
F. University Keys
1. Contractor shall provide a written request to the Facilities Planning, Design and Construction for construction core keys. If the Contractor fails to return a key, a lost key fine shall be charged for the amount of $50.00 per key.
2. Site fences shall be locked with the University standard lock in order to allow the University 24-hour access for maintenance and inspection, or response to an emergency condition. Should the Contractor wish to use a different lock, it shall be double-locked with the University standard lock at all times that the site is secured.
1.6 Superintendent/Supervisory Staff
A. The following requirements are in addition to the requirements of Article 4.15 of the Contract General Conditions:
1. The Contractor shall employ a competent Superintendent able to read, write and communicate fluently in English. The Superintendent shall be on site at all times during which work occurs on the project site and shall be fully authorized to represent Contractor in all matters pertaining to the work of this contract. All communications and agreements with the Superintendent shall be binding. The Superintendent shall be acceptable to the University and shall continue in the capacity of Superintendent for the duration of the project unless the Superintendent ceases employment with Contractor or the University otherwise agrees. The Superintendent shall not be employed on any other project by the Contractor during the course of this project.
2. Work shall not occur on the site except under the direct supervision of the Superintendent. Failure to maintain a Superintendent on the Project site at all times that work is occurring will result in the issuance of a stop work notice by the University Representative. Any schedule impact resulting from said stop work order shall be the responsibility of the Contractor; no additional costs for delay will be due Contractor, nor will assessment of liquidated damages be suspended to account for the work stoppage.
3. In addition to the Superintendent, Contractor shall assign a full-time project manager solely dedicated to the work of this project for the duration of the project.
1.7 Special Project Safety Requirements
A. At every concurrent project with a value of over $20,000 the contractor shall provide at least 10 hardhats in a tub available for all subcontractors, employees, vendors, etc. who show up to the project without them. The hard hats shall have the contractor’s name on it.
End of Section 01010
18111 Nordhoff Street Northridge, California 91330
JOC SPECIAL CAMPUS ACCOMMODATION
DIVISION ONE – SECTION 011400
GENERAL INSTRUCTIONS:
The Campus Special Campus Accommodation (SCA) process has been established to ensure contractors’ scheduled campus impact can be properly coordinated with Campus Operations. The process is a Three-Step Procedure:
Part I Initiate the SCA process to determine campus impacts, determine mutually agreeable dates and requirements, establish all participants, communication and coordination, etc. Part I is required within 21 days of the issuance of the Notice to Proceed initiates the MOP coordination process.
MOP Following Part I, coordinate the MOP by holding, at minimum, weekly meetings with the contractor, subcontractor, PPM representatives and CSUN PM/IOR. MOPs may require additional detailed workplans. MOPs will be held at least 14 days prior to the anticipated shutdown.
Part II Upon determining the impact, mitigation measures, confirmation of the date and time, responsible parties, shut-down contacts, completed MOP, etc., the Part II SCA form is completed to confirm the shut-down date/time.
REQUIREMENTS:
1. The contractor’s responsible PM or superintendent shall complete Special Campus
Accommodation (SCA) forms. The responsibility of completing the SCA form and process shall not be delegated to subcontractors.
2. Incomplete SCA forms will not be reviewed and will be returned to the contractor.
3. SCA number shall be assigned by the Contractor and be sequential for project.
4. The SCA Part I process shall be submitted within 21 days of the issuance of the NTP to provide enough time to schedule necessary meetings, identification of impacts, safety measures, prepare the necessary Work Plans and Method of Procedure to approve SCA Part II.
5. FPDC Project Manager and Inspector are both required to be on-site and cover the full duration of all SCA scheduled work.
STEP 1 - SCA PART I PROCEDURES:
1. The purpose of SCA Part I is to initiate the necessary meetings, coordination, identification of impacts, etc. with the University, PPM, Campus Departments, and FPDC to coordinate a proposed impact to campus operations and start coordination of the required MOP.
2. Elements:
A. Identification Of Meeting Participants B. Identification of the Method of Procedure Supervisor C. Identification of all necessary FPDC, PPM, EH&S, Contractor, and
Subcontractor staff required for the duration of the outage D. Development of Work Plans (if applicable). Work Plans shall detail the following:
I. Barricade and fencing locations II. Haul routes
III. Routing of vehicular and pedestrian traffic around specific construction area(s) IV. Utility shutdowns/tie-in to existing utilities V. Disabled access routes
VI. Fire department access to university buildings VII. Vehicular traffic access to buildings
VIII. Parking spaces impacted IX. Construction site and contractor parking access X. Large equipment access (cranes, loaders, backhoes, etc.)
XI. Work within pedestrian thoroughfares and campus roads (coordinate with Jodi Johnson, CSUN Disability Res & Srvcs 818-677-2684).
XII. Work within the inner-campus area E. Contractor’s Method of Procedure Supervisor shall complete the Method of
Procedure template for all electrical and other utility shutdowns as deemed required by the University.
F. Identify additional special permits required:
I. Confined space
II. TBD
3. Contractors shall not proceed with SCA unless a fully executed PART II SCA is returned to the contractor.
STEP 2 – MOP PROCEDURES:
1. Please refer to the JOC Method of Procedure form for detailed information.
STEP 3 – SCA PART II PROCEDURES:
1. The purpose of SCA Part II form is to obtain final approval of the dates, submittal of final work plan, and submittal of final Method of Procedure associated with Part I.
2. Contractor’s Method of Procedure Supervisor shall complete the Method of Procedure template
A. Identify all steps B. Identify the responsible party for each step C. Identify start date and times for each step, as well as the completion date and times D. Identify all parties necessary to initial each step prior to starting and confirmation upon completion (of each step) E. Identify all Emergency Contacts F. Coordinate with the CSUN PM and identify which steps initiate stakeholder’s group text messages. These activities shall be identified on the final MOP.
3. Utility Method of Procedure Pre-SCA Approval Conference – Requires All Parties, and all employees scheduled to work an outage to meet and walk through each line item of the Method of Procedure, physically walk the outage (all locations) and walk through the Method of Procedure.
4. Identify Communications Protocols
5. Contractors shall not proceed with SCA unless a fully executed SCA is returned to the contractor
Summary:
1. SCA Part I initiates the process and must be submitted within 21 days of the issuance of the NTP.
2. MOP coordination with Work Plans, if applicable, to be submitted 14 days prior to the shutdown, and will be coordinated by weekly meetings at a minimum.
3. Final MOP/Work Plan meeting to walk through each step with all involved parties is required.
4. SCA Part II is then circulated for approvals 7 days prior to the shutdown.
5. Only after SCA Part II is returned to the contractor can the shutdown commence.
6. The last signature on Part II is Work Control Coordinator, Maricela Amador maricela.amador@csun.edu. This must be received by Maricella 48 hours prior to the expected shutdown. Maricela will then put it on PPM’s schedule
Der
Manager of Construction Services Director of Engineering Services Electrical Shop Supervisor/AD
Plumbing Shop Supervisor/AD Mechanical Services/AD Grounds
Custodial Police Parking
USU TUC Associated Students
EH&S
PART I – SCA INITIATION PROCESS
REQUIRED 21 DAYS OF ISSUANCE OF NTP
DATE: SCA#:
PROJECT:
REASON FOR REQUEST:
LOCATION AND IMPACTS:
WORK TO BE PERFORMED BY CONTRACTOR:
PROPOSED START DATE / TIME: FINISH DATE / TIME: DURATION:
WORK PLAN ATTACHED: YES / NO METHOD OF PROCEDURE ATTACHED: YES / NO
Contractor / Requester’s Signature: Date:
SECTION TO BE FILLED OUT BY THE CSUN PM
Planning Narrative:
Weekly Coordination Meeting Date/Time:
Project Manager/ IOR Signature: Date:
Program Manager Signature: Date:
Manager of Construction Services Signature: Date:
Required Meeting Participants:
Der
Cell Phone #:
Cell Phone #
CSUN Manager of Construction Services Text Group Notification: Issued
Enter Group Text names here.
METHOD OF PROCEDURE SUPERVISOR:
CONTRACTOR ALTERNATE CONTACT: :
PART II – FINAL SCA
APPROVAL REQUIRED 48 HOURS IN ADVANCE OF WORK
DATE: SCA#:
PROJECT:
START DATE / TIME: FINISH DATE / TIME: DURATION:
REASON FOR REQUEST:
LOCATION AND IMPACTS:
WORK TO BE PERFORMED BY CONTRACTOR:
WORK PLAN ATTACHED: YES METHOD OF PROCEDURE ATTACHED: YES
EMERGENCY CONTACT LIST ATTACHED: YES FINAL MOP REVIEW MEETING DATE:
Contractor / Requester’s Signature: Date:
WORK PLAN COMPLETE: YES METHOD OF PROCEDURE COMPLETE: YES
CSUN PM/ Inspector of Record Approval: Date:
CSUN Program Manager’s Approval: Date:
INTERNAL APPROVAL PROCESS
CSUN Manager of Construction Services Approval: Date:
CSUN EH&S Director Approval: Date:
CSUN Assistant Director Approval: Date:
CSUN Director of Engineering Services/PPM Approval: Date:
CSUN FDC Director of Design and Construction Approval: Date:
CSUN Engineering Services Coordinator: Date:
Distribution: Facilities Planning, PPM, Contractor, EH&S Public Safety, Project Manager, Room Reservations, Document Control
Supplementary Technical Specifications Page 8
PW2603 Section 01035 - 2
Section 01035 - Alteration Project Procedures
(TO BE USED WITH REMODEL WORK ONLY)
B. (TO BE PROVIDED BY THE ARCHITECT AS REQUIRED)
1.2 General Description and Requirements
A. Coordinate the work of trades and schedule elements of alterations and renovation work by procedures and methods to expedite completion of the work.
B. In addition to demolition specifically shown, cut, move or remove items as necessary to provide access or to allow alterations and new work to proceed. Include such items as:
1. Repair or removal of hazardous or unsanitary conditions.
2. Removal of abandoned items and items serving no useful purpose, such as abandoned piping, conduit, and wiring.
3. Removal of unsuitable or extraneous materials not marked for salvage, such as abandoned furnishings and equipment, and debris such as rotted wood, rusted metals, and deteriorated concrete.
4. Cleaning of surfaces and removal of surface finishes as needed to install new work and finishes.
C. Patch, repair, and refinish existing items to maintain the specified condition for each material, with a smooth and clean transition to adjacent new construction items.
1.3 Sequence and Schedules
A. Schedule work in the sequences specified in Section 01010, Summary of Work.
1.4 Alterations, Cutting, and Protection
A. Assign the work of moving, removal, cutting, and patching to trades qualified to perform the work in a manner to minimize the possibility of damage to each type of work, and provide means of returning surfaces to the appearance of new work.
B. Perform cutting and removal work with minimal disruption and in a manner to avoid damage to adjacent work.
C. Cut finish surfaces such as masonry, tile, plaster, or metals, by methods that terminate surfaces in a straight line at a natural point of division.
D. Perform cutting and patching as specified in Section 01045.
E. Protect existing finishes, equipment, and adjacent construction that is scheduled to remain from damage.
Supplementary Technical Specifications Page 9
PW2603 Section 01035 – 3
1. Protect existing and new work from weather and extremes of temperature.
2. Maintain existing interior work above 60 degrees F.
3. Provide weather protection, waterproofing, heat, and humidity control as needed to prevent damage to remaining work and to new work.
Part 2 - Products
2.01 Products for Patching, Extending and Matching
A. Provide the same products or types of construction as those in the existing structure, as needed to patch, extend, or match the existing.
B. Generally, the Contract Documents will not define products or standards of workmanship present in existing construction; determine products by inspection and necessary testing, and determine quality of workmanship by using existing construction as a sample for comparison.
C. The presence of a product, finish, or type of construction requires that patching, extending, or matching shall be performed as necessary to make the work complete and consistent with identical standards of quality.
Part 3 - Execution
3.1 Performance
A. Patch and extend existing construction using skilled workers capable of matching the existing quality of workmanship. Quality of patched or extended work shall not be less than that specified for new work.
3.2 Adjustments
A. Where partitions are removed, patch floors, walls, and ceilings with finish materials to match the existing.
1. Where removal of partitions results in adjacent spaces becoming one, re-work floors and ceilings to provide smooth and clean planes without breaks, steps, or bulkheads.
2. Where an extreme change of plane of one inch or more occurs, request instructions from the Architect or the University as to the method of making the transition through an RFI.
B. Trim and refinish existing doors as necessary to clear new floor finishes.
3.3 Damaged Surfaces
A. Patch and replace any portion of an existing finished surface that is found to be damaged, lifted, discolored, or shows other imperfections with matching material.
a. Provide adequate support of the substrate prior to patching the finish.
b. Refinish patched portions of painted or coated surfaces in a manner to produce uniform color and texture over the entire surface.
Supplementary Technical Specifications Page 10
PW2603 Section 01035 - 4
c. When existing surface finish cannot be matched, refinish entire surface to nearest intersections.
3.4 Transition from Existing to New Work
A. When new work abuts or finishes flush with existing work, make a smooth and clean transition.
Patched work shall match existing adjacent work in texture and appearance so that the patch or transition is invisible at a distance of five feet.
B. When finished surfaces are cut in such a way that a smooth and clean transition with the new work is not possible, notify the Architect or the University. Terminate existing surface in a neat manner along a straight line at a natural line of division, and provide trim appropriate to the finished surface, or as otherwise directed by the Architect or the University.
3.5 Cleaning
A. Perform periodic and final cleaning as specified in Section 01700.
a. Clean Owner-occupied areas daily.
b. Clean spillage, overspray, and heavy collection of dust in Owner-occupied areas immediately.
B. At completion of work of each trade: clean the area and make surfaces ready for work of successive trades.
C. At completion of alteration work in each area, provide final cleaning and return space to a condition suitable for use by Owner.
End of Section 01035
Supplementary Technical Specifications Page 11
PW2603 Section 01040 - 1
Section 01040 - Coordination
B. (TO BE PROVIDED BY ARCHITECT AS REQUIRED)
A. Section includes: requirements for project coordination and electrical and mechanical coordination of “tight” conditions involving work of the Project.
1.3 Related Sections
A. Section 01300, “Submittals”
1.4 Project Coordination
A. General
1. Coordinate the work; do not delegate responsibility for coordination to any subcontractor.
2. Anticipate the interrelationship of all subcontractors and their relationship with the total work.
3. Resolve differences or disputes between subcontractors and materials suppliers concerning coordination, interference, or the extent of work between sections. The Contractor’s decisions, if consistent with the Contract Documents, shall be final. The Architect is not required to coordinate work between sections and will not do so.
4. Coordinate the work of subcontractors and material suppliers, so that their work is performed in a manner to minimize interference with, and to facilitate the progress of the work.
5. Be responsible for providing anchorage, blocking, joining, and other detailing as required to provide a complete project.
6. Do not obstruct spaces required by Code in front of electrical equipment, access doors, etc.
7. Do not cover any piping, wiring, ducts, etc., until properly inspected and approved and until inspection, and proper certificates have been issued.
8. Remove and replace any and all work under any section which is not in accordance with the Contract Documents with other materials and work which is in conformance with the Contract Documents. Repair or replace all other work damaged by these operations at no increase in contract price.
9. Coordination With Other Contracts: Coordinate work of this Contract with other contracts and contractors as appropriate.
Supplementary Technical Specifications Page 12
PW2603 Section 01040 - 2
10. This work shall be coordinated with all associated work in a manner that will ensure that all work will be accomplished as rapidly as the progress of the project will permit and so that no work will be delayed for want of associated work.
B. Electrical and Mechanical Coordination
1. Work out all “tight” conditions involving work of various sections in advance before installation. If necessary, and before work proceeds in these areas, prepare supplementary drawings for review showing all work in “tight” areas.
2. Provide supplementary drawings and additional work necessary to overcome “tight” conditions at no increase in contract price. Refer to Section 01300, Article titled “Submittals”.
3. Coordinated layout shop drawings shall be dimensionally accurate and detailed, giving complete dimensions of all locations, elevations, and clearances. Show exact locations of the following:
a. Ductwork
b. Piping, including fire protection systems.
c. Valves and piping specialties, including all air vents and drains.
d. Dampers
e. Access doors
f. Control and electrical panels
g. Adjustable frequency controllers
h. Motor control centers and transformers
i. Disconnect switches
j. Elevator equipment
k. Electrical cable trays and main conduits
l. Owner-furnished, Contractor-installed equipment.
4. Coordinated layout shop drawings shall show actual architectural and structural constraints and site conditions.
5. Coordination:
a. Fully coordinate work between trades with actual architectural, structural, and site conditions.
b. Coordinate all adjustments required. Clearly identify these adjustments by circling them on the coordinated layout shop drawings.
c. If Contractor has specific questions regarding coordination of the installation with structural, architectural, and site conditions and work between trades, submit the same with appropriate shop drawings documenting areas in question with Contractor’s proposed installation and submit as an RFI.
6. Submission and review of coordinated layout shop drawings:
a. Prepare reproducible drawings.
b. Submit to each trade for review of space allocated to all trades.
c. Revise drawings to compensate for review by each trade.
d. Review revisions with each trade.
e. Submit to the Architect and the University for review.
Supplementary Technical Specifications Page 13
PW2603 Section 01040 - 3
f. Review of coordinated layout shop drawings is only for verification that the Contractor has performed coordination work as specified herein. Note: Review does not include verification of exact dimensions, clearances, arrangements, and/or compliance with codes.
7. Final coordinated layout shop drawings shall show that all trades affected have made reviews and shall be signed by each trade at completion of coordination.
a. General Contractor is to ensure that each trade has coordinated work with other trades.
b. Include a stamp with a labeled space for each trade to sign on each submittal, indicating that the layout shop drawing has been coordinated.
c. No layout shop drawing will be reviewed without stamped and signed coordination assurance by the General Contractor.
8. Coordinated layout shop drawings showing the work of all trades are required.
Individual trade layout shop drawings will not be accepted.
End of Section 01040
Supplementary Technical Specifications Page 14
PW2603 Section 01045 - 1
Section 01045 - Cutting and Patching
(To Be Included Only When Applicable)
A. This Section specifies administrative and procedural requirements for cutting and patching.
B. Work included in this Section:
1. Cutting and patching not required to be performed as part of the work of other sections.
2. Cutting and patching existing work altered or disturbed to accommodate new construction.
3. Cutting and patching existing work damaged or defaced during new construction as required to restore to existing or better condition at the time of award of Contract.
4. Cutting and patching required to:
a. Install or correct non-coordinated work.
b. Remove and replace defective and non-conforming work.
c. Remove samples of installed work for testing.
C. Refer to other sections and drawings for specific requirements of the extent and limitations applicable to cutting and patching, demolishing, or altering existing work of individual parts of the Work. Requirements of this Section also apply to mechanical and electrical installations.
(Refer to Division-15 and Division-16 Sections for other requirements and limitations applicable to cutting and patching mechanical and electrical installations).
1.3 Submittals
A. Cutting and Patching Proposal: Where approval of procedures for cutting and patching is required before proceeding, submit a proposal describing procedures well in advance of the time cutting and patching will be performed and request approval to proceed with the work plan. Include the following information, as applicable, in the proposal:
1. Describe the extent of cutting and patching required and how it is to be performed.
2. Describe anticipated results in terms of changes to existing construction; include changes to structural elements and operating components as well as changes in the building’s appearance and other significant visual elements.
3. List products to be used and firms or entities that will perform work.
4. Indicate dates when cutting and patching is to be performed.
5. List utilities that will be disturbed or affected, including those that will be relocated and those that will be temporarily out-of-service. Indicate how long service will be disrupted.
Supplementary Technical Specifications Page 15
PW2603 Section 01045 - 2
6. Where cutting and patching involves addition of reinforcement to structural elements, submit details to show how reinforcement is integrated with the original structure.
7. Approval by the Architect or University to proceed with cutting and patching does not waive the Architect’s or University’s right to later require complete removal and replacement of a part of the Work found to be unsatisfactory.
8. Effects on University operations and on concurrent operations construction by other contractors.
1.4 Quality Assurance
A. Requirements for Structural Work: Do NOT cut and patch structural elements in a manner that would reduce their load-carrying capacity or load-deflection ratio.
Obtain APPROVAL from the Architect or the University of the cutting and patching proposal BEFORE cutting and patching the following structural elements:
1. Bearing and retaining walls, Structural concrete, Structural steel
2. Lintels
3. Timber and primary wood framing, Structural decking
4. Stair systems
5. Miscellaneous structural metals Equipment supports
6. Piping, ductwork, vessels, and equipment
B. Operational and Safety Limitations: Do not cut and patch operating elements or safety-related components in a manner that would result in reducing their capacity to perform as intended, or result in increased maintenance, or decreased operational life or safety.
Obtain APPROVAL of the cutting and patching proposal BEFORE cutting and patching the following operating elements or safety-related systems:
1. Primary operational systems and equipment, air or smoke barriers
2. Water, moisture, or vapor barriers, membranes, and flashings
3. Fire protection systems
4. Noise and vibration control elements and Control systems
5. Communication systems, Electrical wiring systems
C. Visual Requirements: Do not cut and patch construction exposed on the exterior or in occupied spaces, in a manner that would, in the Architect’s or University’s opinion, reduce the building’s aesthetic qualities, or result in visual evidence of cutting and patching. Remove and replace the work cut and patched in a visually unsatisfactory manner.
D. If possible, retain the original installer or fabricator throughout construction phases to cut and patch the following categories of exposed work, or if it is not possible to engage the original installer or fabricator, engage another recognized, experienced, and specialized firm:
1. Concrete finishes
2. Masonry
3. Stucco and ornamental plaster
4. Acoustical ceilings
5. Painting
Supplementary Technical Specifications Page 16
PW2603 Section 01045 - 3
6. Wall covering
7. HVAC enclosures, cabinets, or covers
Part 2 - Products
2.1 Materials
A. Use materials that are identical to existing materials unless not available.
1. If identical materials are not available or cannot be used where exposed surfaces are involved, use materials that match existing adjacent surfaces to the fullest extent possible with regard to visual effect (BEFORE PROCEEDING, CONTRACTOR SHALL
OBTAIN APPROVAL OF THE ARCHITECT AND THE UNIVERSITY).
2. Use materials whose installed performance will equal or surpass that of existing materials.
B. Part 3 - Execution
2.2 Inspection
A. Before cutting existing surfaces, examine surfaces to be cut and patched and conditions under which cutting and patching is to be performed. Take corrective action before proceeding, if unsafe or unsatisfactory conditions are encountered.
B. Before proceeding, meet at the site with parties involved in cutting and patching, including asbestos abatement, mechanical and electrical trades. Review areas of potential interference and conflict. Coordinate procedures and resolve potential conflicts before proceeding.
2.3 Preparation
A. Temporary Support: Provide temporary support of Work to be cut where required.
B. Protection: Protect existing construction during cutting and patching to prevent damage. Provide protection from adverse weather conditions for portions of the Project that might be exposed during cutting and patching operations.
C. Avoid interference with use of adjoining areas or interruption of free passage to adjoining areas.
D. Take all precautions necessary to avoid cutting existing pipe, conduit or ductwork serving the building, but scheduled to be removed or relocated until provisions have been made to bypass them.
2.4 Performance
A. General: Employ skilled workers to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time and complete without delay. Cut existing construction to provide for the installation of other components or the performance of other construction activities, and the subsequent fitting and patching required to restore surfaces to their original condition.
Supplementary Technical Specifications Page 17
PW2603 Section 01045 - 4
B. Cutting: Cut existing construction using methods least likely to damage elements to be retained or adjoining construction. Where possible, review proposed procedures with the original installer and comply with their recommendations.
1. In general, where cutting is required, use hand or small power tools designed for sawing or grinding, not hammering and chopping. Cut holes and slots neatly to the required size with minimal disturbance to adjacent surfaces. Temporarily cover openings when not in use.
2. To avoid marring existing finished surfaces, cut or drill from the exposed or finished side into concealed surfaces.
3. Cut through concrete and masonry using a cutting machine such as a carborundum saw or diamond core drill.
4. By-pass utility services such as pipe or conduit, before cutting, where services are shown or required to be removed, relocated or abandoned. Cut-off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal the remaining portion of the pipe or conduit to prevent the entrance of moisture or other foreign matter after bypassing and cutting.
5. Provide fire-safe seals to maintain the fire rating at all penetrations.
C. Patching: Patch with durable seams that are as invisible as possible. Comply with specified tolerances.
1. Where feasible, inspect and test patched areas to demonstrate the integrity of the installation.
2. Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will eliminate evidence of patching and refinishing.
3. Where removal of walls or partitions extends one finished area into another, patch and repair floor and wall surfaces in the new space to provide an even surface of uniform color and appearance. Remove existing floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance. Where patching occurs on a smooth, painted surface, extend the final paint coat over the entire unbroken area containing the patch after the patched area has received primer and a second coat.
4. Patch, repair, or re-hang existing ceilings as necessary to provide an even plane surface of uniform consistency.
5. Replace concrete walkways to the nearest construction joint.
D. Plaster Installation: Comply with manufacturer’s instructions and install thickness and coats as indicated.
2.5 Cleaning
A. Thoroughly clean areas and spaces where cutting and patching are performed or used as access.
Remove completely paint, mortar, oils, putty, and items of similar nature. Thoroughly clean piping, conduit, and similar features before painting or other finishing is applied. Restore the damaged pipe covering to its original condition.
End of Section 01045
Supplementary Technical Specifications Page 18
PW2603 Section 01050 - 5
Section 01050 - Field Engineering
B. (TO BE PROVIDED BY ARCHITECT AS REQUIRED)
1.2 References
A. Section includes: Quality Control, Submittals, and Project Record Documents.
B. See related Section 01700, "Project Closeout”.
1.3 Quality Control
A. The Contractor is solely responsible for the complete, timely and accurate layout of the work including, but not necessarily limited to, horizontal and vertical control and dimensional coordination as necessary to construct the work in accordance with the Contract Documents.
B. Employ a Land Surveyor or a Civil Engineer, registered in the State of California to perform survey work.
C. Employ a Professional Engineer of the discipline required for specific service on the project and licensed in the State of California where required in the technical specifications.
1.4 Survey Reference Points
A. Existing basic horizontal and vertical control points are shown on the Contract Documents.
B. Locate and protect control points prior to starting site work, and preserve all permanent reference points during construction.
1. Make no changes or relocations without prior written notice to Architect or University.
2. Report to Architect and/or University when any reference point is lost or destroyed.
3. Require a surveyor to replace project control points which may be lost or destroyed.
Establish replacements based on original survey control.
1.5 Submittals
A. Submit the name, address, and telephone number of the Surveyor and Engineer before starting survey work.
B. On request of Architect and/or University, submit documentation to verify accuracy of field engineering work.
C. Submit certificate signed by the Engineer and/or Land Surveyor, licensed to practice in the State of California, certifying that elevations and locations of improvements are in conformance with the requirements of the Contract Documents, or if in non-conformance, an explanation of the discrepancy.
Supplementary Technical Specifications Page 19
PW2603 Section 01050 - 6
1.6 Project Record Documents
A. Maintain a complete and accurate log of control and survey work as it progresses.
B. On completion of foundation walls and major site improvements, prepare a certified survey illustrating dimensions, locations, angles, and elevations of construction and site work.
C. Submit Record Documents under provisions of Section 01700.
End of Section 01050
Supplementary Technical Specifications Page 20
PW2603 Section 01060 - 1
Section 01060 - Regulatory Requirements
A. Section includes: Certain Codes and Standards and relevant requirements applicable to the Work required under this Contract.
1.3 Statutory and Jurisdictional Regulations
A. Perform the Work in accordance with Applicable Code Requirements and applicable requirements of all other regulatory agencies, including, but not limited to, the following:
1. State of California Code of Regulations (CCR), Title 24 State Building Standards, (APPLICABLE DATE BY ARCHITECT)
2. (LIST TO BE PROVIDED BY ARCHITECT)
B. Unless otherwise specified, specific references to codes, regulations, standards, manufacturers’ instructions, or requirements of regulatory agencies, when used to specify requirements for materials or design elements, shall mean the edition of each in effect as identified in the Contract Documents.
1.4 Conflicts
Unless otherwise directed by the Architect and/or the University, if a conflict exists between referenced regulatory requirements, comply with the one that establishes more stringent requirements.
Unless otherwise directed by the Architect and/or University, if a conflict exists between referenced regulatory requirements and the Contract Documents, comply with the more stringent requirements.
End of Section 01060
Supplementary Technical Specifications Page 21
PW2603 Section 01095 - 1
Section 01095 - Reference Standards and Definitions
1.2 Definitions
A. General: Basic Contract definitions are included in the Contract General Conditions.
B. Indicated: The term indicated refers to graphic representations, notes, or schedules on the
Drawings, or other Paragraphs or Schedules in the Specifications, and similar requirements in the Contract Documents. Terms such as shown, noted, scheduled, and specified are used to help the reader locate the reference. There is no limitation on location.
C. Directed: Terms such as directed, requested, authorized, selected, approved, required, and permitted mean directed by the Architect, requested by the Architect, and similar phrases.
D. Approve: The term approved, when used in conjunction with the Architect’s action on the Contractor’s submittals, applications, and requests, is limited to the Architect’s duties and responsibilities as stated in the Conditions of the Contract.
E. Regulation: The term regulations include laws, ordinances, statutes, and lawful orders issued by authorities having jurisdiction, as well as rules, conventions, and agreements within the construction industry that control performance of the Work.
F. Furnish: The term furnish means supply and deliver to the project site, ready for unloading, unpacking, assembly, installation, and similar operations.
G. Install: The term install describes operations at the Project site including the actual unloading, unpacking, assembly, erection, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning, and similar operations.
H. Provide: The term provide means to furnish and install, complete and ready for the intended use.
I. Installer: An Installer is the Contractor or an entity engaged by the Contractor, either as an employee, subcontractor, or contractor of lower tier, to perform a particular construction activity, including installation, erection, application, and similar operations. Installers are required to be experienced in the operations they are engaged to perform.
J. The Site: is the space available to the Contractor for performing construction activities, either exclusively or in conjunction, with others performing other work as part of the Project.
K. Testing Agencies: A testing agency is an independent entity engaged to perform specific inspections or tests, either at the Project Site or elsewhere, and to report on and, if required, to interpret results of those inspections or tests.
Supplementary Technical Specifications Page 22
PW2603 Section 01095 - 2
1.3 Specification Content Explanation
A. Specification Format: These Specifications are organized into Divisions and Sections based on the Construction Specifications Institute’s 17-Division format.
B. Abbreviations and Names: Trade association names and titles of general standards are frequently abbreviated. The following acronyms or abbreviations, as referenced in Contract Documents, are defined to mean the associated names. Names and addresses are subject to change and are believed, but not assured, to be accurate and up to date as of the date of Contract Documents.
(LIST TO BE PROVIDED BY ARCHITECT)
End of Section 01095
Supplementary Technical Specifications Page 23
PW2603 Section 01100 - 1
Section 01100 - Special Project Procedures
A. The requirements for the following subjects are included in this Section:
1. Environmental Protection Plan.
2. Smoke/Odor Control.
3. Noise Control.
4. Dust and Air Pollution Control.
5. Welding and Burning.
6. Erosion and Sediment Control.
7. Disposal Operations.
8. Cultural Resources.
1.3 Environmental Protection Plan
A. The requirements of the Article are in addition to those of Article 4.03 of the Contract General Conditions.
B. During the progress of the work, keep the premises occupied in a neat and clean condition and protect the environment both on site and off site, throughout and upon completion of the construction project.
C. In coordination with the Campus, develop an Environmental Protection Plan in detail and submit to the Architect and/or University within 30 calendar days from the date of commencement specified in the Notice to Proceed. Distribute the approved plan to all employees and to all subcontractors and their employees. The Environmental Protection Plan shall include, but not be limited to, the following items:
1. Copies of required permits.
2. Proposed sanitary landfill site.
3. Other proposed disposal sites.
4. Noise Control.
5. Dust Control.
6. Erosion and Sediment Control.
7. Copies of any agreements with public or private landowners regarding equipment, materials storage, borrow sites, fill sites, or disposal sites. Any such agreement made by the Contractor shall be invalid if its execution causes violation of local or regional grading or land use regulations.
Supplementary Technical Specifications Page 24
PW2603 Section 01100 - 2
D. Requirements: All operations shall comply with all federal, state and local regulations pertaining to water, air, solid waste and noise pollution.
E. Definitions of Contaminants:
1. Sediment: soil and other debris that have been eroded and transported by runoff water.
2. Solid waste: rubbish, debris, garbage and other discarded solid materials resulting from construction activities, including a variety of combustible and non-combustible wastes, such as ashes, waste materials that result from construction or maintenance and repair work, leaves and tree trimmings.
3. Chemical waste: includes petroleum products, bituminous materials, salts, acids, alkalis, herbicides, pesticides, disinfectants, organic chemicals and inorganic wastes. Some of the above may be classified as "hazardous."
4. Sanitary wastes:
a. Sewage: domestic sanitary sewage.
b. Garbage: refuse and scraps resulting from preparation, cooking, dispensing and consumption of food.
5. Hazardous materials: except as otherwise specified, in the event the Contractor encounters on the site material reasonably believed to be asbestos, polychlorinated biphenyl (PCB), or other hazardous materials which have not been rendered harmless, the Contractor shall immediately stop work in the area affected and report the condition to the Trustees in writing. The work in the affected area shall not thereafter be resumed except by written agreement of the Trustees and Contractor if in fact the material is asbestos, PCB, or other hazardous materials and has not been rendered harmless.
F. Protection of Natural…