JBMHH-AFH McNair 95pct Specs V1 2020-06-16.pdf
PDF 6 MB Posted
- Attached to
- Joint Base Myer-Henderson Hall: Army Family Housing Renovation Project, Fort McNair, Washington, D. C
- Solicitation number
- W912DR20B0012
About this file
This solicitation is for a firm-fixed price construction contract to renovate historic residential buildings located at Fort McNair. The U.S. Army Corps of Engineers seeks to award a contract valued between $10-25 million to renovate 11 historic family housing units. The construction period is approximately 550 calendar days from notice to proceed. Offerors must submit proposals in a two-step sealed bid process, with step one due on July 23, 2020. Only those selected to advance from step one will receive the step two solicitation amendment. Award will be made to the responsive and responsible bidder offering the lowest price that conforms to the solicitation requirements. Vendors must be registered in the System for Award Management to receive an award. The primary purpose is executing interior and exterior renovations to upgrade infrastructure, comply with codes, and modernize living standards while preserving historic aspects.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Army Corps of Engineers Baltimore District
CONSTRUCTION
SPECIFICATIONS
Joint Base Myer-Henderson Hall (JBM-HH) Army Family Housing
FT. MCNAIR, WASHINGTON, D.C.
VOLUME I
SOLICITATION NO.: W912DR20B0012
DATE: JUNE 22, 2020
THIS PAGE INTENTIONALLY LEFT BLANK
JBMHH-AFH - Fort McNair - FY20 100% Design Submission 06/16/2020
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REPORTING
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 35 SPECIAL INSPECTIONS
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 56 39 TEMPORARY TREE AND PLANT PROTECTION
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 PROJECT IDENTIFICATION
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 91 00.15 10 TOTAL BUILDING COMMISSIONING
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 41 00 DEMOLITION
02 42 91 REMOVAL AND SALVAGE OF HISTORIC CONSTRUCTION MATERIALS
02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS
02 82 00 ASBESTOS REMEDIATION
02 83 00 LEAD REMEDIATION
02 84 16 HANDLING OF LIGHTING BALLASTS AND LAMPS CONTAINING PCBs
AND MERCURY
02 84 33 REMOVAL AND DISPOSAL OF POLYCHLORINATED BIPHENYLS (PCBs)
02 85 00 MOLD REMEDIATION
DI VI SI ON 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DI VI SI ON 04 - MASONRY
04 03 00 CONSERVATION TREATMENT FOR PERIOD MASONRY
04 20 00 UNIT MASONRY
DI VI SI ON 05 - METALS
05 12 00 STRUCTURAL STEEL
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 52 00 METAL RAILINGS
DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES
06 10 00 ROUGH CARPENTRY
06 20 00 FINISH CARPENTRY
06 61 16 SOLID SURFACING AND QUARTZ AGGLOMERATE SURFACING
FABRICATIONS
DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON
PROJECT TABLE OF CONTENTS Page 1
07 21 13 BOARD AND BLOCK INSULATION
07 21 16 MINERAL FIBER BLANKET INSULATION
07 27 19.01 SELF-ADHERING AIR BARRIERS
07 41 13.16 COPPER ROOF PANELS
07 46 46 FIBER-CEMENT SIDING
07 62 13 COPPER SHEET METAL FLASHING AND TRIM
07 92 00 JOINT SEALANTS
DI VI SI ON 08 - OPENI NGS
08 14 00 WOOD DOORS
08 52 00 WOOD WINDOWS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
DI VI SI ON 09 - FI NI SHES
09 01 90.50 PREPARATION OF HISTORIC WOOD FOR PAINTING
09 23 00 GYPSUM PLASTERING
09 26 00 VENEER PLASTER
09 29 00 GYPSUM BOARD
09 30 10 CERAMIC, QUARRY, AND GLASS TILING
09 64 29 WOOD STRIP AND PLANK FLOORING
09 65 00 RESILIENT FLOORING
09 68 00 CARPETING
09 90 00 PAINTS AND COATINGS
DI VI SI ON 10 - SPECI ALTI ES
10 28 13 TOILET ACCESSORIES
DI VI SI ON 11 - EQUI PMENT
11 31 13 ELECTRIC KITCHEN EQUIPMENT
DI VI SI ON 12 - FURNI SHI NGS
12 21 00 WINDOW BLINDS
12 32 00 MANUFACTURED WOOD CASEWORK
DI VI SI ON 13 - Not Used
DI VI SI ON 14 - Not Used
DI VI SI ON 21 - FI RE SUPPRESSI ON
21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
DI VI SI ON 22 - PLUMBI NG
22 00 00 PLUMBING, GENERAL PURPOSE
DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 05 15 COMMON PIPING FOR HVAC
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
PROJECT TABLE OF CONTENTS Page 2
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING
CONTROL SYSTEMS
23 23 00 REFRIGERANT PIPING
23 52 00 HEATING BOILERS
23 81 00 DECENTRALIZED UNITARY HVAC EQUIPMENT
DI VI SI ON 25 - I NTEGRATED AUTOMATI ON
25 05 11.01 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS -
BACNET DDC SYSTEM FOR HVAC
25 05 11.03 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS - HVAC
25 05 11.04 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS -
INTERIOR DISTRIBUTION
25 05 11.05 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS -
POWER SYSTEMS AND METERING
25 05 11.06 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS - FIRE
AND LIFE SAFETY
25 05 11.07 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS -
LIGHTING
DI VI SI ON 26 - ELECTRI CAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
26 56 00 EXTERIOR LIGHTING
DI VI SI ON 27 - Not Used
DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY
28 10 05 ELECTRONIC SECURITY SYSTEMS (ESS)
28 31 74.00 20 INTERIOR FIRE DETECTION AND ALARM SYSTEM
DI VI SI ON 31 - EARTHWORK
31 00 00 EARTHWORK AND HELICAL PILES
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 05 33 LANDSCAPE ESTABLISHMENT
32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 31 19 DECORATIVE FENCES AND GATES
32 92 23 SODDING
32 93 00 EXTERIOR PLANTS
DI VI SI ON 33 - UTI LI TI ES
33 11 00 WATER UTILITY DISTRIBUTION PIPING
33 30 00 SANITARY SEWERAGE
33 40 00 STORM DRAINAGE UTILITIES
DI VI SI ON 34 - Not Used
DI VI SI ON 35 - Not Used
PROJECT TABLE OF CONTENTS Page 3
DI VI SI ON 40 - Not Used
DI VI SI ON 41 - Not Used
DI VI SI ON 42 - Not Used
DI VI SI ON 43 - Not Used
DI VI SI ON 44 - Not Used
DI VI SI ON 45 - Not Used
DI VI SI ON 46 - Not Used
DI VI SI ON 48 - Not Used
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 4
SECTION 01 11 00
SUMMARY OF WORK
08/15
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The U.S. Army Joint Base Myer Henderson Hall (JBMHH) is undertaking a JBMHH Army Family Housing (AFH) Renovation Program. For the purposes of the Program, the buildings are organized stylistically into groups:
Quarters 1, 2, 3, 4, 5, and 6 (Group 1) and Quarters 23, 24, 25, 26, and 27 (Group 5) at Fort McNair, all of which are proposed to undergo interior renovation and exterior repair to bring these houses back into good repair. The work includes 11 historical family housing units located at Fort McNair. Over the years, the units have deteriorated due to age and lack of proper maintenance. In addition, repair work has resulted in the loss of historical preservation, inadequate floor plans, excessive square footage, and lack of energy efficiencies. The scope of this work is to renovate these homes to replace all infrastructure and to bring the homes up to current living standards. These homes are broken down into two Groups (Group 1 and 5) then by Quarters (1-6, 23-27). There will be base and options outlined in the design documents. Group 1 Quarters 1 & 2 along with Group 5 Quarters 23 - 27 are all Base Build. Group 1 Quarters 3 - 6 are to be considered options.
Groups 1 and 5 were designed in the Colonial Revival style: Group 1 as single-family residences and Group 5 as duplex residences. The buildings were designed by McKim, Mead, & White and constructed between 1903 and 1905, with Quarters 27 (Group 5) completed in 1908. The Group 1 single-family residences are located on the northwest corner of the parade ground, on the west side of 2nd Avenue and the east side of 1st Avenue south of B Street. The Group 5 duplex residences are located on the northeast corner of the parade ground, on the east side of 4th Avenue and the west side of 5th Avenue south of B Street. All of these buildings are within the boundaries of the National Register of Historic Places (NRHP)-eligible Fort Lesley J. McNair Historic District (Attachment 1, Maps). The buildings have remained in residential use through the present.
Over the years, Groups 1 and 5 have undergone differing levels of interior and exterior alteration and renovation. Recently, all the Army Family Housing (AFH) at JBMHH was identified to undergo thorough repair and renovation that preserves the historic aspects of the AFH and their settings, improves energy efficiency, complies with state and federal building, fire, and safety codes, meets environmental and sustainability criteria, and meets the current UFC 4-771-02A Army Family Housing Supplement Draft 2013 for a period of at least 25 years.
JBMHH has conducted reviews in accordance with the National Historic Preservation Act (NHPA) and the National Environmental Policy Act (NEPA).
JBMHH has documented the AFH for NEPA and determined that no significant impacts on the human environment would occur. Under Section 106 of the NHPA, numerous agencies and parties have consulted to identify actions to avoid, minimize, and mitigate adverse effects on historic properties. In order to facilitate these efforts, the following outlines approaches for addressing changes to the Quarters.
01 11 00 - 1
The exteriors and interiors of the Groups 1 and 5 residences are divided into three zones of historical significance: Zone 1 is "Primary Historical Significance," Zone 2 is "Secondary Historical Significance," and Zone 3 is "Not Historically Significant." The historical significance of the following elements for the Group 1 residences are outlined in the table below and identified on Sheet G-301:
Zone 1
The entire exterior envelope, including porches, exterior stairs, roof, and roof elements
The entry hall and foyer stair up to the second-floor landing
The office
The living and dining rooms
Zone 2
The rear interior stairway
The kitchen and butler's pantry
The interiors of the first and second floors of the enclosed rear porches
All of the interiors of the second and third floors
Zone 3 All basements and crawlspaces under the front and rear porches (all buildings)
The historical significance of the following elements for the Group 5 residences are outlined in the table below and shown on Sheet G-302:
Zone 1
The entire exterior envelope, including porches, exterior stairs, roof, and roof elements (except for the exterior elevations of the previously renovated rear porches)
Zone 2
The exterior elevations of the previously renovated rear porches
All of the interiors of the first, second, and third floors
Zone 3 All basements and crawlspaces under the front and rear porches (all buildings)
The purpose of zoning the buildings is to define overarching treatments and approaches, as well as significant details and character-defining features requiring preservation. Where significant details and
01 11 00 - 2 character-defining features will be retained, they will be indicated in the scopes of work below.
1.1.2 Location
The work is located on Fort McNair, Washington, DC. The exact location will be shown by the Contracting Officer as well as on the contract documents.
1.2 OCCUPANCY OF PREMISES
Buildings will not be occupied during performance of work under this Contract.
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.3 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.4 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.
Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed.
Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.4.1 Notification Prior to Excavation
Notify the Contracting Officer at least 48 hours prior to starting excavation work.
01 11 00 - 3
1.5 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
Pursuant to Contract Clause FAR 52.245-1 Government Property, the Government will furnish some materials and equipment for installation by the Contractor. These are outlined on the contract documents.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
01 11 00 - 4
SECTION 01 14 00
WORK RESTRICTIONS
11/11
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Construction Phasing Plan; G, AO
1.2 SPECIAL SCHEDULING REQUIREMENTS
1.2.1 Construction Phasing Plan
Furnish to the Contracting Officer for approval a phasing plan consisting of narrative and drawings as applicable clearly defining proposed sequence of construction. Construction at Fort McNair consists of two (2) groups of homes; Group 1 Quarters 1 through 6 and Group 5 Quarters 23 through 27.
It is required that Group 1 and Group 5 homes start at the same time.
Contractor shall stagger crews so that the construction continues to roll through the homes sequentially. As quarters are completed they will be turned over to the government for preparation and occupancy.
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
The site of the work is on a military reservation and all rules and regulations issued by the Commanding Officer covering general safety, security, sanitary requirements, pollution control, traffic regulations and parking, shall be observed by the Contractor. Information regarding these requirements may be obtained by contacting the Contracting Officer, who will provide such information or assist in obtaining same from appropriate authorities.
Ensure that Contractor personnel employed on Joint Base Myer-Henderson Hall (JBM-HH) become familiar with and obey JBM-HH regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.3.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
01 14 00 - 1
1.3.1.2 Facility Security
1.3.1.2.1 General
Contractor and contractor personnel working at JBM-HH shall be required to comply with provisions below. Any questions related to such requirements shall be addressed to JBM-HH security and Department of Public Works (DPW) through the Contracting Officer.
1.3.1.2.2 Background Checks
See paragraph "Access And General Protection/Security Policy And Procedures" below.
1.3.1.2.3 Badges
Personnel permitted to work on post based on background checks will receive badges and vehicles identification. Badges and vehicle identification shall be returned to Fort Myer at completion of project.
1.3.1.2.4 Parking
Parking on post will be restricted to Contractor vehicles only. No privately owned vehicles will be allowed on post. Personnel may park off-post and arrange for vans or buses for transportation to the construction site, or walk in. Vans, buses and drivers will be subject to the same security requirements as construction personnel.
1.3.1.2.5 Parking and Staging
Parking for official Contractor vehicles identified by company placards or logos, construction trailers, private vehicles, and staging will be located at designated areas as directed by the Contracting Officer.
1.3.1.2.6 Foreign Personnel
No illegal aliens are permitted on post. Contractor personnel may include foreign nationals with valid work visa.
1.3.1.2.7 DDOT Vehicle Compliance
All contractor vehicles shall comply with District Department of Transportation (DDOT) requirements, including tags, vehicle registration, vehicle safety, etc. Vehicles not meeting DDOT requirements will be denied entry to JBM-HH.
1.3.1.2.8 Driving Right-of-Ways
All contractor vehicles shall stop, slow down, or give right-of-way for troop traffic on post roads.
1.3.1.2.9 Deliveries
Contractor deliveries shall be scheduled with the Contracting Officer with at least one week's notice especially if delivery involves multiple trucks.
01 14 00 - 2
1.3.1.2.10 Post Threat Levels
If post threat level is elevated to DELTA, Contractor must vacate the post, and may not resume construction for as long as 48 hours or as otherwise directed.
1.3.1.2.11 Memorandum
See attached JBM-HH Regulation 190-16, "Installation Access Control," for guidance in obtaining passes.
1.3.1.2.12 AT Level I Training
1.3.1.2.12.1 General
All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 10 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The Contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the Contracting Officer's Representative (COR) or to the Contracting Officer, if a COR is not assigned, within 5 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: https://jkodirect.jten.mil/Atlas2/faces/page/login/Login.seam.
1.3.1.2.12.2 iWATCH Training
The Contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 10 calendar days of contract award and within 2 calendar days of new employees commencing performance with the results reported to the COR Contractor no later than 12 calendar days after contract award.
1.3.1.2.12.3 OPSEC Training
Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training. New employees must be trained within 10 calendar days of their reporting for duty and annually thereafter.
Level I OPSEC training is available at the following website:
http://cdse.edu/catalog/elearning/GS130.html (Duration: 45 minutes).
1.3.1.2.12.4 Access and General Protection/Security Policy and Procedures
Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
01 14 00 - 3
1.3.1.2.12.5 Contractors That Do Not Require CAC, But Require Access to a Dod Facility or Installation
Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
1.3.1.3 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.3.2 Working Hours
Regular working hours must consist of an 8-hour period between 0800 and 1700, Monday through Friday, excluding Government holidays.
1.3.3 Exclusionary Period
No work must be performed during the Friday after Thanksgiving, the week of Christmas, and the week of New Years.
1.3.4 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
1.3.5 Occupied and Existing Buildings
The Contractor shall be working around existing buildings which are occupied. Do not enter the buildings without prior approval of the Contracting Officer. The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
1.3.6 Utilities
1.3.6.1 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions during normal working hours.
Conform to procedures required in paragraph WORKING HOURS.
01 14 00 - 4
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, are considered utility cutovers pursuant to the paragraph WORKING HOURS. Such interruptions are further limited to 6 hours. This time limit includes time for deactivation and reactivation.
d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
01 14 00 - 5
01 14 00 - 6
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
08/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
View Location Map; G , AO
Progress and Completion Pictures; G , AO
1.3 VIEW LOCATION MAP
Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
1.4 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten views from points located by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file. Include a date designator in file names. Cross reference submittals in the appropriate daily report. Photographs provided are for unrestricted use by the Government.
01 30 00 - 1
1.5 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by Washington, DC law.
1.6 FIRST TIER CONTRACTOR REQUIREMENTS FOR ASBESTOS CONTAINING MATERIALS
Accomplish all contract requirements of Section 02 82 00 ASBESTOS REMEDIATION, assigned to the Designated Competent Person, directly with a first tier subcontractor.
1.7 SUPERVISION
1.7.1 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.
1.7.2 Superintendent Qualifications
The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
For routine projects where the superintendent is permitted to also serve as the Quality Control (QC) Manager as established in Section 01 45 00.00 10 QUALITY CONTROL, the superintendent must have qualifications in accordance with that section.
1.7.2.1 Duties
The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.
The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.7.3 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the
01 30 00 - 2
Contractor.
1.8 PRECONSTRUCTION CONFERENCE
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work must also attend.
1.9 PARTNERING
To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key personnel from the Supported Command, the End User (who will occupy the facility), the Government Design and Construction team and Subject Matter Experts, the Installation, the Contractor and Subcontractors, and the Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.
The Contracting Officer will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.
1.9.1 Formal Partnering
Provide and host the Partnering sessions with key personnel of the Project Team, including Contractor personnel and Government personnel. Pay all costs associated with the Partnering effort including the Facilitator, the meeting room, and other incidental items. In exception, each participant bears their own costs for meals, lodging, and transportation associated with the Partnering sessions.
Before a Partnering session, coordinate with the Facilitator all requirements for incidental items (such as audio-visual equipment, easels, flipchart paper, colored markers, note paper, pens/pencils, colored flash cards), and have these items available at the Partnering session. Provide copies of documents for distribution to all attendees. Provide a Facilitator experienced in conducting Partnering Workshops, and who is acceptable to both the Government and the Contractor. The Facilitator is responsible for leading the team in a timely manner and making sure that issues are identified and resolved. A list of Partnering Facilitators is available from the Contracting Officer.
a. Schedule the Initial Partnering Session for a duration of one day minimum. Locate this session at a place off the construction site, as agreed to by the Contracting Officer and the Contractor. It may take place concurrently with the Pre-Construction Meeting.
b. Schedule follow-on Partnering Session(s) for a maximum of 4 hours.
Schedule them at no more than 3 to six month intervals. Participants are encouraged to utilize electronic means to expedite meetings.
Meetings may be held at a location off-Base, at the project site, or
01 30 00 - 3 in a Government Facility on Base. Follow-on meetings may be held concurrently with other scheduled meetings. Attendees need only be those required to resolve current issues. Recommend using the same Facilitator from the Initial Partnering session to achieve best results and for continuity.
1.9.2 Informal Partnering
The Contracting Officer will organize the Partnering Sessions with key personnel of the project team, including Contractor personnel and Government personnel.
The Initial Partnering session should be a part of the Pre-Construction Meeting. Partnering sessions will be held at a location agreed to by the Contracting Officer and the Contractor (typically a conference room provided by the Resident Engineer office or the Contractor). The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by the Contracting Officer. The Partners will determine the frequency of the follow-on sessions, at no more than 3 to six month intervals.
1.10 ELECTRONIC MAIL (E-MAIL) ADDRESS
Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats. Multiple email addresses are not allowed.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this email address.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
01 30 00 - 4
SECTION 01 32 01.00 10
PROJECT SCHEDULE
02/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AACE INTERNATIONAL (AACE)
AACE 29R-03 (2011) Forensic Schedule Analysis
AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Scheduler Qualifications; G, AO
Preliminary Project Schedule; G, AO
Initial Project Schedule; G, AO
Periodic Schedule Update; G, AO
1.3 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.
01 32 01.00 10 - 1
PART 2 PRODUCTS
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.
2.1.1 Government Default Software
The Government intends to use Primavera P6.
2.1.2 Contractor Software
Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.
2.1.2.1 Primavera
If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.
2.1.2.2 Other Than Primavera
If the contractor chooses software other than Primavera P6, that is compliant with this specification, provide for the Government's use two licenses, two computers, and training for two Government employees in the use of the software. These computers will be stand-alone and not connected to Government network. Computers and licenses will be returned at project completion.
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.
Prepare each Project Schedule using the Precedence Diagram Method (PDM).
3.2 BASIS FOR PAYMENT AND COST LOADING
The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.
01 32 01.00 10 - 2
3.2.1 Activity Cost Loading
Activity cost loading must be reasonable and without front-end loading.
Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
3.2.2 Withholdings / Payment Rejection
Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.
3.3.3 Procurement Activities
Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.3.4 Mandatory Tasks
Include the following activities/tasks in the initial project schedule and all updates.
a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).
b. Submission of mechanical/electrical/information systems layout drawings.
c. Long procurement activities
d. Submission and approval of O & M manuals.
01 32 01.00 10 - 3
e. Submission and approval of as-built drawings.
f. Submission and approval of DD1354 data and installed equipment lists.
g. Submission and approval of testing and air balance (TAB).
h. Submission of TAB specialist design review report.
i. Submission and approval of fire protection specialist.
j. Submission and approval of Building Commissioning Plan, test data, and reports: Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with the contract commissioning requirements. All tasks associated with all building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion.
k. Air and water balancing.
l. Building commissioning - Functional Performance Testing.
m. Controls testing plan submission.
n. Controls testing.
o. Performance Verification testing.
p. Other systems testing, if required.
q. Contractor's pre-final inspection.
r. Correction of punch list from Contractor's pre-final inspection.
s. Government's pre-final inspection.
t. Correction of punch list from Government's pre-final inspection.
u. Final inspection.
3.3.5 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to: environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.3.6 Standard Activity Coding Dictionary
Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11 . This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein. A template SDEF compatible schedule backup file is available on the QCS web site: http://rms.usace.army.mil .
The SDEF format is as follows:
01 32 01.00 10 - 4
Field Activity Code Length Description
1 WRKP 3 Workers per day
2 RESP 4 Responsible party
3 AREA 4 Area of work
4 MODF 6 Modification Number
5 BIDI 6 Bid Item (CLIN)
6 PHAS 2 Phase of work
7 CATW 1 Category of work
8 FOW 20 Feature of work*
*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.
3.3.6.1 Workers Per Day (WRKP)
Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.
3.3.6.2 Responsible Party Coding (RESP)
Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.
a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.
b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record);
ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE).
3.3.6.3 Area of Work Coding (AREA)
Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a
01 32 01.00 10 - 5 building, and different buildings within a complex of buildings.
Activities cannot have more than one Work Area Code.
Not all activities are required to be Work Area coded. A lack of Work Area coding indicates the activity is not resource or space constrained.
3.3.6.4 Modification Number (MODF)
Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.
3.3.6.5 Bid Item Coding (BIDI)
Assign a Bid Item Code to all activities using the Contract Line Item Schedule (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.
3.3.6.6 Phase of Work Coding (PHAS)
Assign Phase of Work Code to all activities. Examples of phase of work are procurement phase and construction phase. Each activity can have only one Phase of Work code.
a. Code proposed fast track design and construction phases proposed to allow filtering and organizing the schedule by fast track design and construction packages.
b. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.
3.3.6.7 Category of Work Coding (CATW)
Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to construction submittal, procurement, fabrication, weather sensitive installation, non-weather sensitive installation, start-up, and testing activities. Each activity can have no more than one Category of Work Code.
3.3.6.8 Feature of Work Coding (FOW)
Assign a Feature of Work Code to appropriate activities based on the Definable Feature of Work to which the activity belongs based on the approved QC plan.
Definable Feature of Work is defined in Section 01 45 00.00 10 QUALITY CONTROL. An activity can have only one Feature of Work Code.
3.3.7 Contract Milestones and Constraints
Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.
01 32 01.00 10 - 6
Mandatory constraints that ignore or effect network logic are prohibited.
No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.
3.3.7.1 Project Start Date Milestone and Constraint
The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.
3.3.7.2 End Project Finish Milestone and Constraint
The last activity in the schedule must be a finish milestone titled "End Project."
Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path. The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.
3.3.7.3 Interim Completion Dates and Constraints
Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.
3.3.7.3.1 Start Phase
Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.
3.3.7.3.2 End Phase
Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.
3.3.8 Calendars
Schedule activities on a Calendar to which the activity logically belongs. Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop Seasonal Calendar(s) and assign to seasonally affected activities as applicable.
If an activity is weather sensitive it should be assigned to a calendar showing non-work days on a monthly basis, with the non-work days selected at random across the weeks of the calendar, using the anticipated adverse weather delay work days provided in the Special Contract Clauses. Assign non-work days over a seven-day week as weather records are compiled on seven-day weeks, which may cause some of the weather related non-work days to fall on weekends .
01 32 01.00 10 - 7
3.3.9 Open Ended Logic
Only two open ended activities are allowed: the first activity "NTP Acknowledged" may have no predecessor logic, and the last activity -"End Project" may have no successor logic.
Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.
3.3.10 Default Progress Data Disallowed
Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the Contractor's schedule.
3.3.11 Out-of-Sequence…
This is the start of the file's text. The full file is on GovTribe.