This Justification & Approval (J&A) document supports a sole-source bridge extension for the System Engineering and Program Support for DoD Teleport (SEPS4T) task order, currently performed by Booz Allen Hamilton (BAH). The modification will extend the current task order for six months from August 1, 2025 to January 31, 2026, allowing time to award new follow-on task orders without interrupting critical support for the Defense Information Systems Agency (DISA).

The extension covers three new competitive task orders in different procurement phases: Transport Services Strategic Advisory Support (TSSAS), Cybersecurity Technical and Analytical Services (CTAS), and Satellite Communications Engineering Support (SCES). These task orders will provide strategic programming, cybersecurity monitoring, and engineering support for DISN systems, with anticipated award dates ranging from March to August 2025. The bridge extension ensures continuity of services for tactical users accessing Defense Information Switched Network (DISN) services, with BAH remaining the sole source contractor due to their specialized expertise and current system understanding.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page 4 of 11 Pages

CUI

System Engineering and Program Support for DoD Teleport JA23-110 MOD 03 situation. The justification is for services that were previously awarded on a competitive basis to Booz Allen Hamilton (BAH). The current task order was competitively awarded via GSA OASIS Unrestricted Pool 1. The PoP end date for the requested bridge action will be January 31, 2025, and as this period does not exceed the ultimate completion date for the GSA OASIS vehicle, task order HC1047- 18-F- 0017 will be modified to add the requested bridge period.

MOD 03: The current bridge expires on July 31, 2025. The new follow-on task orders that will assume this support are currently in different phases of the procurement process and will not be awarded prior to the expiration of the current bridge.

MOD 01: The current bridge expires on January 31, 2025. The new follow-on task orders that will assume this support are currently in different phases of the procurement process and will not be awarded prior to the expiration of the current bridge.

Efforts are currently ongoing to pursue two new competitive task orders (small business set asides). DISA IE is finalizing a performance work statement mapping document to outline the acquisition strategy. Relevant task areas from this requirement are anticipated to move to three separate contract actions.

MOD 01: Efforts are currently ongoing to pursue three new competitive task orders (two small business set asides). Relevant task areas from this requirement are still anticipated to move to three separate contract actions.

New Task Order #1: Transport Services Strategic Advisory Support (TSSAS): This new requirement will provide strategic programming, planning and advisory support services.

The requirement is in development phase, and further market research is needed to finalize the strategy. The projected award date is May 29, 2024, based on the complete/actionable package received by November 1, 2023.

Anticipated contract strategy: to be determined. Anticipated PoP: 1-year base period with 4, 1-year options Estimated task order value:

Funding type: to be determined.

MOD 03: TSSAS was awarded on March 17, 2025. However, PSD was notified of a protest on March 26, 2025. PSD was notified that the protest was resolved on June 11, 2025 and that work will begin on July 14, 2025; therefore, the work that is transitioning to TSSAS will not be included on this bridge extension (August 1, 2025

– January 31, 2026).

Funding Type: Operations and Maintenance, DISA Defense Working Capital Funds

MOD 01: Market research has been completed. The projected award date is March 20, 2025.

Contract strategy: ENCORE III Small Business. Anticipated PoP: 1-year base period with 4, 1-year options. Estimated task order value:

Funding type: to be determined.

New Task Order #2: Cybersecurity Technical and Analytical Services (CTAS): This new requirement will provide monitoring for the life cycle of DISA systems, DISN, major

Page 6 of 11 Pages

Teleport System. Failure to maintain the contractor support provided by BAH until the new task orders are awarded will result in a loss of continuity of services and will be detrimental as it will negatively impact mission-critical functionality and services provided to DISA. Specifically, this could result in mission failure and unnecessarily endanger lives. BAH understands the requirements and currently possesses the requisite expertise and relevant experience to continue performance. A gap in the critical SEPS4T that BAH currently provides is unacceptable as it will result in the loss of critical support of national defense and priority missions. Therefore, a bridge extension to the current task order is requested for up to 16 months. This will allow adequate time for the restructuring of contracts, including award of the new task orders, resolve potential protests, and transition efforts to the new contractor(s).

(2) Minimum Government requirements. DISA and its mission partners depend on the SEPS4T support to provide deployed forces with increased satellite telecommunications for multi-band and multimedia connectivity from deployed locations throughout the world to online DISN service delivery nodes and legacy tactical command, control, communications, computers, and intelligence systems. Due to the breadth and depth of the requirements and the clearance required to support requirements, no alternate contractor can develop the work force necessary to replace the current support team and achieve an initial satisfactory level of support expeditiously before the expiration of the current SEPS4T task order.

(3) Proposed sole source contractor and demonstration of unique source.

BAH, the incumbent on the existing task order, is the only source that can continue to fulfill this requirement within the necessary time frame and without risk of a substantial break in service/support to DISA and its mission partners.

BAH is uniquely postured to support the current SEPS4T task order without a loss of time and work stoppage starting September 30, 2023. BAH understands the requirements and currently possess the requisite expertise and relevant experience.

BAH currently performs support to provide tactical users access to the DISN services in a seamless, interoperable, and economical manner anywhere in the world

The support requires meticulous and highly technical skillsets which are not readily available in the marketplace in the timeframe necessary.

MOD 03: A sole source action is necessary as the current bridge expires on July 31, 2025. The new follow-on task orders that will assume this support (CTAS and SCES) are currently in different phases of the procurement process and will not be awarded prior to the expiration of the current bridge.

MOD 01: A sole source action is necessary as the current bridge expires on January 31, 2025. The new follow-on task orders that will assume this support (TSSAS, CTAS, and SCES) are currently in different phases of the procurement process and will not be awarded prior to the expiration of the current bridge.

(4) Procurement discussion. Efforts are currently ongoing to pursue restructuring of contract requirements, including two new competitive task orders. DISA IE is finalizing a performance work statement mapping document to outline the acquisition strategy, which will ultimately determine the timeline for award of the new task orders.

Page 7 of 11 Pages

(5) Impact - Failure to maintain the contractor support continuity provided by BAH until the previously discussed actions can be awarded and transitioned will result in a loss of continuity of services and cause detrimental effects as it will negatively impact mission-critical functionality and services to military operations. Specifically, this could result in mission failure and unnecessarily endanger lives. The current contractor provides highly specialized and critical support to DISA and DISA’s mission partners, and a gap in service would cause a decline in quality of services to DISA and its mission partners.

5. COST/PRICE FAIR AND REASONABLE DETERMINATION:

MOD 03: Determination of fair and reasonable pricing for this extension modification will be based on the independent government cost estimate, and comparison to the previously negotiated HC104718F0017 task order labor rates at the time of the second bridge award. The contracting officer will determine if the price is fair and reasonable by comparing past rates and labor categories to this task order for current work and requirements of the performance work statement being performed. The final cost/price will be determined fair and reasonable upon completion of negotiations.

MOD 01: Determination of fair and reasonable pricing for this extension modification will be based on the independent government cost estimate, and comparison to the previously negotiated HC104718F0017 task order labor rates at the time of initial bridge award. The contracting officer will determine if the price is fair and reasonable by comparing past rates and labor categories to this task order for current work and requirements of the performance work statement being performed. The final cost/price will be determined fair and reasonable upon completion of negotiations.

Determination of fair and reasonable price for this extension modification will be based on the independent government cost estimate and comparison to the competitively awarded task order labor rates currently on task order HC104718F0017. The contracting officer will determine if the ultimate price is fair and reasonable by comparing past rates and labor categories on this task order for current work and requirements of the performance work statement being performed. The final cost/price will be determined fair and reasonable upon completion of negotiations.

6. MARKET RESEARCH:

MOD 03: This is an extension to the existing bridge to task order HC104718F0017 to ensure continued support until the two new task orders (CTAS and SCES) have been awarded and support is ready to transition. TSSAS has been awarded, an award protest was resolved on June 11, 2025 and that work will begin on July 14, 2025; therefore, the work that is transitioning to TSSAS will not be included on this bridge extension (August 1, 2025 – January 31, 2026). CTAS has been solicited as a HUBZone set-aside via GSA Multiple Award Schedule. SCES has been solicited on a competitive basis under the SETI Full and Open Suite. However, it is not currently feasible to award CTAS and SCES prior to the expiration of the current task order. Therefore, BAH is the only source that can continue providing the necessary level of support without risk of a substantial break in support.

MOD 01: This is an extension to the existing bridge to task order HC104718F0017 to ensure continued support until the three new task orders (TSSAS, CTAS, and SCES) have been awarded and support is ready to transition. Market research has been finalized for the new TSSAS and CTAS requirements. TSSAS has been solicited as a competitive small business set-aside via the ENCORE III contract vehicle and CTAS has been solicited as a HUBZone set-aside via GSA Multiple Award

Page 8 of 11 Pages

Schedule. Market research is being finalized for the new SCES requirement, which is anticipated to be solicited on a competitive basis under the SETI Full and Open Suite. However, it is not currently feasible to award the new task orders prior to the expiration of the current task order. Therefore, BAH is the only source that can continue providing the necessary level of support without risk of a substantial break in support

BAH is the only contractor at this time with the requisite knowledge and technical personnel capabilities to support the requirement in the timeframe necessary for uninterrupted support. Market research is being finalized for the restructuring of contract requirements, to include two new task orders, which indicates they can be competitively solicited allowing fair opportunity. However, it is not currently feasible to execute the restructuring of contract requirements nor award these two new task orders prior to the expiration of the current task order. The Government has determined that the current level of support can only be provided by the incumbent. Therefore, BAH is the only source that can continue providing the necessary level of support without risk of a substantial break in support.

7. ANY OTHER SUPPORTING FACTS: None.

8. ACTIONS THE AGENCY MAY TAKE TO REMOVE OR OVERCOME BARRIERS THAT

LED TO THE EXCEPTION TO FAIR OPPORTUNITY:

(a) Procurement History.

Contract/TO Number: GS00Q14OADU108/HC104718F0017 Brief Description: SEPS4T

Contractor: BAH Business Type: Large Life Cycle Contract Value: $29,776,320 (includes $1,858,653 in optional/unexercised surge) Period of Performance (including all options and FAR 52.217-8):

April 1, 2018 – July 31, 2025

Contract Type: CPFF Basis of Award: Competitively awarded as a task order via GSA

OASIS (Unrestricted Pool 1)

Contract/TO Number: HC1028-08-D-2015-VC30 Brief Description: DoD Teleport Program Office Systems

Engineering Program Management (SEPM) Contractor: BAH Business Type: Large Life Cycle Contract Value: $30,019,307 Period of Performance (including all options and FAR 52.217-8):

October 01, 2012 – March 31, 2018

Contract Type: CPFF Basis of Award: Competitively awarded as a task order via

ENCORE II

Contract/TO Number: HC1028-08-D-2015-VC25

Page 9 of 11 Pages

Brief Description: DoD Teleport Program Office System Program Management and Technical Support

Contractor: BAH Business Type: Large Life Cycle Contract Value: $5,952,837 Period of Performance (including all options and FAR 52.217-8):

October 01, 2011 – July 31, 2012

Contract/TO Number: FA8771-04-D-0006-VC36 Brief Description: DoD Teleport Program Office System Program

Management and Technical Support Contractor: BAH Business Type: Large Life Cycle Contract Value: $8,454,664 Period of Performance (including all options and FAR 52.217-8):

March 24, 2010 – September 30, 2011

Contract Type: CPFF Basis of Award: Awarded as a sole source task order via Air

Force Network-Centric Solutions

(NETCENTS) IDIQ

Contract/TO Number: FA8771-04-D-0006-VC18 Brief Description:

DoD Teleport Systems Program Management and Technical Support

Contractor: BAH Business Type: Large Life Cycle Contract Value: $10,453,754 Period of Performance (including all options and FAR 52.217-8):

March 27, 2008 – April 8, 2010

Contract Type: CPFF Basis of Award: Awarded as a task order via Air Force

Network- Centric Solutions (NETCENTS) IDIQ (task order was competed; BAH was only offeror to submit a proposal)

Contract/TO Number: FA8771-04-D-0006-VC02 Brief Description: DoD Teleport Systems Program Management and Technical Support Contractor: BAH Business Type: Large Life Cycle Contract Value: $16,290,644 Period of Performance (including all options and FAR 52.217-8):

February 11, 2005 – March 28, 2009

Contract Type: CPFF Basis of Award: Awarded as a task order via Air Force

Network-

Page 10 of 11 Pages

(b) This requirement was previously awarded as a sole source task order to BAH; however, the previous two task orders were competitively awarded and efforts are currently ongoing to pursue two new competitive task orders that will encompass IE’s requirements, including tasks from the existing SEPS4T requirement.

MOD 03: This modification is a bridge extension of the existing task order bridge HC104718F0017 until the two new task orders can be awarded. The current task order is set to expire on July 31, 2025.

MOD 01: This modification is a bridge extension of the existing task order bridge HC104718F0017 until the three new task orders can be awarded. The current task order is set to expire on January 31, 2025.

Page 11 of 11 Pages

TECHNICAL CERTIFICATION: I certify that the supporting data under my cognizance which are included in the J&A are accurate and complete to the best of my knowledge and belief.

NAME: SIGNATURE/DATE: See separate signature page

TITLE/ORGANIZATION: PEO Transport IE3/ Program/Management Analyst

PHONE:

REQUIREMENTS CERTIFICATION: I certify that the supporting data under my cognizance which are included in the J&A are accurate and complete to the best of my knowledge and belief.

NAME: SIGNATURE/DATE: See separate signature page

TITLE/ORGANIZATION: Chief, PEO Transport Communications Engineering Division

CONTRACTING OFFICER CERTIFICATION: I certify that this justification is accurate and complete to the best of my knowledge and belief.

NAME: Erica J. Ackeret SIGNATURE/DATE: See separate signature page

TITLE/ORGANIZATION: Contracting Officer/DISA/DITCO/PS8313

PROCURING ACTIVITY COMPETITION ADVOCATE (PACA) APPROVAL: I have reviewed this justification and find it to be accurate and complete to the best of my knowledge and belief.

Since this justification does not exceed $15M, this review serves as approval and my written determination that the aforementioned FAR circumstances apply.

NAME: SIGNATURE/DATE: See separate signature page

TITLE/ORGANIZATION: PACA, DISA

PHONE:

ALL QUESTIONS REGARDING THIS JUSTIFICATION ARE TO BE REFERRED TO

Erica J. Ackeret, , erica.j.ackeret.civ@mail.mil