This Justification and Approval (J&A) document is for a modification to an existing contract with Bryant Healthcare Consultants, Inc. for Hospital Accreditation Compliance Assessments and Leadership Support for the Indian Health Service (IHS). The total estimated contract value is $2,014,920.00, with a three-month base period and potential six-month option. The contract will provide consultation and professional support for the Office of Quality to help IHS healthcare facilities maintain compliance with The Joint Commission (TJC) accreditation standards and Centers for Medicare and Medicaid Services (CMS) Conditions of Participation.
The J&A is justified under FAR 6.302-2 for unusual and compelling urgency, as four IHS healthcare facilities are at risk of non-compliance. Market research included a Request for Information and Sources Sought Notice on SAM.gov from January to March 2025, which yielded 12 and 8 responses respectively, but no companies demonstrated capability to perform the required services within the needed timeframe. The contract aims to address survey findings, provide leadership mentoring, support executive teams, and develop organizational gap analyses to improve hospital accreditation and compliance across infection prevention, leadership, governance, and other critical areas.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JUSTIFICATION AND APPROVAL
FOR OTHER THAN FULL AND OPEN COMPETITION
Completion Instructions: The Department of Health and Human Services (HHS) has established a standard template for the preparation of a J&A for Other Than Full and Open Competition. If this is an 8(a) set-aside, please note this form is not required unless the acquisition is valued (including all options) at greater than $22 million. This template is NOT applicable for actions using simplified acquisition procedures (FAR Part 13), Federal Supply Schedule orders (FAR 8.4) or task or delivery orders subject to fair opportunity (FAR 16.505).
Tailor all aspects of this template to the individual acquisition. Consult FAR Subpart 6.3 for guidance. An addendum may be added in case additional space is needed.
When this document is printed, the blue italic instructions are automatically deleted on the printed version.
Acquisition Title:
Agency:
Acquisition Year (FY):
Author and Title:
2. Description of Action:
Nature: New Requirement Follow-on Requirement
Modification to Existing Purchase Order/Contract Number:
Pricing: Firm-Fixed Price Time & Materials Cost
Other:
Funds: OMA Other Funds:
Name of Proposed Contractor(s):
Street Address:
City, State, Zip:
3. Description of Services or Supplies:
Basis for Approval (FAR 6.303-1(d)): Individual Basis Class Basis
The total estimated value of the proposed action, including all options is $
As applicable, briefly describe the services or supplies required to meet the agency's needs, including make & model number where appropriate. Include quantities of supplies or period of performance for services. Provide information for any options included. If the action is a modification to an existing contract, distinguish clearly between the work covered by the original contract and the work to be obtained by the proposed modification.
75H70425C00002
Hospital Accreditation Compliance Assessments and Leadership Support
Darla McCloskey
AGENCY
Bryant Healthcare Consultants, Inc.
16 Old Stage Rd
Hampton Falls, New Hampshire 03844-2021
2,014,920.00
This service contract will provide consultation and professional support for the Office of Quality (OQ) to obtain expertise in the areas of hospital leadership mentoring, including the executive team (C-suite), support maintenance of The Joint Commission (TJC) accreditation standards and elements of performance (EPs) and Centers for Medicare and Medicaid Services (CMS) Conditions of Participation (CoP) within the Indian Health Service (IHS) system, and provide development of organizational gap analysis to improve and sustain hospital accreditation and compliance with CoPs, including, but not limited to leadership and governance, infection prevention and control, i f l f ili f ( i f d lif f d d ) d i li d i il i i l b
$2,014,920.00
4. Authority and Rationale: Identify the statutory authority, FAR title and FAR citation permitting other than full and open competition. It may be one of the following most commonly used citations by the operating divisions of the Department of Health and Human Services (HHS), but other exceptions may apply per FAR Subpart 6.3.
Actions other than simplified acquisition procedures (select only one and provide an explanation):
FAR 6.302-1: Only one responsible source and no other supplies or services will satisfy agency requirements, 41 U.S.C.
3304(a)(1)
Explain why the intended contractor is the only responsible source who can provide the required supplies or s ervices.
Discuss the unique capabilities, expertise, etc. that support the lack of competition/why no other type of supplies or servic es will satisfy agency requirements. Explain factors/unique qualifications such as proprietary data or exclusive licensing rights, if applicable. When competition is limited to items particular to one manufacturer, this justification must explain why the particular brand name, product, or feature is essential to the Government's requirements, and that market research indicates other companies' similar products, or products lacking the particular feature, do not meet, or cannot be modified to meet the agency's needs in accordance with FAR 11.105. If in connection with a follow-on contract for continued development or production of highly specialized equipment, detail the substantial duplication of cost or unacceptable delays.
FAR 6.302-2: Unusual and compelling urgency, 41 U.S.C. 3304(a)(2) If unusual and compelling urgency is the basis for the justification, explain the chronological events leading up to the requirement and explain why time constraints cannot permit even a limited competition. Describe the detrimental effects/ serious injury to the mission of the requiring activity or to the government, financial or otherwise, that will result if this justification is not approved. Describe impact of required delivery/performance date. Describe the detrimental effects/ serious injury to the mission of the requiring activity or to the government, financial or otherwise, that will result if this justification is not approved and the product or service cannot be provided by the intended sole source contractor. Failure to plan for expiring funds is not a valid reason for citing this exception. May not exceed one year, including all options, unless the head of the agency determines that exceptional circumstances apply.
FAR 6.302-5: Authorized or Required by Statute, 41 U.S.C. 3304(a)(5) Provide a citation to the statutory authorization and a brief description of its content, or identify the specified source or other agency.
Other (See FAR Subpart 6.3 for additional authority) Provide the authority and citation to the applicable section of FAR 6.3.
Provide a full explanation to justify use of the exception.
5. Agency Actions to Take or Remove Barriers That Led to Other Than Full and Open Competition (If applicable):
Describe the actions, if any, the agency may take to remove or overcome any barriers that led to the restricted consideration prior to any subsequent acquisition for the supplies of services is made. If no such actions have been taken, explain why.
Currently four (4) Indian Health Service (IHS) healthcare facilities are in jeopardy of being non-compliant with CMS Conditions of Participation (CoP) and accrediting body regulatory requirements. The anticipated period of performance will be for (3) months with consideration of adding one (1) six (6) month option period. Support is necessary to address the multitude of survey findings and
IHS issued a Request for Information on SAM.gov 1/29/2025-2/12/2025; 12 responses were received from large and small businesses.
However, none of the companies demonstrated capability to perform services required. In addition, a Sources Sought Notice was posted on SAM.gov 3/19/2025-3/29/2025; 8 responses were received from large and small businesses. However, none of the companies demonstrated capability to perform the services required and to meet the timeframe of services to begin no later than August 25, 2025 at the Pine Ridge location. This posting can be found on SAM.gov under notice ID: IHS-25-SS-HCLMSS. Because the need for maintaining compliance is
6. Bridge Contracts:
For contract extensions or bridge contracts when a competitive follow-on is in the process of being developed, summarize history of current contract and explain the reasons for any delays in the acquisition. Include discussion of the milestones f or the follow-on action; the milestones should be as efficient as possible. Discuss why it would be neither cost effective nor realistic to expect another contractor to perform during the brief interim period; include issues such as start -up costs, phase-in, transfer of GFP, recruitment and staffing, etc. If the action is because of a protest, provide a brief discussion of the protest including the date the protest was filed and the basis of the protest. Explain that the action will provide the minimum quant ity or performance period.
7. Actions to Increase Competition:
Describe efforts made to compete the action, including whether a notice was or will be publicized as required by FAR Subpart
5.2 or which exception under FAR 5.202 applies. If a notice was publicized, discuss the number of written responses to the synopsis and the results of the assessment of the written responses. List sources, if any, that expressed, in writing, an interest in the acquisition. Provide rationale if interested sources were rejected. If applicable, state that no other sources have expressed interest, but all offers received shall be considered. Describe what actions will be taken to increase competition before subsequent acquisition of the supplies or services is required. You may state that an action is a one-time requirement, but if a similar requirement arises, every effort will be made to compete it to the maximum extent possible. If action is sole source because of proprietary data or licensing rights and there will be a continuing need for the requirement, there must be evidence that advanced planning has been initiated to overcome the barriers to competition, or there should be documentation to support an analysis that replacement costs/licensing purchase costs outweigh the benefits of competition. If the action is a contract extension or bridge, explain actions to compete the follow-on. If action is an urgent new requirement and a competitive follow-on is anticipated, explain that efforts are underway to facilitate a full and open competition.
8. Market Research:
Describe the extent of the market research conducted to identify all qualified sources and the results thereof. “Market Research” is defined as those attempts you made to ascertain whether other qualified sources exist, and can include contact with knowledgeable experts regarding similar or duplicate requirements, contact with industry, results of a sources sought synopsis, or draft solicitations. Research of the marketplace may consist of written, electronic (i.e. email) telephonic, or world wide web inquiries. Lack of advanced planning is not an acceptable reason for the lack of market research, but true urgency may necessitate abbreviated market research that is limited to readily available historical and commercial information. If ac tion is a contract extension or bridge contract, describe the market research efforts underway or completed for the follow-on. See FAR 10.002(b)(2).
9. Procurement History:
Purchase order or contract number:
Was action competed? Yes No
N/A
IHS issued a Request for Information on SAM.gov 1/29/2025-2/12/2025; 12 responses were received from large and small businesses.
However, none of the companies demonstrated capability to perform services required. In addition, a Sources Sought Notice was posted on SAM.gov 3/19/2025-3/29/2025; 8 responses were received from large and small businesses. However, none of the companies demonstrated capability to perform the services required and to meet the timeframe of services to begin no later than August 25, 2025 at all three locations. Because the need for maintaining compliance is immediate, this short term contract will ensure no disruption in service. It is anticipated the current sources sought notice will result in a multi-award contract for which no barriers to competition are known or
IHS issued a Request for Information on SAM.gov 1/29/2025-2/12/2025; 12 responses were received from large and small businesses.
However, none of the companies demonstrated capability to perform services required. In addition, a Sources Sought Notice was posted on SAM.gov 3/19/25-3/29/2025; 8 responses were received from large and small businesses. However, none of the companies demonstrated capability to perform the services required and to meet the time frame of services to begin no later than August 25, 2025 at the Pine Ridge location.
If action was not competed, state the cited authority, summarize rationale, and describe the actions that were supposed to be taken to increase competition and the results thereof:
Bryant Healthcare Consultants, Inc. was the only company who was capable of performing immediate on-site services for the Pine Ridge location within the alloted time. The J&A was approved by the IHS Competition Advocate under FAR 6.302-2: Unusual and compelling urgency, 41 U.S.C. 3304(a)(2).
10. Additional Information to support the justification:
Failure to maintain accreditation and quality of care at individual facilities, will result in losing facility accreditation or the threat of loss. The utilization of this contract support will provide strategies to IHS facility leadership that will ensure no disruption is services and continue meeting IHS’s mission.