J2 Statement of Work.docx
DOCX document 20 KB Posted
- Attached to
- Superior National Forest GAOA Stony Spur Trail Rehabilitation and Tomahawk Trail Culvert
- Solicitation number
- 12445523Q0090
- Issued by
-
Department of Agriculture Forest Service
About this file
This document outlines a statement of work for a federal contract to rehabilitate the Stony Spur Trail and replace a culvert on the Tomahawk Trail within the Superior National Forest in Minnesota. The scope of work includes trail bed maintenance and graveling on select segments of the Stony Spur Trail, installation of culverts along the trail, and placement of barrier rocks to limit vehicle access. It also involves removing and replacing a 48-inch corrugated metal pipe culvert on the Tomahawk Trail. All work must be completed by October 27, 2023 and is required to be performed on weekdays during daylight hours. Bidders are directed to inspect the work sites to assess conditions and verify information prior to submitting a bid. The related federal contract opportunity is solicitation number 12445523Q0090 being offered by the Department of Agriculture Forest Service for the Superior National Forest GAOA Stony Spur Trail Rehabilitation and Tomahawk Trail Culvert project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| J4 Stony Spur Drawings.pdf | ||
| J1 Wage Determination DB20235022 Lake Cty MN.pdf | ||
| J6 Tomahawk Trail Drawings.pdf | ||
| J3 Stony Spur Specs.pdf | ||
| J5 Tomahawk Trail Specs.pdf | ||
| 12445523Q0090 (4).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GAOA STONY SPUR TRAIL
REHABILITATION AND TOMAHAWK TRAIL CULVERT REPLACEMENT
STATEMENT OF WORK
This project consists of 2 parts – Part 1 is the Rehabilitation of Stony Spur Trail and Part 2 is the Culvert Replacement on the Tomahawk Trail
The Stony Spur Trail (FS Trail 51058), is used as a recreation trail for hiking, ATV, and snowmobile use. This project will maintain the Stony Spur Trail to address defective areas and extend the useful life for these purposes.
In addition, a barrier will be constructed on an adjacent trail to prevent conventional vehicle traffic on a trail section.
Project Location:
The Stony Spur Trail runs between the Town of Babbitt, MN (assumed MP 0.0) eastward to MN Hwy 1 (MP 17.7). The trail roughly parallels the New Tomahawk Road, which is also known as CSAH 70, Scott Road and/or Forest Road 424.
From Ely, MN: The Stony Spur Trail crosses MN Hwy 1 approximately 19 miles South of the intersection of 169 and MN-1 at the east side of Ely.
From Babbitt, MN: The Stony Spur Trail intersects CSAH 70/Scott Road/Forest Road 424 approximately 10 miles East of the intersection of Babbitt Road and CSAH 70/Scott Road/Forest Road 424 on the north side of Babbitt.
The following table gives the approximate trail milepost (MP) and lat/long coordinates of key locations along the Stony Spur Trail:
| Contract Work Sites and Intersections |
| Trail MP |
| Lat |
| Long |
| SITE A - Gravel, culvert |
| 10.10 |
| 47.687230 |
| 91.772542 |
| Intersect: 1431 Hatchet Rd |
| 10.20 |
| 47.687688 |
| 91.770741 |
| Intersect: 178 Stony River Rd |
| 10.84 |
| 47.692171 |
| 91.760478 |
| SITE B - Gravel, culvert |
| 11.45 |
| 47.694575 |
| 91.747617 |
| Intersect: New Tomahawk Rd |
| 11.61 |
| 47.695054 |
| 91.744446 |
| Intersect: 428 Keeley Creek Rd |
| 12.97 |
| 47.705195 |
| 91.726768 |
| SITE C - Gravel, culvert |
| 13.75 |
| 47.710851 |
| 91.713954 |
| Intersect: 427 Denley Creek Rd |
| 14.26 |
| 47.714955 |
| 91.705174 |
| SITE D - Gravel, culvert |
| 15.16 |
| 47.710308 |
| 91.688714 |
| SITE E - Gravel, culvert |
| 15.66 |
| 47.716140 |
| 91.673273 |
| Intersect: Hwy 1 |
| 17.70 |
| 47.728807 |
| 91.645639 |
| SITE F – Boulder barrier |
| 19.87 |
| 47.735086 |
| 91.609197 |
Scope of Work:
The GAOA Stony Spur Trail Rehabilitation and Tomahawk Trail Culvert Replacement includes:
1. Trail bed maintenance and gravelling for select trail segments
2. Culvert placement
3. Placement of barrier rocks (boulders) to limit access to the trail by conventional vehicles
Work tasks may include but are not limited to: Mobilization, dewatering the work areas, removing ruts/potholes/chuckholes or any other trailbed deformities, trailbed compaction, creating proper trailbed drainage, placement and compaction of MnDOT Class 5 gravel, material sourcing, material hauling, installation of culverts, and removal/legal disposal of removed culverts off of National Forest land.
The Contractor shall provide all required labor, equipment, transportation, and materials necessary to complete the described scope of work in conformity with the drawings and specifications, and in accordance with the provisions of the contract. There is no Government Provided Material on this contract.
Performance Time:
Construction shall be completed prior to October 27th, 2023. No work is allowed on evenings, weekends, or government holidays.
Site Visit:
Bidders are urged and expected to inspect the sites where work will be performed and to verify general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after Contract Award.
Part 2: GAOA - Tomahawk Trail Culvert Replacement - Tomahawk Trail - TR 90221-8.64
Part 2 of this project includes the removal and replacement of a 48” corrugated metal pipe culvert. The culvert is located in a section of the Tomahawk Trail, which is an aggregate surfaced road/trail that is primarily used by OHV traffic. The culvert provides water flow from an unnamed stream into the southeast portion of South Farm Lake. Work tasks include (but are not limited to): traffic control, erosion and sedimentation control, dewatering, excavation, demolition of the existing culvert, placement of a new culvert, backfill and compaction, placement of aggregate surfacing, seeding and stabilizing of disturbed areas.
Performance Time:
Construction shall be completed prior to October 27th, 2023. No work is allowed on evenings, weekends, or government holidays.
Site Visit:
Bidders are urged and expected to inspect the sites where work will be performed and to verify general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after Contract Award.