SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-0
Specifications
MARK TWAIN NATIONAL FOREST
POTOSI/FREDRICKTOWN RANGER
DISTRICT
POTOSI ADMIN OFFICE
WINDOW REPLACEMENT
April 2021
Project #2
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-2
Section C - Description/Specifications/Statement of Work
GENERAL SPECIFICATIONS
POTOSI ADMIN OFFICE – WINDOW REPLACEMENT
1.1 SCOPE OF CONTRACT
A. This project includes replacing windows at the Potosi Administrative Site Office.
B. The work of this contract consists of all labor, materials, equipment, rentals, and subcontracted services for, but is not limited to:
1. Removal of existing aluminum-clad wood windows, sash, and frame and trim down to rough opening.
2. Replacement of damaged framing, trim, and siding.
3. Installation of new energy efficient fiberglass double paned, tinted, low-e sliding windows and casement windows.
a. Moisture proofing the windows.
b. Sealing and Caulking.
c. Window color shall be chosen from manufacture’s color selection. To be approved by COR.
4. Interior Cedar Trim and Sills:
a. Replace cedar interior sills to match existing trim.
b. Interior trim shall be removed and salvaged to be reinstalled if needed. If trim is damaged during window removal, replace to match existing.
c. Stain/paint window trim and sills to match existing wood surfaces and to create a seamless finish and color to all areas replaced. Color to be approved by COR.
d. Contractor shall provide submittals/samples after award to be approved.
5. Contractor shall provide a compressive construction schedule detailing the plan of work/action to provide to the District for coordination.
NOTE 1: All building dimensions listed are approximate. Contractor is responsible to confirm actual building dimensions.
NOTE: All items not specifically mentioned in the Contract Documents necessary to complete the specified work shall be incidental to the cost of the project.
1.2 PROJECT LOCATION
A. The Potosi Admin Office is located at 10019 W. State Highway 8, Potosi, Missouri
63664.
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-3
1.3 SITE INFORMAITON AND WORK RESISTRCTIONS
A. Contractor’s Use of Premises: During construction, Contractor will have full use of the building, as directed by the COR. Contractor’s use of premises is limited to performance of work and as follows:
1. Perform construction during weekdays and weekends (8 AM to 6PM, Monday thru Sunday, other than holidays), unless otherwise agreed to in advance by the COR.
Clean up work areas and return to a usable condition at the end of each work period.
B. The Office structure will be occupied during construction, care will be exercised to adhere to schedule and to secure the Government facility after hours. The Contractor will be responsible for signing, limiting access, and safety of public and/or government employees in the area.
C. Remove and replacement of windows shall occur within the same workday, so as to secure the building, conserve energy to hear or cool the building and minimize disturbances to government employees.
D. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:
1. The Contractor is responsible for the security of the Contractor’s equipment and materials.
2. Utilities are available at the site for construction purposes.
3. Driveways, Walkways, and Entrances: Keep driveways, parking garage, loading areas, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1.4 SAFETY
A. Contractor shall comply with all State and Federal safety regulations during the performance of the work.
1.5 STAGING AND STORAGE AREAS
A. Areas for staging operations and storage of materials shall be approved by the COR. The Contractor must request in writing for approval from the COR to stage trailers on site.
1.6 INSPECTION OF WORKSITE
A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-4
additional expenses to the government.
1.7 FIELD VERIFICATION
A. Contractor shall field verify all new and existing dimensions affecting the work of this contract before ordering products.
1.8 GOVERNMENT-FURNISHED PROPERTY
A. None
1.9 DISPOSAL OF MATRIAL
A. Contractor shall remove and dispose of all debris offsite, including materials removed from building.
1.10 START DATE
A. TBD
1.11 CONTRACT TIME
A. Base: 30 Calendar Days
1.12 NOTICE TO PROCEED
A. Performance of the contract shall begin within ten (10) calendar days after receipt of the Notice to Proceed. The Notice to Proceed will be issued by the Contracting Officer at the pre-work conference.
1.13 ABBREVIATIONS AND TERMS
A. The following abbreviations and terms may be used in the contract documents:
1. COR (Contracting Officer’s Representative)
2. CO (Contracting Officer)
3. Owner: Government/Forest Service
4. USDA (United States Department of Agriculture)
END OF SECTION C
SUBMITTAL PROCEDURES 013300-5
SECTION 013300 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals.
See Table 013300-1 for a summary of required submittals.
B. See other specification sections within this package for additional requirements on submittals.
1.2 PROJECT MANAGEMENT AND COORDINATION
A. Coordinate construction to ensure efficient and orderly installation of each part of the Work.
B. Schedule and conduct progress meetings at Project site at weekly intervals. Notify COR of meeting dates and times. Require attendance of each subcontractor or other entity concerned with current progress or involved with planning or coordination of future activities.
1. The contractor will record minutes and distribute to everyone concerned, including the COR.
1.3 SUBMITTAL PROCEDURES
A. Coordinate each submittal with fabrications, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
1. No extensions of the Contact Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing., including resubmittals.
2. Email submittals to COR.
B. Identify deviation from the Contract Documents on submittals.
PART 2 - PRODUCTS
2.1 ACTION SUBMITTALS
A. Product Data: Mark each copy to show applicable products and options. Include the following:
1. Manufacturer's written recommendations, product specifications, and installation instructions.
2. Printed performance curves and operational range diagrams.
3. Testing by recognized testing agency.
SUBMITTAL PROCEDURES 013300-6
4. Compliance with specified standards and requirements.
B. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, he shall request substitution as provided below.
The COR will approve or disapprove the request for substitution.
C. Samples: Submit Samples for each element of construction for review of kind, color, pattern, and texture and for a comparison of these characteristics between submittal and actual component as delivered and installed. Include name of manufacturer and product name on label.
2.2 INFORMATIONAL SUBMITTALS
A. Qualification Data: Include lists of completed projects with project names and addresses, names and addresses of owners, and other information specified.
B. Product Certificates: Prepare written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.
1. Test and Inspection Reports: Comply with requirements in Section 014100 "Quality Control."
2.3 CONTRACTOR’S CONSTRUCTION SCHEUDLE
A. Submit a comprehensive, fully developed schedule within 7 days of date of the Notice to Proceed.
B. Preparation: Indicate each significant construction activity and the location within building separately. Identify first workday of each week.
PART 3 - EXECUTION
3.1 SUBMITTAL REVIEW
A. Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions.
B. COR will review each action submittal, make marks to indicate corrections or modifications required, stamp and mark as appropriate to indicate action taken, and return copies less those retained.
3.2 CONTRACTOR'S CONSTRUCTION SCHEDULE
A. Distribute copies of approved schedule to COR, subcontractors, and parties identified by Contractor with a need-to-know schedule responsibility. When revisions are made, distribute updated schedules to the same parties.
B. Updating: At bi-weekly intervals, update schedule to reflect actual construction progress and activities. Issue revised schedule at each regularly scheduled progress meeting.
SUBMITTAL PROCEDURES 013300-7
1. As the Work progresses, indicate Actual Completion percentage for each activity.
3.3 SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications. The following table is a summary of the required submittals for the project. The table is intended to assist the Contractor and may not be all inclusive. Additional submittals may be required by specific specifications:
TABLE 013000-1
Spec.
Section
Section Title Required Submittal
When Required
013300 Submittal Procedures
Construction Schedule Preconstruction conference
014100 Quality Control
Quality Control Plan Preconstruction conference
014100 Quality Control
Certificates As needed per specifications
014100 Quality Control
Test and Inspection Reports
As needed per specifications.
017320 Selective Demolition
Schedule of Selective Demolition Activities
Prior to beginning work
079200 Joint Sealants Product Data, Color Samples, Warranty
Prior to work
085413 Fiberglass
Windows and Hardware
Product Data, Color Samples, Warranty Prior to work
099300
Staining and Transparent Finishing
Product Data, Color Samples Prior to work
END OF SECTION 013300
QUALITY CONTROL 014100-8
SECTION 014100 - QUALITY CONTROL
PART 1 - GENERAL
1.1 This work shall consist of providing quality control in conformance with the inspection, testing, and product certification requirements of this contract to ensure compliance with the drawings and specifications. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of the contract.
1.2 QUALITY CONTROL
A. The Contractor shall provide and maintain a quality control system that will ensure all services, supplies, and construction work required under this contract conforms to the contract requirements. The Contractor shall perform, or cause to be performed, the sampling, inspection, and testing required to substantiate that all services, supplies, and construction conform to the contract requirements.
B. Retesting/Reinspecting: Contractor shall provide quality-control services for retesting and reinspection for replaced construction work or for work that failed to comply with the requirements under the contract.
1.3 SUBMITTALS
A. Contractor Quality Control Plan
B. Certificates
C. Test and Inspection Reports
D. As-Built Drawings
1.4 MEASUREMENT AND PAYMENT
A. No separate payment will be made for the work included under this section; rather payment shall be considered to be included in the items of work listed in the Schedule of Items.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION
3.1 QUALITY CONTROL SYSTEM
A. General: Perform required testing, inspections, sampling, and similar services per direction specified in the contract drawings and specifications and in accordance with established industry standards.
3.2 CONTRACTOR QUALITY CONTROL PLAN
A. At the time of the preconstruction conference, the Contractor shall submit for approval a written Contractor Quality Control Plan.
QUALITY CONTROL 014100-9
1. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days.
2. The Government reserves the right to require changes in the plan during the contract period as necessary.
3. No change in the approved plan may be made without written concurrence by the Contracting Officer.
4. At a minimum, the plan shall include the following:
a. A list of personnel responsible for quality control and assigned duties.
Include each person's qualifications.
b. A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.
c. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
d. Methods of performing, documenting, and enforcing quality control of all work.
e. Methods of monitoring and controlling environmental pollution and contamination as required by all applicable regulations and laws.
3.3 CERTIFICATES
A. For Contracting Officer’s records, submit copies of certifications, inspection reports, receipts for fee payments, correspondence, records, and similar documents, established for compliance with standards and regulations relevant to the on performance of the work.
3.4 AS-BUILT DRAWINGS
A. The Contractor shall maintain a set of the contract drawings depicting as-built conditions.
These drawings shall be maintained in a current condition and shall be available for review. All variations from the original contract drawings shall be indicated in red on the drawings. Upon completion of the contract work, as-built drawings shall be submitted to the Contracting Officer.
END OF SECTION 014100
CUTTING AND PATCHING 017310-1
SECTION 017310 - CUTTING AND PATCHING
1.1 SUMMARY
A. This Section includes procedural requirements for cutting and patching.
1.2 DEFINITIONS
A. Cutting: Removal of in-place construction necessary to permit installation or performance of other Work.
B. Patching: Fitting and repair work required to restore surfaces to original conditions after installation of other Work.
1.3 QUALITY ASSURANCE
A. Structural Elements: Do not cut and patch structural elements in a manner that could change their load-carrying capacity or load-deflection ratio.
1. Including, but not limited to: Concrete walls, beams, headers, joists, sheathing.
B. Operational Elements: Do not cut and patch operating elements and related components in a manner that results in reducing their capacity to perform as intended or that will result in increased maintenance or decreased operational life or safety.
C. Miscellaneous Elements: Do not cut and patch miscellaneous elements or related components in a manner that could change their load-carrying capacity that results in reducing their capacity to perform as intended, or that will result in increased maintenance or decreased operational life or safety.
D. Visual Requirements: Do not cut and patch construction in a manner that results in visual evidence of cutting and patching. Do not cut and patch construction exposed on the exterior or in occupied spaces in a manner that would, in the Contracting Officer’s Representative’s opinion, reduce the building's aesthetic qualities. Remove and replace construction that has been cut and patched in a visually unsatisfactory manner.
1.4 MEASUREMENT AND PAYMENT
A. There will be no separate measurement or payment for the work in this section. Payment will be included in the unit price for items shown in the Schedule of Items
PART 2 - PRODUCTS—Not used.
3.1 EXAMINATION
CUTTING AND PATCHING 017310-2
A. Examine surfaces to be cut and patched and conditions under which cutting and patching are to be performed.
1. Compatibility: Before patching, verify compatibility with and suitability of substrates, including compatibility with in-place finishes or primers.
2. Proceed with installation only after unsafe or unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Temporary Support: Provide temporary support of Work to be cut.
B. Protection: Protect in-place construction during cutting and patching to prevent damage.
Provide protection from adverse weather conditions for portions of Project that might be exposed during cutting and patching operations.
C. Adjoining Areas: Avoid interference with use of adjoining areas or interruption of free passage to adjoining areas.
3.3 PERFORMANCE
A. General: Employ skilled workers to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time, and complete without delay.
1. Cut in-place construction to provide for installation of other components or performance of other construction, and subsequently patch as required to restore surfaces to their original condition.
B. Cutting: Cut in-place construction by sawing, drilling, breaking, chipping, grinding, and similar operations, including excavation, using methods least likely to damage elements retained or adjoining construction. If possible, review proposed procedures with original Installer; comply with original Installer's written recommendations.
1. In general, use hand or small power tools designed for sawing and grinding, not hammering and chopping. Cut holes and slots as small as possible, neatly to size required, and with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.
2. Concrete: Cut using a cutting machine, such as an abrasive saw or a diamond-core drill.
3. Excavating and Backfilling: Comply with requirements in applicable Division 2 Sections where required by cutting and patching operations.
4. Mechanical and Electrical Services: Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal remaining portion of pipe or conduit to prevent entrance of moisture or other foreign matter after cutting.
C. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other Work. Patch with durable seams that are as invisible as possible. Provide materials and comply with installation requirements specified in other Sections.
CUTTING AND PATCHING 017310-3
1. Inspection: Where feasible, test and inspect patched areas after completion to demonstrate integrity of installation.
2. Exposed Finishes: Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will eliminate evidence of patching and refinishing.
a. Clean piping, conduit, and similar features before applying paint or other finishing materials.
b. Restore damaged pipe covering to its original condition.
3. Floors and Walls: Where walls or partitions that are removed extend one finished area into another, patch and repair floor and wall surfaces in the new space. Provide an even surface of uniform finish, color, texture, and appearance. Remove in-place floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance.
D. Cleaning: Clean areas and spaces where cutting and patching are performed. Completely remove paint, mortar, oils, putty, and similar materials.
END OF SECTION 017310
SELECTIVE DEMOLITION 017320-1
SECTION 017320 - SELECTIVE DEMOLITION
1.1 SUMMARY
A. This Section includes demolition and removal of the following:
1. Selected portions of buildings and structures.
2. Repair procedures for selective demolition operations.
1.2 DEFINITIONS
A. Remove: Detach items from existing construction and legally dispose of them off-site, unless indicated to be removed and salvaged or removed and reinstalled.
B. Remove and Re-use: Detach items from existing construction, prepare them for reuse, and reinstall them where indicated.
C. Existing to Remain: Existing items of construction that are not to be removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.
1.3 MATERIALS OWNERSHIP
A. Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain Government property, demolished materials shall become Contractor's property and shall be removed from Project site.
1.4 SUBMITTALS
A. Schedule of Selective Demolition Activities: Indicate detailed sequence of selective demolition and removal work, with starting and ending dates for each activity, protection of property during demolition, and means of egress.
B. Pre-demolition Photographs or Videotape: Show existing conditions of adjoining construction and site improvements that might be misconstrued as damage caused by selective demolition operations. Submit before Work begins.
1.5 PROJECT CONDITIONS
SELECTIVE DEMOLITION 017320-2
A. Government employees and the public will occupy portions of building immediately adjacent to the selective demolition area. Contractor may close individual rooms during construction but must provide 48-hour notice to the Forest Service so that alternate arrangements for those affected by the work can be arranged.
B. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.
1. Do not close or obstruct walkways, corridors, or other occupied or used facilities unless approved by the Contracting Officer.
C. Government assumes no responsibility for condition of areas to be selectively demolished.
1. Conditions existing at time of inspection for bidding purpose will be maintained by Government as far as practical.
2. Contractor shall move office furniture as needed to complete the work.
3. Government will ensure all fragile/sensitive and loose items are removed and secured prior to contractor moving furniture.
D. Storage or sale of removed items or materials on-site will not be permitted.
1.6 MEASUREMENT AND PAYMENT
A. No separate measurement or payment will be made for work specified in this section. All work will be included in items shown in the Schedule of Items.
PART 2 - PRODUCTS
2.1 REPAIR MATERIALS
A. Use repair materials identical to existing materials.
1. If identical materials are unavailable or cannot be used for exposed surfaces, use materials that visually match existing adjacent surfaces to the fullest extent possible.
2. Use materials whose installed performance equal or surpass that of existing materials.
SELECTIVE DEMOLITION 017320-3
A. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.
B. Inventory and record the condition of items to be removed and reinstalled.
C. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, notify the Contracting Officer of the conflict.
3.2 UTILITY SERVICES
A. Existing Utilities: Maintain services and protect them against damage during selective demolition operations.
B. Do not interrupt existing utilities serving occupied or operating facilities unless authorized in writing by CO.
3.3 PREPARATION
A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, driveways, walks, and other adjacent occupied and used facilities.
1. Do not close or obstruct roads, driveways, walks, walkways, or other adjacent occupied or used facilities without permission from CO.
2. Protect existing site improvements, appurtenances, and landscaping to remain.
B. Temporary Facilities: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.
3.4 POLLUTION CONTROLS
A. Disposal: Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
1. Remove debris from elevated portions of building by chute, hoist, or other device that will convey debris to grade level in a controlled descent.
B. Cleaning: Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.
SELECTIVE DEMOLITION 017320-4
3.5 SELECTIVE DEMOLITION
A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations.
1. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction.
2. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.
3. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.
4. Other materials: Will be demolished in an orderly and organized way. Dispose of all materials legally.
B. Removed and Reinstalled Items:
1. Clean and repair items to functional condition adequate for intended reuse.
2. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.
C. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by CO, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.
3.6 PATCHING AND REPAIRS
A. General: Promptly repair damage to adjacent construction caused by selective demolition operations.
B. Repairs: Where repairs to existing surfaces are required, patch to produce surfaces suitable for new materials.
C. Finishes: Restore exposed finishes of patched areas and extend restoration into adjoining construction in a manner that eliminates evidence of patching and refinishing.
3.7 DISPOSAL OF DEMOLISHED MATERIALS
A. General: Promptly dispose of demolished materials. Do not allow demolished materials to accumulate on-site.
B. Burning: Do not burn demolished materials.
SELECTIVE DEMOLITION 017320-5
C. Disposal: Transport demolished materials off Government property and legally dispose of them.
END OF SECTION 017320
WASTE MATERIAL DISPOSAL 024100-1
SECTION 024100 - WASTE MATERIAL DISPOSAL
1.1 SUMMARY
A. This Section includes the loading, handling, hauling, and placing of construction debris.
1.2 MEASUREMENT AND PAYMENT
A. There will be no separate measurement or payment for work in this Section. Waste material disposal is considered incidental to other items of work shown in the Schedule of Items.
PART 2 - PRODUCTS – NOT APPLICABLE
3.1 Waste material to be removed:
A. All demolition materials, garbage, and other refuse generated.
3.2 Disposal Site:
A. All waste material shall be removed from the project site and legally disposed off Government property in an approved landfill.
1. The contractor is responsible for all costs and permits associated with landfill disposal.
2. The Government is not responsible for waste material upon its departure from the project site.
END OF SECTION 024100
FINISH CARPENTRY 062000-1
SECTION 062000 - FINISH CARPENTRY
PART 1 – GENERAL
1. SUMMARY
A. This section includes the following:
a. Interior Wood Trim and Sills
2. SUBMITTALS
A. Product samples or Data: For each of the materials listed below.
a. Interior Wood Trim and Sills
1. MATERIALS
A. Lumber: DOC PS 20 and grading rules of inspection agencies certified by
American Lumber Standards Committee Board of Review.
B. Exterior Wood Trim: D select (Quality) eastern white, Idaho white, lodgepole, ponderosa, or sugar pine
C. Interior Wood Trim: Softwood Lumber Trim: Eastern white, Idaho white, lodgepole, ponderosa, or sugar pine; Grade D Select (Quality).
D. Wood Molding Patterns: Made to patterns in WMMPA WM 7 from kiln-dried stock graded under WMMPA WM 4.
E. Moldings for Painted Finish: P-Grade eastern white, Idaho white, lodgepole, ponderosa, or sugar pine
1. INSTALLATION
A. Condition finish carpentry in installation areas for 24 hours before installing.
B. Prime lumber for painted/stained finish exposed on the exterior.
C. Install finish carpentry level, plumb, true, and aligned with adjacent materials.
Scribe and cut to fit adjoining work. Refinish and seal cuts.
D. Install wood trim and sills with minimum number of joints practical, using full-length pieces from maximum lengths of lumber available. Stagger joints in adjacent and related trim. Cope at returns and miter at corners.
FINISH CARPENTRY 062000-2
E. Nail siding at each stud. Do not allow nails to penetrate more than one thickness of siding, unless otherwise recommended by siding manufacturer. Seal joints at inside and outside corners and at trim locations.
END OF SECTION 062000
JOINT SEALANTS 079200-1
SECTION 079200 - JOINT SEALANTS
1.1 SUMMARY
A. Section Includes the following, where indicated or required:
1. Silicone joint sealants.
B. Related Sections:
1. Division 08 Section "Glazing" for glazing sealants.
2. Division 09 Section "Gypsum Board" for sealing perimeter joints.
1.2 PROJECT CONDITIONS
A. Do not proceed with installation of joint sealants under the following conditions:
1. When joint substrates are wet.
2. Where joint widths are less than those allowed by joint-sealant manufacturer for applications indicated.
3. Where contaminants capable of interfering with adhesion have not yet been removed from joint substrates.
1.3 MEASUREMENT AND PAYMENT
A. There will be no separate measurement or payment for work in this section. Payment will be included in the contract unit price for items shown in the schedule of items.
PART 2 - PRODUCTS
2.1 MATERIALS, GENERAL
A. Compatibility: Provide joint sealants, backings, and other related materials that are compatible with one another and with joint substrates under conditions of service and application, as demonstrated by joint-sealant manufacturer, based on testing and field experience.
B. Liquid-Applied Joint Sealants: Comply with ASTM C 920 and other requirements indicated for each liquid-applied joint sealant specified, including those referencing ASTM C 920 classifications for type, grade, class, and uses related to exposure and joint substrates.
C. Colors of Exposed Joint Sealants: As selected by Contracting Officer from manufacturer's full range.
JOINT SEALANTS 079200-2
2.2 ELASTOMERIC JOINT SEALANTS
A. Elastomeric Sealant Standard: Comply with ASTM C 920 and other requirements indicated for each liquid-applied chemically curing sealant in the Elastomeric Joint-Sealant Schedule at the end of Part 3, including those referencing ASTM C 920 classifications for type, grade, class, and uses.
B. Available Products: Subject to compliance with requirements, joint sealant schedule, and manufacturer's recommendations, provide one of the products specified in each category below where needed:
1. Elastomeric Joint Sealant Designation: ES1
a. Base Polymer: Neutral-curing silicone.
b. Type: S (single component).
c. Grade: NS (nonsag).
d. Class: 25.
e. Additional Movement Capability: 50 percent movement in extension and 50 percent in compression for a total of 100 percent movement.
f. Use[s] Related to Exposure: NT (nontraffic).
g. Uses Related to Joint Substrates: M (mortar), A (aluminum) and, as applicable to joint substrates indicated, O (other).
h. Products:
1) Dow Corning 795
2) GE Silpruf
3) Tremco Spectrem 2
4) Approved equal
2. Elastomeric Joint Sealant Designation: ES2
a. Base Polymer: Acid-curing silicone.
b. Type: S (single component).
c. Grade: NS (nonsag).
d. Class: 25.
e. Additional Movement Capability: 25 percent movement in extension and 25 percent in compression for a total of 50 percent movement.
f. Use[s] Related to Exposure: NT (nontraffic).
g. Uses Related to Joint Substrates: G (glass), A (aluminum) and, as applicable to joint substrates indicated, O (other).
h. Products:
1) Dow Corning 999-A
2) GE Contractors 1200
3) Pecora 863
4) Tremco Tremsil 300
5) Approved equal
JOINT SEALANTS 079200-3
2.3 JOINT-SEALANT BACKING
A. General: Provide sealant backings of material and type that are nonstaining; are compatible with joint substrates, sealants, primers, and other joint fillers; and are approved for applications indicated by sealant manufacturer based on field experience and laboratory testing.
B. Plastic Foam Joint Fillers: Preformed, compressible, resilient, nonstaining, nonwaxing, nonextruding strips of flexible plastic foam of material indicated below and of size, shape, and density to control sealant depth and otherwise contribute to producing optimum sealant performance:
1. Closed-cell polyethylene foam, nonabsorbent to liquid water and gas, nonoutgassing in unruptured state.
C. Bond-Breaker Tape: Polyethylene tape or other plastic tape recommended by sealant manufacturer for preventing sealant from adhering to rigid, inflexible joint-filler materials or joint surfaces at back of joint where such adhesion would result in sealant failure. Provide self-adhesive tape where applicable.
2.4 MISCELLANEOUS MATERIALS
A. Primer: Material recommended by joint-sealant manufacturer where required for adhesion of sealant to joint substrates indicated, as determined from preconstruction joint-sealant-substrate tests and field tests.
B. Cleaners for Nonporous Surfaces: Chemical cleaners acceptable to manufacturers of sealants and sealant backing materials, free of oily residues or other substances capable of staining or harming joint substrates and adjacent nonporous surfaces in any way, and formulated to promote optimum adhesion of sealants to joint substrates. Confirm compatibility of cleaners with adjacent surfaces prior to application.
C. Masking Tape: Nonstaining, nonabsorbent material compatible with joint sealants and surfaces adjacent to joints.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine joints indicated to receive joint sealants, with Installer present, for compliance with requirements for joint configuration, installation tolerances, and other conditions affecting joint-sealant performance.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
JOINT SEALANTS 079200-4
A. Surface Cleaning of Joints: Clean out joints immediately before installing joint sealants to comply with joint-sealant manufacturer's written instructions and the following requirements:
1. Remove all foreign material from joint substrates that could interfere with adhesion of joint sealant, including dust, paints (except for permanent, protective coatings tested and approved for sealant adhesion and compatibility by sealant manufacturer), old joint sealants, oil, grease, waterproofing, water repellents, water, surface dirt, and frost.
2. Clean porous joint substrate surfaces by brushing, grinding, mechanical abrading, or a combination of these methods to produce a clean, sound substrate capable of developing optimum bond with joint sealants. Remove loose particles remaining after cleaning operations above by vacuuming or blowing out joints with oil-free compressed air. Porous joint substrates include the following:
a. Concrete.
b. Masonry.
c. Unglazed surfaces of ceramic tile.
d. Exterior insulation and finish systems.
3. Remove laitance and form-release agents from concrete.
4. Clean nonporous joint substrate surfaces with chemical cleaners or other means that do not stain, harm substrates, or leave residues capable of interfering with adhesion of joint sealants. Nonporous joint substrates include the following:
a. Metal.
b. Glass.
c. Porcelain enamel.
d. Glazed surfaces of ceramic tile.
B. Joint Priming: Prime joint substrates where recommended by joint-sealant manufacturer or as indicated by preconstruction joint-sealant-substrate tests or prior experience. Apply primer to comply with joint-sealant manufacturer's written instructions. Confine primers to areas of joint-sealant bond; do not allow spillage or migration onto adjoining surfaces.
C. Masking Tape: Use masking tape where required to prevent contact of sealant or primer with adjoining surfaces that otherwise would be permanently stained or damaged by such contact or by cleaning methods required to remove sealant smears. Remove tape immediately after tooling without disturbing joint seal.
3.3 INSTALLATION OF JOINT SEALANTS
A. General: Comply with joint-sealant manufacturer's written installation instructions for products and applications indicated, unless more stringent requirements apply.
B. Install sealant backings of kind indicated to support sealants during application and at position required to produce cross-sectional shapes and depths of installed sealants relative to joint widths that allow optimum sealant movement capability.
JOINT SEALANTS 079200-5
1. Do not leave gaps between ends of sealant backings.
2. Remove absorbent sealant backings that have become wet before sealant application and replace them with dry materials.
C. Install bond-breaker tape behind sealants where sealant backings are not used between sealants and backs of joints.
D. Install sealants using proven techniques that comply with the following and at the same time backings are installed:
1. Place sealants so they directly contact and fully wet joint substrates.
2. Completely fill recesses in each joint configuration.
3. Produce uniform, cross-sectional shapes and depths relative to joint widths that allow optimum sealant movement capability.
E. Tooling of Nonsag Sealants: Immediately after sealant application and before skinning or curing begins, tool sealants according to requirements specified in subparagraphs below to form smooth, uniform beads of configuration indicated; to eliminate air pockets; and to ensure contact and adhesion of sealant with sides of joint.
1. Remove excess sealant from surfaces adjacent to joints.
2. Use tooling agents that are approved in writing by sealant manufacturer and that do not discolor sealants or adjacent surfaces.
3. Provide concave joint profile per Figure 8A in ASTM C 1193, unless otherwise indicated.
4. Provide flush joint profile where indicated per Figure 8B in ASTM C 1193.
5. Provide recessed joint configuration of recess depth and at locations indicated per
Figure 8C in ASTM C 1193.
a. Use masking tape to protect surfaces adjacent to recessed tooled joints.
3.4 CLEANING
A. Clean off excess sealant or sealant smears adjacent to joints as the Work progresses by methods and with cleaning materials approved in writing by manufacturers of joint sealants and of products in which joints occur.
3.5 PROTECTION
A. Protect joint sealants during and after curing period from contact with contaminating substances and from damage resulting from construction operations or other causes so sealants are without deterioration or damage at time of Substantial Completion. If, despite such protection, damage or deterioration occurs, cut out and remove damaged or deteriorated joint sealants immediately so installations with repaired areas are indistinguishable from original work.
JOINT SEALANTS 079200-6
3.6 JOINT SEALANT SCHEDULE (Select from the following where indicated or required)
JOINT SEALANT SCHEDULE
DESIGNATION
ON DATA
SHEETS
JOINT
SEALERS
DESCRIPTION OF JOINT
CONSTRUCTION AND LOCATION
WHERE SEALANT IS TYPICALLY
APPLIED
ES-1
One-Part Neutral Cure Silicone Sealant
Exterior and interior joints in vertical surfaces of concrete and masonry; between concrete masonry and stone; between metal and concrete, mortar, or stone; interior and exterior perimeter joints of metal frames in exterior walls; exterior overhead joints. Joints which are bordered by glass.
ES-2
One-Part Acid Curing Silicon
Exterior and interior joints in vertical surfaces of non-pourous surfaces. To be used on exterior and interior perimeter frames of walls and control and expansion and window joints. Between metal to metal, glass to glass, metal to glass, travertine to travertine, cap beads on glass.
END OF SECTION 079200
FIBERGLASS WINDOWS 085413-1
SECTION 085413 - FIBERGLASS WINDOWS
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes fiberglass-framed windows.
1.3 ACTION SUBMITTALS
A. Product Data: For each type of product.
1. Include construction details, material descriptions, glazing and fabrication methods, dimensions of individual components and profiles, hardware, and finishes for fiberglass windows.
B. Shop Drawings: For fiberglass windows.
1. Include plans, elevations, sections, hardware, accessories, insect screens, operational clearances, and details of installation, including anchor, flashing, and sealant installation.
C. Product Schedule: For fiberglass windows. Use same designations indicated on Drawings.
1.4 INFORMATIONAL SUBMITTALS
A. Qualification Data: For manufacturer and Installer.
B. Product Test Reports: For each type of fiberglass window, for tests performed by a qualified testing agency.
C. Field quality-control reports.
FIBERGLASS WINDOWS 085413-2
1.5 QUALITY ASSURANCE
A. Manufacturer Qualifications: A manufacturer capable of fabricating fiberglass windows that meet or exceed performance requirements indicated and of documenting this performance by test reports and calculations.
B. Installer Qualifications: An installer acceptable to fiberglass window manufacturer for installation of units required for this Project.
1.6 WARRANTY
A. Manufacturer's Warranty: Manufacturer agrees to repair or replace fiberglass windows that fail in materials or workmanship within specified warranty period.
1. Failures include, but are not limited to, the following:
a. Failure to meet performance requirements.
b. Structural failures including excessive deflection, water leakage, and air infiltration.
c. Faulty operation of movable sash and hardware.
d. Deterioration of materials and finishes beyond normal weathering.
e. Failure of insulating glass.
2. Warranty Period:
a. Window: 10 years from date of Substantial Completion.
b. Glazing Units, Non-Laminated: 20 years from date of Substantial Completion.
a. Glazing Units, Laminated: 10 years from date of Substantial Completion.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Source Limitations: Obtain fiberglass windows from single source from single manufacturer.
2.2 WINDOW PERFORMANCE REQUIREMENTS
A. Product Standard: Comply with AAMA/WDMA/CSA 101/I.S.2/A440 for definitions and minimum standards of performance, materials, components, accessories, and fabrication unless more stringent requirements are indicated.
1. Window Certification: WDMA certified with label attached to each window.
FIBERGLASS WINDOWS 085413-3
B. Performance Class and Grade: AAMA/WDMA/CSA 101/I.S.2/A440 as follows:
1. Performance Class: Commercial
C. Thermal Transmittance: NFRC 100 maximum whole-window U-factor of 0.32 Btu/sq. ft.
x h x deg F (1.83 W/sq. m x K )
D. Solar Heat-Gain Coefficient (SHGC): NFRC 200 maximum whole-window SHGC of 0.40.
2.3 FIBERGLASS WINDOWS
A. Basis-of-Design Product: Subject to compliance with requirements, provide Pella Corporation; Pella® Impervia® or approved equal product by one of the following:
1. Accurate Dorwin.
2. Alpen High Performance Products.
3. Inline Fiberglass Ltd.
4. Milgard Manufacturing, Inc.
B. Operating Types: Provide the following operating types in locations indicated on Drawings:
1. Casement
2. Horizontal sliding.
C. Frames and Sashes: Pultruded fiberglass complying with AAMA/WDMA/CSA 101/I.S.2/A440 and with exposed exterior fiberglass surfaces finished with manufacturer's standard enamel coating complying with AAMA 624.
1. Exterior Color: TO be selected manufactures colors and approved by COR
2. Interior Finish: TO be selected manufactures colors and approved by COR
D. Insulating-Glass Units: ASTM E2190.
1. Glass: ASTM C1036, Type 1, Class 1, q3.
a. Tint: Bronze
b. Kind: Fully tempered.
2. Type: double pane argon-filled low-E. Obscure tempered where called out.
3. Type: High Altitude Natural Sun Low-E Coating Insulated Glass with Argon.
E. Glazing System: Manufacturer's standard factory-glazing system that produces weathertight seal.
F. Hardware, General: Provide manufacturer's standard hardware fabricated from aluminum, stainless steel, carbon steel complying with AAMA 907, or other corrosion-resistant material compatible with adjacent materials; designed to smoothly operate, tightly close, FIBERGLASS WINDOWS 085413-4 and securely lock fiberglass windows, and sized to accommodate sash weight and dimensions.
1. Exposed Hardware Color and Finish: As indicated by manufacturer's designations, to be approved by COR.
G. Projected/Casement Window Hardware:
1. Gear-Type Rotary Operators: Complying with AAMA 901 when tested in accordance with ASTM E405, Method A. Provide operators that function without requiring the removal of interior screens or using screen wickets.
a. Type and Style: Match window interior.
b. Easy-slide Operator
2. Hinges: Manufacturer's standard type for sash weight and size indicated.
3. Single-Handle Locking System: Operates positive-acting arms that pull sash into locked position. Provide one arm on sashes up to 27-1/2 inches (700 mm) tall and one arms on taller sashes.
4. Provide standard fiberglass screen.
H. Horizontal-Sliding Window Hardware:
1. Sill Cap/Track: Manufacturer's standard of dimensions and profile indicated; designed to comply with performance requirements indicated and to drain to the exterior.
2. Locks and Latches:
a. Self-aligning, cam-action lock.
b. Allow unobstructed movement of the sash across adjacent sash in direction indicated and operated from the inside only.
c. Windows 37 Inches High or Greater: 2 locks.
3. Roller Assemblies: Low-friction design.
4. Standard Finish: Match window interior.
5. Provide standard fiberglass screen.
I. Weather Stripping: Provide full-perimeter weather stripping for each operable sash unless otherwise indicated.
J. Fasteners: Noncorrosive and compatible with window members, trim, hardware, anchors, and other components.
1. Exposed Fasteners: Do not use exposed fasteners to greatest extent possible. For application of hardware, use fasteners that match finish hardware being fastened.
FIBERGLASS WINDOWS 085413-5
2.4 INSECT SCREENS
A. General: Fabricate insect screens to integrate with window frame. Provide screen for each operable exterior sash. Screen wickets are not permitted.
1. Type and Location: half, outside for sliding sashes. Full, casement/projected.
B. Aluminum Frames: Manufacturer's standard aluminum alloy complying with SMA 1004 or SMA 1201. Fabricate frames with mitered or coped joints or corner extrusions, concealed fasteners, and removable PVC spline/anchor concealing edge of frame.
1. Tubular Framing Sections and Cross Braces: Roll formed from aluminum sheet.
2. Finish for Interior Screens: Baked-on organic coating in color selected by COR from manufacturer's full range
3. Finish for Exterior Screens: Matching color and finish of unit
C. Glass-Fiber Mesh Fabric: 18-by-14 (1.1-by-1.4-mm) mesh of PVC-coated, glass-fiber threads; woven and fused to form a fabric mesh resistant to corrosion, shrinkage, stretch, impact damage, and weather deterioration. Comply with ASTM D3656/D3656M.
1. Mesh Color: [Manufacturer's standard].
2.5 FABRICATION
A. Fabricate fiberglass windows in sizes indicated. Include a complete system for installing and anchoring windows.
B. Glaze fiberglass windows in the factory.
C. Weather strip each operable sash to provide weathertight installation.
2.6 INSTALLATION ACCESSORIES
A. Exterior Perimeter Sealant: Geocel Proflex Tripolymer Sealant, or approved equal. Per manufactures requirements
B. Insulating-Foam Sealant: Dow Chemical Great Stuff Window and Door Insulating Foam Sealant or approved equal.
C. Low-pressure, polyurethane window and door insulating-foam sealant per manufactures requirements.
FIBERGLASS WINDOWS 085413-6
2.7 SOURCE QUALITY CONTROL
A. Factory Testing: Factory test individual standard operable windows for air infiltration in accordance with ASTM E 283, to ensure compliance with this specification
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine openings, substrates, structural support, anchorage, and conditions, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of the Work.
B. Verify rough opening dimensions, levelness of sill plate, and operational clearances.
C. Examine wall flashings, vapor retarders, water and weather barriers, and other built-in components to ensure weathertight window installation.
D. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. Comply with manufacturer's written instructions for installing windows, hardware, accessories, and other components. For installation procedures and requirements not addressed in manufacturer's written instructions, comply with installation requirements in
ASTM E2112.
B. Install windows level, plumb, square, true to line, without distortion, anchored securely in place to structural support, and in proper relation to wall flashing and other adjacent construction to produce weathertight construction.
C. Maintain alignment with adjacent work.
D. Secure assembly to framed openings, plumb and square, without distortion.
E. Place interior seal around window perimeter to maintain continuity of building thermal and air barrier using insulating foam sealant.
F. Seal window to exterior wall cladding with sealant and related backing materials at perimeter of assembly.
G. Leave windows closed and locked.
FIBERGLASS WINDOWS 085413-7
H. Replace trim (unless otherwise indicated in the drawings), or if trim is not usable, install trim that coordinates with other interior trim as approved by the…