J1 Attachment Justification and Approval 4 Pages_Redacted.pdf
PDF 500 KB Posted
- Solicitation number
- 2026-LGR-0042
- Issued by
-
Library of Congress
About this file
This is a Justification and Approval for Other than Full and Open Competition document (Plan ID: 2026-LGR-0042) submitted by the Library of Congress, National Audio-Visual Conservation Center, for a sole-source contract award to Cube-Tec North America, LLC. The contract is valued at an undisclosed amount (redacted) with a performance period from June 1, 2026, through May 31, 2031. The Library is seeking contract support to implement critical upgrades and functionality for the Cube-Tec CD Inspector and Dobbin media archiving systems to preserve compact discs within the recorded sound collection. Required deliverables include implementation of Disc Description Protocol (DDP) file format capability for complete disc image capture with embedded metadata, standard cue-sheet output to comply with the National Audio-Visual Conservation Center's ingest and cataloging protocols, ongoing software support, and the purchase of spare optical disc drives for future drive failure mitigation.
The justification for sole-source award centers on Cube-Tec's unique position as the only responsible source capable of satisfying the Library's requirements. The CD Inspector is a highly specialized system with proprietary hardware and software components designed specifically for professional audio inspection and archival workflows. Only Cube-Tec has authorized access to the proprietary source code and possesses the technical expertise required for system enhancements and updates. The Library contends that engaging an alternative vendor would compromise system integrity, void existing warranties and future maintenance agreements, and result in substantial duplication costs not recoverable through competition. The Contracting Officer James R. Robinson approved the sole-source justification on February 11, 2026, under FAR 6.302-1 authority, confirming accurate and complete justification documentation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| J2 Attachment Statement of Work 3 Pages.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Justification and Approval For Other than Full and Open Competition
Plan ID Number: 2026-LGR-0042
Form Updated 4/14/2023
Justification & Approval
As a legislative branch agency, the Library is subject to the competition and advertising requirements of 41 U.S.C. § 6101. Like the Competition in Contracting Act and the FAR, 41 U.S.C. § 6101 does not require competition when a contracting officer certifies that only one source or brand-name item is available, when dictated by public exigency, or when otherwise authorized by law.
This document sets forth the justification and approval for award of a contract or order by means providing for other than full and open competition per 41 U.S.C. § 6101, LCR 7-210, and, as applicable, FAR 6.302, FAR 13.106-1, FAR 8.405, and FAR 16.505. Contracting without competition shall not be justified on the basis of a lack of advance planning or concerns related to availability of funds.
This form shall be used to support instances where competition will be limited to a single source, a limited number of sources, including where a brand name product is required.
Part 1 – Identification
1. Contracting Agency and Activity: Library of Congress, Library Collections and Services Group, Researcher and Collections Services, National Audio-Visual Conservation Center
2. Nature of Action Being Approved
Contract LoC or Leg Branch Order GSA Schedule or GWAC Other
Plan ID Number: 2026-LGR-0042 Contractor (or Brand Name): Cube-Tec Estimated Value (Base and all options):
Period of Performance: 06/01/2026-05/31/2031
3. Description of Supplies or Services Required to Meet Library Needs
Describe the supplies or services that are required to meet the Library’s minimum needs and the delivery schedule required to meet those needs. Do not focus on a description of the program.
The Library requires the following supplies or services:
The Library of Congress (Library) NAVCC Audio Lab requires contract support to implement critical upgrades and functionality for the Cube-Tec CD Inspector and Dobbin media archiving systems to support the preservation of compact discs within the recorded sound collection. The Disc Description Protocol (DDP) is the industry standard file format for CD replication and manufacturing and enables the Audio Lab to capture complete disc images with rich embedded metadata. Standard cue-sheet output is also required to comply with the NAVCC’s ingest and cataloging protocols. In addition, ongoing software support is required, along with the purchase of spare optical disc drives to address potential future drive failure.
The Library’s rationale for contracting without providing for full and open competition is that only one responsible source-Cube-Tech- can satisfy the agency’s requirements. No other vendor is capable of supply, supporting, or enhancing the Cube-Tec CD Inspector system. The CD Inspector is a highly specialized system consisting of proprietary hardware and software components designed specifically for professional audio inspection and archival workflows. No other company has authorized access to the proprietary source code or the technical expertise required to perform system enhancements or updates. Engaging an alternative vendor would compromise system integrity and quality assurance and would void existing warranties as well as any future maintenance or support agreements with the manufacturer. Because the supplies and services are highly specialized, award to any other source would result in substantial duplication costs to the Government that is not expected to be recovered through competition.
Form Updated 12/10/2025
Part 2 – Program Office Justification & Approval
4. Authority for Contracting Without Competition Over $350,000 For this requirement over $350,000, under FAR part 6, the basis for contracting without providing for full and open competition is:
There is only one responsible source and no other supplies or services will satisfy Library requirements.
41 U.S.C. § 6101(b)(2)(C); FAR 6.302-1.
Library’s minimum needs can only be satisfied by contractor’s unique capabilities or products. FAR 6.302-1(b)(1).
Source controls copyrights, patents, raw materials, or secret processes cannot be acquired otherwise, or similar circumstances. FAR 6.302-
1(b)(2).
Other exception identified in FAR 6.302-1
There is such unusual & compelling urgency that the Government would be seriously injured if competition is not limited.
41 U.S.C. § 6101(b)(2)(B); FAR 6.302-2. Option years are not permitted.
Source is expressly authorized or required by statute (e.g., AbilityOne, UNICOR, GPO, GSA Public Buildings Service, Appropriations Act, etc.) per 41 U.S.C. § 6101(b)(1) and FAR 6.302-5
Other basis authorized in 41 U.S.C. § 6101(b) or FAR part 6.302 Library’s needs can only be satisfied by a brand-name product or item which is essential to the Government’s requirement. FAR 6.302-1(c).
The Product is listed on the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable
IT Standard Data Sheet)
Up to and including $350,000 For this requirement up to $350,000, using simplified acquisition procedures under FAR part 13, the basis for contracting without providing for full and open competition is:
Only one responsible source is reasonably available to meet Library requirements. 41 U.S.C. § 6101(b); FAR 13.106-1.
Product or service is reasonably available from only one source.
Source controls copyrights, patents or other exclusive licensing arrangements.
Urgent circumstances; only one source can reasonably deliver by required date. Option years are not permitted.
Source is expressly authorized or required by statute:
Library’s needs can only be satisfied by a brand-name product The Product is listed the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable
IT Standard Data Sheet)
GSA Schedule Order For this GSA schedule order under FAR part 8, the basis for not competing among GSA schedule-holders and/or specifying a brand name product or item is:
An urgent and compelling need exists, and following GSA procedures would result in unacceptable delays.
FAR 8.405-6(a)(1)(i)(A).
Only one GSA source is capable of fulfilling the requirement at the level of quality required because the supplies or services are unique or highly specialized. FAR 8.405-6(a)(1)(i)(B).
In the interest of economy and efficiency, the new work is a logical follow-on to an original order that was placed competitively among GSA schedule-holders (i.e., the original order was not sole-source or limited-source.) FAR 8.405-6(a)(1)(i)(C).
Library’s needs can only be satisfied by a brand-name product The Product is listed on the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable
IT Standard Data Sheet)
Order Under Multiple Award Indefinite-Delivery Contract or GWAC For this order under FAR subpart 16.5, the basis for contracting without providing for full and open competition is:
The need is so urgent fair opportunity would result in unacceptable delays. 41 U.S.C. § 6101(b)(2)(C) and FAR 16.505(b)(2)(i)(A).
The Library’s minimum needs can only be satisfied by contractor’s unique capabilities or products. 41 U.S.C. § 6101(b)(1) and FAR
16.505(b)(2)(i)(B).
A logical follow-on order in the interest of economy and efficiency. 41 U.S.C. § 6101(b)(1) and FAR 16.505(b)(i)(2)(C).
To satisfy a minimum guarantee. 41 U.S.C. § 6101(b)(1) and FAR 16.505(b)(2)(D).
Authorized or required by statute. 41 U.S.C. § 6101(b)(1) and FAR 16.505(b)(2)(E).
The Library’s minimum needs can only be satisfied by a brand-name product or item which is essential to the Government’s requirement. 41
U.S.C. § 6101(b)(2)(B) and FAR 16.505(a)(4)(i).
The Product is listed on the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable
IT Standard Data Sheet)
5. Rationale for Contracting Without Competition
In supporting an action not providing for full and open competition, it is not sufficient to demonstrate that the contractor is exceptionally well qualified or even the best qualified, or that the required brand name product is well suited to the Library’s needs. The rationale must demonstrate that no one else, or no other competing product, can satisfactorily fulfill the Library’s requirement. Do not focus on the importance of the requirement; the issue is the rationale for not competing.
In supporting urgency, address the following: What are the unexpected facts or the unpredictable events that led to this situation? When is the required delivery or performance start date? Why this date? What specific harm to the Government will occur if the delivery is not made or performance not begun as scheduled? (Note that
Form Updated 12/10/2025
0BPART 3 – CONTRACTING OFFICER DETERMINATIONS & CERTIFICATION
8. Efforts to Solicit from As Many Potential Sources As Practicable Unless a justification is based on FAR 6.302-2, Unusual and compelling urgency, contracting officers shall post justifications for other than full and open competition, including brand name justifications, to the Contract Opportunities website on sam.gov (or eBuy for Brand Name Justifications under FAR Part 8) prior to requesting a proposal or otherwise entering into negotiations.
Advance notice will be published in sam.gov for 15 days before a contract is awarded. FAR 5.203(a).
Advance or concurrent notice will be published in sam.gov for a reasonable time for commercial items FAR 5.203(a) and 12.204(b).
Advance notice will not be published because the action meets the following FAR exception:
Notice would compromise national security. FAR 5.202(a)(1).
Unusual and compelling urgency; notice period would seriously injure Government. FAR 5.202(a)(2).
Expressly authorized or required to be made through another Government agency. FAR 5.202(a)(4).
Order will be placed against an IDIQ contract awarded under FAR 16.5. FAR 5.202(a)(6).
Order will be placed against GSA schedule or other competitively awarded contract. FAR 5.202(a)(11).
Other:
Advance notice will not be published per 41 U.S.C. § 6101; see attached deviation from the FAR per LCR 7-210 § 3.A.
We made the following efforts to interest potential sources in this award: N/A
9. Listing of Sources That Expressed Interest in Writing
The following sources expressed interest in this award: N/A
10. Additional Information
The following additional information is relevant to this justification and approval: N/A
11. Contracting Officer Determination that Price Is Fair and Reasonable As explained in detail below, I have determined that the prices for this contracting action are fair and reasonable based on comparison of the prices to the following (see FAR 15.404-1(b)(2)):
Historical prices paid by the Government Published competitive price lists Library’s Independent Government Estimate Prices obtained through market research Other Prices obtained through competitive proposals
The following analysis (based on attached pricing information) supports my determination: A fair and reasonable price shall be determined before an award is made.
12. Contracting Officer Determination of Responsibility Checked System for Award Management (or will check in the case of competitive proposals for a brand name product)
13. Contracting Officer Determination of Best Value I have determined that this action represents the best value to the Government because: Best value shall be made before an award is executed.
14. Contracting Officer Certification I certify that, to the best of my knowledge and belief, this justification is accurate and complete. For those actions up to $900,000, I approve contracting without competition for this requirement.
James R. Robinson James R. Robinson 02/11/2026
Name
Signature
Date
File details come from the government source that posted it. Updated .