Schedule in Support of Block 17 in the SF-1442 Lift Station Replacement Rosebud Hospital Rosebud, SD
| DESCRIPTION |
| SECTION |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| EXTENDED PRICE |
| Remove Concrete Sidewalk |
| 01270 – Price and Payment |
| 205 |
| SF |
| Remove C&G |
| 01270 – Price and Payment |
| 45 |
| LF |
| Remove Concrete Pavement |
| 01270 – Price and Payment |
| 175 |
| SF |
| Remove Asphalt Pavement |
| 01270 – Price and Payment |
| 30 |
| SF |
| Remove Chainlink Fence |
| 01270 – Price and Payment |
| 130 |
| LF |
| Abandon 4" DIP SFM |
| 01270 – Price and Payment |
| 25 |
| LF |
| Abandon 8" DIP Sewer |
| 01270 – Price and Payment |
| 10 |
| LF |
| Demolish Existing Lift Station |
| 01270 – Price and Payment |
| 1 |
| EA |
| 12" SDR PVC |
| 01270 – Price and Payment |
| 25 |
| LF |
| Install Water Service Line/Connect to Ex. |
| 01270 – Price and Payment |
| 15 |
| 4" RJDIP |
| 01270 – Price and Payment |
| 165 |
| LF |
| 4" 45-DEGREE RJDI BENDS |
| 01270 – Price and Payment |
| 5 |
| EA |
| 4" 90-DEGREE RJDI BENDS |
| 01270 – Price and Payment |
| 6 |
| EA |
| 4" Flanged Resistant Wedge Gate Valve |
| 01270 – Price and Payment |
| 2 |
| EA |
| 4" Cross |
| 01270 – Price and Payment |
| 1 |
| EA |
| 4" RJDIP Dust Cap |
| 01270 – Price and Payment |
| 1 |
| EA |
| 4" MJ Gate Valve |
| 01270 – Price and Payment |
| 1 |
| EA |
| 4" Dismantling Joint |
| 01270 – Price and Payment |
| 1 |
| EA |
| 2" Combination ARV |
| 01270 – Price and Payment |
| 1 |
| EA |
| 4" Flanged Swing Flex Check Valve |
| 01270 – Price and Payment |
| 2 |
| EA |
| Floats |
| 01270 – Price and Payment |
| 1 |
| LS |
| 84"x84" Box Culvert |
| 01270 – Price and Payment |
| 34.1 |
| LF |
| 30"x36" Access Hatch |
| 01270 – Price and Payment |
| 1 |
| EA |
| 24"x24" Access Hatch |
| 01270 – Price and Payment |
| 1 |
| EA |
| Ventilation Blowers and Appurtenances |
| 01270 – Price and Payment |
| 1 |
| EA |
| 4" Stainless Steel Vents |
| 01270 – Price and Payment |
| 2 |
| EA |
| Connect to Existing Force Main |
| 01270 – Price and Payment |
| 1 |
| EA |
| Chopper Pumps or Approved Equal |
| 01270 – Price and Payment |
| 2 |
| EA |
| Motor Control Panel |
| 01270 – Price and Payment |
| 1 |
| EA |
| Sump Pump |
| 01270 – Price and Payment |
| 1 |
| EA |
| Crane and Appurtenances |
| 01270 – Price and Payment |
| 1 |
| LS |
| Electrical |
| 01270 – Price and Payment |
| 1 |
| EA |
| Basket |
| 01270 – Price and Payment |
| 1 |
| EA |
| Gate Catch |
| 01270 – Price and Payment |
| 2 |
| EA |
| Install Concrete Sidewalk |
| 01270 – Price and Payment |
| 205 |
| SF |
| Install C&G |
| 01270 – Price and Payment |
| 45 |
| LF |
| Install Concrete Pavement |
| 01270 – Price and Payment |
| 130 |
| SF |
| Install Access Road |
| 01270 – Price and Payment |
| 235 |
| SF |
| Install Asphalt Pavement |
| 01270 – Price and Payment |
| 30 |
| SF |
| Install Chain-link Fence w/ Dbl Swing Gate |
| 01270 – Price and Payment |
| 130 |
| LF |
| Install Gravel Pad |
| 01270 – Price and Payment |
| 815 |
| SF |
| Grading |
| 01270 – Price and Payment |
| 71 |
| CF |
| Engineered Fill |
| 01270 – Price and Payment |
| 140 |
| CF |
TOTAL:
J08 Block 17 Support Schedule RLSC For evaluation and informational purposes only.
QUOTE SCHEDULE
LIFT STATION REPLACEMENT
ROSEBUD HOSPITAL
ROSEBUD, SD
| DESCRIPTION |
| SECTION |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| EXTENDED PRICE |
| Mobilization |
| 01270 – 2.2.A.1 |
| 1 |
| LS |
| 12-inch SDR 35 PVC Sewer Main W/ Bedding |
| 01270 – 2.2.A.2 |
| 25 |
| LF |
| Connection to Existing Manholes |
| 01270 – 2.2.A.3 |
| 1 |
| EA |
| 4-inch Restrained Joint Ductile Iron Sewer Force Main |
| 01270 – 2.2.A.4 |
| 165 |
| LF |
| 4-inch Gate Valve and Valve Box |
| 01270 – 2.2.A.5 |
| 1 |
| EA |
| Connection to Existing Force Main |
| 01270 – 2.2.A.6 |
| 1 |
| EA |
| Lift Station |
| 01270 – 2.2.A.7 |
| 1 |
| LS |
| Chain Link Fence with Double Swing Gate |
| 01270 – 2.2.A.8 |
| 165 |
| LF |
| Concrete Access Road |
| 01270 – 2.2.A.9 |
| 1 |
| LS |
| Lift Station Abandonment |
| 01270 – 2.2.A.11 |
| 1 |
| EA |
| Site Electrical Service |
| 01270 – 2.2.A.12 |
| 1 |
| LS |
| Telephone Communication Line |
| 01270 – 2.2.A.13 |
| 50 |
| LF |
TOTAL:
All quantities stipulated in the bid schedule or other contract documents are approximate and are to be used: (1) as a basis for estimating the probable cost of the work and (2) for the purpose of comparing the bids submitted.
This is a firm-fixed-priced contract in accordance with block 17 of the SF-1442. Attachment J03 Tech Specs RLSC Section 01270 for Price and Payment information, paragraph 1.2.B b (shown below) is deleted:
“The Contractor shall be paid for actual quantities installed based on the quantities measured in the field. The actual amounts of work completed and materials furnished may differ from estimated quantities. The Contractor shall make no claim for damages, anticipated profits, or otherwise, on account of differences between the estimated amounts and the actual amount of work performed and materials furnished.”