This is a Statement of Work (SOW) for construction of a new lift station at Rosebud Hospital in Rosebud, South Dakota, under the Indian Health Service (IHS). The project involves complete removal and replacement of the existing lift station, which currently serves the hospital, hospital quarters units, and several tribal program buildings. The new lift station will include a wet well, dry well, installation of chopper pumps, force main connections, and a new control system for monitoring flow and equipment status. The existing lift station, in place since the early 1990s, requires replacement every 1-2 years due to unanticipated growth and capacity limitations; in July, both pumps failed simultaneously, necessitating emergency sewage disposal services. The new system will be sized to accommodate planned facility expansion, including additional quarters units and tribal programs.

The contract is a firm-fixed-price engagement with a period of performance of 240 calendar days from Notice to Proceed. All work shall be conducted in accordance with the referenced Plans (J02 Plans RLSC) and Technical Specifications (J03 Tech Specs RLSC). Progress payments will be made following Government acceptance of schedule items and approved invoices. The contractor must maintain an onsite superintendent throughout performance and comply with Rosebud Indian Reservation tribal requirements, including submission of a Compliance Agreement to the Tribal Employment Rights Office (TERO), a 4 percent fee on total contract price, weekly certified payroll reporting, and work permits for non-local Indian employees at $250 annually. All correspondence and inquiries must be directed to the Contracting Officer's Representative, and contractors are prohibited from contacting other IHS personnel during the pre-award phase. Submittal procedures, warranty requirements, schedule and meeting information, and closeout document procedures are detailed in the technical specifications.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

ROSEBUD NEW HOSPITAL LIFT STATION

INDIAN HEALTH SERVICE

ROSEBUD, SD

ROSEBUD HOSPITAL

OCTOBER 2026

Table of Contents

1.Project Description3
2.Scope of Work (SOW)4
3.Period of Performance.4
4.Submittals5
5.Schedule/Meetings5
6.Miscellaneous5
7.Payments to the Contractor6
8.IHS Personnel6
9.Invoice Format7
10.Closeout Documents7

STATEMENT OF WORK

Rosebud New Hospital Lift Station Rosebud Service Unit Rosebud, SD

1. Project Description A. Title:

B. Location: This project is at the Rosebud Hospital, in Rosebud, SD.

C. Period of Performance: 240 calendar days from Notice to Proceed.

D. Description: This project will include the full removal and replacement of the lift station for the Rosebud complex. The existing lift station provides wastewater service to the hospital quarters units, and several tribal program buildings. Once installation is complete the new lift station will take the full sanitary load for the area currently being serviced by the existing lift station and be sized to handle expansion in the future. Then the existing lift station consisting of the wet well, dry well, pumps and piping will be demolished. The new lift station will consist of a wet well, a dry well, installation of chopper pumps, and force main connection. This project will also include a new control system to allow the facility to monitor flow into the lift station and the status of the equipment.

E. Background: The Rosebud Comprehensive Health Care Facility needs to replace the existing sewer lift station due to deterioration and sizing limitations. The existing lift station provides wastewater service to the hospital, hospital quarters units, and several tribal program buildings. Currently the lift station pumps are replaced every other year due to excess wear and overuse. Additionally, the manholes upstream of the lift station have been observed to fill between 25-85% full, which indicates that the current system isn’t keeping up and that there is possible infiltration and inflow (I&I) occurring. A recent field visit showed that the existing dry well had standing water in it and the existing fittings and valves that connect to the force main showed signs of deterioration. The lift station project will incorporate the demolition of the existing wet well, dry well, piping, and pumps, along with the construction of a new lift station, installation of chopper pumps and connection to upstream manholes and gravity sewer.

F. Related Documents

1. This SOW and any other standard government or IHS documents are included and considered a part of this contract.

2. IHS Architecture and Engineering Design Manual – 2019 G. Common Acronyms or Definitions

1. IHS – Indian Health Service

2. CMS – Centers for Medicare & Medicaid Services

3. RB – Rosebud

4. BAS – Building Automation System

5. Metasys – Name of the existing BAS

6. CO – Contracting Officer

7. COR – Contracting Officer’s Representative

8. PM – Project Manager

9. IGCE – Independent Government Cost Estimate

10. BIM – Building Information Model

11. LOD – Level of Design

12. CAD – Computer Aided Design

13. RFI – Request For Information

Scope of Work (SOW): The contractor shall conduct all work in accordance to the Plans (J02 Plans RLSC) and Technical Specifications (J03 Tech Specs RLSC).

2. Submittals A. Contractor to refer to the technical specifications for all required submittal procedures, and submittal items.

3. Warranty A. See project technical specifications (J03 Tech Specs RLSC)

4. Schedule/Meetings A. Contractor to refer to technical specifications for all schedule and meeting information.

5. Miscellaneous A. Occupancy of Government Facilities. The contractor shall be responsible for properly informing the COR of any condition which would jeopardize the building or its contents, such as loss of heat, air conditioning, danger of pipes freezing, loss of electrical power, water, sewer or loss of building security.

B. Correspondence. All correspondence shall be addressed to the COR. Each letter, document, etc., shall contain the following information:

1. Date

2. Project Numbers, Contract Number, Delivery Order Number and Service Unit Name/Location.

3. Name of those who were sent copies.

C. Superintendent. The prime contractor shall have an onsite superintendent for this project while any and all work is being performed unless prior approval is granted from the COR.

D. Tribal Requirements. The Contractor shall verify the Tribal Requirements. The statements 1 through 4 below about Tribal Requirements are provided in good faith but may be changed by the Tribe, so these are not official guidance from HIS.

1. The Contractor and all subcontractors engaging in work on the Rosebud Indian Reservation will be required to comply with the Indian preference and Indian preference program requirements administered by the Oglala Sioux Tribe Tribal Employment Rights Office (TERO).

2. Before commencing work, contractors and sub-contractors are required to submit an acceptable “Compliance Agreement” to the TERO office. Copies of this form can be obtained from the TERO office. Typical requirements of TERO include a fee of 4% on the total contract price, and submission of weekly certified payroll reports to TERO.

3. Additionally, the rules and regulations of the TERO Ordinance require that no person who is not a local Indian shall be employed by a covered employer until a work permit has been obtained for them from TERO. The annual work permit fee for each employee is $250.00.

4. Contractors are strongly encouraged to contact the TERO office at (605) 867-5167 for an explanation of tribal requirements. Other fees may apply.

E. Hours Of Operation

1. Contractor to refer to Technical Specification 01310 – Project Management and Coordination.

6. Payments to the Contractor

1. The Government will pay the Contractor a fixed price, as indicated below, which will constitute full compensation for all Contractor professional and incidental services, travel expenses, and materials necessary to furnish complete project as required and specified in this SOW.

2. Progress payments will be paid following acceptance by the Government of that particular schedule item and a properly submitted and approved invoice.

3. Contractor to refer to Section 01270 for Price and Payment information.

i. All quantities stipulated in the bid schedule or other contract documents are approximate and are to be used: (1) as a basis for estimating the probable cost of the work and (2) for the purpose of comparing the bids submitted.

ii. This is a firm-fixed-priced contract in accordance to block 17 of the SF-1442. Attachment J03 Tech Specs RLSC Section 01270 for Price and Payment information, paragraph 1.2.B b (shown below) is deleted:

“The Contractor shall be paid for actual quantities installed based on the quantities measured in the field. The actual amounts of work completed and materials furnished may differ from estimated quantities. The Contractor shall make no claim for damages, anticipated profits, or otherwise, on account of differences between the estimated amounts and the actual amount of work performed and materials furnished.”

7. IHS Personnel. To preserve the integrity of the acquisition process, do NOT contact any personnel mentioned within the solicitation attachments during the pre-award phase. Route all your questions and concerns about this solicitation through the point of contact stated on block 9 of SF-1442.

**The Contracting Officer might consider possible integrity violations as reason for disqualification.

Contracting Officer’s Representative (COR): To be designated via a separate letter.

8. Invoicing: Refer to Section B.2. of the RFP.

9. Closeout Documents The contractor shall refer to the Technical Specifications for all Closeout Documents, Procedures, and Record Documents.

End of SOW

Statement of Work Page 9

ROSEBUD NEW HOSPITAL LIFT STATION

OCTOBER 2026