J02 - Hiram King House Specifications.pdf
PDF 5 MB Posted
- Solicitation number
- 12445225Q0006
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a detailed specifications document for structural repairs to the historic Hiram King House at the Cradle of Forestry in America in Pisgah Forest, NC. The scope includes crawl space structural repairs, front porch structural repairs, floor joist repairs/reinforcement, wall structural framing repairs, non-structural interior wall repairs, and chimney/stone masonry restoration.
The project requires specialized historic preservation procedures, including careful documentation and protection of existing materials, proper cleaning methods, and use of period-appropriate repair materials and techniques. Key requirements include installation of stainless steel rigid chimney liners, restoration of stone masonry and mortar joints, selective demolition and reinstallation of chimney cap stones, and installation of spark arrestors. The contractor must complete all work within 120 days of Notice to Proceed and employ craftsmen skilled in historic restoration. All submittals require COR approval, including the stone mason's pre-qualification demonstrating experience with historic buildings. The specifications detail requirements for project management, construction progress documentation, waste management, temporary facilities, and closeout procedures. Regular progress meetings are required every two weeks, and extensive photographic documentation must be maintained throughout the project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COVER
NATIONAL FORESTS IN NORTH CAROLINA
PISGAH NATIONAL FOREST
PISGAH RANGER DISTRICT
TRANSYLVANIA COUNTY
STATEMENT OF WORK AND PROJECT SPECIFICATIONS
FOR
CRADLE OF FORESTRY HIRAM KING HOUSE STRUCTURAL REPAIRS
APRIL 2024
SPECIFICATION INDEX
PART 1: ADMINISTRATIVE SPECIFICATIONS
DIVISION 1 – GENERAL REQUIREMENTS
01 10 00 - Summary 01 31 00 - Project Management and Coordination 01 32 00 - Construction Progress Documentation 01 32 33 - Photographic Documentation 01 33 00 - Submittal Procedures 01 35 91 - Historic Treatment Procedures 01 50 00 - Temporary Facilities and Controls 01 73 00 - Execution 01 74 19 - Construction Waste Management and Disposal 01 77 00 - Closeout Procedures 01 78 39 - Project Record Documents
DIVISION 13 – SPECIAL SPECIFICATIONS
13 01 01 Chimney/Fireplace Rehabilitation and Repair
PART 2: STRUCTURAL ENGINEER SPECIFICATIONS
DIVISION 02 – EXISTING CONDITIONS
02 41 16 Structure Demolition 02 41 19 Selective Demolition 02 42 96 Historic Removal and Dismantling
DIVISION 03 – CONCRETE
03 30 00 Cast-In-Place Concrete
DIVISION 04 – MASONRY
04 90 10 Stone Masonry Restoration and Cleaning
DIVISION 06 – WOOD, PLASTIC AND COMPOSITES
06 03 12 Historic Wood Repair 06 10 00 Rough Carpentry 06 20 00 Finish Carpentry
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
07 21 00 Building Insulation 07 62 00 Sheet Metal Flashing and Trim 07 92 00 Joint Sealants
DIVISION 09 – FINISHES
09 90 00 Painting
Hiram King House - Structural Repairs SPECIFICATIONS Formal Documents
HIRAM KING HOUSE - STRUCTURAL REPAIRS Division 01 – General Requirements
SUMMARY | 01 10 00 - 1
SECTION 01 10 00
SUMMARY
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Contractor's use of site and premises.
4. Work restrictions.
5. Specification and Drawing conventions.
B. Related Requirements:
1. Section 01 50 00 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.
1.2 PROJECT INFORMATION
A. Project Identification: Hiram King House – Structural Repairs.
1. Project Location: Cradle of Forestry In America, 11250 Pisgah Highway, Pisgah Forest, NC 28768
B. Owner: US Forest Service
1. Contract Officer’s Representative (COR): Timothy Heim, P.E., 160A Zilicoa Street, Asheville, NC 28801
C. Engineer: Structural Capacity, PC
1. Engineer's Representative: Adrian Durham, P.E., 226 Westinghouse Blvd | Suite 303, Charlotte, NC 28273, (704) 900-8706.
D. Period of Performance: The Period of Performance for the Work shall be 120 days from Notice to Proceed.
SUMMARY | 01 10 00 - 2
1.3 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and consists of the following:
1. Crawl Space Structural Repairs.
2. Front Porch Structural Repairs.
3. Floor Joists Repairs/Reinforcement
4. Wall Structural Framing Repairs
5. Non-structural Interior Wall Repairs
6. Chimney Stone Masonry Restoration and Cleaning
B. Type of Contract:
1. Project will be constructed under a single prime contract.
1.4 CONTRACTOR'S USE OF SITE AND PREMISES
A. Restricted Use of Site: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.
B. Limits on Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits on Use of Site: Confine construction operations to areas of work indicated on the contract drawings.
C. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period.
Repair damage caused by construction operations.
1.5 WORK RESTRICTIONS
A. Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets, work on public streets, rights of way, and other requirements of authorities having jurisdiction.
SUMMARY | 01 10 00 - 3
B. On-Site Work Hours: Limit work in the existing building to normal business working hours of 6 a.m. to 6 p.m., Monday through Friday, unless otherwise indicated.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
1. Notify COR not less than three days in advance of proposed utility interruptions.
2. Obtain COR's written permission before proceeding with utility interruptions.
D. Smoking and Controlled Substance Restrictions: Use of tobacco products , alcoholic beverages, and other controlled substances on Project site is not permitted.
E. Employee Identification: Provide identification tags for Contractor personnel working on Project site. Require personnel to use identification tags at all times.
F. Employee Screening: Comply with Owner's requirements for drug and background screening of Contractor personnel working on Project site.
1.6 OTHER CONTRACTOR REQUIREMENTS
A. The Contractor’s Representative shall be on site at all times while the Work is being performed.
B. The Contractor shall maintain a full set of plans and specifications at the Project site at all times.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 10 00
PROJECT MANAGEMENT AND COORDINATION | 01 31 00 - 1
SECTION 01 31 00
PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. General coordination procedures.
2. Coordination drawings.
3. RFIs.
4. Digital project management procedures.
5. Project meetings.
B. Related Requirements:
1. Section 01 73 00 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
1.2 GENERAL COORDINATION PROCEDURES
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work.
Coordinate construction operations included in different Sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
B. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
PROJECT MANAGEMENT AND COORDINATION | 01 31 00 - 2
1. Preparation of Contractor's construction schedule.
2. Preparation of the schedule of values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Preinstallation conferences.
7. Project closeout activities.
1.3 REQUEST FOR INFORMATION (RFI)
A. General: Immediately on discovery of the need for additional information, clarification, or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.
1. Engineer will return without response those RFIs submitted to COR by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. Owner name.
2. Owner's Project number.
3. Name of COR
4. COR's Project number.
5. Date.
6. Name of Contractor.
7. RFI number, numbered sequentially.
8. RFI subject.
9. Specification Section number and title and related paragraphs, as appropriate.
10. Drawing number and detail references, as appropriate.
11. Field dimensions and conditions, as appropriate.
12. Contractor's suggested resolution. If Contractor's suggested resolution impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
13. Contractor's signature.
14. Attachments: Include sketches, descriptions, measurements, photos, Product
Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
C. RFI Forms: Software-generated form with substantially the same content as indicated above, acceptable to COR.
PROJECT MANAGEMENT AND COORDINATION | 01 31 00 - 3
D. COR's Action: COR will review each RFI, determine action required, and respond. Allow three days for COR's response for each RFI. RFIs received by COR after 1:00 p.m. will be considered as received the following working day.
1. The following Contractor-generated RFIs will be returned without action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract
Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of COR's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. COR's action may include a request for additional information, in which case COR's time for response will date from time of receipt by COR of additional information.
E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log weekly.
1. Project name.
2. Name and address of Contractor.
3. Name and address of COR.
4. RFI number including RFIs that were returned without action or withdrawn.
5. RFI description.
6. Date the RFI was submitted.
7. Date COR's response was received.
F. On receipt of COR's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify COR within three days if Contractor disagrees with response.
1.4 DIGITAL PROJECT MANAGEMENT PROCEDURES
A. Use of COR's Digital Data Files: Digital data files of COR's CAD drawings will be provided by COR for Contractor's use during construction.
1. Digital data files may be used by Contractor in preparing coordination drawings, Shop Drawings, and Project record Drawings.
2. COR makes no representations as to the accuracy or completeness of digital data files as they relate to Contract Drawings.
3. Digital Drawing Software Program: Contract Drawings are available in AutoCAD.
PROJECT MANAGEMENT AND COORDINATION | 01 31 00 - 4
B. PDF Document Preparation: Where PDFs are required to be submitted to COR, prepare as follows:
1. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item.
2. Name file with submittal number or other unique identifier, including revision identifier.
3. Certifications: Where digitally submitted certificates and certifications are required, provide a digital signature with digital certificate on where indicated.
1.5 PROJECT MEETINGS
A. General: Schedule and conduct meetings and conferences at Project site unless otherwise indicated.
B. Preconstruction Conference: Schedule and conduct a preconstruction conference before starting construction, at a time convenient to Owner and COR, but no later than 10 days after issuance of Notice to Proceed.
1. Attendees: Authorized representatives of Owner, Engineer, and their consultants; Contractor and its superintendent; major subcontractors; suppliers;
and other concerned parties shall attend the conference. Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Discuss items of significance that could affect progress, including the following:
a. Responsibilities and personnel assignments.
b. Tentative construction schedule.
c. Phasing.
d. Critical work sequencing and long lead items.
e. Designation of key personnel and their duties.
f. Lines of communications.
g. Use of web-based Project software.
h. Procedures for processing field decisions and Modifications.
i. Procedures for RFIs.
j. Procedures for testing and inspecting.
k. Procedures for processing Applications for Payment.
l. Distribution of the Contract Documents.
m. Submittal procedures.
3. Minutes: Contractor responsible for conducting meeting will record and distribute meeting minutes.
PROJECT MANAGEMENT AND COORDINATION | 01 31 00 - 5
C. Progress Meetings: Conduct progress meetings at biweekly intervals.
1. Attendees: In addition to representatives of Owner and Engineer, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting.
Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.
a. Contractor's Construction Schedule: Review progress since the last meeting. Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule.
Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
1) Review schedule for next period.
b. Review present and future needs of each entity present, including the following:
1) Interface requirements.
2) Sequence of operations.
3) Status of submittals.
4) Deliveries.
5) Off-site fabrication.
6) Access.
7) Site use.
8) Temporary facilities and controls.
9) Progress cleaning.
10) Quality and work standards.
11) Status of correction of deficient items.
12) Field observations.
13) Status of RFIs.
14) Status of Proposal Requests.
15) Pending changes.
16) Status of Change Orders.
17) Pending claims and disputes.
PROJECT MANAGEMENT AND COORDINATION | 01 31 00 - 6
PART 2 - PRODUCTS (Not Used)
END OF SECTION 01 31 00
CONSTRUCTION PROGRESS DOCUEMNTATION | 01 32 00 - 1
SECTION 01 32 00
CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Contractor's Construction Schedule.
2. Construction schedule updating reports.
3. Daily construction reports.
4. Site condition reports.
1.2 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction Project. Activities included in a construction schedule consume time and resources.
1. Critical Activity: An activity on the critical path that must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships.
Network calculations determine when activities can be performed and the critical path of Project.
C. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.
D. Event: The starting or ending point of an activity.
CONSTRUCTION PROGRESS DOCUEMNTATION | 01 32 00 - 2
1.3 INFORMATIONAL SUBMITTALS
A. Format for Submittals: Submit required submittals in the following format:
1. Working electronic copy of schedule file.
2. PDF file.
B. Contractor's Construction Schedule: Initial schedule, of size required to display entire schedule for entire construction period.
C. Construction Schedule Updating Reports: Submit with Applications for Payment.
1.4 COORDINATION
A. Coordinate Contractor's Construction Schedule with the schedule of values, submittal schedule, progress reports, payment requests, and other required schedules and reports.
1. Secure time commitments for performing critical elements of the Work from entities involved.
2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
1.5 CONTRACTOR CONSTRUCTION SCHEDULE REQUIREMENTS
A. Submit a comprehensive, fully developed, Contractor's Construction Schedule within 10 days after issuance of Notice to Proceed.
B. Update the Contractor's Construction Schedule as applicable when changes to the Construction Schedule occur.
C. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line.
1. For construction activities that require three months or longer to complete, indicate an estimated completion percentage in 10 percent increments within time bar.
CONSTRUCTION PROGRESS DOCUEMNTATION | 01 32 00 - 3
PART 2 - PRODUCTS (Not Used)
END OF SECTION 01 32 00
PHOTOGRAPHIC DOCUMENTATION | 01 32 33 - 1
SECTION 01 32 33
PHOTOGRAPHIC DOCUMENTATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for the following:
1. Preconstruction photographs.
2. Concealed Work photographs.
3. Periodic construction photographs.
4. Final completion construction photographs.
B. Related Requirements:
1. Section 01 77 00 "Closeout Procedures" for submitting photographic documentation as Project Record Documents at Project closeout.
2. Section 024116 "Structure Demolition" for photographic documentation before building demolition operations commence.
3. Section 02 41 19 "Selective Demolition" for photographic documentation before selective demolition operations commence.
1.2 INFORMATIONAL SUBMITTALS
A. Key Plan: Submit key plan of Project site and building with notation of vantage points marked for location and direction of each photograph. Indicate elevation or story of construction. Include same information as corresponding photographic documentation.
B. Digital Photographs: Submit image files within 5 days of taking photographs.
1. Submit photos on thumb-drive. Include copy of key plan indicating each photograph's location and direction.
2. Identification: Provide the following information with each image description.
a. Name of Project.
b. Name and contact information for photographer.
c. Name of COR.
d. Name of Contractor.
e. Date photograph was taken.
PHOTOGRAPHIC DOCUMENTATION | 01 32 33 - 2
f. Description of location, vantage point, and direction.
g. Unique sequential identifier keyed to accompanying key plan.
1.3 FORMATS AND MEDIA
A. Digital Photographs: Provide color images in JPG format, produced by a digital camera with minimum sensor size of 12 megapixels, and at an image resolution of not less than 3200 by 2400 pixels. Use flash in low light levels or backlit conditions.
B. Digital Images: Submit digital media as originally recorded in the digital camera, without alteration, manipulation, editing, or modifications using image-editing software.
1.4 CONSTRUCTION PHOTOGRAPHS
A. General: Take photographs with maximum depth of field and in focus.
1. Maintain key plan with each set of construction photographs that identifies each photographic location.
B. Preconstruction Photographs: Before commencement of the Work, take photographs of Project site and surrounding properties, including existing items to remain during construction, from different vantage points, as directed by COR.
C. Periodic Construction Photographs: Take minimum of 20 photographs weekly. Select vantage points to show status of construction and progress since last photographs were taken.
D. Final Completion Construction Photographs: Take a minimum of 20 photographs after date of Substantial Completion for submission as Project Record Documents.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 01 32 33
SUBMITTAL PROCEDURES | 01 33 00 - 1
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. The work of this section consists of submittal requirements before and during construction.
B. The Contractor shall furnish the submittals listed below to the COR for approval prior to ordering/purchasing. Additional submittals may be required if deemed necessary by the COR.
1. Informational Submittals
a. Contractor's Construction Schedule
b. Key Plan of Project Site Photographs
c. Project Site Photographs
d. Stone mason's pre-qualification
e. Closeout Submittals including Record Drawings
2. Actions Submittals
a. Stainless steel rigid chimney liner pipe.
b. Cleaning compounds for historic stone masonry.
c. Demonstration samples of mortar work.
1.2 SUBMITTAL FORMATS
A. All submittals shall be submitted via email in electronic PDF format.
B. Submittals shall be identified on a transmittal cover sheet that shall be signed by the contractor or representative. Include the following information in each submittal:
1. Project name.
2. Date.
C. Options: Identify options requiring selection by COR.
1.3 SUBMITTAL PROCEDURES
A. Submit all submittal items required for each category of work concurrently.
B. All submittals will be evaluated by the COR and returned marked either approved, approved with notations, or rejected.
SUBMITTAL PROCEDURES | 01 33 00 - 2
1.4 PRODUCT SUBMITTAL REQUIREMENTS
A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. Mark each submittal to show which products and options are applicable.
2. Include the following information, as applicable:
a. Manufacturer's catalog cuts.
b. Manufacturer's product specifications.
c. Standard color charts.
d. Statement of compliance with specified referenced standards.
e. Availability and delivery time information.
B. Incomplete submittals are unacceptable and will be returned for resubmittal without review.
C. COR will not accept submittals received from sources other than Contractor.
D. Shop Drawings: Prepare Project-specific information, drawn accurately to scale.
1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:
a. Identification of products.
b. Schedules.
c. Compliance with specified standards.
d. Notation of coordination requirements.
e. Notation of dimensions established by field measurement.
f. Relationship and attachment to adjoining construction clearly indicated.
g. Seal and signature of professional engineer if specified.
E. Samples: Submit Samples for review of type, color, pattern, and texture for a check of these characteristics with other materials.
1. Transmit Samples that contain multiple, related components, such as accessories together in one submittal package.
2. Identification: Permanently attach label on unexposed side of Samples that includes the following:
a. Project name and submittal number.
b. Generic description of Sample.
c. Product name and name of manufacturer.
d. Sample source.
1.5 SUBSTITUTIONS:
A. If the Contractor intends to provide or install an item that is an "or equal" or differs from that which is specified, he/she shall submit all product data and information to the COR for review prior to ordering/purchase.
SUBMITTAL PROCEDURES | 01 33 00 - 3
B. The contractor shall submit one digital copy of the manufacturer's description of all "or equals" proposed in lieu of name brands specified. This description shall include:
1. Product name and model number
2. Manufacturer
3. Product description
4. Technical data
5. Samples, as required by COR
C. A request for approval of “equals” constitutes a representation that Contractor:
1. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.
2. Will provide the same warranties for the proposed item as for the item specified.
3. Has determined that the proposed item is compatible with interfacing items.
4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
5. Waives all claims for additional expenses that may be incurred as a result of the substitution.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 013300
3.1
HISTORIC TREATEMENT PROCEDURES | 01 35 91 - 1
SECTION 01 35 91
HISTORICAL TREATMENT PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes general protection and treatment procedures for designated historic spaces, areas, rooms, and surfaces in Project.
1.2 DEFINITIONS
A. Consolidate: To strengthen loose or deteriorated materials in place.
B. Design Reference Sample: A sample that represents COR's prebid selection of work to be matched; it may be existing work or work specially produced for Project.
C. Dismantle: To disassemble or detach a historic item from a surface, or a nonhistoric item from a historic surface, using gentle methods and equipment to prevent damage to historic items and surfaces; disposing of items unless indicated to be salvaged or reinstalled.
D. Historic: Spaces, areas, rooms, surfaces, materials, finishes, and overall appearance that are important to the successful preservation, rehabilitation, restoration and reconstruction as determined by COR.
E. Match: To blend with adjacent construction and manifest no apparent difference in material type, species, cut, form, detail, color, grain, texture, or finish; as approved by
COR.
F. Refinish: To remove existing finishes to base material and apply new finish to match original, or as otherwise indicated.
G. Reinstall: To protect removed or dismantled item, repair and clean it as indicated for reuse, and reinstall it in original position, or where indicated.
H. Remove: To take down or detach a nonhistoric item located within a historic space, area, or room, using methods and equipment to prevent damage to historic items and surfaces; disposing of items unless indicated to be salvaged or reinstalled.
HISTORIC TREATEMENT PROCEDURES | 01 35 91 - 2
I. Repair: To correct damage and defects, retaining existing materials, features, and finishes while employing as little new material as possible. This includes patching, piecing-in, splicing, consolidating, or otherwise reinforcing or upgrading materials.
J. Replace: To remove, duplicate, and reinstall entire item with new material. The original item is the pattern for creating duplicates unless otherwise indicated.
K. Replicate: To reproduce in exact detail, materials, and finish unless otherwise indicated.
L. Reproduce: To fabricate a new item, accurate in detail to the original, and from either the same or a similar material as the original, unless otherwise indicated.
M. Restore: To consolidate, replicate, reproduce, repair, and refinish as required to achieve the indicated results.
N. Retain: To keep an element or detail secure and intact.
O. Reversible: New construction work, treatments, or processes that can be removed or undone in the future without damaging historic materials unless otherwise indicated.
P. Salvage: To protect removed or dismantled items and deliver them to Owner ready for reuse.
Q. Stabilize: To provide structural reinforcement of unsafe or deteriorated items while maintaining the essential form as it exists at present; also, to reestablish a weather-resistant enclosure.
R. Strip: To remove existing finish down to base material unless otherwise indicated.
1.3 PROJECT MEETINGS FOR HISTORIC TREATMENT
A. Preliminary Historic Treatment Conference: Before starting historic treatment work, conduct conference at Project site.
1. Attendees: In addition to representatives of Owner, COR, and Contractor and installers whose work interfaces with or affects historic treatment shall be represented at the meeting.
2. Agenda: Discuss items of significance that could affect progress of historic treatment work, including review of the following:
a. Governing regulations.
b. Areas where existing construction is to remain and the required protection.
c. Sequence of historic treatment work operations.
HISTORIC TREATEMENT PROCEDURES | 01 35 91 - 3
d. Storage, protection, and accounting for salvaged and specially fabricated items.
e. Existing conditions, staging, and structural loading limitations of areas where materials are stored.
3. Reporting: COR will record conference results and distribute copies to everyone in attendance and to others affected by decisions or actions resulting from conference.
B. Coordination Meetings: Conduct specifically for historic treatment work at bi-weekly intervals. Coordination meetings are in addition to specific meetings held for other purposes, such as progress meetings and preinstallation conferences.
1. Agenda: Review and correct or approve minutes of previous coordination meeting. Review other items of significance that could affect progress of historic treatment work. Include topics for discussion as appropriate to status of Project.
2. Reporting: Record meeting results and distribute copies to everyone in attendance and to others affected by decisions or actions resulting from each meeting.
1.4 MATERIALS OWNERSHIP
A. Historic items, relics, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, antiques, and other items of interest or value to Owner that may be encountered or uncovered during the Work, regardless of whether they were previously documented, remain Owner's property.
1.5 STORAGE AND HANDLING OF HISTORIC MATERIALS
A. Identification: Photograph, tag, and catalog historic items to be salvaged or reinstalled.
1. Identify each item with a nonpermanent location identification tag indicating item name or use, location, and location identification number to document its original location. Indicate original locations on plans, elevations, sections, or photographs by annotating the identifying tag.
a. For groups of material such as brick, provide location identification tag for pallet or container. Do not tag individually.
B. Salvaged Historic Materials:
1. Clean loose dirt and debris from salvaged historic items unless more extensive cleaning is indicated.
HISTORIC TREATEMENT PROCEDURES | 01 35 91 - 4
2. Pack or crate items after cleaning; cushion against damage during handling.
Label contents of containers.
3. Store items in a secure area until delivery to Owner.
4. Transport items to Owner's storage area on-site.
5. Protect items from damage during transport and storage.
C. Historic Materials for Reinstallation:
1. Repair and clean historic items for reuse as indicated.
2. Pack or crate items after cleaning and repairing; cushion against damage during handling. Label contents of containers.
3. Protect items from damage during transport and storage.
4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment unless otherwise indicated. Provide connections, supports, and miscellaneous materials to make items functional for use indicated.
D. Existing Historic Materials to Remain: Protect construction indicated to remain against damage and soiling from construction work. Where permitted by COR, items may be dismantled and taken to a suitable, protected storage location during construction work and reinstalled in their original locations after historic treatment and construction work in the vicinity is complete.
E. Storage: Store historic items within a weathertight enclosure where they are protected from moisture, weather, condensation, and freezing temperatures.
1. Secure stored materials to protect from theft.
2. Control humidity so that it does not exceed 85 percent. Maintain temperatures 5 deg F or more above the dew point.
PART 2 - PRODUCTS - (Not Used)
PART 3 - EXECUTION
3.1 PROTECTION
A. Protect persons, motor vehicles, surrounding surfaces of building, building site, plants, and surrounding buildings from harm resulting from historic treatment procedures.
1. Use only proven protection methods, appropriate to each area and surface being protected.
2. Provide temporary barricades, barriers, and directional signage to exclude the public from areas where historic treatment work is being performed.
HISTORIC TREATEMENT PROCEDURES | 01 35 91 - 5
3. Erect temporary barriers to form and maintain fire-egress routes.
4. Erect temporary protective covers over walkways and at points of pedestrian and vehicular entrance and exit that must remain in service during historic treatment work.
5. Contain dust and debris generated by historic treatment work, and prevent it from reaching the public or adjacent surfaces.
6. Provide shoring, bracing, and supports as necessary. Do not overload structural elements.
7. Protect floors and other surfaces along hauling routes from damage, wear, and staining.
B. Temporary Protection of Historic Materials:
1. Protect existing historic materials with temporary protections and construction.
Do not remove existing materials unless otherwise indicated.
2. Do not attach temporary protection to historic surfaces except as indicated as part of the historic treatment program and approved by COR.
C. Comply with each product manufacturer's written instructions for protections and precautions. Protect against adverse effects of products and procedures on people and adjacent materials, components, and vegetation.
D. Utility and Communications Services:
1. Notify Owner, COR, authorities having jurisdiction, and entities owning or controlling wires, conduits, pipes, and other services affected by historic treatment work before commencing operations.
2. Disconnect and cap pipes and services as required by authorities having jurisdiction, as required for historic treatment work.
3. Maintain existing services unless otherwise indicated; keep in service, and protect against damage during operations. Provide temporary services during interruptions to existing utilities.
3.2 PROTECTION FROM FIRE
A. Follow fire-prevention plan and the following:
1. Comply with NFPA 241 requirements unless otherwise indicated.
2. Remove and keep area free of combustibles, including rubbish, paper, waste, and chemicals, unless necessary for the immediate work.
a. If combustible material cannot be removed, provide fire blankets to cover such materials.
HISTORIC TREATEMENT PROCEDURES | 01 35 91 - 6
3. Prohibit smoking by all persons within Project work and staging areas.
B. Heat-Generating Equipment and Combustible Materials: Comply with the following procedures while performing work with heat-generating equipment or combustible materials, including welding, torch-cutting, soldering, brazing, removing paint with heat, or other operations where open flames or implements using high heat or combustible solvents and chemicals are anticipated:
1. Obtain Owner's approval for operations involving use of open-flame or welding or other high-heat equipment. Notify Owner at least 72 hours before each occurrence, indicating location of such work.
2. Do not perform work with heat-generating equipment in or near rooms or in areas where flammable liquids or explosive vapors are present or thought to be present. Use a combustible gas indicator test to ensure that area is safe.
3. Use fireproof baffles to prevent flames, sparks, hot gases, or other high-temperature material from reaching surrounding combustible material.
4. Prevent the spread of sparks and particles of hot metal through open windows, doors, holes, and cracks in floors, walls, ceilings, roofs, and other openings.
5. Fire Watch: Before working with heat-generating equipment or combustible materials, station personnel to serve as a fire watch at each location where such work is performed. Fire-watch personnel shall have the authority to enforce fire safety. Station fire watch according to NFPA 51B, NFPA 241, and as follows:
a. Train each fire watch in proper operation of fire-control equipment and alarms.
b. Prohibit fire-watch personnel from other work that would distract from fire-watch duties.
c. Cease work with heat-generating equipment whenever fire-watch personnel are not present.
d. Have fire-watch personnel perform final fire-safety inspection each day beginning no sooner than 60 minutes after conclusion of hot work activity to detect hidden or smoldering fires and to ensure that proper fire prevention is maintained.
C. Fire-Control Devices: Provide and maintain fire extinguishers, fire blankets, and rag buckets for disposal of rags with combustible liquids. Maintain each as suitable for type of fire risk in each work area. Ensure that nearby personnel and fire-watch personnel are trained in fire-extinguisher and blanket use.
HISTORIC TREATEMENT PROCEDURES | 01 35 91 - 7
3.3 PROTECTION DURING APPLICATION OF CHEMICALS
A. Protect motor vehicles, surrounding surfaces of building being restored, building site, plants, and surrounding buildings from harm or spillage resulting from applications of chemicals and adhesives.
B. Cover adjacent surfaces with protective materials that are proven to resist chemicals selected for Project unless chemicals being used will not damage adjacent surfaces as indicated in historic treatment program. Use covering materials and masking agents that are waterproof and UV resistant and that will not stain or leave residue on surfaces to which they are applied. Apply protective materials according to manufacturer's written instructions. Do not apply liquid masking agents or adhesives to painted or porous surfaces. When no longer needed, promptly remove protective materials.
C. Do not apply chemicals during winds of sufficient force to spread them to unprotected surfaces.
D. Neutralize alkaline and acid wastes and legally dispose of off Owner's property.
E. Collect and dispose of runoff from chemical operations by legal means and in a manner that prevents soil contamination, soil erosion, undermining of paving and foundations, damage to landscaping, or water penetration into building interior.
3.4 GENERAL HISTORIC TREATMENT
A. Ensure that supervisory personnel are present when historic treatment work begins and during its progress.
B. Record existing work before each procedure (preconstruction), and record progress during the work. Use digital preconstruction documentation photographs or video recordings. Comply with requirements in Section 01 32 33 "Photographic Documentation."
C. Perform regular inspections of Project site as the Work progresses to detect hazards resulting from historic treatment procedures.
D. Follow the procedures in subparagraphs below and procedures approved in historic treatment program unless otherwise indicated:
1. Retain as much existing material as possible; repair and consolidate rather than replace.
2. Use additional material or structure to reinforce, strengthen, prop, tie, and support existing material or structure.
3. Use reversible processes wherever possible.
HISTORIC TREATEMENT PROCEDURES | 01 35 91 - 8
4. Use historically accurate repair and replacement materials and techniques unless otherwise indicated.
5. Record existing work before each procedure (preconstruction) and progress during the work with digital preconstruction documentation photographs or video recordings. Comply with requirements in Section 01 32 33 "Photographic Documentation."
E. Notify COR of visible changes in the integrity of material or components whether from environmental causes including biological attack, UV degradation, freezing, or thawing or from structural defects including cracks, movement, or distortion.
1. Do not proceed with the work in question until directed by COR.
F. Where missing features are indicated to be repaired or replaced, provide work with appearance based on accurate duplications rather than on conjecture, subject to approval of COR.
G. Where work requires existing features to be removed or dismantled and reinstalled, perform these operations without damage to the material itself, to adjacent materials, or to the substrate.
H. Identify new and replacement materials and features with permanent marks hidden in the completed Work to distinguish them from original materials. Record a legend of identification marks and the locations of the items on record Drawings.
END OF SECTION 01 35 91
TEMPORARY FACILITIES AND CONTROLS | 01 50 00 - 1
SECTION 01 50 00
TEMPORARY FACILITIES AND CONTROLS
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes requirements for temporary utilities, support facilities, and security and protection facilities.
B. The Project site does not have running water or toilet facilities. Water can be accessed at an exterior yard hydrant adjacent to the King House. Electricity is not available at the project site for the Contractor’s use. Contractor is responsible for their own power supply requirements.
C. Related Requirements:
1. Section 01 10 00 "Summary" for work restrictions and limitations on utility interruptions.
1.2 USE CHARGES
A. Installation, removal, and use charges for temporary facilities shall be included in the Contract Sum unless otherwise indicated. Allow other entities engaged in the Project to use temporary services and facilities without cost, including, but not limited to, Owner’s construction forces, COR and authorities having jurisdiction.
1.3 QUALITY ASSURANCE
A. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70.
B. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary utility before use. Obtain required certifications and permits.
1.4 PROJECT CONDITIONS
A. Temporary Use of Permanent Facilities: Engage Installer of each permanent service to assume responsibility for operation, maintenance, and protection of each permanent
TEMPORARY FACILITIES AND CONTROLS | 01 50 00 - 2
service during its use as a construction facility before Owner's acceptance, regardless of previously assigned responsibilities.
B. There are no restroom facilities available at the Project site. Contractor shall make appropriate arrangements for temporary portable toilet at location indicated on plans and maintain sanitary jobsite and work crew conditions.
PART 2 - PRODUCTS
2.1 EQUIPMENT
A. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures.
PART 3 - EXECUTION
3.1 INSTALLATION, GENERAL
A. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required by progress of the Work.
B. Provide each facility ready for use when needed to avoid delay. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities.
3.2 TEMPORARY UTILITY INSTALLATION
A. General: Install temporary service or connect to existing service.
1. Arrange with utility company, Owner, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services.
B. Sewers and Drainage: Provide temporary utilities to remove effluent lawfully.
C. Sanitary Facilities: Provide temporary toilets, wash facilities, safety shower and eyewash facilities, and drinking water for use of construction personnel. Comply with requirements of authorities having jurisdiction for type, number, location, operation, and maintenance of fixtures and facilities.
TEMPORARY FACILITIES AND CONTROLS | 01 50 00 - 3
D. Electric Power Service: Provide electric power service and distribution system of sufficient size, capacity, and power characteristics required for construction operations.
E. Lighting: Provide temporary lighting with local switching that provides adequate illumination for construction operations, observations, inspections, and traffic conditions.
1. Install and operate temporary lighting that fulfills security and protection requirements without operating entire system.
3.3 SUPPORT FACILITIES INSTALLATION
A. Comply with the following:
1. Utilize designated area within existing building for temporary field offices.
2. Maintain support facilities until COR schedules Substantial Completion inspection. Remove before Substantial Completion. Personnel remaining after Substantial Completion will be permitted to use permanent facilities, under conditions acceptable to Owner.
B. Traffic Controls: Comply with requirements of authorities having jurisdiction.
1. Protect existing site improvements to remain including curbs, pavement, and utilities.
2. Maintain access for fire-fighting equipment and access to fire hydrants.
C. Parking: Use designated areas of Owner's existing parking areas for construction personnel, as noted on plans.
D. Storage and Staging: Use designated areas of Project site for storage and staging needs.
E. Waste Disposal Facilities: Comply with requirements specified in Section 01 74 19 "Construction Waste Management and Disposal."
F. Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste from construction operations. Comply with requirements of authorities having jurisdiction. Comply with progress cleaning requirements in Section 01 73 00 "Execution."
TEMPORARY FACILITIES AND CONTROLS | 01 50 00 - 4
3.4 SECURITY AND PROTECTION FACILITIES INSTALLATION
A. Protection of Existing Facilities: Protect existing vegetation, equipment, structures, utilities, and other improvements at Project site and on adjacent properties, except those indicated to be removed or altered. Repair damage to existing facilities.
1. Where access to adjacent properties is required in order to affect protection of existing facilities, obtain written permission from adjacent property owner to access property for that purpose.
B. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction as required to comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
C. Temporary Erosion and Sedimentation Control: Provide measures to prevent soil erosion and discharge of soil-bearing water runoff and airborne dust to undisturbed areas and to adjacent properties and walkways, according to requirements of EPA Construction General Permit or authorities having jurisdiction, whichever is more stringent.
1. Verify that flows of water redirected from construction areas or generated by construction activity do not enter or cross tree- or plant-protection zones.
2. Inspect, repair, and maintain erosion- and sedimentation-control measures during construction until permanent vegetation has been established.
3. Clean, repair, and restore adjoining properties and roads affected by erosion and sedimentation from Project site during the course of Project.
4. Remove erosion and sedimentation controls and restore and stabilize areas disturbed during removal.
D. Stormwater Control: Comply with requirements of authorities having jurisdiction.
Provide barriers in and around excavations and subgrade construction to prevent flooding by runoff of stormwater from heavy rains.
E. Temporary Enclosures: Provide temporary enclosures for protection of construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities. Provide temporary weathertight enclosure for building exterior.
F. Temporary Fire Protection: Install and maintain temporary fire-protection facilities of types needed to protect against reasonably predictable and controllable fire losses.
Comply with NFPA 241; manage fire-prevention program.
1. Prohibit smoking in construction areas. Comply with additional limits on smoking specified in other Sections.
TEMPORARY FACILITIES AND CONTROLS | 01 50 00 - 5
2. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition according to requirements of authorities having jurisdiction.
3. Develop and supervise an overall fire-prevention and -protection program for personnel at Project site. Review needs with local fire department and establish procedures to be followed. Instruct personnel in methods and procedures. Post warnings and information.
3.5 OPERATION, TERMINATION, AND REMOVAL
A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses.
B. Maintenance: Maintain facilities in good operating condition until removal.
1. Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation, and similar facilities on a 24-hour basis where required to achieve indicated results and to avoid possibility of damage.
C. Temporary Facility Changeover: Do not change over from using temporary security and protection facilities to permanent facilities until Substantial Completion.
D. Termination and Removal: Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Substantial Completion. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired.
1. Materials and facilities that constitute temporary facilities are property of Contractor. Owner reserves right to take possession of Project identification signs.
2. At Substantial Completion, repair, renovate, and clean permanent facilities used during construction period. Comply with final cleaning requirements specified in Section 017700 "Closeout Procedures."
END OF SECTION 01 50 00
EXECUTION | 01 73 00 - 1
SECTION 01 73 00
EXECUTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section…