J.4 STATEMENT OF WORK (4 PAGES).pdf

PDF 170 KB Posted

Attached to
FOREST WIDE ROOF REPAIRS Federal contract opportunity
Solicitation number
1240LT23Q0120
Issued by
Department of Agriculture Forest Service

About this file

This statement of work outlines roof replacement projects at multiple locations for the Uinta-Wasatch-Cache National Forest. The contractor will provide all labor, materials, and equipment to remove and dispose of existing roof coverings, install underlayment, flashing, trim, vent collars, and asphalt, cedar, or metal shingles based on the schedule of items. Locations include buildings in Pleasant Grove, UT, Kamas, UT, Mountain View, WY, and Heber City, UT. The contractor must coordinate work with the contracting officer's representative, obtain approvals for staging and storage areas, and use traffic control signing. The projected start date is July 2023 over 100 calendar days for base bids and 60 additional days for optional bids. Specification sections address accident prevention, mobilization, submittals, historic treatment, quality control, demolition, waste disposal, carpentry, insulation, asphalt shingles, wood shingles, metal shingles, and sheet metal work.

View the file

Other files for this federal contract opportunity

Other files attached to FOREST WIDE ROOF REPAIRS, newest first.
File Type Posted
Building 3.jpg JPG image
Building 1 - Back.jpg JPG image
Building 2 - Facing West.jpg JPG image
Building 1 - Front.jpg JPG image
Building 2 - Facing East.jpg JPG image
Building 1 - Singles.jpg JPG image
1240LT23Q0120.0004 - FOREST WIDE ROOF REPAIRS (4 PAGES).pdf PDF
1240LT23Q0120.0003 - Forest Wide Roof Repairs (5 Pages).pdf PDF
1240LT23Q0120.0002 - Forest Wide Roof Repairs (3 Pages).pdf PDF
Site Photos.zip ZIP file
American Fork Hydro Electric Plant.png PNG image
Willow Creek Guard Station and Storage Building.png PNG image
American Fork Fee Station.png PNG image
Mill Hollow Guard Station.png PNG image
Specifications_UWCRoofReplacementPlan.pdf PDF
Mountain View Complex.png PNG image
1240LT23Q0120.0001 - Amendment 1 - Location.Wage Determinations Corrections.pdf PDF
J.1 (Amend 0001) Wage Determinations (Uinta County, WY) (WY20230018) (06.30.2023) (7 Pages).pdf PDF
1240LT23Q0120 - FOREST WIDE ROOF REPAIRS (33 PAGES).pdf PDF
J.3 Wage Determinations (Utah County, UT) (UT20230087) (08.11.2023) (7 PAGES).pdf PDF
J.7 Mill Hollow GS Pictures (6 PAGES).pdf PDF
J.5 EXPERIENCE QUESTIONNAIRE (3 PAGES).pdf PDF
J.8 Mountain View Site Pictures (2 PAGES).pdf PDF
J.6 American Fork Hyderoelectric Power Plant Roof Pictures (18 PAGES).pdf PDF
J.9 Willow Creek GS Pictures (3 PAGES).pdf PDF
J.10 Willow Creek Storage Building Pictures (3 PAGES).pdf PDF
J.11 List of Sustainable Products (1 PAGE).pdf PDF
J.2 Wage Determinations (Wasatch County, UT) (UT20230078) (08.11.2023) (6 PAGES).pdf PDF
J.1 Wage Determinations (Uintah County, UT) (UT20230077) (08.11.2023) (6 PAGES).pdf PDF
Show all 29

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001 - 1

Section C - Description/Specifications/Statement of Work

USDA FOREST SERVICE, R-4

UINTA-WASATCH-CACHE ROOF REPLACEMENT PLAN

PART 1 - GENERAL SPECIFICATIONS

1.1 SCOPE OF CONTRACT

A. This project includes all work required to rehabilitate multiple roof covering systems owned by the Forest Service on the Uinta-Wasatch-Cache National Forest. The contractor shall provide all labor, materials, and equipment necessary to complete all the BID ITEMS as described in the contract documents.

B. is not limited to removal and disposal of the existing roof coverings (dispose per local jurisdiction rules), furnish and installation of underlayment materials, sheet metal flashing and trim, new vent collars, and asphalt or cedar shingle roof coverings based on schedule of items. Shingles shall be per the specifications, and color options must be provided to CO. The more stringent of the manufactures’ installation instructions and specifications herein are required. Measurement of the roof components and quantities shall be the responsibility of the contractor. Please see drawings and pictures for additional details.

C. This project is to be constructed while the buildings may be occupied by the user.

Coordination and phasing of work the COR is required. Staging and storage of materials are to be coordinated with the COR prior to the start of the project. Damages to any portion of the building while this project is completed are to be repaired with matching finishes of what is now installed. Clean out any debris that falls into the landscaping.

D. Optional Bid Items:

1. Multiple locations listed in section 1.2 will be optional bid items. Please refer to the Schedule of Items (SOI) for full list of base bid and optional bid locations as well as roofing material to be installed.

E. Quantities associated with these options are identified in the Schedule of Items.

1.2 PROJECT LOCATION

A. American Fork Hydroelectric Power Plant building is near Pleasant Grove, UT. Head north on UT-146 N/ Canyon Rd for 3.1 miles. Turn right onto W Alpine Loop Rd and continue for 2.8 miles and the building will be to the left.

1. 40.437759°, -111.723919°

B. Mill Hollow Guard Station near Kamas, UT. From Kamas, head south on UT-32 S for

2.2 miles. Turn left onto UT-35 E/ E 2200 S/ Main Village Way and continue for 3.4 miles. Continue onto E State Hwy 35 for 0.6 miles and take N Wolf Creek Ranch Rd, E

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001 - 2

Forest Creek Rd, and Heber Mountain Rd for 21.1 miles to FR 054/ S Mill Hollow Rd in Wasatch County.

1. 40.495978°, -111.083026°

C. The Annex at the Mountain View Ranger Station Site is in Mountain View, WY. See the address and coordinates below for the location.

1. 321 WY-414, Mountain View, WY 82939

2. 41.269742°, -110.331550°

D. The Mountain View Paper Shed is in the same site as the Annex. See address and coordinates below for the location.

1. 321 WY-414, Mountain View, WY 82939

2. 41.269566°, -110.331567°

E. The Mountain View Icehouse is in the same site as the Annex. See address and coordinates below for the location.

1. 321 WY-414, Mountain View, WY 82939

2. 41.269748°, -110.331801°

F. The Mountain View Garage is in the same site as the Annex. See address and coordinates below for the location.

1. 321 WY-414, Mountain View, WY 82939

2. 41.269635°, -110.331816°

G. The Mountain View Pump House is in the same site as the Annex. See address and coordinates below for the location.

1. 321 WY-414, Mountain View, WY 82939

2. 41.269766°, -110.332156°

H. Willow Creek Guard Station near Heber City, UT. From Heber City, head south on S Main St/ US-40 E for 23.4 miles. Turn right on to S Strawberry Rd and continue for 13.8 miles. Continue onto Trail Hollow for 1.6 miles and take a slight left onto Forest Rd. 345.

After 0.2 miles, continue straight to the Willow Creek Guard Station.

1. 40.025124°, -111.145638°

I. Willow Creek Storage Building near Heber City, UT. From Heber City, head south on S Main St/ US-40 E for 23.4 miles. Turn right on to S Strawberry Rd and continue for 13.8 miles. Continue onto Trail Hollow for 1.6 miles and take a slight left onto Forest Rd. 345.

After 0.2 miles, continue straight to the Willow Creek Guard Station Storage building.

The building will be towards the right of the guard station.

1. 40.025025°, -111.145595°

J. The American Fork Fee Station is near Pleasant Grove, UT. Head north on North Canyon Rd and turn right onto UT-92. The Fee station will be to the right.

1. 682 American Fork Canyon Rd, Pleasant Grove, UT 84062

2. 40.435440, -111.746441

1.3 SITE INFORMATION AND LIMITATIONS

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001 - 3

A. The district office has a limited amount of parking spaces available. Please plan accordingly with any additional use of space for trailers, materials, or equipment.

B. Construction sites will not be closed to the public or forest service during construction.

The contractor will be responsible for signing and limiting public and forest service access to the portions of the building and site where the construction is taking place.

C. There is existing electrical service for the site. Contractor shall have permission to use existing electrical services during construction. Contractor shall be aware of the use of electrical services and shall limit the use of electrical services to the construction alone.

Contractor is responsible for turning off all lights and power so as not to waste electrical services. Contractor shall provide connections and extensions of services as required for construction operations.

D. There is Water service on site. Contractor is to provide connections and extensions of services as required for construction operations.

E. Public toilet facilities are available on site.

F. Construction Hours – Hours of operation for the construction, demolition, excavation, and subsequent cleanup shall be only between the hours between 7:00 a.m. and 7:00 p.m.

Monday through Saturday.

1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING

A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the CO and Utah Department of Transportation. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the schedule of items.

1.5 WORK CAMPS, STAGING AND STORAGE AREAS

A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage trailers on site.

1.6 INSPECTION OF WORKSITE

A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.

1.7 PROJECTED START DATE

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001 - 4

A. July 2023

1.8 CONTRACT TIME

A. Base Bid: 100 Calendar Days

B. Optional Bid: Additional 60 Calendar Days

1.9 SPECIFICATIONS

A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to or are included in payment for other pay items in this contract. These items are considered incidental, and no additional compensation will be made.

SECTION 011700 - ACCIDENT PREVENTION

SECTION 011900 - MOBILIZATION

SECTION 013300 - SUBMITTAL PROCEDURES

SECTION 013591 - HISTORIC TREATMENT PROCEDURES

SECTION 014100 - QUALITY CONTROL

SECTION 017320 - SELECTIVE DEMOLITION

SECTION 024100 - WASTE MATERIAL DISPOSAL

SECTION 061000 - ROUGH CARPENTRY

SECTION 072100 - THERMAL INSULATION

SECTION 073110 - ASPHALT SHINGLES

SECTION 073115 - WOOD SHINGLES

SECTION 073116 - METAL SHINGLES

SECTION 076200 - SHEET METAL FLASHING AND TRIM

Section C - Description/Specifications/Statement of Work
1. Multiple locations listed in section 1.2 will be optional bid items. Please refer to the Schedule of Items (SOI) for full list of base bid and optional bid locations as well as roofing material to be installed.
A. American Fork Hydroelectric Power Plant building is near Pleasant Grove, UT. Head north on UT-146 N/ Canyon Rd for 3.1 miles. Turn right onto W Alpine Loop Rd and continue for 2.8 miles and the building will be to the left.
1. 40.437759 , -111.723919
1. 40.495978 , -111.083026
1. 40.025124 , -111.145638
1. 40.025025 , -111.145595
J. The American Fork Fee Station is near Pleasant Grove, UT. Head north on North Canyon Rd and turn right onto UT-92. The Fee station will be to the right.
1. 682 American Fork Canyon Rd, Pleasant Grove, UT 84062
2. 40.435440, -111.746441
B. Construction sites will not be closed to the public or forest service during construction. The contractor will be responsible for signing and limiting public and forest service access to the portions of the building and site where the construction...
C. There is existing electrical service for the site. Contractor shall have permission to use existing electrical services during construction. Contractor shall be aware of the use of electrical services and shall limit the use of electrical service...
D. There is Water service on site. Contractor is to provide connections and extensions of services as required for construction operations.
E. Public toilet facilities are available on site.
F. Construction Hours – Hours of operation for the construction, demolition, excavation, and subsequent cleanup shall be only between the hours between 7:00 a.m. and 7:00 p.m. Monday through Saturday.

File details come from the government source that posted it. Updated .