Summary of Glulam Trail Bridge Standard Plan

This is a U.S. Department of Agriculture Forest Service standard construction plan for glulam stringer trail bridges located at South Walker Creek and Boundary Trail on the Caribou Targhee National Forest, Westside Ranger District. The plan was revised on December 4, 2025, and consists of five detailed specification sheets covering bridge design, materials, and construction requirements.

The standard plan specifies construction of trail bridges using Douglas Fir (DF) glulam stringers with a 24F-V4 combination symbol rating. Bridge components include three stringers per structure (25 to 60 feet span depending on pedestrian load requirements), 3" x 8" minimum deck planks, solid sawn timber or glulam curb rails, and steel diaphragms. Decking, running planks, and railing systems require treatment with pentachlorophenol or copper naphthenate for exposed conditions. The specifications detail bearing shoe assemblies, timber sill or concrete sill connections, anchor bolt details with malleable iron washers, and gabion foundation basket systems. Materials must conform to American National Standards Institute (ANSI) 117 specifications for glulam members, ASTM standards for reinforcing steel, and Western Wood Products Association grading rules. Foundation designs include both timber sill connections on undisturbed soil and concrete sill options with standard gabion basket sizes ranging from 6 to 12 feet in length. All construction must comply with federal highway project specifications (FP-03) and current trail bridge construction standards.

View the file

Other files for this federal contract opportunity

Other files attached to Westside Trail Bridge Replacements, newest first.
File Type Posted
J.3 Nail-lam Drawings (6 Pages).pdf PDF
1240LP26Q0053 - Westside Trail Bridge Replacements.pdf PDF
J.1 Statement of Work (1 Page).pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

963 - GLULAM TRAIL BRIDGE GSB

7152-2.1 7152 25 FT 24 FT 90 200 24F-V4 DF 5 1/8" x 16 1/2" Yes DF 3x Yes SS DF 3x 9 FT 28 1/2" Yes

7152-2.1 DF CURB 9" X DF 3x 4 FT See Notes SS 12"x12"x7' Yes Bridge has three stringers- - - - - See Notes

55 1/8"

SOUTH WALKER CREEK & BOUNDARY TRAIL BRIDGES

CARIBOU TARGHEE NATIONAL FOREST

WESTSIDE RANGER DISTRICT

12/4/2025

1 5

7244-1 7144 25 FT 24 FT 55 1/8" 90 200 24F-V4 DF 5 1/8" x 16 1/2" YES DF 3x YES SS DF 3x 9 FT 28 1/2" YES

7244-1 DF CURB 9" X DF 3x 4 FT See Notes SS 12"x12"x7' Yes See Notes Bridge has three stringers

SOUTH WALKER CREEK & BOUNDARY TRAIL BRIDGES

CARIBOU TARGHEE NATIONAL FOREST

WESTSIDE RANGER DISTRICT

12/4/2025

2 5

JonathanWheeler2 Oval

963 - GLULAM TRAIL BRIDGE

A

A

GSB

SOUTH WALKER CREEK & BOUNDARY TRAIL BRIDGES

CARIBOU TARGHEE NATIONAL FOREST

WESTSIDE RANGER DISTRICT

12/4/2025

3 5

SOUTH WALKER CREEK & BOUNDARY TRAIL BRIDGES

CARIBOU TARGHEE NATIONAL FOREST

WESTSIDE RANGER DISTRICT

12/4/2025

4 5

965 - TRAIL BRIDGE SUBSTRUCTURES

B

B

GAB

SOUTH WALKER CREEK & BOUNDARY TRAIL BRIDGES

CARIBOU TARGHEE NATIONAL FOREST

WESTSIDE RANGER DISTRICT

12/4/2025

5 5

JonathanWheeler2 Oval