This document is a Statement of Work for a federal contract opportunity that involves the reconstruction of the Mackinaw Campgrounds in the Fishlake National Forest in Utah. The key details are:

The project includes removing and disposing of existing campground site furniture, demolishing and removing designated restrooms, pulverizing asphalt, constructing new asphalt roads and spurs, new family units and tent pads, a new group site with pavilion, new precast concrete restrooms, renovating existing restrooms, and modifying and installing new utilities including electrical, sewer, and water lines. Optional work may include portions of the work above. The project is located approximately 42 miles southeast of Richfield, Utah and the contractor can use designated government sources and pits for disposal and select borrow. The contract has a start date of September 16, 2024 and a base bid of 365 calendar days. Detailed technical specifications for the various construction and renovation activities are provided.

View the file

Other files

File Type Posted
Amendment 1_1240LT24R0004.pdf PDF
Mackinaw CG Site Visit Sign In.pdf PDF
MakcinawSiteVisit.docx DOCX document
1240LT24R0004.pdf PDF
J.4 Fishlake.P2.Mack.SOI.Final.03.01.2024.xlsx XLSX spreadsheet
J.5 Determination of Responsibility.pdf PDF
J.1 Wage Determination.pdf PDF
J.3 Fishlake.P2.Mack.Dwg.Final.03.01.2024.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FINAL – 3/1/2024

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-1

Section C - Description/Specifications/Statement of Work

GENERAL SPECIFICATIONS

FISH LAKE RECREATION COMPLEX PHASE 2 MACKINAW CAMPGROUND

Final – 3/1/2024

1.1 SCOPE OF CONTRACT

A. This project includes reconstruction of the Mackinaw Campgrounds (Little Mackinaw, Mackinaw and Mackinaw Extension Campgrounds).

B. The work includes:

1. Removal and disposal of existing campground site furniture, demolition and removal of designated restrooms, and asphalt pulverizing.

2. Constructing new asphalt roads and spurs.

3. Constructing new family units and tent pads; and installing new campground site furniture.

4. Constructing a new group site with pavilion.

5. Installing new precast concrete restrooms.

6. Renovating existing restrooms as designated.

7. Modifying and installing new utilities, including new electrical, sewer and water lines.

C. Optional work that may be awarded includes portions of the work above, as described in the Schedule of Items.

D. Quantities associated with these options are identified in the Schedule of Items.

1.2 PROJECT LOCATION

A. The project is located in the Fremont Ranger District of the Fishlake National Forest, Sevier County, Utah. GPS Coordinates: 38.531000°, -111.740957°. It is located approximately 42 miles by road Southeast of Richfield, Utah. From Interstate 70, the project may be accessed via Utah Roads 119, 24 and 25.

B. Government Sources and Pits:

C. Pelican Point Pit: 38.575799°, -111.693237° (approx. 5 miles by road from project). The pit can be accessed from Utah Road 25 and Forest Road 34 (Pelican Overlook Road).

a. Disposal Area: This pit shall be used as a disposal area according to Section 024100 “Waste Material Disposal.”

b. Select Borrow: This pit is also a potential government source for select borrow according to Section 312010 “Select Borrow.” However, imported select borrow is not anticipated for this project.

D. Gates Lake Pit: 38.753255°, -111.680278° (approx. 20 miles by road from project). The pit can be accessed from Utah Road 25 and Forest Roads 640 and 40 (Gates Lake Road).

a. Barrier Rocks: This pit is a government source for barrier rocks according to Section 322205 “Barrier Rocks.”

Solicitation No.: 1240LT24R0004 J.2 Attachment

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-2

1.3 SITE INFORMATION AND LIMITATIONS

A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:

1. Construction sites will be closed to the public during construction. The Forest Service will issue a closure order to the public. The Contractor will be responsible for signing and limiting public access.

2. Contractor will provide all materials and labor necessary to protect streams, wet or dry, during construction activities. The Contractor will be required to submit a stream protection plan and receive approval from the COR, in writing, prior to the beginning of construction.

3. All construction equipment shall be pressure washed before entering National Forest System lands. The removal of mud and debris from treads, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.

4. Water is available at the site for construction purposes. When the seasonal portion of the water system is shut-down, water is available nearby. Coordinate water access with the Contracting Officer.

5. Toilet facilities are available at the site seasonally. When the seasonal portion of the water system is shut-down, the contractor shall provide temporary toilet facilities (porta-potty) at the site during all construction work.

1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING

A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR and Utah Department of Transportation. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.

1.5 WORK CAMPS, STAGING AND STORAGE AREAS

A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage trailers (work or housing) on site.

1.6 INSPECTION OF WORKSITE

A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor

Solicitation No.: 1240LT24R0004

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-3

from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.

1.7 START DATE

A. Sept. 16, 2024.

1.8 CONTRACT TIME

A. Base Bid: 365 Calendar Days

1.9 SPECIFICATIONS

A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.

Section 000501 - Shower And Rest Room Building Remodel, Unit B Section 000502 - Historic Stone Restroom, Unit E Section 010250 - Construction Staking Section 011250 - Measurement And Payment With Asphalt Section 011900 - Mobilization Section 013300 - Submittal Procedures Section 014100 - Quality Control Section 023701 - Sediment And Erosion Control Measures Section 024100 - Waste Material Disposal Section 024102 - Removal And Disposal Of Structures And Obstructions Section 033000 - Cast-In-Place Concrete Section 033020 - Concrete From Packaged Dry Mix For Minor Structures Section 033540 - Concrete Sidewalk And Stairs Section 040902 - Stone Restoration And Cleaning Section 055210 - Pipe And Guard Rail Railings Section 073129 - Wood Shingles And Shakes Section 074623 - Wood Siding And Trim Section 076200 - Sheet Metal Flashing And Trim Section 079200 - Joint Sealants Section 080152 - Historic Treatment Of Wood Windows Section 087100 - Door Hardware Section 088001 - Glazing For Historic Windows Section 090190 - Maintenance Repainting Section 099100 - Painting Section 099113 - Exterior Painting Section 099123 - Interior Painting Section 099300 - Staining And Transparent Finishing Section 099300.10 - Preparation And Application Of Transparent Finishes For Shingles Section 099600 - High-Performance Coatings

Solicitation No.: 1240LT24R0004

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-4

Section 101110 - Three Panel Bulletin Board Section 101400 - Signs Section 101415 - Site Identification Sign (Hdpe) Section 129400 - Family Unit And Site Furnishings Section 129410 - Group Site And Site Furnishings Section 129702 - Fee Tube Section 133401 - Precast Concrete Flush Restroom Building Section 136000 - Pre-Manufactured Shelter Section 221100 - Water Distribution Systems Section 221102 - Curb Valves And Boxes Section 221105 - Water Hydrants Section 221116 - Domestic Water Piping Section 221300 - Sewer Systems Section 224216.13 - Commercial Lavatories Section 260000 - Common Work Results For Electrical Section 260519 - Low-Voltage Electrical Power Conductors And Cables Section 260526 - Grounding And Bonding For Electrical Systems Section 260533.13 - Conduits For Electrical Systems Section 260533.16 - Boxes And Covers For Electrical Systems Section 260553 - Identification For Electrical Systems Section 262726 - Wiring Devices Section 311000 - Clearing And Grubbing Section 312000 - Earthwork Section 312010 - Select Borrow Section 312100 - Project Site Preparation And Grading Section 312225 - Excavation & Embankment Section 321200 - Hot-Mix Asphalt Paving Section 321204 - Crushed Aggregate Base Or Surface Course Section 321210 - Rockery Retaining Wall Section 322100 - Tent Pads Section 322205 - Barrier Rocks Section 322622 - Precast Concrete Curb Stops Section 322640 - Pavement Marking Section 322706 - Asphalt Pavement Pulverizing Section 323116 - Gates For Roads Section 329206 - Seeding

END OF SECTION C

May 2024

Solicitation No.: 1240LT24R0004

SHOWER AND REST ROOM BUILDING REMODEL, UNIT B 000501-1

USDA FOREST SERVICE, R4

FISH LAKE RECREATION COMPLEX PHASE 2 MACKINAW CAMPGROUND

SECTION 000501 - SHOWER AND REST ROOM BUILDING REMODEL, UNIT B

PART 1 - GENERAL

1.1 SUMMARY

A. This work includes all labor, fees and materials associated with installing a new cedar shake roof and flashing, interior and exterior paint work, new water fountain, door hardware, and other minor repairs as shown in the drawings and specifications.

B. Work will include the following.

1. Remove existing cedar shake roof materials and flashing as shown in drawings and specifications.

2. Install new cedar shake roof construction and flashing for 8 skylights and other penetrations per design as shown in drawings and specifications.

3. Prep and stain wood siding and trim as shown in drawings and specifications..

4. Remove and replace door hardware as shown in drawings and specifications.

5. Replace water fountain and create frost proof water line as shown in drawings and specifications.

6. Perform other minor repairs as described in drawings and specifications.

1.2 REFERENCE SPECIFICATIONS

A. The publications listed below form a part of this specification to the extent referenced.

The publications are referred to in the text by the basic designation only.

2021 International Building Code 2004 Americans with Disabilities Act/Architectural Barriers Act Guidelines (ADA/ABAG) (http://www.access-board.gov/adaag/html/adaag.htm)

1.3 RELATED WORK

A. The work shall be in accordance with the contract drawings.

B. The work shall be in accordance with the following subsidiary specifications. The subsidiary specifications are referred to in the text by the Section designation only.

1. SECTION 073129 – WOOD SHINGLES AND SHAKES

2. SECTION 074623 – WOOD SIDING

3. SECTION 076200 – SHEET METAL FLASHING AND TRIM

4. SECTION 079200 – JOINT SEALANTS

5. SECTION 080152 – HISTORIC TREATMENT OF WOOD WINDOWS

6. SECTION 087100 – DOOR HARDWARE

7. SECTION 090190 – MAINTENANCE REPAINTING

8. SECTION 099113 – EXTERIOR PAINTING

9. SECTION 099123 – INTERIOR PAINTING

Solicitation No.: 1240LT24R0004 J.2 Attachment http://www.access-board.gov/adaag/html/adaag.htm

SHOWER AND REST ROOM BUILDING REMODEL, UNIT B 000501-2

10. SECTION 099600 – HIGH PERFORMANCE COATINGS

11. SECTION 221116 – DOMESTIC WATER PIPING

12. SECTION 224216 – LAVATORY

1.4 MEASUREMENT AND PAYMENT

A. Improvement to existing 8-unit shower and restroom building Unit B – Measurement and Payment shall be Lump Sum Quantity (LSQ) as shown in the Schedule of Items for the demolition work and remodel of the building. Payment shall include removing existing roofing down to existing sheathing, installing cedar shake roof and flashing, prep and paint of all exterior woodwork, replacement of door hardware and water fountain, and other minor repairs as shown in the drawing and specifications.

PART 2 - PRODUCTS - Not Applicable

PART 3 - EXECUTION

3.1 GENERAL

A. Work shall be completed in accordance with the contract drawings and specifications.

3.2 DEMOLITION

A. All Demolition of the Comfort Station Remodel shall be executed as directed in Specification 017320 – SELECTIVE DEMOLITION.

3.3 CONSTRUCTION ENVIRONMENT

A. Contractor shall maintain a clean, trash-free construction environment throughout the progress of work.

3.4 CLEANUP

A. Cleanup shall include disposal of waste materials in accordance with Section 024100.

END OF SECTION

February 2024

Solicitation No.: 1240LT24R0004

HISTORIC STONE RESTROOM, UNIT E 000502-1

USDA FOREST SERVICE, R4

FISH LAKE RECREATION COMPLEX PHASE 2 MACKINAW CAMPGROUND

SECTION 000502 - HISTORIC STONE RESTROOM, UNIT E

PART 1 - GENERAL

1.1 SUMMARY

A. This work includes all labor, fees and materials associated with prepping and staining the existing cedar shake roof, repairing the rubble screen wall, restoration of windows and doors, interior and exterior painting and staining, replace faucet handles, and prep and seal ceramic tile flooring as shown in the drawings and specifications.

B. Work will include the following.

1. Prep and stain existing cedar shake roof as shown in drawings and specifications.

2. Prep and stain wood siding and trim as shown in drawings and specifications.

3. Prep and paint the ceiling,

4. Restoration of doors and windows as shown in drawings and specifications.

5. Prep and seal ceramic tile flooring as described in drawings and specifications.

1.2 REFERENCE SPECIFICATIONS

A. The publications listed below form a part of this specification to the extent referenced.

The publications are referred to in the text by the basic designation only.

2021 International Building Code 2004 Americans with Disabilities Act/Architectural Barriers Act Guidelines (ADA/ABAG) (http://www.access-board.gov/adaag/html/adaag.htm)

1.3 RELATED WORK

A. The work shall be in accordance with the contract drawings.

B. The work shall be in accordance with the following subsidiary specifications. The subsidiary specifications are referred to in the text by the Section designation only.

1. SECTION 040902 – STONE RESTORATION & CLEANING

2. SECTION 073129 – WOOD SHINGLES AND SHAKES

3. SECTION 074623 – WOOD SIDING

4. SECTION 076200 – SHEET METAL FLASHING AND TRIM

5. SECTION 079200 – JOINT SEALANTS

6. SECTION 080152 – HISTORIC TREATMENT OF WOOD WINDOWS

7. SECTION 087100 – DOOR HARDWARE

8. SECTION 088001 – GLAZING FOR HISTORIC WINDOWS

9. SECTION 090190 – MAINTENANCE REPAINTING

10. SECTION 099113 – EXTERIOR PAINTING

11. SECTION 099123 – INTERIOR PAINTING

12. SECTION 099300 – STAINING AND TRANSPARENT FINISHING

Solicitation No.: 1240LT24R0004 J.2 Attachment http://www.access-board.gov/adaag/html/adaag.htm

HISTORIC STONE RESTROOM, UNIT E 000502-2

13. SECTION 099600 – HIGH PERFORMANCE COATINGS

14. SECTION 224216 – LAVATORY

1.4 MEASUREMENT AND PAYMENT

A. Improvement to existing historic restroom building Unit E – Measurement and Payment shall be Each (EA) as shown in the Schedule of Items for the demolition work and remodel of the building. Payment shall include restoration of roof, doors, windows, prep and paint of all exterior woodwork, replacement of door hardware, and resealing ceramic tile flooring as shown in the drawing and specifications.

PART 2 - PRODUCTS - Not Applicable

PART 3 - EXECUTION

3.1 GENERAL

A. Work shall be completed in accordance with the contract drawings and specifications.

3.2 DEMOLITION

A. All Demolition of the Comfort Station Remodel shall be executed as directed in Specfication 017320 – SELECTIVE DEMOLITION.

3.3 CONSTRUCTION ENVIRONMENT

A. Contractor shall maintain a clean, trash-free construction environment throughout the progress of work.

3.4 CLEANUP

A. Cleanup shall include disposal of waste materials in accordance with Section 024100.

END OF SECTION

February 2024

Solicitation No.: 1240LT24R0004

CONSTRUCTION STAKING 010250-1

USDA FOREST SERVICE, R4

FISH LAKE RECREATION COMPLEX PHASE 2 MACKINAW CAMPGROUND

SECTION 010250 - CONSTRUCTION STAKING

PART 1 - GENERAL

1.1 SUMMARY

A. This work shall consist of the construction staking of roads, parking lots, parking spurs, family units, tent pads, paths, stairways, culverts, retaining walls, buildings, and utilities in accordance with the Drawings and Specifications. The work includes the furnishing of all labor, equipment, instruments, materials, transportation and other incidentals necessary to complete the construction staking in accordance with these specifications and acceptable engineering practice.

1.2 QUALITY CONTROL

A. Construction staking shall be accomplished under the direction of a Civil Engineer, Engineering Technician, or Land Surveyor closely associated and familiar with construction staking; periodic visits to the project site are required.

1.3 MEASUREMENT AND PAYMENT

A. Measurement shall be lump sum for surveying and staking the project through all phases of construction.

PART 2 - PRODUCTS

2.1 GOVERNMENT-FURNISHED SURVEY CONTROL SHEETS

A. The Government will provide the contractor with a set of survey control sheets showing horizontal and vertical control for site to be staked. The Government will provide the Contractor with layout information that will include:

1. Control Points - Northing, Easting, Existing Elevations.

2. Roads, Spurs, Parking Areas - Northing, Easting, and Finish Elevations for centerline and edge of roads, spurs, parking areas.

3. Pathways and Trailways - Northing, Easting, and Finish Elevations for centerline.

4. Buildings and Other Structures - Northing, Easting, and Finish Elevations for corners of buildings, other structures (septic tanks, fencing, etc).

5. Camp Sites, Picnic Sites, and Tent Pads - Northing, Easting, and Finish Elevations for corners of Camp Picnic Sites.

6. Utility Lines - Northing, Easting, and Existing Ground Elevations for centerline of utilities (Water Line, Sewer Line, Electrical Lines).

7. Drainfields - Northing, Easting, for corners of Drainfields.

8. Segmented Retaining Walls - Northing, Easting, and Finish Elevations and Existing

Elevations (for reference) for subgrade (at top and bottom of wall) at start and end

Solicitation No.: 1240LT24R0004

CONSTRUCTION STAKING 010250-2

of wall, corners, stairs, and at maximum 25 foot along wall. (points at top of wall and bottom of wall). Note - Top of wall shall be a minimum of 4 inches above finish grade and bottom of wall shall be a minimum of 12 inches below finish grade.

2.2 STAKES

A. Identification stakes and hubs shall be of sufficient length and width to provide and solid set in the ground and to provide space for marking above ground when applicable. Other dimensions and materials may be used, such as steel reinforcing bars, wire flagging and markers, and metal pins, if approved in writing by the Contracting Officer (CO). The top 2 inches of all slope, guard, reference, clearing, and structure stakes shall be painted or marked with plastic flagging. Colors used on stakes or for flagging shall be as follows:

1. Roads, parking lots, and parking spurs -Orange

2. Waterlines, utilities, and culverts -Blue

3. Family Units, group units, stairs, and paths -Red

4. Buildings, excavation and grading -Yellow

5. Tent pads -Blue/White Striped

2.3 SURVEY NOTE PAPER AND BOOKS

A. Paper for survey notes shall be moisture-resistant paper. Notes shall be contained in books with covers that will protect the contents and retain the pages in numerical sequence during field use. Field notebooks or note paper shall be furnished by the contractor.

PART 3 - EXECUTION

3.1 GENERAL

A. The Contractor shall be required to provide all necessary staking and control for all phases of construction. The contractor shall use the data and information shown on the project drawings to establish the location of all facilities to be constructed under this contract.

The Contractor may choose any method of establishing horizontal and vertical controls provided the following minimum precision and accuracy requirements are met.

B. Accuracy requirements:

1. Minimum position close; 1/1000

2. Vertical closure: 0.05 ft (vertical)/station (100 feet horizontal)

3. Cross section and slope stake precision:

a. Allowable deviation of cross section line projection from a true perpendicular to tangents, a true bisector of angle points, or a true radius of curves: +/-3 degrees.

b. Cross section topography measurements shall be taken so that variations in ground form a straight line connecting the cross section points will not exceed: 1.0 ft.

Solicitation No.: 1240LT24R0004

CONSTRUCTION STAKING 010250-3

c. Horizontal and vertical accuracy for slope stake, slope stake references, and clearing limits. In feet or percentage of horizontal distance measured form centerline or reference stake, whichever is greater. Slope reference stakes and slope stakes: 0.15 ft or 0.6%. Clearing limits: 1.0 ft.

3.2 ESTABLISHING AND REFERENCING IMPROVEMENT LOCATIONS

A. Access Roads, Parking Spurs, and Parking lots:

1. Slope stakes (cut and fill catch points), clearing limits, and slope stake references shall be established on both sides of the centerline at each station established. Slope stakes and slope stake references shall be located on a line at right angles to tangents and on radial lines or curves. Slope stake catch points shall be located by using the grading plans and/or profiles, typical road section templates, as shown on the drawings and the information provided with staking points.

2. Slope stakes shall be set at 50-foot intervals, at significant breaks in the ground profile, culvert locations, and widening transition points. Slope stakes shall be set at 25 foot intervals around curves having a radius less than 100 feet.

B. Group Units, Family Units and tent Pads

1. Slope stakes shall be established at the corners of family units. Slope stakes shall be written to reference the finish grade of the unit or pad being staked.

C. Paths and Trails

1. Slope stakes (cut and fill catch points), clearing limits, and slope stake references shall be established on both sides of the centerline at each station established. Slope stakes and slope stake references shall be located on a line at right angles to tangents and on radial lines or curves. Slope stake catch points shall be located by using the grading plans and/or profiles, and typical path and trail section templates as shown on the drawings.

2. Slope stakes shall be set at 10-foot intervals, at significant breaks in the ground profile, culvert locations, and widening transition points.

D. Culverts

1. Slope stakes and slope reference stakes shall be set at all culvert locations. A culvert reference stake and hub shall be set on the centerline of the culvert 10 feet from each end or beyond the clearing limit, which ever is greater. The following shall be recorded on these stakes:

a. The actual field measured length

b. The vertical and horizontal distance from hubs to the invert at the ends of the culvert.

E. Waterline, Sewerline, & other Utilities

1. Waterline, Sewerline, & other Utilities shall be staked at the locations shown on the drawings with the specified minimum burial depth. Waterline and sewerline elevations shall be accurately staked to provide for drainage as indicated on the

Solicitation No.: 1240LT24R0004

CONSTRUCTION STAKING 010250-4

drawings. Grade stakes shall be established as necessary to provide the control for the construction work.

F. Buildings

1. Slope stakes and slope stake references shall be established at each corner and as necessary to provide adequate construction control.

3.3 DISCREPANCIES

A. The contractor shall compare the staked centerline horizontal and vertical alignment with the design data. Differences between previously recorded and observed elevations of bench marks shall be referred to the Contracting Officer. Differences in centerline profile elevations exceeding 1 foot at any two or more consecutive points shall be reported to the contracting Officer for evaluation and possible revision. Staking of these areas shall be deferred until the Contacting Officer resolves these differences.

3.4 VERTICAL CONTROL

A. Vertical control for construction shall be as referenced on the Drawings.

3.5 MARKING STAKES

A. All stakes shall be legibly marked, in the format agreed upon with the Contracting Officer, with a stake pencil that leaves an imprinted or with waterproof ink. Marking shall conform to the nomenclature below;

PI Point of Intersection of tangents PC Point of curvature POC Point on curve Pt Point of tangency POT Point on tangent RP Reference point P P-line (preliminary location line) L L-line (final location line) BM Bench mark TBM Temporary bench mark BT Begin taper (any) ET End taper (any) C Cut F Fill L Centerline D Ditch W Width

3.6 SURVEY NOTES

A. All survey data shall be neatly recorded in survey books. All survey notes shall become the property of the Forest Service. Errors shall be deleted by lining out. Date, crew

Solicitation No.: 1240LT24R0004

CONSTRUCTION STAKING 010250-5

names and positions, instrumentation, and weather shall be recorded in the notes at the beginning of each day’s work. The party chief shall sign or initial each page of the notes immediately after the last entry for each day’s work.

B. Electronically recorded survey notes shall be consecutively numbered and headed to identify the contents. The notes shall be supported and accompanied by a bound book that records the project name and for each day identifies date, crew names and positions, instrumentation, weather, type of survey, stationing of sections between which survey was performed, and survey data or sketched that cannot be electronically recorded. The party chief shall sign or initial the electronically recorded notes and Day Book immediately after the last entry for each day’s work.

END OF SECTION 010250

May 2024

Solicitation No.: 1240LT24R0004

MEASUREMENT AND PAYMENT WITH ASPHALT 011250-1

USDA FOREST SERVICE, R4

FISH LAKE RECREATION COMPLEX PHASE 2 MACKINAW CAMPGROUND

SECTION 011250 - MEASUREMENT AND PAYMENT WITH ASPHALT

PART 1 - GENERAL

1.1 SUMMARY

A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.

B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.

1.2 DETERMINATION OF QUANTITIES

A. The following measurements and calculations shall be used to determine contract quantities for payment.

1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.

2. For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.

3. For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.

4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.

5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.

6. For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.

7. For bituminous material, volumes will be measured at 60°F or will be corrected to the volume at 60°F by using ASTM D1250 for asphalts. Emulsified asphalt will be measured at 60°F, or measured by converting the gallonage at another temperature to gallonage at 60°F by means of the following formula:

Solicitation No.: 1240LT24R0004

MEASUREMENT AND PAYMENT WITH ASPHALT 011250-2

Gallons at 60°F = Gallons at A°F 1+0.00025 (A°F - 60°F)

* A°F is the temperature of the material at the time the gallonage is measured.

a. For vehicular shipments, net certified scale weights or weights based on certified volumes will be used as a basis of measurement. Measurements will be adjusted when bituminous material has been lost from the vehicle or the distributor, has been wasted, or has otherwise not been incorporated into this work. Determining true weights of hauling vehicles shall be made by weighing the empty vehicles at least once a day at the times the CO directs.

Each vehicle shall bear a plainly legible identification mark.

b. When bituminous materials are shipped, net certified weights, or volume corrected for loss of foaming, can be used for computing quantities.

B. Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."

1.3 UNITS OF MEASUREMENT

A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:

1. Acre: Make longitudinal and transverse measurements for area computations horizontally.

2. 50lb Bag: Measurement will be for the actual number of 50lb bags of standard bentonite grout.

3. 94lb Bag: Measurement will be for the actual number of 94lb bags of standard cement or grout.

4. Cubic Yard (CY): A measurement computed by one of the following methods:

a. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.

b. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.

c. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery.

Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.

5. Each (EA): One complete unit, which may consist of one or more parts.

6. Gallons (GAL): The quantity shall be measured by any of the following methods:

a. Measured volume in container.

b. Metered volume by approved metering system.

c. Commercially package volume.

Solicitation No.: 1240LT24R0004

MEASUREMENT AND PAYMENT WITH ASPHALT 011250-3

7. Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.

8. Linear Foot (LF): Measurement of work along its length from point-to-point;

parallel to the base or foundation. Do not measure overlaps.

9. Lump Sum (LS): One complete unit.

10. Mile: Measured horizontally along the centerline of each roadway, approach, or ramp.

11. Pound (LB): For sacked or packaged material, measurement will be the net weight as packed by the manufacturer.

12. Square Foot (SF): Measured on a plane parallel to the surface being measured.

13. Square Yard (SY): Measured on a plane parallel to the surface being measured.

14. Ton: Measured as a short ton consisting of 2,000 pounds.

1.4 METHOD OF MEASUREMENT

A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:

1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.

2. DESIGNED QUANTITIES (DQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:

a. As a result of changes in the work authorized by the CO.

b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.

c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.

3. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.

4. STAKED QUANTITIES (SQ) - These quantities are determined from staked measurements prior to construction.

5. VEHICLE QUANTITIES (VQ) - These quantities are measured or weighed in hauling vehicles.

1.5 PRICE ADJUSTMENT (for Out-of-Specification Bituminous Materials)

A. Bituminous materials are defined as all types and grades of asphalt cement, liquid asphalt, emulsified asphalt, and dust oil.

Solicitation No.: 1240LT24R0004

MEASUREMENT AND PAYMENT WITH ASPHALT 011250-4

B. If bituminous material fails one or more test requirements, and the Contracting Officer determines it is in the public interest to accept the material at a reduced price, the price reduction shall be based on the test results giving the largest percent price adjustment.

The contractor may remove and replace the defective material or accept the adjustment.

C. The price reduction shall apply to all pay items affected.

D. Price adjustment will be based on samples taken in duplicate in accordance with AASHTO T40 under the supervision of the Contracting Officer. Samples shall be sent to an authorized laboratory. The laboratory shall test one of each duplicate sample and retain the other. When any test result is not within the specification limits, the laboratory shall immediately notify the Contractor, the supplier, and the Contracting Officer. The Contractor, after notifying the Contracting Officer, may check test the retained sample.

E. If the retained sample tests satisfactorily, the material will be accepted. If the retained sample also fails, the following schedule of price adjustments shall apply. The average of test values for the two samples will determine the basis for price adjustment, except when test results on the samples differ by more than the applicable AASHTO or ASTM Repeatability Unit; then, the test result numerically nearest the specification requirement will be used. (A repeatability unit is defined as D2S or D2S% limit for single operator precision described in ASTM C670.)

F. The schedule of price adjustments shall not apply to the following tests:

Test AASHTO Test Method Spot Test T102 Particle Charge T59 Ductility T51

G. Bituminous materials failing to meet specifications for these tests shall be removed and replaced.

H. See Table 011250-1 for the schedule of price adjustments for bituminous materials that do not meet specifications.

Table 011250-1

Schedule of Price Adjustments for Out-of-Specification Bituminous Materials.

Application

Deviation from Specification Limit Measured in Reproducibility Units*.

Less than 1 1 but less than 2

2 but less than 3

3 or more

Price reduction applicable to bituminous base course and pavement mixture or to seal coat and bituminous material paid for as a separate item.

0% 5% 25% Remove & Replace

Price reduction applicable to bituminous material paid for as a separate item.

0% 10% 25% Remove & Replace

* A reproducibility unit is defined as D2S or D2S% limit for multi-laboratory precision described in ASTM recommended practice C670.

Solicitation No.: 1240LT24R0004

MEASUREMENT AND PAYMENT WITH ASPHALT 011250-5

The Sieve Test (AASHTO T59) results may be exempt from the Schedule of Price Adjustments provided the contractor's quality assurance program includes checking the uniformity of bituminous spread rates in increments no greater than 1 foot over the width of the spray bar and variation between increments is no greater than 5 percent.

PART 2 - PRODUCTS (NOT APPLICABLE)

PART 3 - EXECUTION (NOT APPLICABLE)

END OF SECTION 011250

May 2024

Solicitation No.: 1240LT24R0004

MOBILIZATION 011900-1

USDA FOREST SERVICE, R4

FISH LAKE RECREATION COMPLEX PHASE 2 MACKINAW CAMPGROUND

SECTION 011900 - MOBILIZATION

PART 1 - GENERAL

1.1 SUMMARY

A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.

1.2 MEASUREMENT AND PAYMENT

A. The measurement shall be lump sum for mobilization. Payment shall be as follows:

1. Bond premiums will be reimbursed after receipt of the evidence of payment.

2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.

3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.

4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.

5. Progress payments for mobilization and preparatory work shall be subject to retainage.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION 011900

May 2024

Solicitation No.: 1240LT24R0004

SUBMITTAL PROCEDURES 013300-1

USDA FOREST SERVICE, R4

FISH LAKE RECREATION COMPLEX PHASE 2 MACKINAW CAMPGROUND

SECTION 013300 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals. See Table 013300-1 for a summary of required submittals.

B. See other specification section within this package for additional requirements on submittal.

1.2 SUBMITTAL PROCEDURES

A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.

1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.

2. If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Allow 14 days for processing each re-submittal.

4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.

C. Identification: Place a permanent label or title block on each submittal for identification.

1. Indicate name of firm or entity that prepared each submittal on label or title block.

2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.

3. Include the following information on label for processing and recording action taken:

a. Project name.

b. Date.

Solicitation No.: 1240LT24R0004

SUBMITTAL PROCEDURES 013300-2

c. Name and address of Contractor.

d. Name of manufacturer.

e. Unique identifier, including revision number.

f. Number and title of appropriate Specification Section.

g. Drawing number and detail references, as appropriate.

h. If more than one item is shown on submittal sheet, identify item.

D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.

E. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.

F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.

1.3 MEASUREMENT AND PAYMENT

A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.

PART 2 - PRODUCTS

2.1 ACTION SUBMITTALS – (Submittals requiring CO approval)

A. General: Prepare and submit Action Submittals required by individual Specification Sections.

1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's written recommendations.

b. Manufacturer's product specifications.

c. Manufacturer's installation instructions.

d. Manufacturer's catalog cuts.

e. Wiring diagrams showing factory-installed wiring.

f. Compliance with recognized trade association standards.

g. Compliance with recognized testing agency standards.

Solicitation No.: 1240LT24R0004

SUBMITTAL PROCEDURES 013300-3

C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Include the following information, as applicable:

a. Dimensions.

b. Identification of products.

c. Fabrication and installation drawings.

d. Roughing-in and setting diagrams.

e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.

f. Notation of dimensions established by field measurement.

2. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.

D. Contractor's Construction Schedule: The contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 5 day of commencement of work.

E. Samples: Prepare physical units of materials or products, including the following:

1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.

2.2 INFORMATIONAL SUBMITTALS – (Submittals NOT requiring CO approval)

A. General: Prepare and submit Informational Submittals required by other Specification Sections.

1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will not return copies.

2. Certificates and Certifications: Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.

3. Test and Inspection Reports: Comply with requirements in Section 014100 "Quality Control."

B. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.

C. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.

D. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.

Solicitation No.: 1240LT24R0004

SUBMITTAL PROCEDURES 013300-4

E. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.

PART 3 - EXECUTION

3.1 GENERAL

A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.

B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

C. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.

D. Submittals not required by the Contract Documents will not be reviewed and may be discarded.

E. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, he shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution.

F. Requests for substitutions will only be considered if contractor submits the following:

1. Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution.

Submit additional information if required by Contracting Officer. All items in the above information shall be circled, tagged, or marked in some way to indicate all deviations or differences which the proposed item differs from the originally specified item.

2. Similar data as above for item originally specified. All items shall be marked to identify where/how the proposed substitution will differ.

3. A statement by the Contractor that the proposed substitution is in full compliance with the contract documents, applicable codes, and laws.

4. The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.

3.2 SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications. The following table is a summary of the required

Solicitation No.: 1240LT24R0004

SUBMITTAL PROCEDURES 013300-5

submittals for the project - the table is to assist the Contractor and may not be all inclusive

– additional submittals may be required by specific specifications:

TABLE 013000-1

Spec.

Section Section Title Subse ction Required Submittal

C General Specifications 1.3A Stream Protection Plan C General Specifications 1.4A Traffic Control Plan

010250 Construction Staking 3.6 A Survey Notes 013300 Submittal Procedures 2.1D Construction Schedule 014100 Quality Control 1.3 A Contractor quality control plan 014100 Quality Control 1.3 B Permits, Licenses, and Certificates 014100 Quality Control 1.3 C Test and inspection reports 014100 Quality Control 1.3 D As-Built drawings 023701 Sediment & Erosion Control

Measures 1.2A Sediment & Erosion Control Plan

033000 Cast-in-Place Concrete 1.3A Product Data 033000 Cast-in-Place Concrete 1.3B Design Mix 033000 Cast-in-Place Concrete 1.3C Shop Drawings 033000 Cast-in-Place Concrete 1.3D Samples 033540 Concrete Sidewalk and Stairs 1.2A Product Data 033540 Concrete Sidewalk and Stairs 1.2B Design Mixtures 033540 Concrete Sidewalk and Stairs 1.2C Reinforcement 033540 Concrete Sidewalk and Stairs 1.2D Material Test Reports 040902 Stone Restoration and Cleaning 1.3A Product Data 040902 Stone Restoration and Cleaning 1.3B Samples 055210 Pipe and Guard Rail Railings 1.3A Product Data 055210 Pipe and Guard Rail Railings 1.3B Shop Drawings 073129 Wood Shingles and Shakes 1.3A Product Data 073129 Wood Shingles and Shakes 1.3B Qualification Data 073129 Wood Shingles and Shakes 1.3C Maintenance Data 073129 Wood Shingles and Shakes 1.3D Warranties 074623 Wood Siding and Trim 1.3A Product Data 076200 Sheet Metal Flashing and Trim 1.3A Product Data 076200 Sheet Metal Flashing and Trim 1.3B Shop Drawings 076200 Sheet Metal Flashing and Trim 1.3C Samples 079200 Joint Sealants 1.2A Product Data 080152 Historic Treatment of Wood

Windows 1.3A Product Data

080152 Historic Treatment of Wood Windows

1.3B Qualification Data

080152 Historic Treatment of Wood Windows

1.3C Historic Treatment Program

087100 Door Hardware 1.2A Product Data 087100 Door Hardware 1.2B Shop Drawings 087100 Door Hardware 1.2C Other Action Submittals

Solicitation No.: 1240LT24R0004

SUBMITTAL PROCEDURES 013300-6

Spec.

Section Section Title Subse ction Required Submittal

088001 Glazing for Historic Windows 1.4A Product Data 088001 Glazing for Historic Windows 1.4B Samples 090190 Maintenance Repainting 1.4A Product Data 090190 Maintenance Repainting 1.4A Samples 099100 Paint 1.4A Color Selection Sheets 099123 Interior Painting 1.3A Product Data 099123 Interior Painting 1.3B Sustainable Design Submittals 099123 Interior…