J.1 - Statement of Work (SOW).pdf
PDF 101 KB Posted
- Attached to
- South Fork Bunk House Well
- Solicitation number
- 1240LT24R0019
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is a Statement of Work (SOW) for the South Fork Bunkhouse Well Project. The key details are:
The Forest Service is seeking a contractor to drill and develop a new potable water well, perform water quality analysis, install an existing submersible pump, and connect the new waterlines to the existing water lines and wellhead. The magnitude of the project is less than $35,000. The work is anticipated to commence 180 days after the Notice to Proceed, with an expected completion within 60 days. Required bid items include well construction, water quality analysis, and submersible pump controller installation. Optional bid items cover additional well depth and a new submersible pump. Contractor questions are due by 8/23/2024, and proposals are due by 8/30/2024. This is a total small business set-aside contract opportunity with the Forest Service.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK (SOW)
SOUTH FORK BUNKHOUSE WELL PROJECT
GENERAL SPECIFICATIONS
SCOPE OF WORK
The Rio Grande National Forest is seeking a Contractor to drill and develop a new potable water well, perform all necessary water quality analysis for use as a Public Water System, install an existing submersible pump and installation of a new pump control panel and all wiring and appurtenances. The Government shall provide a trench, waterlines, and power to the new well once the well has been successfully developed. The Contractor shall connect the new waterlines to the existing water lines and the new wellhead. The purpose of the main contract items is to ensure the current private water system remains supplied with potable water and that the system can continue adhere to the regulations and requirements of a Public Water System.
Optional items will include provisions for well construction and development beyond the depth estimated and a new submersible pump should the existing pump be inadequate for use in the newly constructed well.
BACKGROUND
In the town of South Fork, Colorado the Rio Grande National Forest operates a private water system consisting of a bunkhouse and ancillary dwelling with an existing well that supplies the ancillary dwelling with water, which contains the current water supply pressure tank, and then supplies the bunkhouse with water. The current well is 120 feet deep and is located as specified on Form GWS-44. The well replacement permit stipulates a maximum pumping rate of 15 gallons per minute and has an annual yield of 3 acre-feet from an unconfined aquifer (Type II).
LOCATION
South Fork, Colorado 81154 37°38'15.4"N 106°39'36.7"W 37.637611, -106.660194
MAGNITUDE OF PROJECT
Less than $35,000.00
PERIOD OF PERFORMANCE
The work is anticipated to commence 180 days after receiving the Notice to Proceed (NTP) sometime in late 2024 or early to mid- 2025. The work is expected to be completed within 60 days after the work is started (Subject to change).
TECHNICAL REQUIREMENTS
BID ITEMS
1. BID ITEM 0001 Well Construction and Development
The Contractor shall provide all materials, labor, equipment, tools, transportation, permits, licenses, supervision, expertise, and other incidentals necessary to successfully construct a new functioning potable water supply well in accordance with all the rules described in the Colorado Code of Regulations (CCR) - Colorado Division of Water Resources - Well Construction Rules 2 CCR-402-2 (NOTE: The Contractor shall adhere to all the rules described in these regulations whether mentioned specifically or not.)
The newly constructed well shall be constructed to according to 2 CCR-402-2 Rule 10 Minimum Construction Standards for Water Wells. The well shall conform to 2 CCR-402-2 Rule 10 Section 10.4.6 for Wells Constructed into a Type 2 Aquifer as stated on the Well Permit Application. It shall be of the pit less adapter Type, and the casing shall extend 18 inches above ground level. The newly constructed wellhead and casing shall be protected by a hinged steel enclosure (i.e. stick-up or monument) capable of being locked with a standard government padlock and allows for maintenance of the well and wellhead components.
The Contractor shall install and construct the well in accordance with the specifications, drawings, and applicable manufacturer’s recommendations.
The Contractor shall salvage the existing submersible pump from the existing well to be used in the newly constructed well. The Contractor shall furnish and install all necessary piping, check valves, and wiring for the existing submersible pump to function in the newly constructed well.
The newly constructed well shall have a yield of 15 gallons-per-minute and an annual yield of 3 acre-feet.
The Government has estimated the new well to be 150 feet in depth for bidding purposes. The Bid quantity shall be in linear feet and include all necessary casing material, grouting material and wiring required to reach well development depth. The Contractor shall provide pricing per linear foot. This pricing shall also be used for Option Item 1001 Additional Well Construction Depth, to ensure well development if additional construction beyond 15% of the specified depth is required. (FAR 52.211-18 Variation in Estimated Quantity)
The Contractor shall develop the well and install the casing and all necessary grouting in a timely manner to avoid the possibility of a borehole collapse.
The Contractor shall install all materials and appurtenances in accordance with the manufacturer's specifications and recommendations. The Contractor shall submit specifications of the well casing, capping, vent, enclosure, and grouting materials prior to the construction and development of the well.
The Contractor shall perform disinfection procedures according to 2 CCR-402-2 Rule 15 Minimum Disinfection Standards.
The Contractor shall install the well at no more than 200 feet from the location specified in the well replacement permit: 37°38'15.4"N 106°39'36.7"W. The Contractor shall coordinate with COR on the specific placement of the well within the 200-foot radius.
The Contractor shall conduct testing according to 2 CCR-402-2 Rule 12 Well Testing and submit a Well Construction and Yield Estimate Report (GWS-31) to the Colorado Division of Water Resources to verify well construction.
The Contractor shall be responsible for the remediation of any failed wells that do not meet the requirements described in the specifications of this contract.
The Contractor shall utilize the Government supplied water lines and power conduit to complete the connections between the newly constructed well and the existing water supply pressure tank water lines. The Contractor shall furnish and install the necessary additional power conduit, water lines, and equipment to complete this task.
2. BID ITEM 0002 Water Quality Analysis and Testing The Contractor shall perform National Primary and Secondary Contaminants and laboratory analysis of water quality per EPA, Safe Drinking Water Act, and the Colorado Code of Regulations – 5 CCR 1002-11 Colorado Primary Drinking Water Regulations.
The Contractor shall perform all the necessary tests and documentation to bring the newly constructed well into compliance consistent with a Public Water System (PWS) (but shall remain classified as a private water system) as outlined in the Colorado Code of Regulations.
The Contractor shall submit the results of the water quality analysis tests to the Government and all applicable Colorado State Water Authorities in a timely manner once results are received.
3. BID ITEM 0003 Submersible Pump Controller Unit and Wiring The Contractor shall provide all materials and expertise to install a new submersible pump control panel in the ancillary bunkhouse building containing the current water pressure supply tank and all necessary wiring, conduit, switches, grounding, and trenching to function properly.
The Contractor shall submit the pump control panel model, manufacturer’s specifications, documentation, and manuals prior to the installation of the pump control panel.
The Contractor shall ensure compatibility with the existing submersible pump and a new submersible pump model of equivalent specifications.
OPTIONAL BID ITEMS
The Government shall not guarantee the award of these optional bid items.
1. OPTION ITEM 1001 Additional Well Construction Depth If the Contractor cannot develop or construct a well with a viable water source at or near the specified 150 feet in depth, The Contractor shall bid per-foot depth beyond the 150 feet until a viable water source suitable for development is reached, not to exceed 200 feet total well depth.
The Contractor shall be responsible for the remediation of the well if a viable water source cannot be located for development up to the 200 feet.
2. OPTION ITEM 1002 New Submersible Pump. The Contractor shall furnish and install a submersible pump and all associated pump wiring, fittings, conduit, and control panel to transmit water from the new well source to the water supply pressure tank.
Pump appurtenances, wiring, conduit, and their quantities shall be considered incidental to this bid item.
The Contractor shall field verify quantities of wiring, conduit, and quantities of materials prior to installation of the pump and related appurtenances.
The submersible pump shall be capable of producing the maximum flow rate of 15 gallons per minute.
The Contractor shall submit the proposed pump model, manufacturer’s specifications, documentation, and manuals prior to the installation of the pump.
GOVERNMENT FURNISHED
The Government shall supply a trench containing water distribution lines and power lines and conduit from the newly constructed well to the tie-in-point for the existing water supply pressure tank lines. The Contractor shall complete the connection of the water lines and power lines.
The Government shall complete the abandonment of the existing well according to Colorado Division of Water Resources 2 CCR 402-2 Rule 16 – Standards for Plugging, Sealing, and Abandoning Wells and Boreholes and complete the Well Abandonment Report and submit to the Colorado Division of Water Resources.
KEY DELIVERABLES
Item No. Deliverable / Item
Title Description Delivery
Format Due By
1 Project Schedule/Timeline
Timeline describing the approximate timeline of each task (mobilization, well construction, well development, water testing, e.g.)
Via email to COR
10 days Before start of project and mobilization.
2 Well Construction
– Well Construction Material List
Manufacturer’s model numbers, specifications, and/or manuals for the proposed materials to construct a pitless adapted well including but not limited to:
Casing Material Grouting Material Cap Component Types Cap Vent Component Types Pitless Adapter Components Conduit Type Wiring Type Check Valve Types
Via email to COR
Due 15 days before Project Start and Mobilization
Protective enclosure
3 Submersible Pump Controller Unit Documentation (includes wiring and conduit).
Manufacturer’s Warranty
Model number, specifications, and manual for the submersible pump controller unit and all related wiring and conduit.
Manufacturer’s standard warranty. Manufacturer’s Warranty
Via Email to COR
Due 10 days before Project Start and Mobilization
4 Well Construction Yield Estimate Report
GWS-44 Yield Estimate Report
Copied to the COR Via email (or hardcopy)
Due within 5 days of being sent to the Colorado Division of Water Resources
5 Water Quality Analysis Report
Report detailing the results of the water quality testing as required by the Colorado Code of Regulations and Safe Drinking Water Act
Via Email to the COR
Due within 5 days of being sent to the Colorado Department of Public Health
Option Item 1002
New Submersible Pump Documentation and Material List
Manufacturer’s model number, specifications, and manual for the proposed submersible pump. The pump shall provide the necessary 15 gallons-per-minute yield.
Via Email to the COR
Due 15 days before project start and mobilization and after option item award
TRAVEL
The project location is located within the town of South Fork, Colorado.
CONTRACTOR’S KEY PERSONNEL
Foreman(s) – Contractor shall provide a foreman or foremen with all the necessary expertise to oversee and complete the project.