J 1(a) Attachment 2 CDRLs (RVLTD).pdf

PDF 3 MB Posted

Attached to
Rotorcraft Vertical Lift Technology Development Federal contract opportunity
Solicitation number
80ARC020R0011
Issued by
National Aeronautics and Space Administration Ames Research Center

About this file

This solicitation is for the Rotorcraft Vertical Lift Technology Development contract to provide engineering, research and development, systems analysis and modeling and simulation services to the National Aeronautics and Space Administration Ames Research Center. Services include aeronautical engineering, research and development, systems analysis, and modeling and simulation across a wide spectrum of rotary wing technology topics. The current incumbent contracts are cost plus fixed fee IDIQ contracts awarded in 2014 to five companies. This competitive acquisition will result in a new multiple-award hybrid IDIQ contract with both cost plus fixed fee and firm fixed price task orders, having a five year ordering period from the effective date. Proposals are due by August 21, 2020 and contract award is expected in February 2021. The solicitation identifies small business subcontracting goals and provides the point of contact for any questions by the specified due date.

View the file

Other files for this federal contract opportunity

Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RVLTD CONTRACT DATA REQUIREMENTS LIST (CDRL)

For purposes of this document, "time" is defined as follows: Time, if stated as a number of days, is calculated using calendar days, unless otherwise specified. It includes Saturdays, Sundays, and legal federal holidays. If, however, the last day falls on a Saturday, Sunday, or legal federal holiday, then the period shall include the next business day.

Unless otherwise specified below, reports may be submitted electronically to each of the identified recipients.

With the exception of the IT Security Plan and Organizational Conflicts of Interest Mitigation Plan, all items in the CDRL will be based on task order awarded.

TABLE OF CONTENTS

Line item No. Title

1 Monthly Progress Report 2 Mishap Report 3 Contractor Monthly Accident Report 4 Contractor Requests for Government Provided Property (DoD Industrial Plant And Equipment

Requisition System DD1419) 5 Property Management Report 6 NASA Property in the Custody of Contractors (NF 1018) 7 Initial Financial Management Report 8 Monthly Financial Management Report 9 New Technology Report

10 IT Security Management Plan

Subcontract Consent Package Individual Subcontractor Report

Summary Subcontract Report Organizational Conflicts of Interest Mitigation Plan

File details come from the government source that posted it. Updated .