This document is an appendix for the IVHM Boiler Exhaust Replacement project. It outlines the scope of work for removing and replacing three existing boiler exhaust stacks. The vendor will be responsible for removing the entire existing exhaust stack, approximately 30 linear feet, and fabricating and installing new 16-inch diameter welded carbon steel pipe exhaust stacks of the same length. The new stacks must include a rain cap, pipe flanges, and a square-to-round fitting above the roof. The vendor will utilize existing roof penetrations and ensure all work areas are sealed and watertight. All work must be completed during normal business hours and carry a minimum 1-year warranty. The vendor will be responsible for the proper disposal of any waste generated.
Pricing terms, set-asides, incumbent contractors, funding sources, and other commercial details are not provided in this appendix. The document focuses solely on the technical specifications and scope of work for the boiler exhaust stack replacement project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CPO Notice 2020~8.06 Procurement and Electronic Submission | — | |
| IVHM Boiler Exhaust RFQ~6.doc | DOC document | |
| Standard Terms~85.pdf | ||
| Standard Certs~11.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IVHM Boiler Exhaust Replacement Appendix A Provide labor and materials for the removal of existing boiler exhaust stack, fabrication of a new exhaust stacks, and installation of new exhaust stacks. There are 3 separate exhaust stacks that will need to be removed and replaced with new.
General Specifications
· Vendor will remove the entire existing boiler exhaust stack this includes everything from the boiler and through the roof approximately 30 lineal feet.
· Vendor will fabricate approximately 30 lineal feet of boiler exhaust stack to include:
· Metal utilized must be welded carbon steel pipe and must have a minimum thickness of 16 gauge.
· Boiler exhaust stack to be fitted with a rain cap, pipe flanges, and feature a square to round fitting above the roof.
· Boiler exhaust stack to be a diameter of 16 inches
· Boiler exhaust stack will need to bolt into existing mounting plate located on boiler.
· Vendor will install new boiler exhaust stack starting at boiler and exiting through the roof.
· Vendor will utilize existing penetrations for new boiler exhaust stack through any walls, ceilings, or roofs.
· Vendor will wrap new boiler exhaust stack with 2 1/2" thick mineral wool and finish with aluminum jacket.
· The boiler exhaust stack will be wrapped from the boiler to the roof penetration.
· Vendor will ensure that penetration from the attic to the roof is sealed.
· Must be a watertight seal to ensure no water leaks into attic.
· Vendor must ensure that all penetrations are sealed
· All parts and labor must carry a minimum of a 1 year warranty
· Vendor will be responsible for the proper removal and disposal of any waste created during job from facility grounds.
· Vendor will ensure work area is clear of debris and garbage when work is completed.
· Vendor will coordinate and schedule all work through the Chief Engineer.
· All work to be completed during normal business hours Monday-Friday 08:00 AM – 05:00 PM excluding State and Federal holidays.
· Chief engineer will sign off that work is satisfactory at the completion of the project.
· Vendor must bring all materials and tools to job site. The facility will not be responsible for the storage or transportation of any tools and/or materials.
IVHM Boiler Exhaust Replacement Appendix B Boiler Room to Attic