IVHM Boiler Exhaust Appendices .docx

DOCX document 1001 KB Posted

Attached to
IVHM FY21 Boiler Exhaust Replacement
Solicitation number
21-497DVA-MANTE-B-20771
Issued by
Kane County, Illinois

About this file

This document is an appendix to a state and local contract opportunity issued by the Illinois government for the replacement of boiler exhaust stacks at a facility. The work includes the removal of the existing 30-linear foot boiler exhaust stacks, fabrication of new 16-inch diameter carbon steel stacks, and installation of the new stacks. The new stacks must be fitted with a rain cap, pipe flanges, and a square-to-round transition above the roof, and must be wrapped in mineral wool insulation. All work must be coordinated with the facility's Chief Engineer and completed during normal business hours. The contract requires a minimum 1-year warranty on all parts and labor.

The pricing terms are not specified, but the contract opportunity indicates that the vendor must provide all materials and tools required for the project. There are no mentions of set-asides, incumbents, funding requirements, or other salient financial details.

View the file

Other files

File Type Posted
Standard Certs V.18.1~17.doc DOC document
Forms A Section V.18.1~37.doc DOC document
CPO Notice 2020.06 Procurement and Electronic Submission —
IVHM Boiler Exhaust RFQ~4.doc DOC document
Standard Terms and Conditions v.20.1~60.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IVHM Boiler Exhaust Replacement Appendix A Provide labor and materials for the removal of existing boiler exhaust stack, fabrication of a new exhaust stacks, and installation of new exhaust stacks. There are 3 separate exhaust stacks that will need to be removed and replaced with new.

General Specifications

· Vendor will remove the entire existing boiler exhaust stack this includes everything from the boiler and through the roof approximately 30 lineal feet.

· Vendor will fabricate approximately 30 lineal feet of boiler exhaust stack to include:

· Metal utilized must be welded carbon steel pipe and must have a minimum thickness of 16 gauge.

· Boiler exhaust stack to be fitted with a rain cap, pipe flanges, and feature a square to round fitting above the roof.

· Boiler exhaust stack to be a diameter of 16 inches

· Boiler exhaust stack will need to bolt into existing mounting plate located on boiler.

· Vendor will install new boiler exhaust stack starting at boiler and exiting through the roof.

· Vendor will utilize existing penetrations for new boiler exhaust stack through any walls, ceilings, or roofs.

· Vendor will wrap new boiler exhaust stack with 2 1/2" thick mineral wool and finish with aluminum jacket.

· The boiler exhaust stack will be wrapped from the boiler to the roof penetration.

· Vendor will ensure that penetration from the attic to the roof is sealed.

· Must be a water tight seal to ensure no water leaks into attic.

· All parts and labor must carry a minimum of a 1 year warranty

· Vendor will be responsible for the proper removal and disposal of any waste created during job from facility grounds.

· Vendor will ensure work area is clear of debris and garbage when work is completed.

· Vendor will coordinate and schedule all work through the Chief Engineer.

· All work to be completed during normal business hours Monday-Friday 08:00 AM – 05:00 PM excluding State and Federal holidays.

· Chief engineer will sign off that work is satisfactory at the completion of the project.

· Vendor must bring all materials and tools to job site. The facility will not be responsible for the storage or transportation of any tools and/or materials.