Text version

Sheet1

INDEPENDENT GOVERNMENT ESTIMATE
CONTRACT:PUMP AND MOTOR CONTINGENCY
CONTRACTOR:TBD
PURCHASE ORDER:TBD
SHIP:TBD
LOCATION:NAVY REGION SOUTHWEST
ITEM NO CLINDESCRIPTIONQUANTITYUNITUNIT PRICEAMOUNT
0001COMMERCIAL INDUSTRIAL SERVICES (CIS) PUMPS AND MOTORS CONTRACT IS TO PROVIDE LABOR, RIGGING SERVICES, CRANE, TRANSPORTATION, EQUIPMENT, AND MATERIALS FOR THE REMOVAL, OVERHAUL, REASSEMBLY, SHOP TEST, RE-INSTALLATION, ALIGNMENT AND ADJUSTMENTS, SHIPBOARD OPERATIONAL TEST OF THE NR-3 FIRE PUMP AND MOTOR UNIT ASSEMBLY ONBOARD THE USS COMSTOCK (LSD-45).1LOT
PROVIDE LABOR, SERVICES, EQUIPMENT AND MATERIALS FOR THE RIGGING (OFFLOAD AND ONLOAD), CRANE SUPPORT AND TRANSPORTATION OF THE NR-3 FIRE PUMP AND MOTOR UNIT FROM THE SHIP TO THE SHOP FOR REPAIRS AND TRANSPORT REPAIRED FIRE PUMP AND MOTOR UNIT BACK TO THE SHIP FOR RE-INSTALLATION AND OPTEST IN ACCORDANCE WITH THE REQUIREMENTS OF THE CONTRACT AND THE STATEMENT OF WORK
PROVIDE LABOR, SERVICES, EQUIPMENT, AND MATERIALS TO ACCOMPLISH THE OVERHAUL OF THE FIRE PUMP IN ACCORDANCE WITH TECH MANUAL S6226-CF-MMA-010 TO INCLUDE REPLACEMENT OF THE SHAFT SLEEVES, BEARINGS, LUBRICATION FITTINGS, O-RINGS, GASKETS, SLINGERS, MECHANICAL SEAL, CASE AND WEARING RINGS.

ACCOMPLISH THE OVERHAUL OF THE FIRE PUMP MOTOR IN ACCORDANCE WITH NAVSEA STANDARD ITEM 009-113 TO INCLUDE THE INSTALLATION OF NEW BEARINGS, THERMISTORS, SEALS, O-RINGS, GASKETS, FITTINGS, LOCK WASHERS, LOCKNUTS, FLEXIBLE CONNECTORS, CONDUIT BOX, SHAFT BUILD-UP, IMPELLER HOUSING HARDWARE, IMPELLER HOUSING COVER REPAIR, REFURBISHMENT AND PAINTING FLEXIBLE CONDUIT AND GROUND STRAPS IN ACCORDANCE WITH THE REQUIREMENTS OF THE CONTRACT AND THE STATEMENT OF WORK. ADDITIONAL WORK ALSO COVERS THE BUILD-UP AND MACHINING OF THE BEARING HOUSINGS OR MOTOR SHAFT WHEN REQUIRED.

(SEE NOTES 1 AND 2)

PROVIDE LABOR, SERVICES, EQUIPMENT AND MATERIALS FOR THE SHIPBOARD AND SHOP OERATIONAL TEST OF THE OVERHAULED FIRE PUMP AND MOTOR UNIT ASSEMBLY
PROVIDE LABOR, SERVICES, EQUIPMENT AND MATERIALS FOR THE PREPARATION AND PAINTING OF THE FIRE PUMP AND MOTOR UNIT IN ACCORDANCE WITH NAVSEA STANDARD ITEMS 009-32
PROVIDE LABOR (40 HOURS), SERVICES, EQUIPMENT, AND MATERIALS FOR THE MACHINING HOURS (IF REQUIRED) IN ACCORDANCE WITH THE REQUIREMENTS OF THE CONTRACT AND THE STATEMENT OF WORK

(SEE NOTE 2)

NET AMT

MILESTONE EVENT
1. Purchase Order Start Date15-May-23
2. Remove and transport to shop15-17 May 23
3. Overhaul and Shop Test17-May to 26-Jun-23
4. Delivery to ship26-27 Jun-23
5. Purchase Order End Date27-Jun-23
NOTES:
1. Refer to Technical Manual S6225-W6-MMA-010, Technical Manual for Navy Standard Titanium Centrifugal Pump 1000 GPM (NAVSEA Drawing No. 803-5773203) for detailed procedures on the overhaul of the Fire Pump and Motor to include shipboard shop operational testing.
2. If machining hours are required, submit CFR to the SUPERVISOR with the result of UNSAT measurement not conforming in accordance with the Technical Manual S6225-W6-MMA-010, Technical Manual for Navy Standard Titanium Centrifugal Pump 1000 GPM (NAVSEA Drawing No. 803-5773203).