ITEMIZED PRICE LIST.pdf

PDF 205 KB Posted

Attached to
USS ASHLAND (LSD48) - PUMPS AND MOTORS
Solicitation number
N5523623Q0191
Issued by

About this file

This itemized price list document outlines pricing for a contingency contract to provide pump and motor overhaul services for the USS Ashland (LSD-48). The contractor will be responsible for removing, transporting, overhauling, testing and reinstalling the NR-2 fuel oil purifier motor onboard the ship. Services include rigging, crane support, transportation to and from the shop, disassembly and inspection, repair or replacement of parts, machining of housing or shaft if needed, operational testing at the shop, preparation and painting, and reinstallation of the motor. Pricing is provided on a firm fixed price basis for the labor hours and materials required to complete the scope of work in accordance with the contract and statement of work. Key milestones include removal of the existing motor by September 6th, delivery of the overhauled motor back to the ship by October 4th, and contract completion by October 10th. The solicitation was issued by the Department of the Navy Naval Sea Systems Command for the USS Ashland.

View the file

Other files

File Type Posted
SF18.pdf PDF
N5523623Q0191_RFC.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT: PUMP AND MOTOR CONTINGENCY

CONTRACTOR: TBD

PURCHASE

ORDER:

TBD

SHIP: USS ASHLAND (LSD-48)

LOCATION: NAVY REGION SOUTHWEST

ITEM NO CLIN DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT

COMMERCIAL INDUSTRIAL SERVICES (CIS) PUMPS

AND MOTORS CONTRACT IS TO PROVIDE LABOR,

RIGGING SERVICES, CRANE, TRANSPORTATION,

EQUIPMENT, AND MATERIALS FOR THE REMOVAL,

OVERHAUL, REASSEMBLY, SHOP TEST, DELIVERY,

ALIGNMENT AND ADJUSTMENTS OF THE NR-2 FUEL

OIL PURIFIER MOTOR ONBOARD THE USS ASHLAND

(LSD-48)

1 LOT

PROVIDE LABOR, SERVICES, EQUIPMENT AND MATERIALS

FOR THE RIGGING (OFFLOAD AND ONLOAD), CRANE

SUPPORT AND TRANSPORTATION OF THE NR-2 FUEL OIL

PURIFIER MOTOR FROM THE SHIP TO THE SHOP FOR

REPAIRS AND DELIVER THE OVERHAULD NR-2 FUEL OIL

PURIFIER MOTOR BACK TO THE MOTOR FOUNDATION IN

ACCORDANCE WITH THE REQUIREMENTS OF THE

CONTRACT AND THE STATEMENT OF WORK (SEE NOTE 4)

ACCOMPLISH THE OVERHAUL OF THE NR-2 FUEL OIL

PURIFIER MOTOR IN ACCORDANCE WITH NAVSEA

STANDARD ITEM 009-33 TO INCLUDE THE INSTALLATION

OF NEW BEARINGS, THERMISTORS, SEALS, O-RINGS,

GASKETS, FITTINGS, LOCK WASHERS, LOCKNUTS,

FLEXIBLE CONNECTORS, CONDUIT BOX, SHAFT BUILD-

UP, SHAFT ALIGNMENT,REFURBISHMENT AND PAINTING

FLEXIBLE CONDUIT AND GROUND STRAPS IN

ACCORDANCE WITH THE REQUIREMENTS OF THE

CONTRACT AND THE STATEMENT OF WORK. ADDITIONAL

WORK ALSO COVERS THE BUILD-UP AND MACHINING OF

THE BEARING HOUSINGS OR MOTOR SHAFT WHEN

REQUIRED.

(SEE NOTE 3)

PROVIDE LABOR, SERVICES, EQUIPMENT AND MATERIALS

FOR THE SHOP TEST OPERATIONAL OF THE OVERHAULED

NR-2 FUEL OIL PURIFIER MOTOR

PROVIDE LABOR, SERVICES, EQUIPMENT AND MATERIALS

FOR THE PREPARATION AND PAINTING OF THE NR-2 FUEL

OIL PURIFIER MOTOR IN ACCORDANCE WITH NAVSEA

STANDARD ITEMS 009-32

PROVIDE LABOR (40 HOURS), SERVICES, EQUIPMENT, AND

MATERIALS FOR THE MACHINING HOURS (IF REQUIRED)

IN ACCORDANCE WITH THE REQUIREMENTS OF THE

CONTRACT AND THE STATEMENT OF WORK

(SEE NOTE 3)

NET AMT $0.00

MILESTONE EVENT

ITEMIZED PRICE LIST

3. Repair and Shop Test

1. Purchase Order Start Date

2. Remove and transport to shop

01-Sep-26

1-6-Sep-23

6-Sep to 4-Oct-23

4. Delivery to ship 4-10-Oct-23

4. Remove existing NR-2 FUEL OIL PURIFIER MOTOR from the motor foundation and install the repaired Motor back onto the foundation.

5. Purchase Order End Date

NOTES:

1. In the event the requirements stated in the SOW has changed from NAVSEA Standard Item 009-33 to 009-17 as a result of the disassembly inspection, the Contractor shall submit one legible copy, in hard copy or approved transferrable media, of a CFR listing the recommendations of repair requirements to the SBS. The change in scope will require the Contractor to submit a revised estimated cost towards the performance of the new repair recommendation.

2. Refer to Technical Manual S9541-AM-MMA-010, Technical Manual for Fuel Oil Purifier Assembly for detailed procedures on the overhaul of the Fuel Oil Purfier Motor to include shop operational testing.

3. If machining hours are required, submit CFR to the SUPERVISOR with the result of UNSAT measurement not conforming in accordance with the Technical Manual S9541-AM-MMA-010.

10-Oct-23

File details come from the government source that posted it. Updated .