This is Addendum #2 to Invitation to Bid ITB21-0006 issued by the Henry County Water Authority (HCWA) Purchasing and Inventory Department for the design-build of a 150-foot monopole radio antenna tower for remote water meter reading. The project involves the installation of a monopole tower with associated antenna equipment, electrical service, foundation work, and site development at a location on HCWA-owned property in Henry County, Georgia. Prospective bidders were permitted to visit the site by contacting Bill Banks at 404.392.4006. The bid deadline was Thursday, October 14, 2021 at 2:00 PM, with submissions accepted either in person at the HCWA Operations Pavilion located at 1020 Industrial Parkway, McDonough, Georgia 30253, or online through Quest CDN (Project Number 8033373). Site visits did not require an access road, tree removal was not anticipated to be necessary, and large cranes could be brought into the fenced compound. The addendum clarifies that contract time extensions may be granted for supplier lead times upon prompt notification to HCWA.

Key specifications and requirements addressed in the addendum include that antenna loads, grounding specifications, electrical service requirements, foundation and tower drawings, as-built drawings, and landscaping plans are detailed in the Statement of Work. Foundation design is preferred over direct-set monopole installation based on soils engineering analysis, and all foundation spoils and construction debris must be hauled away from the site. Electrical work must comply with the National Electrical Code, and the 3rd party electrician is Wallace Electric; any electrical cost overruns beyond the bid allowance require owner approval and final change order adjustment. A bid bond equal to five percent (5%) of the base bid is required. The addendum does not specify contract duration, funding source, or total project budget.

Text of this file

Purchasing and Inventory Department

INVITATION TO BID

ITB 21-0006

Design Build of 150' Monopole Radio Antennae

ADDENDUM #2

Questions and Answers

We have received the following questions.

1. Question: Are we to provide an access road to the tower location? If so, what are the specifications?

Answer: No Access road.

2. Question: Can we visit the site? If so, please list contact and phone number.

Answer: Yes. Contact Bill Banks at 404.392.4006

3. Question: Can we cut down trees from around the fenced compound to get the crane into the compound and monopole installed?

Answer: Tree removal should not be necessary.

4. Question: Are there any issues with bringing a large crane into the compound?

Answer: No. There are overhead utilities in the area. All those must be protected and all safety regulations must be followed.

5. Question: Are there any underground utilities within the foundation area?

Answer: There are no underground utilities within tower location. The pole is to be located within the private property owned by Henry County. Henry County will coordinate utility locations with their property limits with Contractor.

6. Question: We need to know how many antennas and lines (and microwave dishes) and what size. We need the specific information for all levels so that the tower manufacturer can calculate the loading.

Answer: Refer to Statement of Work Monopole Tower line G.

7. Question: Can you supply the grounding specifications? Does it have to be approved by an engineer?

If so, what specifications do you want to go by? R56, etc?

Answer: See Statement of Work Monopole Work and Engineering 10, Monopole Tower K, Site Inspections 5 and 7, and Section Test Results

1020 Industrial Parkway, McDonough, GA 30253 (678) 583-3690 • www.hcwa.com http://www.hcwa.com/

8. Question: Does the new underground electrical service have to be in conduit? If so, what size?

Answer: All electrical work shall comply with the National Electrical Code.

9. Question: Is this a new 200-amp service?

Answer: Please see Statement of Work Electrical

10. Question: Who will be responsible to approve the foundation and tower drawings?

Answer: The Owner, HCWA, through the Submittal process

11. Question: How are we to provide the as-built drawings when page 14 of 20 says no site drawings are required?

Answer: See Statement of Work Drawings C and D.

12. Question: Can the total contract time be extended due to supplier lead times?

Answer: Yes, any extended lead times must be reported promptly to HCWA for an extension or suspension of contract time.

13. Question: Page 5 of 20, “E” references landscaping. Do you have a landscape plan?

Answer: See Statement of Work SITE DEVELOPMENT AND EROSION AND SEDIMENT CONTROLS E and F

14. Question: Can foundation spoils be left onsite? Or do they have to be hauled away?

Answer: Foundation spoils and all other construction debris must be hauled away.

15. Question: Is a direct set monopole an option?

Answer: Foundation or Pier are the preferred design and the soils engineering did not take into consideration a direct set monopole design.

16. Question: Who is the 3rd party electrician?

Answer: Wallace Electric

17. Question: What happens if the 3rd party electrical pricing goes over the allotted amount from the bid items schedule?

Answer: Allowance are approved by Owner and managed by Contractor. Allowances are decreased and increased upon final change order. Wallace Electric has performed other monopole electrical work for Henry County.

18. Question: How much is the Bid Bond?

Answer: Five percent (5%) of the base bid.

All other terms and conditions remain in effect. Bids are due Thursday October 14, 2021 2:00 PM.

Either in person at:

Henry County Water Authority Operations Pavilion 1020 Industrial Parkway McDonough, GA. 30253

Please note, all visitors to our facilities must wear masks.

Or submit online at: Quest CDN search project number 8033373 on Quest CDN to find this bid.

Please note, Quest CDN charges a $15 to submit your bid on line.

If you would like to bid on line and have never used Quest CDN please http://www.questcdn.com/ to register prior to the bidding dead line. Membership registration is required to submit a bid on line, registration is free, you only pay to submit your bid. For assistance with Quest CDN email mailto:info@questcdn.com or call (952) ‐233‐1632.

I have read and incorporated the information contained in this addendum 2 into my bid.

Signed Date

Print Name Title https://qap.questcdn.com/qap/projects/prj_browse/ipp_browse_grid.html?projType=all&provider=7558194&group=7558194 http://www.questcdn.com/ mailto:info@questcdn.com

Other files

File Type Posted
Award Information —
ITB21-0006 - Monopole Antennae —
ITB21-0006 Addendum #1 —
Bid Results —

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .