ITB_WS_73_-_Eglin_Lift_Station_Technical_Specifications.pdf
PDF 1 MB Posted
- Attached to
- Eglin Parkway Lift Station Replacement
- Solicitation number
- ITB WS 67-26
- Issued by
- Okaloosa County, Florida
About this file
This is a technical specifications document for the Eglin Parkway Lift Station Replacement project in Florida. The project scope encompasses site preparation and installation of a corrosion-proof polymer concrete precast wet well using the caisson method with tremie pour for the bottom seal, including clearing and grubbing, erosion and sedimentation control installation, excavation, wet well section assembly with watertight joints and retainer straps, tremie seal concrete pouring, secondary bottom pour with chamfered edges, buoyancy calculations, watertightness testing, and backfilling operations. Additionally, the work includes furnishing and installing two approximately 34 horsepower submersible heavy-duty explosion-proof non-clog sewer pumps with base elbows, stainless steel discharge piping, guide rail systems, pump control panels, and all appurtenances required for project completion in accordance with the contract documents and plans.
The technical specifications document provides detailed engineering and performance requirements for materials, equipment, and construction methods but does not contain information regarding pricing terms, set-asides, response deadlines, bid due dates, site visit schedules, bidder meetings, award dates, contract terms, renewal options, incumbent information, or funding sources. Contractors responding to this opportunity should reference the primary invitation for bid document and related contract opportunity materials for complete procurement details, timeline requirements, and financial terms.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Summary of Work Page 01 10 00-1
SECTION 01 10 00
SUMMARY OF WORK
ARTICLE 1 – - GENERAL
1.1 SECTION INCLUDES
A. General Description of Project B. CONTRACTOR - Responsibility C. OWNER - Responsibility D. Contractor’s Use of Site and Equipment Offload
1.2 GENERAL DESCRIPTION OF PROJECT
A. Supply and construct components of a new sanitary sewer pumping station wet well. Bid shall include:
1. The project includes procurement of materials only for two (2) 34 HP submersible non-clog pumps, a complete electrical control system, and secondary level monitoring equipment.
2. Furnishing and installation of a polymer concrete wet well structure constructed using the caisson method, including all excavation, dewatering, installation, and backfilling required to complete the structure in place.
3. Furnishing and installation of concrete masonry unit retaining wall, including all required excavation, dewatering, bedding, backfill, and compaction required to complete the structure in place.
4. Materials and installation of site landscaping.
B. Additive Bid Item :
1. An additive bid item is included for the installation of the pumping equipment, including pumps, internal piping, fittings, and appurtenances within the wet well. The stainless steel wet well discharge piping shall be extended 24” from top of the wet well and shall include 125 lb flange fitting for connection to the discharge piping.
C. Contracting Method: Direct Bid (MATERIAL AND INSTALLATION).
1.3 CONTRACTOR RESPONSIBILITY
A. The following items are intended to identify the general materials and deliverables to be included in the Contractor’s bid proposal. The price shall be all inclusive and equipment listed in bid to be fully functional with parts and services provided.
1. Furnish the following pumps and pump components and appurtenances.
a. Cut openings and field fabricate sleeves for all pipe penetration and electrical pump leads. Coordinate with OWNER on final location and elevation. Provide mechanical seal between carrier pipe and sleeve after installation and testing.
b. Provide minimum 60 ft pump electrical leads for each pump and floats. Leads shall be capable of being extended for termination by Owner into Disconnect Switch and
Summary of Work Page 01 10 00-2
Junction Box.
c. Deliver and offload at project site location in accordance with the Specifications and shall include all necessary material and labor to secure structure as a permanent fixture. Coordinate with the OWNER a minimum 3 weeks in advance of delivery.
2. Furnish the following motor control center and control panel components and appurtenances:
a. Deliver at project site location a fully operational and pre-tested Motor Control Center to operate a duplex sewer pumping station as defined in the specifications and contract documents.
b. Deliver at project site location a fully operational and pre-tested control panel assembly for a duplex sewer pumping station as detailed in the specifications and Contract Drawings. This shall include the instrumentation and controls.
c. All required electrical equipment shall be supplied as identified in the Contract Drawings. Control System and Power Distribution System shall also be fully circuit tested to comply with operational specification and drawings. Simulated load test shall be performed to verify functionality. All tests shall be coordinated with the OWNER and witnessed by OWNERS authorized representative. Testing shall occur within a 150-mile radius of the project location and shall occur during normal working hours and within a one-day time period. Contractor / Supplier may elect to perform testing outside this radius and shall include all travel and lodging expenses in proposal for the Owner or it’s Representative to travel to and from the testing location. Coordinate with the OWNER a minimum 2 weeks in advance of testing schedule.
1.4 OWNER RESPONSIBILITY
A. OWNER will perform certain activities in connection with the Work as follows:
1. Furnish and Install the following components and appurtenances.
a. All above discharge piping, valves and fittings outside the wet well (See Contract
Drawings for Owner Responsibility)
b. ARV valves, taps, and pressure gauges.
c. Influent piping (Material Contractor to field fabricated sleeves after installation of wet well)
d. Below ground electrical and control wiring and conduits
e. Below ground flow meter vault
f. Control Panel mounting material and foundation, including electrical stub-ups
g. Electrical Rack Foundation pad, including electrical stub-ups
h. Generator and generator pad
i. Below ground electrical and control wiring and conduits
j. Electrical Equipment Rack and supporting structures
1.5 MATERIAL CONTRACTOR'S USE OF SITE
A. CONTRACTOR'S use of the Site shall be confined to the areas as coordinated with owner.
Summary of Work Page 01 10 00-3
B. CONTRACTOR shall:
1. coordinate with the OWNER and assume full responsibility for delivery of equipment to the project site and the associated labor, material and equipment required to fully offload the specified equipment at the OWNERS specified location.
2. Obtain and pay for all additional storage or work areas required for its operations and testing, prior to schedule delivery.
END OF SECTION
Measurement and Payment Page 01 27 00-1
SECTION 01 27 00
MEASUREMENT AND PAYMENT
ARTICLE 1 – GENERAL
1.1 SUMMARY
A. This Section specifies administrative and procedural requirements for handling and processing Contract modifications.
B. See Division 1 Section "Allowances" for procedural requirements for handling and processing allowances.
C. See Division 1 Section "Unit Prices" for administrative requirements for using unit prices.
1.2 MINOR CHANGES IN THE WORK
A. ENGINEER will issue supplemental instructions authorizing Minor Changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on form provided by ENGINEER.
1.3 PROPOSAL REQUESTS
A. OWNER-Initiated Proposal Requests: ENGINEER will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.
1. Proposal Requests issued by ENGINEER are for information only. Do not consider them instructions either to stop work in progress or to execute the proposed change.
2. Within time specified in Proposal Request after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.
a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include costs of labor and supervision directly attributable to the change.
d. Include an updated CONTRACTOR's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
B. CONTRACTOR-Initiated Proposals: If latent or unforeseen conditions require modifications to the Contract, CONTRACTOR may propose changes by submitting a request for a change to
ENGINEER.
Measurement and Payment Page 01 27 00-2
1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.
2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
4. Include costs of labor and supervision directly attributable to the change.
5. Include an updated CONTRACTOR's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
6. Comply with requirements in Division 1 Section "Product Requirements" if the proposed change requires substitution of one product or system for product or system specified.
C. Proposal Request Form: Use forms provided by ENGINEER
1.4 ALLOWANCES
A. Allowance Adjustment: To adjust allowance amounts, base each Change Order proposal on the difference between purchase amount and the allowance, multiplied by final measurement of work-in-place. If applicable, include reasonable allowances for cutting losses, tolerances, mixing wastes, normal product imperfections, and similar margins.
1. Include installation costs in purchase amount only where indicated as part of the allowance.
2. If requested, prepare explanation and documentation to substantiate distribution of overhead costs and other margins claimed.
3. Submit substantiation of a change in scope of work, if any, claimed in Change Orders related to unit-cost allowances.
4. OWNER reserves the right to establish the quantity of work-in-place by independent quantity survey, measure, or count.
B. Submit claims for increased costs because of a change in scope or nature of the allowance described in the Contract Documents, whether for the Purchase Order amount or CONTRACTOR's handling, labor, installation, overhead, and profit. Submit claims within 14 days of receipt of the Change Order or Construction Change Directive authorizing work to proceed.
OWNER will reject claims submitted later than 14 days after such authorization.
Measurement and Payment Page 01 27 00-3
1. Do not include CONTRACTOR's or subcontractor's indirect expense in the Change Order cost amount unless it is clearly shown that the nature or extent of work has changed from what could have been foreseen from information in the Contract Documents.
2. No change to CONTRACTOR's indirect expense is permitted for selection of higher- or lower-priced materials or systems of the same scope and nature as originally indicated.
1.5 CHANGE ORDER PROCEDURES
A. On OWNER's approval of a Proposal Request, ENGINEER will issue a Change Order for signatures of OWNER and CONTRACTOR on forms provided by ENGINEER.
1.6 BASE BID ITEMS
A. Item 1 – Mobilization and Demobilization
1. Method of Measurement:
a. Lump Sum (LS): The lump sum price for Mobilization and Demobilization shall be full compensation for Mobilization and Demobilization activities required for all Work as shown and specified. Payments shall include all costs for mobilizing, general conditions for project, bonds and insurance, temporary facilities, demobilizing, and all incidental and appurtenances required to complete the Work as shown and specified in the Contract Documents. The total amount of mobilization shall not exceed 5% of the total Base Bid Price. Payments shall be made at a rate of 25% of mobilization, paid over the first four applications for partial payment.
B. Item 2 – Site Preparation
1. Method of Measurement:
a. Lump Sum (LS): Site Preparation will be paid on a Lump Sum basis. Payment includes all labor, equipment, and incidentals required to clear, grub, remove, and dispose of trees, vegetation, debris, and existing features within the limits shown in the plans. Disposal of cleared debris shall be in accordance with all local, state, and federal regulations. No separate measurement will be made for individual components of the work.
b. The lump sum price shall further include compensation for activities required for developing a stormwater pollution prevention plan (SWPPP), installing, maintaining, and removing all erosion and sediment control measures and devices in accordance with all local, state, and federal regulations and the Contract Documents.
Measurement and Payment Page 01 27 00-4
C. Item 3 – Wet Well Installation
1. Method of Measurement:
a. Lump Sum (LS): The Lump Sum price shall constitute full compensation for furnishing and installing a complete polymer concrete wet well structure using the caisson construction method, in place and accepted. Payment shall include all labor, materials, equipment, and incidentals necessary to complete the work, including furnishing and installing the polymer concrete wet well sections and top slab with hatches, frames, and grates, including all associated work; installation of all joints, seals, gaskets, and grouting required to provide a watertight structure;
and full assembly, alignment, and setting of all wet well components.
b. The Lump Sum price shall further include all penetrations and sleeves required for influent sewer connections, discharge piping, electrical conduits, and any other piping or utility interfaces, including watertight seals and integration with the wet well structure. The Lump Sum price shall also include all excavation within the wet well footprint necessary to advance and install the caisson, including internal excavation, handling of materials, and maintenance of excavation stability; all dewatering required to construct the wet well in dry or controlled conditions;
removal and legal off-site disposal of excavated and unsuitable materials; and all incidental work required to complete the installation. The work also includes all sheeting, shoring, and caisson installation operations required to safely construct the wet well and any surface restoration within the limits of disturbance.
c. No separate measurement or payment will be made for individual components or incidental operations required to complete the work. The Lump Sum price shall include all work necessary to provide a complete, functional, and structurally sound wet well installation.
D. Item 4 – Concrete Pours
a. Lump Sum (LS): The Lump Sum price shall constitute full compensation for furnishing and installing a watertight tremie seal pour with keyway along with installation of the polymer concrete wet well bottom and grouting, chamfering, and all other incidentals necessary for a tremie pour plug and wet well base.
Payment shall include all labor, materials, equipment, and incidentals necessary to complete the work, including furnishing and installing the polymer concrete base, placement of the tremie concrete plug, including all associated work; construction of the polymer concrete bottom, including benching and chamfers; installation of all joints, seals, gaskets, and grouting required to provide a watertight structure;
and full assembly, alignment, and setting of all relevant components for the wet well base.
E. Item 5 – Submersible Pumping Station Equipment
1. Method of Measurement:
a. The Lump Sum price for Submersible Pumping Station Equipment shall constitute full compensation for furnishing all labor, materials, equipment, and incidentals necessary for the procurement and delivery of two (2) 34 HP non-clog submersible
Measurement and Payment Page 01 27 00-5 pumps, one complete electrical and control system, and secondary level monitoring equipment, all as shown in the Plans and in accordance with the Contract Documents.
b. This item is intended to include the cost of equipment only and does not include installation. The Lump Sum price shall include all costs associated with procurement, fabrication, factory testing, delivery, and readiness for installation.
c. The Lump Sum price shall further include all costs associated with submittals, shop drawings, product data, design calculations, operations and maintenance manuals (preliminary and final), warranties, spare parts, special tools, manufacturer’s services, freight, handling, storage, and all other requirements specified in the Contract Documents, including but not limited to Sections 01 33 00, 11145, 16005,and all applicable drawings.
d. No separate measurement or payment will be made for individual components or requirements associated with this item. The Lump Sum price shall include all work necessary to provide a complete and operable pumping station equipment package ready for installation.
F. Item 6 – Stainless Steel Inlet Baffle
1. Method of Measurement:
a. The Lump Sum price for the Stainless Steel Inlet Baffle shall constitute full compensation for furnishing all labor, materials, equipment, and installation of Stainless Steel Inlet Baffle, 5’ x 5’ ¼” Type 316 SS, Bent with 2” Flanges, Supplied with ½” Type 316 SS Wedge Anchors (3” Minimum Embedment, 8 per side), Nuts, and Washers
b. All work related to this item shall be performed after the Owner’s installation of incoming gravity pipe and coring. No payment will be made for work performed under this item before the Owner’s gravity pipe installation.
G. Items 7, 8 , and 9
1. See Bid Form for specifications and requirements to be paid as lot items under Item 5 Submersible Pumping Station Equipment.
H. Item 10 – Testing and Closeout
1. Method of Measurement:
a. The Lump Sum price for Testing and Closeout shall constitute full compensation for furnishing all labor, materials, equipment, and testing for all site installations including backfill and compaction, removal of erosion control measures, and site restoration.
b. The Lump sum price for Testing and Closeout shall further include compensation for all project closeout activities to include as-built drawings, warranties, inspections, and all other work related to closeout as specified in the Plans and Contract Documents.
Measurement and Payment Page 01 27 00-6
I. Item 11 – Installation of two Quercus Virginiana
1. Method of Measurement
a. Lump Sum (LS): The Lump Sum price for Installation of two Quercus Virginiana shall constitute full compensation for furnishing and installing all labor, materials, equipment, and incidentals necessary to complete all landscaping work in accordance with the Plans and Contract Documents, in place and accepted.
b. The Lump Sum price shall include, but not be limited to, site preparation; fine grading; furnishing and installation of all plant materials, including for the complete installation of two Quercus Virginiana ‘Cathedral’ Live Oak Trees: 9” caliper. /20’ height. Minimum; Roots Ball and Burlap or Container with matching canopies, soil preparation and amendments; mulch; staking, guying, and plant protection; and installation of all appurtenances required for a complete landscaping system.
c. The Lump Sum price shall further include all watering, fertilization, trimming, cleanup, replacement of unacceptable or dead plant materials, and maintenance during the establishment or warranty period, as specified in the Contract Documents. All costs associated with submittals, plant sourcing, delivery, storage, coordination, and compliance with applicable specification sections shall be included.
d. No separate measurement or payment will be made for individual components, maintenance activities, or incidental work required to complete the landscaping.
The Lump Sum price shall include all work necessary to provide a complete, healthy, and fully established landscaping installation.
e. Work included under Item 11 will be completed after the Owner completes all other site work and with a mutually agreed upon schedule of installation coordinated with the owner and/or general contractor. No additional mobilization will be paid for any landscaping work.
1.7 ADDITIVE BID ITEM
A. Item 12 – Hardened Steel Pump Impeller and Wear Ring
1. Method of Measurement:
a. The unit price for the Hardened Steel Pump Impeller and Wear Ring shall constitute full compensation for supplying a hardened steel impeller and wear ring in place of a coated system.
b. Material shall be ASTM A532llc with min 15% CrMo-HC. Hardness shall be minimum 690 Bn.
B. Item 13 – Installation of Lift Station Equipment in 10’ Polymer Concrete Wet Well:
1. Method of Measurement:
a. Lump Sum (LS): The Lump Sum price for Wet Well Mechanical Equipment Installation shall constitute full compensation for furnishing all labor, materials, equipment, and incidentals necessary to install the submersible pumps, discharge piping, fittings, electrical, controls, and all appurtenances within the polymer
Measurement and Payment Page 01 27 00-7 concrete wet well, complete and in place, in accordance with the Plans and Contract Documents.
b. The Lump Sum price shall include installation and setting of pumps; furnishing and installation of discharge piping, guide rails, base elbows, pump mounting systems, pipe supports, brackets, all fittings; all hardware, fasteners, and accessories required for a complete and operational system. The work shall also include all lifting, rigging, alignment, anchoring, and assembly required to properly install the equipment.
c. The Lump Sum price shall further include all work required inside the wet well necessary to complete the installation up to the point where the discharge piping exits the wet well structure, including coordination with penetrations and connection points. This item expressly excludes work outside the wet well and any piping or appurtenances beyond the exterior top of the wet well.
d. No separate measurement or payment will be made for individual components or incidental operations required to complete the work. The Lump Sum price shall include all work necessary to provide a complete, functional, and operable wet well mechanical system within the limits described above.
A. Item 14 – Closed Loop Glycol Motor Cooling System
1. Method of Measurement:
a. The unit price for a Closed Loop Glycol Motor Cooling System shall constitute full compensation for supplying a closed-loop motor cooling system compatible with the supplied pump.
b. Cooling fluid shall be propylene glycol with water mix.
1.8 CONSTRUCTION CHANGE DIRECTIVE
A. Work Change Directive: ENGINEER may issue a Construction Change Directive on forms provided by ENGINEER. Work Change Directive instructs CONTRACTOR to proceed with a change in the Work, for subsequent inclusion in a Change Order.
1. Work Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.
2.
3. Work Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.
B. Documentation: Maintain detailed records on a time and material basis of work required by the Work Change Directive.
1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.
ARTICLE 2 – PRODUCTS (NOT USED)
ARTICLE 3 – EXECUTION (NOT USED)
Measurement and Payment Page 01 27 00-8
Project Management and Coordination 01 31 00-1
SECTION 01 31 00
PROJECT MANAGEMENT AND COORDINATION
ARTICLE 1 – GENERAL
1.1 SUMMARY
C. All work herein described shall be performed by the CONTRACTOR, or his approved subcontractors, who shall bear all responsibility for it.
D. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Coordination Drawings.
2. Project meetings.
1.2 OTHER WORK AND EXISTING FACILITIES
E. The CONTRACTOR shall coordinate his work with the OWNER so that the work will not restrain or hinder the OWNER’s operation of existing facilities.
F. Connections to the existing facilities or alteration of existing facilities will be made at times when the use of the piping or facility can be conveniently interrupted for the period of time needed to make the connection or alteration.
G. After having coordinated his work with the OWNER, the CONTRACTOR shall notify the ENGINEER of the time, time limits and methods of each connection or alteration and have the approval of the Engineer before any work is undertaken on the connections or alterations.
H. CONTRACTOR shall reference the General Conditions for coordination of OWNER’s work by others, if any, and coordinate CONTRACTOR’s Work with OWNER or OWNER’s designated coordinator.
1.3 OTHER UTILITIES
A. The CONTRACTOR shall coordinate his operations with all utility companies near or adjacent to the area of his work. The CONTRACTOR shall require said utilities to identify in the field their property and provide drawings as necessary to locate them.
1.4 COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
Project Management and Coordination 01 31 00-2
2. Coordinate installation of different components with other CONTRACTORs to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Prepare similar memoranda for OWNER and separate CONTRACTORs if coordination of their Work is required.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other CONTRACTORs to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of CONTRACTOR's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Pre-demolition conferences.
7. Project closeout activities.
1.5 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum
Project Management and Coordination 01 31 00-3 clearance requirements. Provide alternate sketches to ENGINEER for resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.
2. Sheet Size: At least 11 by 17 inches but no larger than 22 by 34 inches (750 by 1000 mm).
3. Number of Copies: Submit 6 opaque copies of each submittal. ENGINEER will return 1 copy.
4. Refer to individual Sections for Coordination Drawing requirements for Work in those Sections.
B. Photographs and other records of examination.
1.6 PROJECT MEETINGS
A. General: ENGINEER will schedule and conduct meetings and conferences at Project site, unless otherwise indicated, and as appropriate perform the following:
1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify OWNER and ENGINEER of scheduled meeting dates and times.
2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.
3. Minutes: Record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including OWNER and ENGINEER, within 20 days of the meeting.
B. Preconstruction Conference: Refer to Supplementary Conditions. ENGINEER will schedule a preconstruction conference before starting construction, at a time convenient to OWNER and CONTRACTOR, but no later than 15 days after execution of the Agreement. Hold the conference at Project site or another convenient location. Conduct the meeting to review responsibilities and personnel assignments.
1. Attendees: Authorized representatives of OWNER, ENGINEER, and their consultants;
CONTRACTOR and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Discuss items of significance that could affect progress, including the following:
a. Tentative construction schedule.
b. Phasing.
c. Critical work sequencing and long-lead items.
d. Designation of key personnel and their duties.
e. Procedures for processing field decisions and Change Orders.
Project Management and Coordination 01 31 00-4
f. Procedures for requests for interpretations (RFIs).
g. Procedures for testing and inspecting.
h. Procedures for processing Applications for Payment.
i. Distribution of the Contract Documents.
j. Submittal procedures.
k. Preparation of Record Documents.
l. Use of the premises.
m. Work restrictions.
n. OWNER's occupancy requirements.
o. Responsibility for temporary facilities and controls.
p. Construction waste management and recycling.
q. Parking availability.
r. Office, work, and storage areas.
s. Equipment deliveries and priorities.
t. CONTRACTOR’s Safety Plan.
u. Security.
v. Progress cleaning.
w. Working hours.
3. Minutes: ENGINEER will record and distribute meeting minutes.
C. Preliminary Schedule Acceptability Review Meeting: As set forth in the General Conditions.
D. Progress Meetings: ENGINEER will schedule and conduct progress meetings at biweekly intervals. Coordinate dates of meetings with preparation of payment requests.
1. Attendees: In addition to representatives of OWNER and ENGINEER, each CONTRACTOR, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.
a. CONTRACTOR's Construction Schedule: Review progress since the last meeting.
Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to CONTRACTOR's Construction Schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to
Project Management and Coordination 01 31 00-5 do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
1) Review schedule for next period.
b. Review present and future needs of each entity present, including the following:
1) Interface requirements.
2) Sequence of operations.
3) Status of submittals.
4) Deliveries.
5) Off-site fabrication.
6) Access.
7) Site utilization.
8) Temporary facilities and controls.
9) Work hours.
10) Hazards and risks.
11) Progress cleaning.
12) Quality and work standards.
13) Status of correction of deficient items.
14) Field observations.
15) Requests for interpretations (RFIs).
16) Status of proposal requests.
17) Pending changes.
18) Status of Change Orders.
19) Pending claims and disputes.
20) Documentation of information for payment requests.
3. Minutes: ENGINEER will record and distribute to CONTRACTOR the meeting minutes.
4. Reporting: Distribute minutes of the meeting to each party present and to parties who should have been present.
a. Schedule Updating: Revise CONTRACTOR's Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized.
Issue revised schedule concurrently with the report of each meeting.
E. Quality Control and Coordination Meeting(s):
1. Scheduled by ENGINEER as necessary to review test and inspection reports and other matters relating to quality control of Work and work of other CONTRACTORs.
Project Management and Coordination 01 31 00-6
2. Attendees will include ENGINEER, OWNER’S Representative, CONTRACTOR, CONTRACTOR’s designated quality control representative, selected Subcontractors and Suppliers.
F. Pre-demolition Meetings:
1. When required by OWNER, convene at site prior to commencing Work.
2. Require attendance of entities directly affecting, or affected by, Work.
3. Notify ENGINEER four days in advance of meeting date.
4. Provide suggested agenda to ENGINEER to include reviewing conditions of demolition, preparation and installation or application procedures, and coordination with related Work and work of others.
G. Other Meetings: In accordance with Contract Documents and as may be required by OWNER.
1.8 PROGRESS OF WORK
A. Include the Milestones and sequences of Work specified herein as a part of the progress schedule required under Section 01 31 00, PROJECT MANAGEMENT AND COORDINATION.
B. Shutdown of Existing Facilities:
1. All existing facilities shall be decommissioned prior to starting the Work.
2. If connections to existing services or utilities or other work require the temporary shutdown of any existing operations or utilities, such activities shall be approved by the ENGINEER and shall be planned in detail with appropriate scheduling of the Work and coordinated with the ENGINEER. Such anticipated shutdowns and restarts shall be shown on the CONTRACTOR'S progress schedule and shall be updated with each schedule update.
Appearance of the shutdown on the schedule shall not constitute acceptance by the ENGINEER to proceed. Requests for shutdown shall include the nature and duration of the interruption of services and shall include plans to expedite the Work, such as provisions for alternating work force in shifts, if necessary, and standby materials and equipment should any complications arise in completing the Work. The proposed plan shall be submitted to the ENGINEER at least 7 days prior to the planned activities. The ENGINEER will respond within 2 working days as to the acceptability of the planned shutdown. If the shutdown plan does not interfere with the operation of the system to maintain operations that meet current flows, and the shutdown plan is otherwise approved by the ENGINEER, every attempt will be made by the OWNER to comply with such shutdown; however, the OWNER reserves the right to deny the shutdown at any time due to emergency or unexpected events.
3. All materials and equipment (including emergency equipment) necessary to expedite the tie-in shall be on hand prior to the shutdown of existing services or utilities.
4. It may be necessary to do certain parts of the construction Work outside normal working hours in order to avoid undesirable conditions. The CONTRACTOR shall do this Work at such
Project Management and Coordination 01 31 00-7 times as specified herein, and at no additional cost to the OWNER. Do not make connections between existing work and new Work until necessary inspection and tests have been completed on the new Work and it is found to conform in all respects to the requirements of the Contract Documents.
C. Construct Work in stages to allow for OWNER'S continuous uninterrupted operation during work activities. Coordinate construction schedule with the OWNER.
D. Be responsible for temporary connections and pay for associated costs required to maintain OWNER'S operations.
E. Perform Work continuously during critical connections and changeovers, and as required to prevent interruption of OWNER'S operations. Coordinate proposed Work with the owner before effecting shutdowns. Under no circumstances cease Work at the end of a normal working day if such actions may inadvertently cause a cessation of any facility operating process, in which case, remain onsite until necessary repairs are complete.
F. Do not close lines, open valves, or take other action which would affect the operation of existing systems, except as specifically required by the Contract Documents and after approval of
ENGINEER.
1.9 ADJACENT FACILITIES AND PROPERTIES
A. Examination:
1. Following acceptance of the Notice-to-Proceed, and before Work at site is started, CONTRACTOR, OWNER, and ENGINEER shall make thorough examination of pre-existing conditions including existing buildings, structures, and other improvements in vicinity of Work, as applicable, which might be damaged by CONTRACTOR’s operations. Periodic reexamination shall be jointly performed.
2. Record observations for signature of ENGINEER and CONTRACTOR.
B. Documentation:
1. Submit three copies of photographs or other records documenting examination for ENGINEER's signature. ENGINEER will review, sign, and return one record copy of every observation document and photograph to CONTRACTOR to be kept on file in CONTRACTOR’s field office as site records.
2. These observations and photographs are intended for use as indisputable evidence in ascertaining whether and to what extent damage occurred as a result of CONTRACTOR’s operations, and are for protection of adjacent property owners, CONTRACTOR, and
OWNER.
1.10 OWNER FACILITIES
A. Operation and Shutdown of Existing Facilities:
Project Management and Coordination 01 31 00-8
1. Continuous operation of OWNER’s facilities is of critical importance. Schedule and conduct activities to enable existing facilities to operate continuously, unless otherwise specified.
2. Conduct Work outside regular working hours on prior written consent of OWNER to meet Project schedule and avoid undesirable conditions.
3. Do not proceed with Work affecting a facility’s operation without obtaining ENGINEER’s advance approval of the need for and duration of such Work.
B. Relocation of Existing Facilities:
1. During construction, it is expected that minor relocations of Work will be necessary.
2. Provide complete relocation of existing structures and Underground Facilities, including piping, utilities, equipment, structures, electrical conduit wiring, electrical duct bank, and other necessary items.
3. Use only new materials for relocated facility. Match materials of existing facility, unless otherwise shown or specified.
4. Perform relocations to minimize downtime of existing facilities.
5. Install new portions of existing facilities in their relocated position prior to removal of existing facilities, unless otherwise accepted by ENGINEER.
1.11 PHYSICAL CONDITIONS
A. Exercise reasonable care to verify locations of existing subsurface structures and Underground Facilities.
B. Thoroughly check immediate and adjacent areas subject to excavation by visual examination (and by electronic metal and pipe detection equipment, as necessary) for indications of subsurface structures and Underground Facilities.
C. Make exploratory excavations where existing Underground Facilities or structures may potentially conflict with proposed Underground Facilities or structures. Conduct exploratory excavations in presence of ENGINEER and sufficiently ahead of construction to avoid possible delays to CONTRACTOR’s Work.
1.12 REFERENCE POINTS AND SURVEYS
A. Location and elevation of bench marks are shown on Drawings.
B. Dimensions for lines and elevations for grades of structures, appurtenances, and utilities are indicated on Drawings, together with other pertinent information required for laying out Work.
If conditions vary from those indicated, notify ENGINEER immediately, who will make minor adjustments required.
Project Management and Coordination 01 31 00-9
C. ENGINEER may perform checks to verify accuracy of CONTRACTOR’s layout Work and that completed Work complies with Contract Documents.
D. Any existing survey points or other control markers destroyed without proper authorization will be replaced by owner of the survey points or control markers at the CONTRACTOR’s expense.
E. CONTRACTOR’s Responsibilities:
1. Provide additional survey and layout as required.
2. Locate and protect reference points prior to starting site preparation.
3. Notify ENGINEER at least 3 working days in advance of time when grade and line to be provided by others will be needed.
4. Check and establish exact location of existing facilities prior to demolition work and any connections thereto.
5. In event of discrepancy in data or staking provided by ENGINEER, request clarification before proceeding with Work.
6. Preserve and leave undisturbed control staking until ENGINEER has completed checks it deems necessary.
7. Re-establish reference points resulting from destruction by CONTRACTOR’s operations.
8. Retain professional land surveyor or civil engineer registered in state of Project who shall perform or supervise engineering surveying necessary for additional construction staking and layout.
9. Maintain complete accurate log of survey Work as it progresses as a Record Document.
10. On request of ENGINEER, submit documentation.
11. Provide competent employee(s), tools, stakes, and other equipment and materials as ENGINEER may require to:
a. Establish control points, lines, and easement boundaries.
b. Check layout, survey, and measurement Work performed by others.
c. Measure quantities for payment purposes.
d. Assist OWNER’s staff during bypassing or other interruption of normal operation.
12. Cooperate with ENGINEER so that checking and measuring may be accomplished with least interference to CONTRACTOR’s operations.
ARTICLE 3 – EXECUTION
Project Management and Coordination 01 31 00-10
1.9 SALVAGE OF MATERIALS
A. OWNER reserves the right to salvage the following equipment and materials prior to and during demolition. Specific materials to be salvaged include:
1. Five blowers and enclosures.
B. Salvage materials for OWNER’s use.
1. Remove material with extreme care so as not to damage for future use.
2. Promptly remove from Work area salvaged materials.
3. Store materials on site where instructed by OWNER.
C. Meet with ENGINEER and OWNER prior to starting to dismantle equipment or piping designated to be salvaged. ENGINEER will indicate locations where equipment is to be disconnected. Unless modified by ENGINEER, CONTRACTOR shall disassemble valves, pipes, and equipment at normal connection points.
D. Provide new or repair damaged equipment or material specified or indicated to be salvaged that is damaged during removal. Store equipment as directed.
01 32 00-1
Construction Progress Documentation
SECTION 01 32 00
CONSTRUCTION PROGRESS DOCUMENTATION
ARTICLE 1 – GENERAL
1.1 SUMMARY
E. This Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. CONTRACTOR's Construction Schedule.
2. Submittals Schedule.
3. Daily construction reports.
4. Field condition reports.
1.2 DEFINITIONS
F. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
G. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.
H. Float: The measure of leeway in starting and completing an activity.
1. Float time belongs to OWNER.
1.3 SUBMITTALS
I. Submittals Schedule: Submit three copies of schedule. Arrange the following information in a tabular format:
1. Scheduled date for first submittal.
2. Specification Section number and title.
3. Submittal category (action or informational).
01 32 00-2
4. Name of subcontractor.
5. Description of the Work covered.
6. Scheduled date for ENGINEER's final release or approval.
J. Preliminary Network Diagram: Submit 3 opaque copies, large enough to show entire network for entire construction period. Show logic ties for activities.
K. CONTRACTOR's Construction Schedule: Submit 3 opaque copies of initial schedule, large enough to show entire schedule for entire construction period.
1. Submit an electronic copy of schedule, using software indicated, on CD-R, and labeled to comply with requirements for submittals. Include type of schedule (Initial or Updated) and date on label.
L. CPM Reports: Concurrent with CPM schedule, submit 3 copies of each of the following computer-generated reports. Format for each activity in reports shall contain activity number, activity description, cost and resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.
1. Activity Report: List of all activities sorted by activity number and then early start date, or actual start date if known.
2. Logic Report: List of preceding and succeeding activities for all activities, sorted in ascending order by activity number and then early start date, or actual start date if known.
3. Total Float Report: List of all activities sorted in ascending order of total float.
M. Daily Construction Reports: Submit 3 copies at monthly intervals.
N. Field Condition Reports: Submit 3 copies at time of discovery of differing conditions.
1.4 COORDINATION
O. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors.
P. Coordinate CONTRACTOR's Construction Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.
1. Secure time commitments for performing critical elements of the Work from parties involved.
2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
ARTICLE 2 – PRODUCTS
01 32 00-3
1.1 SUBMITTALS SCHEDULE
Q. Preparation: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, resubmittal, ordering, manufacturing, fabrication, and delivery when establishing dates.
1. Coordinate Submittals Schedule with list of subcontracts, the Schedule of Values, and CONTRACTOR's Construction Schedule.
2. Submit concurrently with the first complete submittal of CONTRACTOR's Construction Schedule.
2.2 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL
R. Time Frame: Extend schedule from date established for Notice to Proceed to date of Final Completion.
1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order.
S. Activities: Treat each story or separate area as a separate numbered activity for each principal element of the Work. Comply with the following:
1. Activity Duration: Define activities so no activity is longer than 10 days, unless specifically allowed by ENGINEER.
2. Submittal Review Time: Include review and resubmittal times indicated in Division 1 Section 01 33 00 "Submittals" in schedule. Coordinate submittal review times in CONTRACTOR's Construction Schedule with Submittals Schedule.
3. Substantial Completion: Indicate completion in advance of date established for Substantial Completion, and allow time for ENGINEER's administrative procedures necessary for certification of Substantial Completion.
T. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.
1. Phasing: Arrange list of activities on schedule by phase.
2. Work under More Than One Contract: Include a separate activity for each contract.
3. Work by OWNER: Include a separate activity for each portion of the Work performed by
OWNER.
4. Work Restrictions: Show the effect of the following items on the schedule:
a. Coordination with existing construction.
b. Limitations of continued occupancies.
01 32 00-4
c. Completion of demolition before Substantial Completion.
d. Use of premises restrictions.
e. Seasonal variations.
f. Environmental control.
5. Work Stages: Indicate important stages of construction for each major portion of the Work.
6. Other Constraints:
U. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and Final Completion, and the following interim milestones:
1. Mobilization of major equipment to be used for demolition
2. Demolition of each major structure
3. Demolition of underground utilities
4. Site Restoration
V. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis using fragnets to demonstrate the effect of the proposed change on the overall project schedule.
2.3 CONTRACTOR'S CONSTRUCTION SCHEDULE (CPM SCHEDULE)
W. General: Prepare network diagrams using AON (activity-on-node) format.
X. Preliminary Network Diagram: Submit diagram within 14 days of date established for the Notice to Proceed. Outline significant construction activities for the first 120 days of construction.
Include skeleton diagram for the remainder of the Work and a cash requirement prediction based on…