This is a sealed bid solicitation issued by the City of Midland, Michigan for the replacement of a digestor boiler system at the Water Reclamation Facility. The project encompasses the removal and installation of two boilers, two return pumps, two circulation pumps, and two access hatches. A mandatory pre-bid meeting is scheduled for November 6, 2025 at 10:00 AM at 2305 Bay City Road, Midland, Michigan 48642. Sealed bids will be accepted until 2:00 PM on Tuesday, November 18, 2025. The bid pricing must include furnishing and installation of each component, with all work to be performed during normal business hours Monday through Friday, 7:00 AM to 5:00 PM. The contractor must submit a project plan two weeks prior to construction start and attend daily site meetings with the department. The successful bidder will be required to complete the project within a specified number of calendar days from construction start, as indicated in the proposal form.
Bidders must submit a certified check or bid bond in the amount of not less than five percent (5%) of the total proposal price with their bid submission. Payment shall be made monthly using AIA G702 and G703 forms with a 5% retainage held until project completion and owner sign-off on final completion. The successful contractor must furnish performance and payment bonds in the amount of 100% of the contract price and provide commercial general liability insurance with minimum limits of $1,000,000 per occurrence and $2,000,000 aggregate, automobile liability insurance of $1,000,000, and workers compensation insurance with employer liability limits of at least $500,000 per occurrence. Liquidated damages apply based on contract amount, ranging from $100 to $400 per calendar day. Bid documents are available for download through Bidnet Direct by the SOVRA/MITN Purchasing Group at https://www.bidnetdirect.com/mitn. Technical questions should be directed to Ryan Putt, City of Midland Utilities Project Manager, at rputt@midland-mi.org or (989) 837-3508.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DIGESTOR BOILER
SYSTEM REPLACEMENT
BID NO. 4585
NOVEMBER 18, 2025
DIGESTOR BOILER SYSTEM REPLACEMENT
TABLE OF CONTENTS
TABLE OF CONTENTS PAGE
TITLE PAGE 01
TABLE OF CONTENTS 02
INVITATION TO BID 03
CITY OF MIDLAND STANDARD INSTRUCTIONS TO BIDDERS 04
PROPOSAL 05
TECHNICAL SPECIFICATIONS
1) PROJECT OVERVIEW 07
2) SCOPE OF WORK 07
3) MANDATORY PRE-BID MEETING 07
4) GENERAL CONDITIONS 07
5) DIGESTOR BOILER SYSTEM REPLACEMENT 08
6) GENERAL INFORMATION 08
6.1 QUESTIONS AND CLARIFICATIONS 08
6.2 ADDENDA 09
6.3 BONDING 09
6.4 SCHEDULE & CONSTRUCTION PHASING 09
6.5 APPLICATIONS FOR PAYMENT 09
6.6 CHANGE ORDERS 10
EXHIBIT AND ATTACHMENTS:
Attachment 1: Special Provisions for Construction Work Exhibit A: Existing Conditions Exhibit B: Flexible Steel Water-Tube Boiler Specifications Exhibit C: Proposed Boiler Drawing Exhibit D: Methane Gas Composition
INVITATION TO BID
Sealed bids will be accepted until 2:00 PM, Tuesday, November 18, 2025 to provide the City of Midland with pricing for replacement of two existing digestor boilers at the Water Reclamation Facility, per the attached specifications and standard instructions. Technical questions shall be directed to Ryan Putt, City of Midland Utilities Project Manager at rputt@midland-mi.org.
Bid should be submitted in a sealed envelope clearly marked as “BID 4585 – DIGESTOR BOILER SYSTEM
REPLACEMENT. Bid submission can be delivered or mailed ATTN: Purchasing to City of Midland, Office of the City
Clerk, 333 W. Ellsworth Street, Midland, MI 48640.
Mandatory pre-bid meeting: will be held Thursday, November 6, 2025 at 10:00 AM at 2305 Bay City Road, Midland, MI
48642. Meeting starting point will be at the Administration Building.
A certified check or bid bond for a sum of not less than five percent (5%) of the amount of the Proposal will be required with each bid.
Bid documents are available for download at Bidnet Direct by SOVRA/MITN Purchasing Group.
Registration is required to view and download bid package and specifications; follow link at https://www.bidnetdirect.com/mitn. Information can also be obtained directly from the Purchasing Department which is part of the Finance Department at City Hall, Midland, MI or by emailing purchasing@midland-mi.org.
Invitation to Bid and all its pages, documents and attachments, including those added subsequently by written notice, submitted and properly executed, shall constitute the contract between the City of Midland and the successful vendor when approved and accepted by the City.
The City reserves the right to accept or reject all or any parts of any and all bids, to waive irregularities and to award in the best interests of the City of Midland.
Christina Evans
Christina Evans Accounting Manager Midland, Michigan
CITY OF MIDLAND, MICHIGAN
STANDARD INSTRUCTIONS TO BIDDERS
1. Receipt and Opening of Bids: Sealed bids will be accepted and date/time stamped upon receipt in the office of the City Clerk, City Hall, 333 West Ellsworth, Midland, MI 48640-5132, until the time indicated on the attached Invitation to Bid for goods or services listed in the specifications and will be publicly opened and read aloud.
2. Form of Bid: Bids shall be submitted on the enclosed form with any exceptions, deviations or modifications to the published requirements clearly noted and explained.
3. Submission of Bids:
A) Envelopes containing bids shall be sealed and clearly marked on the outside of the envelope with the name and address of the bidder, the title and bid number of the project, and the date and time of the scheduled bid opening.
B) Any bid received after the scheduled opening time will not be accepted and will be returned unopened.
C) Any bidder may withdraw their bid response by written request at any time prior to the scheduled bid opening.
D) Telephonic or faxed bids will not be accepted and telephonic, telegraphic, or faxed amendments to bids or withdrawals will not be accepted under any circumstances.
E) Unless otherwise specified, no bid may be withdrawn, changed, or modified in any way for a period of sixty
(60) calendar days from the date of the bid opening.
F) Negligence on the part of the bidder in preparing the bid confers no rights for the withdrawal of the bid after opening.
G) Bids received prior to the time of bid opening will be securely kept unopened. No responsibility will attach to any officer or employee of the City for the premature opening of a bid not properly addressed or identified.
H) In case of a discrepancy between unit prices and their extensions, the unit price bid shall govern.
4. Brand Names: Wherever in the specifications or proposal form brand names, trade names, manufacturer, or catalog numbers are called, it is for establishing a grade or quality level only and the phrase “or equal” is deemed to follow unless a prequalified list or the term “only”, “no exceptions”, or similar phrase is included.
5. Taxes: The City of Midland is exempt from State and Federal taxes. However, property purchased by a contractor to be used in the construction, alteration, repair, or improvement of property owned by the City is taxable to the contractor.
Therefore, the price bid for contracts other than construction contracts must be exclusive of taxes and will be so construed. Construction contracts will be construed to include all applicable taxes unless the contract specifies otherwise.
6. Acceptance of Bids: The City will award to the lowest, responsive, responsible vendor that meets the functional requirements and needs expressed by the specifications. Tie bids will be awarded based on the most favorable terms for payment and/or delivery schedule or other costs associated with the award process. Receipt of a purchase order or properly executed contract covering the materials or services as described in the bid will indicate the award of bid and contract of purchase.
7. City’s Rights: The City reserves the right to accept or reject any or all bids, to waive irregularities or defects, to award on a split-order or lump-sum basis, and accept other than the low bid when deemed to be in the City’s best interests.
8. Non Appropriations: The City shall be bound, hereunder, only to the extent that funds shall have been appropriated and budgeted or are otherwise available for the purpose of this contract. In the event that no funds or insufficient funds are appropriated and budgeted, or are otherwise unavailable by any means whatsoever in any fiscal period of payments due under this contract, then the City shall immediately notify the Contractor of such occurrence and this contract shall terminate the last day of the fiscal period for which appropriations were received without penalty or expense to the City of any kind, whatsoever.
9. Delivery: Bids shall include all delivery charges with terms of Freight Prepay - FOB Midland, MI.
10. Laws: The laws of the State of Michigan shall govern the rights, obligations, and remedies of the Parties under this bid and any agreement reached through this process. The City of Midland is a Michigan municipal corporation.
11. Disclosure: All of the information included in your bid response is subject to the “Freedom of Information Act” and may be disclosed in its entirety after the formal, public bid opening has been completed. Bid tabulations will be available MITN website, https://www.bidnetdirect.com/mitn subsequent to bid opening date.
12. Independent Price Determination: By submission of this proposal, the bidder certifies that the pricing structure offered has been arrived at independently without consultation, communication, or agreement of such prices for the purpose of restricting competition with any other bidder or competitor.
13. Acceptance of Materials: All components used in the manufacture or construction of materials, supplies, and equipment, and all finished goods, shall be new, the latest make/model, of the best quality, and highest grade workmanship. In the event the delivered material is found to be defective or does not conform to specifications, the City reserves the right to cancel the order upon written notice to the bidder and return the materials to the bidder at the bidder’s expense.
14. Non-Iran Linked Business: By signing bid/quote response form, I certify and agree on behalf of myself and the company submitting this proposal the following: (1) that I am duly authorized to legally bind the company submitting this proposal;
and (2) that the company submitting this proposal is not an “Iran linked business,” as that term is defined in Section 2(e) of the Iran Economic Sanctions Act, being Michigan Public Act No. 517 of 2012; and (3) That I and the company submitting this proposal will immediately comply with any further certifications or information submissions requested by the City in this regard.”
PROPOSAL FOR
ITB 4585 –DIGESTOR BOILER SYSTEM REPLACEMENT
NOVEMBER 18, 2025; 2:00 PM
Date __________________
Name of Bidder ________________________________________________________________
Bidder’s Address ________________________________________________________________
Bidder’s Phone Number _____________________ Bidder’s Email _________________________
To: City of Midland Office of the City Clerk Attn: Purchasing 333 W. Ellsworth Street Midland, MI 48640-5132
Proposal for: ITB 4583 – DIGESTOR BOILER SYSTEM REPLACEMENT
1. The undersigned, hereinafter called the CONTRACTOR, hereby declares that they have read the “Instruction to Bidders”.
The CONTRACTOR, hereby proposes to furnish all specified and necessary equipment, devices, provide supervision including all overhead and profit to meet the construction schedule;
all in accordance with the project documents and other contract documents. Including:
Addendum No. __________, Dated __________
Addendum No. __________, Dated __________
Addendum No. __________, Dated __________
GRAND TOTAL
________________________________________________ Dollars ($_________________________)
Boilers Total Line Cost Furnish two boilers, per specifications $ Remove Existing/Install two boilers $ subtotal $ Return Pump Furnish two pumps, per specifications $ Remove Existing/Install two pumps $ subtotal $ Circulation Pump Furnish two pumps, per specifications $ Remove Existing/Install two pumps $ subtotal $ Access Hatches Remove/Salvage two hatches $ Re-Install two hatches $ subtotal $
2. Construction completion schedule (Please note: This schedule shall be for 100% completion of project) The undersigned agrees, if awarded the contract, the project will be completed within _______ calendar days of construction start.
3. The undersigned has carefully examined the bidding and contract documents, and any and all Addenda issued, and agrees to be bound by all requirements thereof in the submission of his proposal, and in the performance of the contract if awarded this proposal.
4. The undersigned agrees that his proposal shall not be withdrawn until sixty (60) days after the time set for receipt of proposals.
5. Payment terms
a. Payment shall be made monthly utilizing AIA G702 & G703 forms. A 5% retainage will be held by the City until the conclusion of all work being completed and owner signing off on the final completion.
6. Address, Legal Status and Signature of Bidder
The undersigned bidder does hereby designate the address given below as the legal address to which all notices, directions, or other communications may be served or mailed.
Address: ________________________________________________________________
City: ________________________ State: __________________ Zip: ________________
The undersigned bidder does hereby declare that the bidder has the legal status checked below:
_________ Individual
_________ Co-Partnership
_________ Corporation incorporated under the laws of the State of ____________
This proposal is submitted in the name of: __________________________________________
(Name of Bidder)
By: ____________________________________
Title: ____________________________________
Signed and sealed this ___________________ day of ___________________, 20_____.
Bids may be inspected at the bid opening or in the Procurement Office during normal business hours.
Tabulations will be available at the MITN website subsequent to bid open date.
LATE BIDS WILL BE REJECTED.
1) PROJECT OVERVIEW:
The City of Midland Water Reclamation Plant is requesting proposals for replacement of the digestor boiler system. The system upgrade consists of two boilers, two return pumps, and two circulation pumps. The contactor will provide required equipment, material, and labor to perform the work.
Bid pricing to include furnishing and installation of each component. The City reserves the right to reduce project scope, if necessary, post bid.
2) SCOPE OF WORK:
2.1 Contractor shall perform complete removal and replacement of existing equipment. All associated items related to new boiler and pump installation shall be included.
2.2 The project shall be installed in accordance with the Invitation to bid document, Special Provisions for Construction, and the City of Midland Construction Standard Divisions, which can be found at the following link: https://cityofmidlandmi.gov/1695/Construction-Standards- Divisions. Where conflicts exist within the documents, the Special Provisions shall supersede the Standard Divisions.
2.3 The contractor will determine the appropriate means and methods to construct the project. The department shall approve material and methods of construction.
2.4 Contractor shall be responsible for the mobilization, maintenance, and operation of all required personnel and equipment for removal and installation.
2.5 Contractor shall be responsible for disposal of all debris generated from the project.
2.6 Contractor must attend a mandatory pre bid meeting and conduct a site review to understand project scope, door dimensions, and existing site conditions.
3) MANDATORY PRE-BID MEETING:
A mandatory pre-bid meeting is scheduled to take place at the City of Midland’s Water Reclamation Facility on November 6, 2025 at 10:00 AM at 2305 Bay City Road, Midland, MI 48642. Meeting starting point will be at the Administration Building.
4) GENERAL CONDITIONS:
4.1 All work to be performed during normal working hours: Monday through Friday, 7:00 AM - 5:00 PM.
Work outside the designated time may be scheduled upon approval and direction of the department.
4.2 Contractor to verify, confirm, and provide new equipment. Items must conform to codes and industry installation standards.
4.3 Contractor will attend an in-person project kick off meeting to review the project scope, establish a plan, and confirm schedule and duration.
4.4 The Contractor shall prepare a Project Plan and will submit to the department two weeks (14 days) prior to the start of the project. Contractor shall respond to questions and comments, and make appropriate revisions as necessary.
4.5 Contractor shall coordinate daily site meetings with the department to go over that is to be accomplished for the day.
4.6 Contractor shall be responsible for assuring quality of work including management of subcontractor activities.
4.7 The contractor is responsible for securing and closing out any permits necessary to complete the project and coordinating any site visits and/or inspections required. Copies of documents shall be provided to City staff.
5) DIGESTOR BOILER SYSTEM REPLACEMENT:
5.1 Contractor shall perform removal and reinstallation of access hatches. New equipment will be plumbed to fit existing conditions.
One boiler to be decommissioned at a time. Contractor must coordinate sequencing with the City.
The vendor shall be responsible for verification of correct material and installation procedures as they adhere to local and state building codes. Reference Exhibit C- Flexible Steel Water-Tube Boiler Specifications.
5.2 The following items are to be replaced by the contractor.
Two of each type:
Boilers - Natural Gas & Methane Compatible: Remove and replace existing boilers. Plumbing and anchoring shall be included within bid pricing. New boilers shall be the same or equal in quality to the following. Check testing and start-up shall be included in the bid pricing.
Acceptable Brands/models: Bryan Boilers RV Series Boiler Model RV500-W-FD, Webster Burner Dig.
Gas, CSD-1 Boiler Trim, Model JB2G/SG/05 w/ FM/IRI/CSD-1 w/ Modulation, Added LMV51 w/ AZL, 50# Relief Valve, Siemens LMV5 linkage less system controls
Pumps - Return: Remove and replace existing return pumps. Plumbing and anchoring shall be included within bid pricing. New pumps shall be similar design and quality.
Pumps - Circulation: Remove and replace existing circulation pumps. Plumbing and anchoring shall be included within bid pricing. New pumps shall be similar design and quality.
Access Hatches: Hatches will be salvaged and re-installed. No new material or parts needed.
6) GENERAL INFORMATION
6.1 QUESTIONS AND CLARIFICATIONS:
The City of Midland Official Point of Contact, for submission of questions and clarifications related to this bid:
RYAN PUTT,
City of Midland Utilities Project Manager 2305 Bay City Road Midland, MI 48642
(989) 837-3508 rputt@midland-mi.org
All inquiries and other correspondence or concerns regarding the bid should be directed to the City of Midland’s Official Point of Contact are to be transmitted in writing via US Mail or email only. DO NOT CALL – the telephone number is provided for courier delivery purposes only.
6.2 ADDENDA:
Prior to the deadline for submission of proposals, City reserves the right to issue addenda. All addenda issued to contractor prior to date of receipt of proposals shall become a part of this proposal, and all proposals are include the work therein described. Proposers are responsible for ensuring receipt of all addenda and incorporating any changes into their proposal. Proposer shall acknowledge receipt of any addenda. Addenda will be posted at Michigan Inter- Governmental Trade Network (MITN) Purchasing Group website and on the City of Midland website.
6.3 BONDING:
The successful contractor shall furnish a performance bond in the amount of 100% of the contract price and security for the faithful performance of the project. The contractor shall also provide a payment bond in the amount of 100% of the contract price as a security for payment of all persons or companies that supply materials and/or labor in connection with this project.
Surety bonds shall be provided through firms that are listed as approved on the U.S. Treasury Department’s Circular 570. This prevision only applies if bid is over $50,000.00.
6.4 SCHEDULE & CONSTRUCTION PHASING:
Prior to the beginning of work, representative from the contactor and City shall meet at a mutually agreeable time to discuss coordination of schedules. The contractor shall submit, for approval by the City Facility Manager, a construction schedule at the time of the preconstruction meeting.
6.5 APPLICATIONS FOR PAYMENT:
The Contractor shall submit by the 25th of each month a progress payment application using AIA forms for Applications for Payment. A 5% retainage will be held by the City until the conclusion of all work being completed and owner signing off on the final completion.
A. APPLICATION PREPARATION:
Complete every entry on the form. Include notarization and execution by a person authorized to sign legal documents on behalf of the Contractor. The City will return incomplete applications without action. Include amounts of Change Orders and Construction Change Directives issued prior to the last day of the construction period covered by the application.
B. INITIAL APPLICATION FOR PAYMENT:
Administrative actions and submittals, that must precede or coincide with submittal of the first Application for Payment, include the following:
1. List of subcontractors
2. Contractor’s construction Schedule (preliminary if not final)
3. Copies of permits
4. Copies of authorizations and licenses from governing authorities for performance
5. Certificates of insurance and insurance policies
6. Performance and payment bonds
7. Health and safety plans
C. FINAL PAYMENT APPLICATION:
Administrative actions and submittals that must precede or coincide with submittal of the final Application for Payment include the following:
1. Completion of Project closeout requirements
2. Completion of items specified for completion after Substantial Completion
3. Ensure that unsettled claims will be settled
4. Ensure that incomplete work is not accepted and will be completed without delay
5. Transmittal of required project construction records to the City
6. Proof that taxes, fees, and similar obligations were paid
7. Removal of temporary facilities and services
8. Removal of surplus materials, rubbish, and similar elements
6.6 CHANGE ORDERS:
When latent or unforeseen conditions require modifications to the Contract, the contractor may propose changes by submitting a request for a change to the City.
A. Include a statement outlining the reason for the change and the effect of the change on the work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract sum and Contract time.
B. Change order proposals will be completed on contractor provided forms. If change order is approved, the City will provide signed City document authorizing change order to proceed.
CITY OF MIDLAND, MICHIGAN
SPECIAL PROVISIONS FOR CONSTRUCTION WORK
1. Confined Space Entry Obligations:
a) All contractors and sub-contractors conducting permit-required confined space entry shall have a written permit-required space program meeting the requirements of the Michigan Occupational Safety and Health Administration (MIOSHA) General Industry Safety Standards Commission, Part 90.
Confined Space Entry; and Occupational Health Standards Commission, Part 490. Permit-Required Confined Spaces, as well as current confined space entry team training documentation and a rescue plan. Contractors shall provide written proof of that program, training records and rescue plan upon request, before the bid is awarded or at any time after the bid is awarded.
b) Contractors shall comply with all MIOSHA confined space standards and all other regulations concerning confined space entry at all times.
c) The City of Midland is in compliance with all MIOSHA standards pertaining to confined space entry. A copy of the City of Midland Master Plan for Permit-Required Confined Space Entry can be obtained from the Human Resources Department in City Hall, 333 West Ellsworth, Midland, Michigan 48640.
2. Liquidated Damages:
a) If the contractor fails to finish the project prior to the completion date established in the contract including approved extensions, liquidated damages will be charged for each calendar day that the work remains incomplete. If no completion date is listed in the specifications, this clause will be null and void.
b) The amount of liquidated damages will be deducted from the money due the contractor prior to final payment or in the case where the remaining amount due is less than the total amount of liquidated damages, the City shall have the right to recover the difference from the contractor or the contractor’s surety.
c) Unless specifically amended or modified by the bid specifications, the schedule for liquidated damages shall be as follows:
CONTRACT AMOUNT
FROM TO LIQUIDATED DAMAGES
$ 0 $50,000 $100 per calendar day $50,001 $100,000 $200 per calendar day $100,001 $500,000 $300 per calendar day $500,001 and up $400 per calendar day
d) The amounts set forth in the above schedule are not to be considered punitive, but rather predetermined and reasonable amounts to compensate for the detriment to the public and to defray expenses incurred by the City due to delay in the completion of the project.
3. Bid Security:
a) A bid security, as a guarantee of good faith, in the form of a certified check, cashier’s check, or bidder’s bond may be required to be submitted for this project as indicated on the bid response form.
b) If alternate bids are being proposed, only one bid security will be required in the amount of the highest proposed total bid.
c) Such bid security will be returned to the unsuccessful bidders upon award of the bid and to the successful bidder upon approval by the City of the executed contract and any additional bonds required or to all bidders upon rejection of the bid in it’s entirety by the City.
d) Bid security shall be forfeited to the City as liquidated damages, not as a penalty, if the successful bidder fails or refuses to enter into a contract with the City according to the terms of the bid or fails to provide sufficient bonds and/or insurance certificates as required by the City and established in this specification document.
4. Insurance Certificate:
The successful vendor shall supply to the City prior to award an Insurance Certificate in the minimum amount prescribed below listing the City of Midland as “Additional Insured”. All certificates of insurance shall be on the standard ACCORD CERTIFICATE OF INSURANCE form showing the specific limits of insurance required. The contractor shall not commence any work on this project until a valid form has been delivered to the City and has been approved by the City Attorney.
Commercial General Liability Insurance The contractor shall procure and maintain during the life of this contract, Commercial General Liability Insurance on an occurrence basis with limits of liability not less than $1,000,000 per occurrence and $2,000,000 aggregate combined single limit, Personal Injury, Bodily Injury and Property Damage.
Coverage shall include the following: a) contractual liability; b) products and completed operations; c) independent contractors; d) broad form general liability extensions or equivalent; e) per contract aggregate.
Automobile Liability The contractor shall procure and maintain during the life of this contract, automobile liability insurance, including applicable No-Fault coverages, with limits of liability of not less than $1,000,000 per occurrence combined single limit bodily injury and property damage. Coverage shall include all owned, non-owned, and hired vehicles.
Workers Compensation Liability Insurance The contractor shall procure and maintain during the life of this contractor, Workers Compensation Insurance, including employers liability coverage in accordance with all applicable statues of the state of Michigan. Employer liability limits shall be at least $500,000/$500,000/$500,000.
5. Performance and Payment Bond The successful contractor shall furnish a performance bond in the amount of 100% of the contract price as security for the faithful performance of the project. The contractor shall also provide a payment bond in the amount of 100% of the contract price as security for payment of all persons or companies that supply materials and/or labor in connection with this project. Surety bonds shall be provided through firms that are listed as approved on the U.S. Treasury Department’s Circular 570.
6. Subcontractor Usage:
The City has the right of approval on subcontractors used for any City project. The use of ineligible vendors as subcontractors may cause the main contractor to be placed on the City’s list of ineligible vendors. The City does not pay subcontractors directly, that is the responsibility of the general. For a list of the City’s ineligible vendors, contact the City Purchasing Agent.
City of Midland APPENDIX XII
Contractor Safety Qualification Statement
Description of work or job name:_______________________________________________ Contract No.:
Contract Company: ___________________________________ Owner/CEO: ______________________ Phone:
Safety Officer:________________________________________ Title: _____________________________ Phone:
Contractor experience modification rate (EMR): ________ OSHA Recordable Injury Incident Rate (past year):
We have received a written copy of and agree to follow the requirements of the City of Midland’s “Contractor Safety Program:”
Yes No Comments:
We have an active written safety program which will be provided to City representatives upon request.
Yes No Comments:
We understand the essential requirements of the following applicable safety regulations and agree to make a good faith effort to follow them. We further certify that these applicable regulations are readily accessible to employees:
Yes
N/A Yes N/A
a. Use of reflective safety vests h. Welding and cutting
b. Confined space entry i. Hazard communication (“right-to-know”)
c. Control of hazardous energy j. Alcohol and drug use
d. Elevated work k. Bloodborne pathogens
e. Excavations, trenches & shoring l. Respiratory protection
f. Personal protective equipment m. Other applicable regulations:
g. Work area protection and traffic control
Project-specific concerns of applicable safety regulations and safety control measures will be discussed and documented at the pre-project meeting with City representatives.
Important! The City reserves the right to request verification, in writing, of the contractor’s current safety program, training and certification records, and emergency response plans as applicable to the work being done.
Other comments: ____________________________________________________________________________
We attest that the above information is true to the best of our knowledge and can be substantiated if requested.
Received by:
Contract Representative: ____________________________ Contracting Dept.:_______________________
Title: ______________________________ Date: __________ Name: ___________________Date: _________
MI Contractor’s License No. (if applicable): ___________ Original to: Contracting Department
Copy to: Contractor
4/05 GP
Contractor Project Safety Plan To be completed at pre-project meeting along with City contract representative.
Project name: _________________________________________________ Date: ________
*Safety Concerns of the Job (check all that apply)
1. Traffic control* 9. Welding and cutting
2. Hazardous energy 10. Bloodborne infectious diseases
3. Excessive noise 11. Chemical exposures**
4. Hazardous chemicals 12. Trenching/excavations
5. Falling objects 13. Eye hazards
6. Confined space 14. Foot hazards
7. Elevated work 15. Hand hazards
8. Respiratory hazards 16. Other: _________________________________________
* Must attach traffic control plan ** Must have copies of MSDSs for all hazardous chemicals on-site.
Safety Concern (see above)
Control measures (protective equipment, engineering controls, administrative controls, other measures) rputt Text Box Exhibit A: Existing Conditions rputt Image rputt Image rputt Text Box Access Hatches rputt
Boilers rputt
Exhibit A: Existing Conditions rputt Image rputt Image rputt Text Box Circulation Pumps rputt
Return Pumps
EXHIBIT B - FLEXIBLE STEEL WATER-TUBE BOILER SPECIFICATIONS
STEEL WATER-TUBE BOILERS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Contract Documents to include Conditions and Drawings.
1.2 SUMMARY
A. This Section includes packaged flexible water-tube boilers for generating hot water.
1. Boilers.
2. Controls and boiler trim.
3. Fuel burning system.
1.3 SUBMITTALS
A. Product Information: Include rated capacities, shipping, operating weights and accessories for each model indicated on the schedule.
B. Shop Drawings: Provide detail on equipment assemblies and indicate dimensions, required clearances, components, and location and size of field connections.
1. Wiring Diagrams: Show detail wiring for power, signal, and control systems and differentiate between factory and field wiring.
1.4 CONTRACT CLOSEOUT SUBMITTALS
A. Manufacturer’s Field Startup and Test Reports
B. Operation and Maintenance Data
1.5 REFERENCES-STANDARDS
A. ANSI Z21.13: Gas-Fired Low Pressure Steam and Hot Water Boilers
B. ASME Boiler and Pressure Vessel Code: Section IV, Heating Boilers
C. ASME Boiler and Pressure Vessel Code: Section I, Power Boilers
1. High Pressure, High Temperature Water in excess of 160 PSIG/250°F.
D. ASME CSD-1: Control Standard
E. NFPA 31: Standard for the Installation of Oil-Burning Equipment
F. NFPA 54 (AGA Z223.1): National Fuel Gas Code
G. NFPA 58: Storage and Handling of Liquefied Petroleum Gases
H. NFPA 70: National Electrical Code.
I. Underwriters’ Laboratories, Inc. (UL) Listed Products
1.6 QUALITY ASSURANCE
A. Factory tests to confirm construction of the unit per ASME
1.7 DELIVERY, STORAGE AND PROTECTION
A. Protect boiler package from damage by leaving factory inspection openings and shipping packaging in place until final installation.
B. If stored outside prior to final installation, boiler package must be protected from the elements and ground water with tarps and blocking as needed.
1.8 WARRANTY
A. General Warranty: Boiler Package shall be warranted against defects in workmanship and materials for 12 months after start-up or 18 months from ship date, whichever shall be less.
B. Thermal Shock Warranty: The boiler vessel shall be warranted for 25 years against thermal shock on a non-prorated basis.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Manufacturer shall meet all aspects of the specifications: Provide boilers by one of the following:
1. Bryan Steam LLC (RV Series)
2.2 PACKAGED BOILER
A. Description: The boiler shall be constructed and assembled as a completely packaged unit ready for field connections to the water supply, return connection, electrical power supply, fuel supply(s), relief valve discharge, building management controls and flue-gas vent.
1. The water boiler shall be manufactured in strict accordance with ASME Heating Boiler
Code, Section IV, and shall bear the ASME “H” stamp for maximum working pressure of
160 PSIG and 250° F temperature.
a. Also available for higher pressures up to 250 PSIG and temperatures to 300°F per
ASME Section I)
2. The boiler shall be built to withstand 150 degree delta “T”
3. The boiler shall have no less than 5 sq. feet of heating surface per boiler horsepower, verified by documentation with 80% combustion efficiency standard.
4. A tube removal and replacement shall be demonstrated at time of start-up. Demonstration time not to exceed 40 minutes.
B. Vessel and Tube Construction
1. The boiler shall be constructed on a heavy steel frame.
2. The boiler pressure vessel shall be provided with adequately sized upper and lower drums.
3. A minimum of two downcomers shall be provided and shall be located inside furnace chamber to maximize proper thermal internal water circulation.
4. No external water circulation source shall be required.
5. Steel water tubes are to be 1½” O.D., .095 wall thickness, six-pass, flexible serpentine bend design, not subject to thermal shock damage.
6. Individual water tubes shall be easily removable and replaceable without either welding or rolling.
7. The boiler shall have no more than two tube configurations.
8. The boiler shall be furnished with an adequate number of tappings and inspection openings to facilitate internal boiler inspection and cleaning.
C. Furnace/Combustion Chamber Construction
1. Access to the furnace/combustion chamber is gained by a hinged access door(s) with an opening of no less than 26" wide x 62" high maximum to allow for inspection of the interior chamber and the burner head. All remaining panels shall be individually removable.
2. All access panels shall be affixed to the pressure vessel frame and insulated with 2” mineral fiber mono block and 2” high temperature ceramic blanket insulation and be fully gasketed for pressurized firing.
3. The furnace/combustion chamber shall be primarily of water-wall design with one side of removable panels.
4. The stationary interior wall shall be lined with 2” ceramic blanket insulation.
5. The front and rear walls are insulated with 5” mineral fiber mono block and 2” ceramic blanket insulation.
6. The floor beneath the tubes shall be lined with 2” mineral wool insulation, 1” mineral fiber mono block insulation and 2” ceramic blanket insulation.
7. The boiler furnace/combustion chamber and flueways shall be designed to operate at a positive 0.50” w.c. at the boiler flue outlet.
8. The boiler will require a “positive pressure” type metal flue.
D. Jacket Construction
1. The boiler shall be complete with a metal jacket, 16 gauge, zinc-coated rust resistant steel casing, finished with a suitable heat resisting paint and shall be constructed on a structural steel frame and properly insulated with no less than 1½” fiberglass insulation.
2. Complete jacket and insulation shall be easily removable and reinstalled.
3. The boiler shall incorporate individually removable jacket doors, with handles providing easy access to combustion chamber and access panels.
4. The entire tube area shall be easily accessible for fireside cleaning.
5. All appropriate controls where possible, shall be mounted on boiler front.
6. Any external downcomers shall be provided with factory supplied insulation, jacketing and guards to prevent human contact to high temperature surfaces while boiler is operating.
2.3 HOT-WATER BOILER TRIM
A. The boiler shall be provided with the following trim and controls
1. Safety-Relief Valve(s)
2. Combination thermometer and pressure gauge
3. Water temperature control operator
4. High limit safety control
5. Low water cutoff
B. Optional boiler trim and controls
1. Manual reset type high limit
2. Manual reset type low water cutoff
3. Auxiliary low water cutoff
4. Low water cutoff feeder
5. UL, CSD-1, FM, GE-GAP, NFPA-85 or other insurance requirements
6. Barometric damper
7. Indirect water heating coils for domestic, pool or process hot water
8. Other controls and boiler trim, as specified
2.4 GAS BURNER AND CONTROL EQUIPMENT
A. Boiler shall be furnished with a UL listed force draft flame retention gas burner. Burner shall be complete with integral motor and blower for supplying sufficient combustion air with normal vent conditions.
B. Fuel
1. Digester gas
2. Natural gas
C. The following controls shall be furnished.
1. Main manual gas shutoff valves
2. Motorized gas valve operator and auxiliary safety shutoff gas valve (RV500)
3. High and low gas pressure switches
4. Gas pilot shutoff and solenoid valves
5. Gas pilot ignition assembly with ignition transformer
6. Pilot and main gas pressure regulators
7. Modulating burner (RV500 to RV800)
8. Adjustable cam gas metering valve (RV500 to RV800)
9. Burner mounted control panel containing:
a. Four indicator lights – call for heat, ignition, fuel and flame safeguard alarm
b. Air safety switch
c. Fused on/off switch
d. Firing rate potentiometer with manual / auto switch (RV500 to RV800)
e. Motor starter(s) – where applicable
f. Honeywell electronic combustion safety control
2.5 OIL BURNER AND CONTROL EQUIPMENT
A. Boiler shall be furnished with a UL listed force draft, pressure atomizing type oil burner, suitable for operation with No. 2 fuel oil. Burner shall be complete with integral motor and blower for supplying sufficient combustion air with normal vent conditions.
B. Fuel
1. No. 2 heating fuel oil
2. No. 2 diesel fuel oil
3. JP-8
4. Arctic fuel oil
C. The following controls shall be furnished
1. Oil valves – primary and auxiliary
2. Two-stage fuel oil burner mounted (RV350-RV500)
3. Remote mounted oil pump (RV550 to RV800)
4. Direct spark oil igniter assembly (RV350 to RV450) with ignition transformer and oil ignition and nozzle assembly
5. Gas pilot oil ignition assembly (RV500 to RV800) with gas pilot shutoff valve, solenoid valve and gas pilot pressure regulator; Gas pilot ignition assembly with ignition transformer and an oil nozzle assembly.
6. Modulating burner (RV500 to RV800)
7. Adjustable cam oil metering valve (RV500 to RV800)
8. Burner mounted control panel containing:
a. Four indicator lights – call for heat, ignition, fuel and flame safeguard alarm
b. Air safety switch
c. Fused on/off switch
d. Firing rate potentiometer with manual / auto switch (RV500 to RV800)
e. Motor starter(s) – where applicable
f. Honeywell electronic combustion safety control
2.6 COMBINATION GAS/OIL BURNER AND CONTROL EQUIPMENT
A. Boiler shall be furnished with a UL listed force draft, pressure atomizing, dual fuel burner, suitable for operation with No. 2 fuel oil and natural gas (or other gas). Burner shall be complete with integral motor and blower for supplying sufficient combustion air with normal vent conditions
B. Fuel
1. Natural gas.
2. Liquid Propane gas
3. No. 2 heating fuel oil
4. No. 2 diesel fuel oil
5. JP-8
6. Arctic fuel oil
C. The following controls shall be furnished
1. Main manual gas shutoff valves
2. Motorized gas valve operator and auxiliary safety shutoff gas valve (RV350 to RV500)
3. Motorized gas valve with proof of closure operator and auxiliary safety shutoff gas valve
(RV550 to RV800)
4. High and low gas pressure switches
5. Gas pilot shutoff and solenoid valves
6. Gas pilot ignition assembly with ignition transformer
7. Pilot and main gas pressure regulators
8. Oil valves – primary and auxiliary
9. Two-stage fuel oil burner mounted (RV350-RV500)
10. Remote mounted oil pump (RV550 to RV800)
11. Direct spark oil igniter assembly (RV350 to RV450) with ignition transformer and oil ignition and nozzle assembly
12. Gas pilot oil ignition assembly (RV500 to RV800) with gas pilot shutoff valve, solenoid valve and gas pilot pressure regulator; Gas pilot ignition assembly with ignition transformer and an oil nozzle assembly.
13. Modulating burner (RV500 to RV800)
14. Adjustable cam gas metering valve (RV500 to RV800)
15. Burner mounted control panel containing:
a. Four indicator lights – call for heat, ignition, fuel and flame safeguard alarm
b. Air safety switch
c. Fused on/off switch
d. Firing rate potentiometer with manual / auto switch (RV500 to RV800)
e. Motor starter(s) – where applicable
f. Honeywell electronic combustion safety control
g. Manual fuel selection switch
D. Optional burner controls and accessories
1. Two-stage high-low burner with proven LFS (RV350 to RV450)
2. Modulating burner (RV350 to RV450)
3. Auxiliary motorized safety shutoff gas valve
4. Alarm bell(s) or horn(s)
5. Fireye combustion safety control
6. UL, CSD-1, FM, GE-GAP, NFPA-85 or other insurance requirements
7. Indicator lights – as specified
8. Direct spark ignition of oil (dual fuel burners)
9. Boiler skid mounted burner control panel
10. Boiler skid mounted burner oil pump set (RV350 to RV450)
11. Adjustable cam gas or oil metering valve(s) (RV350 to RV450)
12. Sub 30 PPM Low NOx burner
13. Linkageless Controls
a. Siemens LMV
b. Honeywell ControLinks
14. Other controls. As specified
2.7 BOILER INTERFACE TO BUILDING MANAGEMENT SYSTEM
A. The following points must be available to the building management, automation or energy system for status or adjust as specified.
1. Boiler Enable/Disable
2. Hot Water Supply Temperature Set-Point
3. Summary Alarm
B. Communications
1. Specified points shall be available via (select)
a. Dry Contacts
b. ModBus
c. Communications bridge to specified protocol
C. Lead/Lag Control Panel
1. Boiler Supplier to provide Lead/Lag Control Panel to sequence and control boilers.
2.8 SPARE PARTS
1. Boiler Manufacturer shall provide two spare boiler tubes for each different tube configuration used in each boiler. Boiler tubes shall be supplied to the owner at time of tube removal and replacement demonstration.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Install boiler on concrete pad larger than boiler base according to manufacturer's written instructions and referenced standards.
EFFECTIVE DATE:
REPLACES:
4. DIMENSIONS ARE SUBJECT
TO CHANGE WITHOUT NOTICE.
1. ALL DIMENSIONS ARE IN
INCHES THOSE IN PARENTHESES
2. LOCATION DIMENSIONS
3. GAS TRAIN, CONTROL AND
BURNER CONFIGURATION WILL
VARY DEPENDING ON JOB
SPECIFICATIONS & CONDITIONS.
NOTES:
CONSULT FACTORY FOR
CERTIFIED DIMENSIONS.
ARE ALL ±1/2".
ARE CENTIMETERS.
BRYAN BOILERS
ORDER NO.:
PERU, INDIANA 46970
783 NORTH CHILI AVE
FORM NO.: 2155
RV SERIES FORCED DRAFT WATER BOILERS
(RV450-RV800) REVERSE CONSTRUCTION
12/9/03
UNLESS OTHERWISE NOTED,
5. ALL FLANGES ARE 150#
CENTER LINE.
FLANGES TO STRADDLE
5. CONTROL TAPPINGS 3/4" NPT
2. FORCED DRAFT BURNER
4. ASME NAMEPLATE
3. RELIEF VALVE
1. PROBE TYPE L.W.C.O.-
19. COMB. CHAMBER DRAIN 1" NPT
18. FLAME OBSERVATION PORT
17. HEIGHT OVER SUPPLY
16. HEIGHT OVER JACKET
15. DRAIN CONNECTION 2" NPT10. VENT CONNECTION 1" NPT
14. LIFTING LUGS
13. OIL PUMP LOCATION
12. BURNER CENTER LINE
9. ELEC. ENCLOSURE-
8. CLNOUT./INSP. OPNG.-1 1/2"NPT
7. PRESS./TEMP. GAUGE
6. JACKET ACCESS PANELS
ORDER REV. NO.:
G-SUPPLY / RETURN NOZZLE SIZE
D-LENGTH OVER BASE
C-FLUE DIAMETER
B-FLUE LOCATION
A-LENGTH OVER JACKET
BOILER MODEL
H-BURNER EXTENSION
120 1/2" (306.1)
18 3/4" (47.6)
16" (40.6)
153 1/4" (389.3)
6" FLG
(15.2)
16" (40.6)
6" FLG
(15.2)
130 1/4" (330.8)
18 3/4" (47.6)
18 3/4" (47.6)
18 3/4" (47.6)
16" (40.6)
16" (40.6)
6" FLG
(15.2)(15.2)
6" FLG 6" FLG
(15.2) (15.2)
6" FLG
143 1/4" (363.9)
152 3/4" (338.0)
175 1/4" (445.1)
197 3/4" (502.3)
20 3/4" (52.7)
20" (50.8)
20 3/4" (52.7)
20" (50.8)
163" (414.0)
175 3/4" (446.4)
185 1/4" (470.5)
214 1/2" (544.8)
237 1/4" (602.6)
RV450 RV500 RV550 RV600 RV700 RV800
25 1/2"
B
A
8" (20.3)
(64.8)
9 1/4" (23.5)
20"
66" (127.0)
(50.8)
(81.3)
32"MINIMUM TUBE
REMOVAL CLEARANCE
48"
BURNER
SERVICE AREA
87 1/2"
90"
33 1/2"
(222.3)
(228.6)
(85.1)
8 19
FRONT VIEW RIGHT SIDE VIEW REAR VIEW
PLAN VIEW
D
H
C
FG
(121.9)
CONSULT FACTORY FOR BURNER EXTENSION
SUPPLY RETURN
7/24/03
16" Gas Train Total Estimated Width is 66"
BBotbyl Highlight
DRoberts Line
DRoberts Line
BRYAN BOILERS RV SERIES FORCED DRAFT
WATER BOILERS REVERSE CONSTRUCTION
Form # >> 2155 Date >> 4/5/2004
BOILER MODEL RV450 RV500 RV550 RV600 RV700 RV800
INPUT MBH 4,500 5,000 5,500 6,000 7,000 8,000
(KW) 1,318.5 1,465.0 1,611.5 1,758.0 2,051.0 2,344.0
OUTPUT* MBH 3,780 4,200 4,620 5,040 5,880 6,720
(KW) 1,107.5 1,230.6 1,353.6 1,476.7 1,722.8 1,968.9
BOILER HORSEPOWER* HP 113 125 138 151 176 201
(KW) 1,106.6 1,229.6 1,352.5 1,475.5 1,721.4 1,967.3
TUBE DIAMETER INCHES 1.50 1.50 1.50 1.50 1.50 1.50
(CM) 3.81 3.81 3.81 3.81 3.81 3.81
NUMBER OF TUBES 61 67 75 81 95 109
PRESSURE VESSEL
VOLUME GAL 181 200 216 236 278 309
(L) 685.1 757.0 817.6 893.3 1,052.2 1,169.6
HEATING SURFACE SQ FT 544 597 668 722 847 972
(SQ M) 50.6 55.5 62.1 67.1 78.7 90.3
OPERATING WEIGHT LBS 9,829 10,747 11,621 12,498 14,278 16,026
(KG) 4,458.4 4,875.0 5,271.2 5,668.9 6,476.4 7,269.5
SHIPPING WEIGHT LBS 8,320 9,080 9,820 10,530 11,960 13,450
(KG) 3,774.0 4,118.7 4,454.4 4,776.4 5,425.1 6,100.9
RELIEF VALVE TYPICAL - 30 PSIG (206.8 KPA)
QUANTITY (2) 740 (2) 740 (2) 740 (2) 740 (2) 740 (2) 740
SIZE INCHES 1½ x 2 2 x 2½ 2 x 2½ 2 x 2½ 2 x 2½ 2 x 2½
(CM) 3.81 x 5.08 5.08 x 6.35 5.08 x 6.35 5.08 x 6.35 5.08 x 6.35 5.08 x 6.35
CAPACITY-TOTAL MBH 5,800 10,500 10,500 10,500 10,500 10,500
(KW) 1,699.4 3,076.5 3,076.5 3,076.5 3,076.5 3,076.5
RELIEF VALVE TYPICAL - 125 PSIG (861.8 KPA)
QUANTITY (1) 174A (1) 174A (2) 174A (2) 174A (2) 174A (2) 174A
SIZE INCHES 1½ x 1½ 1½ x 1½ 1¼ x 1¼ 1¼ x 1¼ 1¼ x 1¼ 1¼ x 1¼
(CM) 3.81 x 3.80 3.81 x 3.81 3.17 x 3.17 3.17 x 3.17 3.17 x 3.17 3.17 x 3.17
CAPACITY-TOTAL MBH 6,460 6,460 10,740 10,740 10,740 10,740
(KW) 1,892.8 1,892.8 3,146.8 3,146.8 3,146.8 3,146.8
* Output and Boiler HP based on an average natural gas combustion effiiciency.
BBotbyl Highlight
October 19, 2010
CTI and Associates, Inc.
Phil Riley
Dear Phil Riley:
RE: Midland WWTP Order No.: 1009A00
FAX: (248) 486-5050
TEL: (248) 486-5100
51331 W. Pontiac Trail Wixom, Michigan 48393
RTI Laboratories 31628 Glendale St.
Livonia, Michigan 48150
Website: www.rtilab.com
TEL: 734.422.8000 FAX: 734.422.5342
RTI Laboratories received 1 sample(s) on 9/29/2010 for the analyses presented in the following report.
Charles O`Bryan
There were no problems with the analytical events associated with this report unless noted in the Case Narrative.
This report may only be reproduced in its entirety. Individual pages, reproduced without supporting documentation, do not contain related information and may be misinterpreted by other data reviewers.
Quality control data is within laboratory defined or method specified acceptance limits except if noted.
If you have any questions regarding these tests results, please feel free to call.
Sincerely, Director, Quality Management 31628 Glendale St.
Livonia, Michigan 48150 http://www.rtilab.com
Project: Midland WWTP CLIENT: CTI and Associates, Inc.
10/19/2010
Case Narrative 1009A00
Date:
WO#:
RTI Laboratories 31628 Glendale St.
Livonia, Michigan 48150
Website: www.rtilab.com
TEL: 734.422.8000 FAX: 734.422.5342
This report in its entirety consists of the documents listed below. All documents contain the RTI Work Order Number assigned to this report.
1. Paginated Report including: Case Narrative, Analytical Results and Applicable Quality Control Summary Reports.
2. A Cover Letter that immediately precedes the Paginated Report.
3. Paginated copies of the Chain of Custody Documents supplied with this sample set.
Concentrations reported with a J flag in the Qual field are values below the reporting limit (RL) but greater than the established method detection limit (MDL). There is greater uncertainty associated with these results and data should be considered as estimated. These analytes are not routinely reviewed nor narrated below as to their potential for being laboratory artifacts.
Concentrations reported with an E flag in the Qual field are values that exceed the upper quantification range. There is greater uncertainty associated with these results and data should be considered as estimated.
Any comments or problems with the analytical events associated with this report are noted below.
Analytical Comments for METHOD ASTM-D240, SAMPLE 1009A00-001A: During the testing process it was determined that the sample was not compatible with the BTU instrumentation available at the laboratory. Unable to report data for this analysis.
Volatile organic compounds detected in the sample but not included in the standard TO15 list of compounds are provided in the attached document - GCMS TIC Report_1009A00_v1.pdf
Client Sample ID Digester Gas
Collection Date: 9/29/2010 10:45:00 AM
Matrix: AIR
CLIENT: CTI and Associates, Inc.
Lab ID: 1009A00-001
10/19/2010
Analytical Report 1009A00
Date Reported:
WO#:
(consolidated)
Analyses Result Qual Units Date AnalyzedDFRL
RTI Laboratories 31628 Glendale St.
Livonia, Michigan 48150
Website: www.rtilab.com
TEL: 734.422.8000 FAX: 734.422.5342
NONCONDENSABLE GASES AND LIGHT HYDROCARBONS ASTM-D2504 Analyst: MB
Methane 10/13/2010 5:39:31 PM2.0 % 474
HYDROGEN SULFIDE OSHA-1008 Analyst: BV
Hydrogen sulfide 10/14/2010 3:33:20 PM13 mg/m³ 133.33ND
HEAT CONTENT, BTU D240 Analyst: LK
BTU…