This document is Addendum No. 6 to ITB 27-16TM issued by the City of Hampton, Virginia on October 30, 2026, for structural repairs to 100 Exploration Way. The addendum revises the bid due date from November 4, 2026 at 11:00 a.m. to November 10, 2026 at 11:00 a.m. The project involves reinforcement of existing HSS (hollow structural steel) braces using 1/4" reinforcement plates with Complete Joint Penetration (CJP) welds. Bidders are instructed to base material quantities and pricing on current structural drawings showing 8" x 8" x 1/4" HSS members, as confirmed by measurement during a site visit on October 7, 2026. The addendum clarifies that CJP splicing of reinforcement plate sections may be performed in place while positioned against existing HSS members, and that project-specific, engineer-signed welding procedures are acceptable using either backing or non-permanent steel backing methods, provided care is taken to prevent damage to original tube members.

The addendum includes eight photographs documenting existing conditions at the project site, specifically showing crossbeam attachments, ductwork clearances, and connection details for informational purposes. Bidders must acknowledge receipt of this addendum or their bids may not be considered. All other terms and conditions of the original Invitation to Bid remain unchanged. Inquiries should be directed to Gary Sightler, Director of Procurement for the City of Hampton, at 757-727-2206 or gary.sightler@hampton.gov. Complete project documentation and submission instructions are available on the City's bids portal at https://www.hampton.gov/bids.aspx?bidID=1273.

View the file

Other files

File Type Posted
ITB 27-16TM Addendum 4.pdf PDF
ITB 27-16TM Addendum 5.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DATE:

ITB NO./NAME:

DATE ISSUED:

BID DUE:

SUBJECT:

ADDENDUM NO. 6

October 30, 2026 ITB 27-16TM Exploration Way August 18, 2026 November 10, 2026 at 11:00 a.m. (Revised) Due Date Update and Additional Information

Addendum No. 6 is issued to provide the following updates:

1. The due date and time for bids has been revised from November 4, 2026 at 11:00 a.m. to November 10, 2026 at 11:00 am.

2. Answers to questions received following the site visit on October 7, 2026:

a. Question: Existing HSS size: During the site visit, we measured the one exposed HSS brace and it appeared to be approximately 10" × 10".

The current structural drawings identify the braces to be reinforced as HSS8×8×1/4. Should bidders assume the remaining braces are 10" × 10" based on the exposed existing condition, or should material quantities and pricing continue to be based on the 8" × 8" members shown on the drawings?

Answer: An accessible brace on the third floor was measured and confirmed at 8x8x1/4. Bidders shall price based on current drawings.

b. Comment/Question: CJP splicing of the 1/4" reinforcement plates:

The drawings allow the 1/4" reinforcement plates to be installed in separate sections provided the sections are joined with a Complete Joint Penetration (CJP) weld. We would like clarification on whether the plate sections may be fit and CJP-spliced in place while positioned against the existing HSS, or whether the sections must first be CJP-spliced together away from the HSS and then installed as one continuous assembly—for example, assembling an approximately 24' plate on the floor and then raising the completed piece into position.

Answer: The engineer of record takes no exception to the CJP welds being done in place while the plates are positioned against the existing HSS as long as care is taken so not to cause damage or burn through to the original tube members.

c. Comment/Question: AWS D1.1 addresses CJP groove-weld configurations both with backing and with procedures that do not leave permanent steel backing, depending on the approved joint detail and WPS. Our intent would be to provide a project-specific, engineer-signed WPS based on the splice configuration approved by the Engineer of Record.

We are capable of performing the splice using either method.

However, splicing the reinforcement plates in place would be significantly easier and more cost-effective, particularly on the upper floors. It would allow the shorter plate sections to be brought into position individually and joined on the existing HSS rather than attempting to raise and maneuver an assembled plate approximately 20'–24' or longer through existing building interferences and into its final position.

Answer: This method/approach is acceptable to the City.

3. Photos of crossbeam and ductwork at 100 Exploration Way are included with this Addendum for informational purposes.

Bidders must take due notice and be governed accordingly. This addendum must be acknowledged as indicated in the Invitation to Bid or your Bid may not be considered.

All other terms and conditions of the Invitation to Bid remain the same.

For the City of Hampton

Gary Sightler, Director of Procurement 1 Franklin Street Hampton, VA 23669 Phone: 757-727-2206 Email: gary.sightler@hampton.gov mailto:gary.sightler@hampton.gov

Addendum 6 Picture 1 - Crossbeam attachment (welded to horizontal beam)

Picture 2 Distance from wall to ductwork-inner wall inside stair

Picture 3 Distance from wall to ductwork inner wall inside stair

Picture 4 Crossbeam thickness

Picture 5 Distance from inner wall to ductwork (outside of stairwell)

Picture 6 Crossbeam thickness close-up

Picture 7 inside view

Picture 8 connection

1-ITB 27-16TM Addendum 6
Addendum 6- P.1 crossbeam attachment.welded to horizontal beam.
Addendum 6- P.2 distance from wall to ductwork. innerwall inside stair.
Addendum 6- P.3 distance from wall to ductwork. innerwall outside stair.
Addendum 6- P.4 crossbeam thickness.
Addendum 6- P.5 distance inner wall to duckwork outside stairwell
Addendum 6- P.6 crossbeam close-up
Addendum 6- P.7 crossbeam inside view
Addendum 6- P.8 crossbeam connection