ITB 26-PW11: Pavement Preservation Asphalt Rejuvenation Project
This Invitation to Bid (ITB) is issued by the City of Milton Public Works Department in Milton, Georgia, for an asphalt pavement preservation and rejuvenation project. The scope of work involves furnishing all labor, materials, equipment, and services necessary to apply an asphalt rejuvenating agent to approximately 175,767 square yards of asphaltic concrete surface courses across 23 city-owned subdivisions and streets. The rejuvenating agent shall be a maltene-based cationic emulsion composed of petroleum oils and resins, with Reclamite manufactured by Golden Bear Oil (division of Tricor Refining, LLC) identified as the standard product, though qualified alternates may be submitted. Bids must be submitted electronically through the City's BidNet procurement portal by August 26, 2026, at 2:00 p.m. EST, with a virtual bid opening scheduled for approximately 2:30 p.m. the same day. The deadline for written questions is August 17, 2026, at 5:00 p.m., with official answers posted by August 19, 2026. The contract award is anticipated on or about September 21, 2026, with the selected contractor required to commence work within ten calendar days of the Notice to Proceed and complete all work within 60 days from that date, weather permitting. The contract term extends through December 31, 2026, with potential weather-related schedule adjustments to be negotiated between the City and Contractor.
Compensation shall be provided as a lump sum price for all work, materials, labor, equipment, and incidental costs necessary to complete the project. The bidder must submit a five percent bid bond payable to the City of Milton, with the successful bidder required to provide Performance and Payment Bonds equal to 100 percent of the base bid price and a Maintenance Bond of one-third the contract price, guaranteeing repair or replacement for defective workmanship or materials for two years post-completion. The contractor must obtain and maintain comprehensive general liability insurance of $1,000,000 per occurrence with $2,000,000 umbrella coverage, comprehensive automobile liability of $1,000,000 combined single limit, and workers' compensation with employers' liability limits of $1,000,000 per accident, all with A.M. Best ratings of A-6 or higher. Applicators must have a minimum of three years' experience applying the rejuvenating product and must submit documentation of five reference projects with contact information. All work shall comply with Georgia Department of Transportation Standard Specifications and current edition standards. The City retains the right to reject any or all bids and reserves the right to cancel the contract at any time with 30 days' written notice. Payment will be made based on actual quantities of work completed and accepted, with retainage provisions allowing the City to retain ten percent of completed work value if the contract remains below 50 percent completion or if construction schedule maintenance is inadequate.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ITB 26-PW11 1 | P a g e
Bid Number:
ITB 26-PW11
Project Name Asphalt Pavement Preservation and Rejuvenation Project
Due Date and Time: August 26, 2026, by 2:00 p.m. EST
*Link for virtual bid opening will be posted as a “Communication” under this solicitation listing on the City’s procurement portal, BidNet Direct.
Number of Pages: 105
ISSUING DEPARTMENT INFORMATION
Issue Date:
August 6, 2026
City of Milton Public Works Department 2006 Heritage Walk Milton, GA 30004
Phone: 678-242-2500
Website: www.miltonga.gov
INSTRUCTIONS TO BIDDERS
Electronic Submittal: **Bids must be submitted electronically via Milton’s BidNet procurement portal/platform at www.miltonga.gov If you have not registered as a vendor via BidNet we encourage you to register. There is no cost to join, and you will be notified of any potential bid opportunities with the City of Milton as well as other agencies who are part of the Georgia Purchasing Group.
Mark Face of Envelope/Package:
Bid Number: ITB 26-PW11 Name of Company or Firm
Special Instructions:
Deadline for Written Questions August 17, 2026 by 5:00 p.m.
Submit questions online via the BidNet Direct procurement portal at www.miltonga.gov/finance/bids-rfps
BIDDERS MUST COMPLETE THE FOLLOWING
Bidder Name/Address:
Authorized Bidder Signatory:
(Please print name and sign in ink)
Bidder Phone Number: Bidder FAX Number:
Bidder Federal I.D. Number: Bidder E-mail Address:
BIDDERS MUST RETURN THIS COVER SHEET WITH BID RESPONSE
CITY OF MILTON INVITATION TO BID
(THIS IS NOT AN ORDER)
http://www.miltonga.gov/ http://www.miltonga.gov/
ITB 26-PW11 2 | P a g e
Table of Contents
Topic Page
Definitions 3
Invitation to Bid 4
Schedule of Events 5
Bidding Instructions (What must be submitted) 6
Insurance/Bond Requirements 7
Bid Form and Addenda Acknowledgement 11
Bid Bond (3 pages) 13
Qualifications Signature and Certification 16
Corporate Certificate 16
List of Subcontractors 17
Contractor Affidavit and Agreement (eVerify) 18
Disclosure Form 19
Project Specifications 20
Bid Submittal Form 32
General Conditions 33
EPD Air Quality Rules 38
Sample Contract Agreement 39
ITB 26-PW11 3 | P a g e
DEFINITIONS
COMPW: City of Milton Public Works Department
CY: Cubic Yard
GDOT: Georgia Department of Transportation
ENGINEER: The City of Milton Director of Public Works or a duly authorized representative.
ADA: Americans with Disabilities Act
EA: Each
GAL: Gallon
LF: Linear Feet
LM: Linear Mile
LS: Lump Sum
SY: Square Yard
TN: Ton
MUTCD: Manual on Uniform Traffic Control Devices
OSHA: Occupational Safety and Health Administration
FHWA: Federal Highway Administration
AASHTO: American Association of State Highway and Transportation Officials
FOB: Free on Board
ITB 26-PW11 4 | P a g e
Invitation to Bid ITB 26-PW11
The City of Milton is accepting sealed electronic bids from qualified firms for the Public Works Department in conformance with Title 32, Chapter 4, Article 4, Part 2 of the Official Code of Georgia Annotated. All work will be done in accordance with Georgia Department of Transportation’s (GDOT) Standard Drawings, Standard Specifications (current edition), and Pay Items Index as standards and specifications for the construction and completion of the work required. All bidders must comply with all general and special requirements of the bid information and instructions enclosed herein.
Sealed bids will be received no later than 2:00 PM Local Time on August 26, 2026. Electronic bids shall be submitted online via BidNet Direct, the City’s procurement portal, at www.miltonga.gov/finance/bids-rfps .
At approximately 2:30 P.M. Local Time on the day bids are received the bids will be publicly opened and the bidder’s name and total bid amount will be read aloud at: City of Milton City Hall, 2006 Heritage Walk, Milton, GA 30004. *Link for the virtual bid opening will be posted as a “Communication” under this solicitation listing on the City’s procurement portal, BidNet Direct.
Bids received after the above time will not be accepted.
Questions must also be submitted online in the same manner listed above for bids. Deadline for questions is August 17, 2026, at 5:00 p.m. Official answers to questions and potential changes to the ITB (Addendums) will be posted at the same web locations as the ITB on or about August 19, 2026. Any other form of interpretation, correction, or change to this ITB will not be binding upon the City. It is the bidder’s responsibility to check the websites for potential updates. Please refer to Bid (ITB 26-PW11) and bid name (Pavement Preservation Asphalt Rejuvenation Project) when requesting information.
The City of Milton reserves the right to reject any or all bids and to waive technicalities and informalities, and to make award in the best interest of the City of Milton.
The selected contractor must be able to start work within ten (10) calendar days after the “Notice to Proceed” is issued. The time of completion for the project is to be determined prior to the issuance of the “Notice to Proceed.” If weather affects the required completion schedule, The City and selected contractor will negotiate a new completion date. Section
108.08 of the State of Georgia Department of Transportation Standard Specifications Construction of Transportation Systems (current edition) shall be applied.
http://www.miltonga.gov/finance/bids-rfps
ITB 26-PW11 5 | P a g e
SCHEDULE OF EVENTS
FOR REFERENCE ONLY - DO NOT SUBMIT WITH BID RESPONSE
EVENT DATE
ITB Issue Date August 6, 2026
Deadline for Receipt of Written Questions 5:00 PM on August 17, 2026
Posting of Written Answers by City to Websites on or about August 19, 2026
ITB DUE No Later than 2:00 P.M. on August 26, 2026
Tentative Contract Award (on/about) September 21, 2026
Notice to Proceed (on/about) To be coordinated with the Contractor
NOTE: PLEASE CHECK THE CITY WEBSITE (http://www.miltonga.gov) FOR ADDENDA
AND SCHEDULE UPDATES.
http://www./
ITB 26-PW11 6 | P a g e
BIDDING INSTRUCTIONS
FAILURE TO RETURN THE FOLLOWING BID DOCUMENTS COULD RESULT IN THE BID
BEING DEEMED NON-RESPONSIVE AND BEING REJECTED:
Item Description Page(s) 1 Filled out and Signed Invitation to Bid (Cover Sheet) 1 2 Bid Form and Addenda Acknowledgement (2 pages) 11-12 3 Bid Bond (3 pages) 13-15 4 Qualifications Signature and Certification 16 5 List of Subcontractors 17 6 Contractor Affidavit and Agreement (eVerify) 18 7 Disclosure Form 19 8 Bid Submittal Form 32
INFORMATION AND INSTRUCTIONS
The purpose of this solicitation is to enter a lump sum price “purchasing contract” with one firm to be the primary supplier of Pavement Preservation Asphalt Rejuvenation Project, ITB 26-PW11.
No specification expressed or implied shall be construed as any type of restrictive specification that would limit competition.
Unless clearly shown as “no substitute” or any words to that effect, any items in these contract documents which have been identified, described or referenced by a brand name or trade name are for reference only. Such identification is intended to be descriptive but not restrictive and is to indicate the general quality and characteristics of products that may be offered. Each bid item for which an equivalent item is proposed must be individually identified on the bid sheet with the following information: brand name, model or manufacturer’s number or identification regularly used in the trade. Photographs, specifications and cut sheets shall be provided of the proposed alternative. The City shall be the sole judge of the suitability of the proposed alternative and may consider function, design, materials, construction, workmanship, finishes, operating features, overall quality, local service facilities, warranty terms and service or other relevant features.
The City reserves the right to cancel the contract at any time, without cause, with 30 days’ written notice.
ITB 26-PW11 7 | P a g e
Title to any supplies, materials, equipment or other personal property shall remain the Contractors’ until fully paid for by the City.
All items to be bid FOB, Milton, Georgia. No sales taxes are to be charged.
Any damage to any building or traffic control device, or equipment incurred during the course of work shall be repaired at the Contractor’s expense to the complete satisfaction of the City of Milton with no additional expense to the City.
EVALUATION
The City intends to evaluate the ITB on the lowest, responsible and responsive bidder.
Bids may be found nonresponsive at any time during the evaluation or contract process, if any of the required information is not provided; the submitted price is found to be inadequate; or the proposal is not within the specifications described and required in the ITB. If a bid is found to be non-responsive or non-qualified, it will not be considered further.
INSURANCE REQUIREMENTS
Within ten (10) days of Notice of Award, and at all times that this Contract is in force, the Contractor shall obtain, maintain and furnish the City Certificates of Insurance from licensed companies doing business in the State of Georgia with an A.M. Best Rating A-6 or higher and acceptable to the City.
Within ten (10) days of Notice of Award, and at all times that this Contract is in force, the Contractor shall obtain, maintain and furnish the City Certificates of Insurance from licensed companies doing business in the State of Georgia with an A.M. Best Rating A-6 or higher and acceptable to the City. Insurance requirements are provided below and included in the CONTRACT AGREEMENT (Section 7.K).
(1) Requirements: The Contractor shall have and maintain in full force and effect for the duration of this Agreement, insurance insuring against claims for injuries to persons or damages to property which may arise from or in connection with the performance of the Work by the Contractor, its agents, representatives, employees or subcontractors. All policies shall be subject to approval by the City Attorney as to form and content. These requirements are subject to amendment or waiver if so approved in writing by the City.
(2) Minimum Limits of Insurance: Contractor shall maintain the following insurance policies with limits no less than:
(a) Comprehensive General Liability of $1,000,000 (one million dollars) limit per single occurrence, $2,000,000 (two million dollars) umbrella, including coverage for bodily and personal injury, sickness, disease or
ITB 26-PW11 8 | P a g e death, injury to or destruction of property, including loss of use resulting therefrom, vandalism, property loss and theft.
(b) Comprehensive Automobile Liability (owned, non-owned, hired) of $1,000,000 (one million dollars) combined single limit per occurrence for bodily and personal injury, sickness, disease or death, injury to or destruction of property, including loss of use resulting therefrom.
(c) Workers' Compensation limits as required by the State of Georgia and Employers Liability limits of $1,000,000 (one million dollars) per accident.
(3) Deductibles and Self-Insured Retentions: Any deductibles or self-insured retentions must be declared to and approved by the City in writing.
(4) Other Insurance Provisions: The policy is to contain, or be endorsed to contain, the following provisions:
(a) General Liability and Automobile Liability Coverage.
(i) The City and City Parties are to be covered as insureds. The coverage shall contain no special limitations on the scope of protection afforded to the City or City Parties.
(ii) The Contractor’s insurance coverage shall be primary noncontributing insurance as respects to any other insurance or self-insurance available to the City or City Parties. Any insurance or self-insurance maintained by the City or City Parties shall be in excess of the Contractor’s insurance and shall not contribute with it.
(iii) Any failure to comply with reporting provisions of the policies shall not affect coverage provided to the City or City Parties.
(iv) Coverage shall state that the Contractor’s insurance shall apply separately to each insured against whom claim is made or suit is brought, except with respect to the limits of the insurer's liability.
(v) Coverage shall be provided on a “pay on behalf” basis, with defense costs payable in addition to policy limits. There shall be no cross-liability exclusion.
(vi) The insurer agrees to waive all rights of subrogation against the City and City Parties for losses arising from Work performed by the Contractor for the City for General Liability coverage only.
ITB 26-PW11 9 | P a g e
(b) Workers' Compensation Coverage: The insurer providing Workers’
Compensation Coverage will agree to waive all rights of subrogation against the City and City Parties for losses arising from Work performed by the Contractor for the City.
(c) All Coverages:
(i) Each insurance policy required by this clause shall be endorsed to state that coverage shall not be suspended, voided, canceled, reduced in coverage or in limits except after thirty (30) days prior written notice by certified mail, return receipt requested, has been given to the City.
(ii) Policies shall have concurrent starting and ending dates.
(5) Acceptability of Insurers: Insurance is to be placed with insurers authorized to do business in the State of Georgia and with an A.M. Bests' rating of no less than A:VI.
(6) Verification of Coverage: Contractor shall furnish the City with certificates of insurance and endorsements to the policies evidencing coverage required by this clause prior to the start of Work. The certificate of insurance and endorsements shall be on a form utilized by Contractor’s insurer in its normal course of business and shall be received and approved by the City within ten
(10) days of the Notice of Award. The City reserves the right to require complete, certified copies of all required insurance policies, at any time. The Contractor shall provide proof that any expiring coverage has been renewed or replaced at least two (2) weeks prior to the expiration of the coverage.
(7) Subcontractors: Contractor shall include all subcontractors as insureds under its policies or shall furnish separate certificates and endorsements for each subcontractor. All coverage for subcontractors shall be subject to all of the requirements stated in this Agreement, including but not limited to naming the Parties as additional insureds.
(8) Claims-Made Policies: Contractor shall extend any claims-made insurance policy for at least six (6) years after termination or final payment under the Agreement, whichever is later.
(9) City as Additional Insured and Loss Payee: The City shall be named as an additional insured and loss payee on all policies required by this Agreement, except the City need not be named as an additional insured and loss payee on any Workers’ Compensation policy.
ITB 26-PW11 10 | P a g e
BONDING REQUIREMENTS
Each bid must be accompanied with a BID BOND (bond only: certified checks or other forms are not acceptable) in an amount equal to five percent (5%) of the base bid, payable to the City of Milton. Said bid bond guarantees the bidder will enter into a contract to construct the project strictly within the terms and conditions stated in this bid and in the bidding and contract documents, should the construction contract be awarded.
The Successful Bidder shall be required to furnish PAYMENT AND PERFORMANCE BONDS for the faithful performance on the contract and a bond to secure payment of all claims for materials furnished and/or labor performed in performance of the project, both in amounts equal to one hundred percent (100%) of the base bid price.
The Successful Bidder shall also be required to furnish a MAINTENANCE BOND, in the amount of one-third (1/3) of the contract price, guaranteeing the repair or replacement caused by defective workmanship or materials for a period of two (2) years from the completion of construction.
Bonds shall be issued by a corporate surety appearing on the Treasury Department’s most current list (Circular 570 as amended) and be authorized to do business in the State of Georgia. Bonds shall be on the forms provided by the City and subject to the review and approval of the City Attorney.
Date of Bond must not be prior to date of Contract. If Contractor is a Partnership, all partners shall execute Bond.
OATH
Prior to commencing the Work, the successful bidder shall execute a written oath as required by O.C.G.A. §§ 32-4-122 and 36-91-21(e).
COST OF PREPARING A BID
The costs for developing and delivering responses to this ITB and any subsequent presentations of the proposal as requested by the City are entirely the responsibility of the bidder. The City is not liable for any expense incurred by the bidder in the preparation and presentation of their proposal. All materials submitted in response to this ITB become the property of the City of Milton.
ITB 26-PW11 11 | P a g e
[BIDDERS MUST RETURN THIS FORM WITH BID RESPONSE]
BID FORM and ADDENDA ACKNOWLEDGEMENT
TO: PURCHASING OFFICE
CITY OF MILTON
MILTON, GEORGIA 30004
Ladies and Gentlemen:
In compliance with your Invitation to Bid, the undersigned, hereinafter termed the Bidder, proposes to enter into a Contract with the City of Milton, Georgia, to provide the necessary machinery, tools, apparatus, other means of construction, and all materials and labor specified in the Contract Documents or as necessary to complete the Work in the manner therein specified within the time specified, as therein set forth, for:
Bid Number ITB 26-PW11 Pavement Preservation Asphalt Rejuvenation Project
The Bidder has carefully examined and fully understands the Contract, Specifications, and other documents hereto attached, has made a personal examination of the Site of the proposed Work, has satisfied himself as to the actual conditions and requirements of the Work, and hereby proposes and agrees that if his bid is accepted, he will contract with the City of Milton in full conformance with the Contract Documents.
Unless otherwise directed, all work performed shall be in accordance with the Georgia Department of Transportation Standard Specifications, Construction of Transportation Systems (current edition).
It is the intent of this Bid to include all items of construction, and all Work called for in the Specifications, or otherwise a part of the Contract Documents.
In accordance with the foregoing, the undersigned proposes to furnish and construct the items listed in the attached Bid schedule for the unit prices stated.
The Bidder agrees that the cost of any work performed, materials furnished, services provided, or expenses incurred, which are not specifically delineated in the Contract Documents, but which are incidental to the scope, intent, and completion of the Contract, shall be deemed to have been included in the prices bid.
ITB 26-PW11 12 | P a g e
The Bidder further proposes and agrees hereby to promptly commence the Work with adequate forces within ten (10) calendar days from the Notice to Proceed, and to complete all Work as scheduled.
If weather affects the required completion schedule, the City and selected Bidder will negotiate a new completion date.
Attached hereto is an executed Bid Bond in the amount of __________________ Dollars ($ (Five Percent of Amount Bid).
If this bid shall be accepted by the City of Milton and the undersigned shall fail to execute a satisfactory contract in the form of said proposed Contract, and give satisfactory Performance and Payment Bonds, or furnish satisfactory proof of carriage of the insurance required within ten days from the date of Notice of Award of the Contract, then the City of Milton may, at its option, determine that the undersigned abandoned the Contract and there upon this bid shall be null and void, and the sum stipulated in the attached Bid Bond shall be forfeited to the City of Milton as liquidated damages.
Bidder acknowledges receipt of the following addenda:
Addendum No. Date viewed
Bidder further declares that the full name and resident address of Bidder’s Principal is as follows:
Signed, sealed, and dated this _______ day of _____________, 20_____
Bidder _______________________ (Seal) Company Name
Bidder Mailing Address:
Signature: ________________________________________
Print Name: ______________________________________
Title: _____________________________________________
ITB 26-PW11 13 | P a g e
[BIDDERS MUST RETURN THESE SHEETS WITH BID RESPONSE]
BID BOND
BIDDER (Name and Address):
SURETY (Name and Address of Principal Place of Business):
OWNER (hereinafter referred to as the “City” (Name and Address):
City of Milton, Georgia ATTN: Purchasing Office 2006 Heritage Walk Milton, Georgia 30004
BID
BID DUE DATE:
PROJECT (Brief Description Including Location):
BOND
BOND NUMBER:
DATE (Not later that Bid due date):
PENAL SUM: _______________________________________________________________________
(Words) (Figures)
IN WITNESS WHEREOF, Surety and Bidder, intending to be legally bound hereby to the City, subject to the terms printed below or on the reverse side hereof, do each cause this Bid Bond to be duly executed on its behalf by its authorized officer, agent or representative.
BIDDER SURETY
(Seal) (Seal) Bidder’s Name and Corporate Seal Surety’s Name and Corporate Seal
By: By: ___________________________ Signature and Title: Signature and Title:
(Attach Power of Attorney)
Attest: Attest:_________________________ Signature and Title: Signature and Title:
ITB 26-PW11 14 | P a g e
Note: (1) Above addresses are to be used for giving any notice required by the terms of this Bid Bond.
(2) Any singular reference to Bidder, Surety, the City or any other party shall be considered plural where applicable.
1. Bidder and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors and assigns to pay to the City upon Default of Bidder the penal sum set forth on the face of this Bond.
2. Default of Bidder shall occur upon the failure of Bidder to deliver within the time required by the Bidding Documents (or any extension of that time agreed to in writing by the City) the executed Agreement required by the Bidding Documents and any performance and payment Bonds required by the Bidding Documents.
3. This obligation shall be null and void if:
3.1 The City accepts Bidder’s Bid and Bidder delivers within the time required by the Bidding Documents (or any extension of that time agreed to in writing by the City) the executed Agreement required by the Bidding Documents and any performance and payment Bonds required by the Bidding Documents;
or
3.2 All Bids are rejected by the City; or
3.3 The City fails to issue a Notice of Award to Bidder within the time specified in the Bidding Documents (or any extension of that time agreed to in writing by Bidder and, if applicable, consented to by Surety when required by paragraph 5 hereof).
4. Payment under this Bond will be due and payable upon Default by Bidder within 30 calendar days after receipt by Bidder and Surety of a written Notice of Default from the City, which Notice will be given with reasonable promptness and will identify this Bond and the Project and include a statement of the amount due.
5. Surety waives notice of, as well as any and all defenses based on or arising out of, any time extension to issue a Notice of Award agreed to in writing by the City and Bidder, provided that the total time, including extensions, for issuing a Notice of Award shall not in the aggregate exceed 120 days from Bid due date without Surety’s written consent.
6. No suit or action shall be commenced under this Bond either prior to 30 calendar days after the Notice of Default required in paragraph 4 above is received by Bidder and Surety or later than one year after Bid due date.
7. Any suit or action under this Bond shall be commenced only in a court of competent jurisdiction located in the State of Georgia.
8. Notices required hereunder shall be in writing and sent to Bidder and Surety at their respective addresses shown on the face of this Bond. Such notices may be sent by personal delivery, commercial courier or by United States Registered or Certified Mail, return receipt requested, postage pre-paid, and shall be deemed to be effective upon receipt by the party concerned.
ITB 26-PW11 15 | P a g e
9. Surety shall cause to be attached to this Bond a current and effective Power of Attorney evidencing the authority of the officer, agent or representative who executed this Bond on behalf of Surety to execute, seal and deliver such Bond and bind the Surety thereby.
10. This Bond is intended to conform to all applicable statutory requirements. Any applicable requirement of any applicable statute that has been omitted from this Bond shall be deemed to be included herein as if set forth at length. If any provision of this Bond conflicts with any applicable statute, then the provision of said statute shall govern and the remainder of this Bond that is not in conflict therewith shall continue in full force and effect.
11. The term “Bid” as used herein includes a Bid, offer or proposal, as applicable under the particular circumstances.
12. The terms of this Bid Bond shall be governed by the laws of the State of Georgia.
ITB 26-PW11 16 | P a g e
QUALIFICATIONS SIGNATURE AND CERTIFICATION
I certify that this offer is made without prior understanding, agreement, or connection with any corporation, firm, or person submitting a proposal for the same materials, supplies, equipment, or services and is in all respects fair and without collusion or fraud. I understand collusive bidding is a violation of State and Federal Law and can result in fines, prison sentences, and civil damage awards. I agree to abide by all conditions of the proposal and certify that I am authorized to sign this proposal for the proposer. I further certify that the provisions of the Official Code of Georgia Annotated, including but not limited to Title 32, Chapter 4, Article 4, Part 2 and Sections 45-10-20 et seq. have not been violated and will not be violated in any respect.
Authorized Signature______________________________Date_______________________
Print/Type Name______________________________________________________________
Print/Type Company Name Here_______________________________________________
CORPORATE CERTIFICATE
I, ___________________________________, certify that I am the Secretary of the Corporation named as Contractor in the foregoing bid; that _______________________________________ who signed said bid in behalf of the Contractor, was then (title)_________________________ of said Corporation; that said bid was duly signed for and in behalf of said Corporation by authority of its Board of Directors, and is within the scope of its corporate powers; that said Corporation is organized under the laws of the State of _________________________________.
This ________________ day of ________________, 20______
______________________________________(Seal) (Signature)
ITB 26-PW11 17 | P a g e
LIST OF SUBCONTRACTORS
I do _________, do not _______, propose to subcontract some of the work on this project. I propose to Subcontract work to the following subcontractors:
Company Name:___________________________________________________
ITB 26-PW11 18 | P a g e
CONTRACTOR AFFIDAVIT AND AGREEMENT
STATE OF GEORGIA
By executing this affidavit, the undersigned contractor verifies its compliance with O.C.G.A. § 13-10- 91, stating affirmatively that the individual, firm, or corporation which is engaged in the physical performance of services on behalf of the City of Milton has registered with, is authorized to use and uses the federal work authorization program commonly known as E-Verify, or any subsequent replacement program, in accordance with the applicable provisions and deadlines established in O.C.G.A. § 13-10-91. Furthermore, the undersigned contractor will continue to use the federal work authorization program throughout the contract period and the undersigned contractor will contract for the physical performance of services in satisfaction of such contract only with subcontractors who present an affidavit to the contractor with the information required by O.C.G.A. § 13-10-91(b).
Contractor hereby attests that its federal work authorization user identification number and date of authorization are as follows:
I hereby declare under penalty of perjury that eVerify Number
Date of Authorization
Name of Contractor
Pavement Preservation Asphalt Rejuvenation Project Name of Project
City of Milton, Georgia Name of Public Employer the foregoing is true and correct.
Executed on ____________, ______, 20____ in ____________________(city), ______(state).
Signature of Authorized Officer or Agent
Printed Name and Title of Authorized Officer or Agent
SUBSCRIBED AND SWORN BEFORE ME ON
THIS THE ______ DAY OF ______________,20___.
NOTARY PUBLIC
[NOTARY SEAL]
My Commission Expires:
ITB 26-PW11 19 | P a g e
DISCLOSURE FORM
This form is for disclosure of campaign contributions and family member relations with City of Milton officials/employees.
Please complete this form and return as part of your bid package when it is submitted.
Name of Bidder __________________________________________________
Name and the official position of the Milton Official to whom the campaign contribution was made (Please use a separate form for each official to whom a contribution has been made in the past two (2) years.)
List the dollar amount/value and description of each campaign contribution made over the past two (2) years by the Applicant/Opponent to the named Milton Official.
Amount/Value Description
Please list any family member that is currently (or has been employed within the last 9 months) by the City of Milton and your relation:
ITB 26-PW11 20 | P a g e
PROJECT SPECIFICATIONS
Bidders shall submit with the bid a qualification sheet listing project(s) that meet the experience requirement along with references. List should include project date, location, description, and contact information.
1. Where contract documents reference "The Department" or "GA Department of Transportation" or “The Engineer”, it shall also mean "City of Milton."
2. All traffic control measures, and signage are the responsibility of the Contractor.
Contractor shall coordinate all work with the City of Milton.
3. Replace, in kind, any vegetation or landscaping damaged during construction. Include cost in the price bid.
4. Unless otherwise directed, all work performed under this contract shall be in accordance with the Georgia Department of Transportation Standard Specifications, Construction of Transportation Systems (current edition), and Special Provisions modifying them, except as noted herein.
PROSECUTION AND PROGRESS
Construction shall begin no later than TEN (10) calendar days past the issuance of Notice to Proceed. The time of completion for the projects will be 60 days from the date of the Notice to Proceed.
If weather (beyond normal) affects the required completion schedule, The City and selected contractor will negotiate a new completion date.
Normal workday for this project shall be 7:30 am to 7:30 pm and the normal workweek shall be Monday through Friday. The City will consider extended workdays or workweeks upon written request by the Contractor on a case by case basis. No work will be allowed on Sunday or national holidays (i.e. Memorial Day, July 4th, Labor Day, etc.). Lane closures will only be permitted between the hours of 9:00am and 4:00pm, Monday-Friday, unless otherwise approved by the City.
The work will require bidder to provide all labor, administrative forces, equipment, materials and other incidental items to complete all required work. The City shall perform a Final Inspection upon completion of all work. The Contractor will be allowed to participate in the Final Inspection.
All repairs shall be completed by the contractor at his expense prior to issuance of Final Acceptance.
ITB 26-PW11 21 | P a g e
APPLICATOR EXPERIENCE
The Asphalt Rejuvenation agent shall be applied by an experienced applicator of such material.
The bidder shall have a minimum of three years’ experience in applying the product proposed for use. He must submit with his bid a list of five projects on which he applied said rejuvenator.
He shall indicate the project dates, number of square yards treated in each and the name and phone number of the government official in charge of each project.
A project superintendent knowledgeable and experienced in application of the Asphalt Rejuvenation agent must be in control of each day's work. The bidder shall submit a written experience outline of the project superintendent.
PERMITS AND LICENSES
The Contractor shall procure all permits and licenses, pay all charges, taxes and fees, and give all notices necessary and incidental to the due and lawful prosecution of the work.
MATERIALS
Contractor will be responsible for replacing any work performed with material from rejected sample lot at no cost to the City.
DEVIATION OF QUANTITIES
The quantities given are estimates only and will vary from those indicated. Payment will be made based on actual quantities of work completed and accepted. The City reserves the right to add or delete quantities at any time. Contractor will notify the City in writing if additional items are identified or quantities of contract items will exceed plan. At no time will Contractor proceed with work outside the prescribed scope of services for which additional payment will be requested without the written authorization of the City.
EROSION CONTROL
It is the responsibility of the Contractor to follow all Federal, State and Local erosion and sediment control laws and specifications. This includes meeting all NPDES guidelines. The Contractor shall serve as the Primary Permittee for this project and is responsible for filing the NOI and all necessary fees associated with it.
Erosion/Sediment Control measures shall be installed and maintained by the Contractor throughout the duration of the project. The Contractor is responsible for the removal and disposal, off project site, of all installed temporary erosion/sediment control measures when affected areas have been restored to a level where vegetative coverings will minimize erosion.
The cost for this will be considered incidental to the project and included in the overall bid.
UTILITIES
There are utilities in the project area. The Contractor shall be responsible for locating and coordinating any utility relocation necessary for completion of the work. Utility plan sheets provided are based on early coordination and are subject to change.
Call “811 Know what’s below Call before you dig.” Locate, maintain and protect existing utilities at all times during construction.
ITB 26-PW11 22 | P a g e
TEMPORARY TRAFFIC CONTROL
The Contractor shall, at all times, conduct his work in accordance with the traffic control plan and so as to assure the least possible obstruction of traffic. The safety and convenience of the general public and the residents along the roadway and the protection of persons and property shall be provided for by the Contractor as specified in the State of Georgia, Department of Transportation Standard Specifications Sections 104.05, 107.09 and 150.
Traffic whose origin and destination are within the limits of the project shall be provided ingress and egress at all times unless otherwise specified by the City. The ingress and egress include entrances and exits VIA driveways at various properties, and access to the intersecting roads and streets. The Contractor shall maintain sufficient personnel and equipment (including flaggers and traffic control signing) on the project at all times, particularly during inclement weather, to ensure that ingress and egress are safely provided when and where needed.
The Contractor shall furnish, install and maintain all necessary and required barricades, signs, temporary striping and other traffic control devices in accordance with the MUTCD and DOT specifications, and take all necessary precautions for the protection of the workers and safety of the public.
All existing signs, markers and other traffic control devices removed or damaged during construction operations will be reinstalled or replaced at the Contractor’s expense. At no time will Contractor remove regulatory signing which may cause a hazard to the public. The Contractor shall, within 24 hours place temporary pavement markings (paint or removable tape) matching existing pavement markings on milled or patched pavements.
All personnel and equipment required for maintaining temporary traffic control, public convenience and safety will be included in the contract price.
PROTECTION AND RESTORATION OF PROPERTY AND LANDSCAPE
The Contractor shall be responsible for the preservation of all public and private property, crops, fishponds, trees, monuments, highway signs and markers, fences, grassed and sodded areas, mail boxes and supports, water meters, etc. along and adjacent to the highway, road or street, and shall use every precaution necessary to prevent damage or injury thereto, unless the removal, alteration, or destruction of such property is provided for under the contract. No stone or asphalt chunks shall be left in the right-of-way and screened topsoil shall be placed in all disturbed areas before grassing. Contractor is responsible for ensuring that all permanent grassing shall match the existing grassing
When or where any direct or indirect damage or injury is done to public or private property by or on account of any act, omission, neglect or misconduct in the execution of the work, or in consequence of the non-execution thereof by the Contractor, he shall restore, at his/her own expense, such property to a condition similar or equal to that existing before such damage or injury was done, by repairing, rebuilding or otherwise restoring as may be directed, or she/he shall make good such damage or injury in an acceptable manner. The Contractor shall correct all disturbed areas before retainage will be released.
ITB 26-PW11 23 | P a g e
CLEANUP
All restoration and clean-up work shall be performed daily. Operations shall be suspended if the contractor fails to accomplish restoration and clean-up within an acceptable period of time.
Asphalt and other debris shall be removed from gutters, sidewalks, yards, driveways, etc. Failure to perform clean-up activities may result in suspension of the work. All pavement areas shall be clean and dry prior to placing tack coat, asphaltic concrete or other materials.
SAFETY
Beginning with mobilization and ending with acceptance of work, the Contractor shall be responsible for providing a clean and safe work environment at the project site. The Contractor shall comply with all OSHA regulations as they pertain to this project.
ITB 26-PW11 24 | P a g e
STANDARD SPECIFICATIONS FOR ASPHALT SURFACE PRESERVATION
WITH A MALTENE BASED ASPHALT REJUVENATING AGENT
Scope
This work shall consist of furnishing all labor, material, and equipment necessary to perform all operations for the application of an asphalt rejuvenating agent to asphaltic concrete surface courses. The rejuvenation of surface courses shall be by spray application of a maltene based cationic rejuvenating agent composed of petroleum oils and resins emulsified with water. All work shall be in accordance with the specifications, the applicable drawings, and subject to the terms and conditions of this contract.
Material Specifications
The asphalt rejuvenating agent shall be an emulsion composed of a petroleum resin oil base uniformly emulsified with water. Each bidder must submit with his bid a certified statement from the asphalt rejuvenator manufacturer showing that the asphalt rejuvenating emulsion conforms to the required physical and chemical requirements.
SPECIFICATIONS
Test Method Requirements Tests ASTM AASHTO Min. Max.
Tests on Emulsion:
Viscosity @ 25C, SFS D-244 T-59 15 40 Residue, % W1 D-244(Mod.) T-59(Mod) 60 65 Miscibility Test2 D-244(Mod.) T-59(Mod) No Coagulation Sieve Test, %W3 D-244(Mod.) T-59(Mod) - 0.1 Particle Charge Test D-244 T-59 Positive Percent Light Transmittance4 GB GB - 30
Tests on Residue from Distillation:
Flash Point, COC, C D-92 T-48 196 - Viscosity @ 60C, cSt D-445 - 100 200 Asphaltenes, %w D-2006-70 - - 1.00 Maltene Dist. Ratio D-2006-70 - 0.3 0.6
PC + A15
S + A2
PC/S Ratio5 D-2006-70 - 0.5 -
ITB 26-PW11 25 | P a g e
Saturated Hydrocarbons,S5 D-2006-70 - 21 28 1 ASTM D-244 Modified Evaporation Test for percent of residue is made by heating 50 gram sample to 149 C (300 F) until foaming ceases, then cool immediately and calculate results.
2 Test procedure identical with ASTM D-244-60 except that .02 Normal Calcium Chloride solution shall be used in place of distilled water.
3 Test procedures identical with ASTM D-244-60 except that distilled water shall be used in place of two percent sodium oleate solution.
4 Test procedure is attached.
5 Chemical composition by ASTM Method D-2006-70:
PC = Polar Compounds, A1 = First Acidaffins A2 = Second Acidaffins, S = Saturated Hydrocarbons
PROCEDURE FOR DETERMINING PERCENT LIGHT TRANSMITTANCE ON
ASPHALT REJUVENATING AGENT
SCOPE:
This procedure covers the determination of percent light transmittance of the asphalt rejuvenating agent.
APPARATUS:
1) Container may be either glass, plastic or metal having a capacity of 6,000 ml.
2) Graduated cylinder, 1,000 ml, or greater
3) Light transmittance measuring apparatus, such as Bausch and Lomb or Lumetron spectrophotometer
4) Graduated pipette having 1 ml capacity to 0.01 ml accuracy
5) Suction bulb for use with pipette
6) Test tubes compatible with spectrophotometer, 3/4” X 6, Bausch and Lomb, Catolog No. 33-17- 81, (B&L)
CALIBRATION OF SPECTROPHOTOMETER:
Calibrate spectrophotometer as follows: (a) Set wavelength at 580 mu, (b) Allow spectrophotometer to warm-up thirty minutes, (c) Zero percent light transmittance (%LT) scale, (d) Rinse test tube three times with tap water and fill to top of circle marking on B&L test tube or approximately 2/3 full, (e) Place tube in spectrophotometer and set %LT scale at 100, and (f) repeat steps (c) and (e) two times or until no further adjustments are necessary.
ITB 26-PW11 26 | P a g e
PROCEDURE:
1) Shake, stir or otherwise thoroughly mix emulsion to be tested. Place sample of emulsion in beaker and allow to stand one minute.
2) Place 2,000 ml tap water in container.
3) Suck 1.00 ml emulsion into pipette using suction bulb. Wipe off outside of pipette.
4) Using suction bulb, blow emulsion into container.
5) Rinse pipette by sucking in diluted emulsion solution and blowing out.
6) Clean pipette with soap or solvent and water. Rinse with acetone.
7) Stir diluted emulsion thoroughly.
8) Rinse out tube to be used with the diluted emulsion three times and fill to top of circle.
9) Calibrate spectrophotometer.
10) Place diluted emulsion sample tube in spectrophotometer, cover and read %LT to nearest tenth.
11) Repeat steps 9 and 10 until three identical consecutive readings are achieved.
12) The elapsed time between addition of emulsion to dilution of water and final %LT reading should not exceed 5 minutes.
MATERIAL PERFORMANCE
The asphalt rejuvenating agent shall have the capability to penetrate the asphalt pavement surface. The asphalt rejuvenating agent shall be absorbed and incorporated into the asphalt binder. Verification that said incorporation of the asphalt rejuvenating agent into the asphalt binder has been affected shall be by analysis of the chemical properties of said asphalt binder i.e. viscosity shall be improved to the following extent. Viscosity shall be reduced by a minimum of forty, (40%) percent as determined by dynamic shear rheometer (DSR) method for asphalt testing in accord with AASHTO T315-05. This analysis shall apply to extracted asphalt binder, taken from cores extracted fifteen to thirty days following application, in the upper 3/8” of pavement.
In addition, the treated areas shall be sealed in-depth to the intrusion of air and water. The rejuvenating agent shall have a record of at least five years of satisfactory service as an asphalt rejuvenating agent and in-depth sealer. Satisfactory service shall be based on the capability of the material to decrease the viscosity of the asphalt binder and provide an in-depth seal.
Reclamite®, manufactured by D&D Emulsion, Inc., Mansfield, Ohio, is a product of know quality and accepted performance. The bidder must submit with his bid the manufacturer's certification that the material proposed for use is in compliance with the specification requirements. The bidder must submit with his bid previous use documentation and test data conclusively demonstrating that; the rejuvenating agent has been used successfully for a period of five years by government agencies such as Cities, Counties, etc; and that the asphalt rejuvenating agent has been proven to perform, as heretofore required, through field testing by government agencies as to the required change in asphalt binder viscosity. Testing data shall be submitted indicating such product performance on a sufficient number of projects to insure product consistency. In addition, testing data shall be submitted to indicate said product performance over a testing period of three years to ensure reasonable life expectancy. RECLAMITE®, a product of Golden Bear Oil, a division of Tricor Refining, LLC. is a product of known quality and accepted performance.
ITB 26-PW11 27 | P a g e
APPLICATOR EXPERIENCE
The asphalt-rejuvenating agent shall be applied by an experienced applicator of such material.
The bidder shall have a minimum of three years’ experience in applying the product proposed for use. He must submit with his bid a list of five projects on which he applied said rejuvenator.
He shall indicate the project dates, number of square yards treated in each and the name and phone number of the government official in charge of each project.
A project superintendent knowledgeable and experienced in application of the asphalt-rejuvenating agent must be in control of each day's work. The bidder shall submit a written experience outline of the project superintendent.
PRODUCT STANDARDS AND ALTERNATES
The product "Reclamite"® for the asphalt rejuvenating agent as manufactured by Golden Bear oil, a division of Tricor Refining, LLC. is the standard for these specifications and the prices quoted on the Bid Sheet Base Bid shall be for this standard. Should a bidder wish to submit a bid for alternates to the Standard, said prices shall be entered on the BID SHEET as the "Alternate Bid" for each item. In the event that the bidder submits no bid for the Standard, only the "Alternate Bids" should be completed.
Bidders may offer an ALTERNATE for the Standard specified in the Specifications provided the bidder adheres to the following and submits same with his bid.
(a) List the proposed alternate on the BID SHEET form giving the product name and price.
(b) Furnish complete specifications and descriptive literature for the alternate as well as a one-gallon sample of the material proposed for use. Such descriptive and detailed information shall be complete and at least equal in detail to the agency’s requirements for the standard item for which the alternate is offered.
(c) Submit a current Material Safety Data Sheet for the alternate materials.
The agency will give the alternate consideration. The Contractor may furnish only those alternate items included in his proposal and approved by the agency prior to award of a contract.
(d) Furnish all required test data and use documentation as hereto for required.
If no ALTERNATE is indicated on the BID SHEET, the Contractor shall furnish the STANDARD (brand) specified in the attached specifications. Should the ALTERNATE offered be found unacceptable by the agency based on the data submitted with the bid and no bid is entered on the BID SHEET for the Standard, then said bid will be considered non-responsive.
ITB 26-PW11 28 | P a g e
APPLICATION TEMPERATURE/WEATHER LIMITATIONS
The temperature of the asphalt rejuvenating emulsion, at the time of application, shall be as recommended by the manufacturer. The asphalt-rejuvenating agent shall be applied only when the existing surface to be treated is thoroughly dry and when it is not threatening to rain. The asphalt-rejuvenating agent shall not be applied when the ambient temperature is below 40 F.
HANDLING OF ASPHALT REJUVENATING AGENT
Contents in tank cars or storage tanks shall be circulated at least forty-five minutes before withdrawing any material for application. When loading the distributor, the asphalt rejuvenating agent concentrate shall be loaded first and then the required amount of water shall be added.
The water shall be added into the distributor with enough force to cause agitation and thorough mixing of the two materials. To prevent foaming, the discharge end of the water hose or pipe shall be kept below the surface of the material in the distributor that shall be used as a spreader.
The distributor truck will be cleaned of all of its asphalt materials and washed out to the extent that no discoloration of the emulsion may be perceptible. Cleanliness of the spreading equipment shall be subject to the approval and satisfaction of the Engineer.
RESIDENT NOTIFICATION
The Contractor shall distribute by hand, a typed notice to all residences and businesses on the street to be treated. The notice will be delivered no more than 24 hours prior to the treatment of the road. The notice will have a local phone number that residents may call to ask questions.
The notice shall be of the door hanger type that secures to the door handle of each dwelling.
Unsecured notices will not be allowed. The Contractor shall also place the notice on the windshield of any parked cars on the street. Hand distribution of this notice will be considered incidental to the contract.
APPLICATING EQUIPMENT
The distributor for spreading the emulsion shall be self-propelled, and shall have pneumatic tires.
The distributor shall be designed and equipped to distribute the asphalt rejuvenating agent uniformly on variable widths of surface at readily determined and controlled rates from 0.05 to
0.5 gallons per square yard of surface, and with an allowable variation from any specified rate not to exceed 5 percent of the specified rate.
Distributor equipment…