About this file
This is an Invitation to Bid (ITB 26-040) issued by the City of Sandy Springs, Georgia for guardrail maintenance and repair services on Project T-7500. The City seeks a qualified contractor to provide all labor, materials, equipment, supervision, and incidentals for repairing and replacing guardrail at nine locations, including removal and installation of Type W beam and Type T beam guardrail, anchors, terminals, posts, offset blocks, hardware, grading, shoulder work, and site restoration in compliance with current GDOT Standard Specifications. The contract includes both base work at identified locations and an on-call guardrail repair and replacement component for future locations across the City, with work authorized only through written purchase orders or work orders. A non-mandatory pre-bid conference is scheduled for February 26, 2026 at 1:00 PM Eastern Time. Written questions are due by March 6, 2026 at 5:00 PM. Bids must be submitted online through the Bonfire Portal by March 20, 2026 at 2:00 PM EST. The selected contractor must commence work within ten calendar days of receiving the Notice to Proceed, with a required completion timeline of 270 calendar days for Substantial Completion and an additional 21 days for Final Completion. Bidders are encouraged to independently inspect the project sites to assess existing conditions.
Payment is based on unit prices specified in the bid schedule, with maintenance work quantities unknown at bid time and subject to City authorization through purchase orders reflecting actual site conditions and market conditions. The contractor must be registered with GDOT as a Qualified Routine Maintenance Contractor in the Guardrail Maintenance work class or provide documented experience installing new guardrails in compliance with GDOT standards and FHWA accepted crashworthy systems. Materials must meet GDOT Section 859 specifications from GDOT certified suppliers unless approved otherwise. A bid bond is required if the bid price exceeds $100,000, with performance and payment bonds required upon award, each in an amount equal to 100% of the total contract price. Liquidated damages are assessed at $500 per day for delays in Substantial Completion and $250 per day for delays in Final Completion beyond the 21-day punch list period. The contractor must maintain comprehensive insurance including Workers' Compensation, Commercial General Liability ($1,000,000 each occurrence/$2,000,000 aggregate), Automobile Liability ($1,000,000), and Umbrella coverage ($3,000,000). Restricted work hours prohibit lane closures during 6:00-9:00 AM and 3:30-7:00 PM without written approval, and no work is permitted on specified federal holidays without approval.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Scope of Work_Exhibit A.pdf | ||
| Vendor Responsibility Questionnaire (VRQ)_Leg.docx | DOCX document | |
| 20210226_00 Guardrail Replacement_2nd Set Fin.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION TO BID
26-040 Guardrail Maintenance and Repair Project
BID DUE DATE & OPENING March 20, 2026, 2:00 PM EST Join Teams Meeting https://teams.microsoft.com/meet/26984765960096?p=CPPGDlLaCO9buyCn2M Meeting ID: 269 847 659 600 96
Passcode: KA67Yk27
NON-MANDATORY PRE-BID CONFERENCE ATTENDANCE
Time: February 26, 2026, at 1:00 PM Eastern Time (US and Canada)
Join Teams Meeting https://events.gcc.teams.microsoft.com/event/93450431-7ae7-42aa-ba22-c94ca989d83d@c6279049-e794-4541-8247-8e8261a33321
QUESTIONS DUE
March 6, 2026, 5:00 P.M.
Bids shall only be accepted online through the Bonfire Portal at:
https://sandysprings.bonfirehub.com/projects/222160/details
Any proposal submitted in any other format (email, paper, fax, mail, etc.) will not be accepted for any reason.
GENERAL INFORMATION:
1. All communications regarding this solicitation must be with the assigned Procurement Agent, Connie Donley, cdonley@sandyspringsga.gov.
2. All questions or requests for clarification must be sent via Bonfire under Message Vendor
Discussions: https://sandysprings.bonfirehub.com/projects/222160/details Questions are due no later than March 6, 2026, 5:00 p.m. Questions received after this date and time may not be answered. There is a pre-bid meeting associated with this solicitation.
3. Questions and clarifications will be answered in the form of an addendum. Any addenda, schedule changes and other important information regarding the solicitation related to this solicitation will be posted on Bonfire website at https://sandysprings.bonfirehub.com/projects/222160/details. It is the Offeror’s responsibility to check the Bonfire portal for any addendum or other communications related to this solicitation.
4. The form of contract (“Contract”) the City intends to execute with the successful Offeror is included in this ITB. Offerors are urged to read this Contract, including exhibits carefully prior to submitting a bid. In general, the City is unable to negotiate or revise contract provisions. If an Offeror believes certain contract provisions are out of date, not applicable or place an undue burden or cost on the Offeror or the City, the Offeror must address these concerns in writing during the question-and-answer period. The Procurement Manager will review and determine the appropriate response. If the City determines a change is warranted, an addendum will be posted to this ITB. If a firm is unwilling to execute the Contract, whether modified by addendum or not, a bid should not be submitted.
5. The City of Sandy Springs reserves the right to reject all bids and to waive technicalities and informalities, and to make award in the best interest of the City of Sandy Springs.
6. The City of Sandy Springs is not responsible for any technical difficulties. It is highly recommended that all potential contractors submit their quotes prior to the due date of this solicitation.
TERMS & CONDITIONS
1. All applicable Federal and State of Georgia laws and City of Sandy Springs ordinances, licenses and regulations of all agencies having jurisdiction shall apply to Offerors throughout and are incorporated herein.
2. Professionals requiring special licenses shall be licensed in the State of Georgia, and shall be responsible for those portions of the work as may be required by law.
3. No bid shall be accepted from, and no contract will be awarded to, any person, firm, or corporation that (i) is in arrears to the City with respect to any debt, (ii) is in default with respect to any obligation to the City, or (iii) is deemed irresponsible or unreliable by the City.
4. The City shall be able to request of Offeror satisfactory evidence that it has the necessary financial resources to accomplish the requirements of the contract.
5. From the date this ITB is issued until a firm is selected, Offerors are not allowed to communicate with any staff or elected officials of the City regarding this solicitation, except at the direction of Connie Donley, Procurement Agent in charge of this solicitation. Any unauthorized contact may disqualify the Offeror from further consideration. Contact information for the single point of contact is as follows:
Connie Donley, Procurement Agent City of Sandy Springs 1 Galambos Way Sandy Springs, Georgia 30328 Email: cdonley@sandyspringsga.gov
6. All Offerors are hereby notified that any digital content, applications, websites, or technology services provided under this solicitation must comply with the accessibility standards established under the Americans with Disabilities Act (ADA) and Web Content Accessibility Guidelines (WCAG)
2.1 Level AA. Offerors must demonstrate their ability to deliver products and/or services that are accessible to individuals with disabilities, including compatibility with assistive technologies such as screen readers, keyboard navigation, and voice recognition tools.
7. While the City has every intention to make an award as a result of this solicitation, issuance of the ITB in no way constitutes a commitment by the City to award and execute a contract. Upon a determination such actions would be in its best interest, the City, in its sole discretion, reserves the right to:
a. Cancel or terminate this ITB at any time. A notice of cancellation will be issued. If the ITB is cancelled, the City will not reimburse any Offeror for preparation of its Proposal.
Proposals may be returned upon request if unopened;
b. Reject any or all Bids received, make a contract award based directly on the Proposals received in the best interest of the City, in its sole discretion, or enter into further discussions with one (1) or more Offerors;
c. Waive and/or amend any undesirable, inconsequential, or inconsistent provisions/specifications of this ITB which would not have significant impact on any Proposal;
d. Make partial award or no award if it is in the best interest of the City to do so; and
e. Terminate any contract if the City determines adequate funds are not available.
DEFINITIONS
SSPWD: Sandy Springs Public Works Department
GDOT: Georgia Department of Transportation
ADA: Americans with Disabilities Act. The federal act that gives civil rights protections to the disabled similar to those provided to individuals based on race, color, sex, national origin, age and religion. It guarantees equal opportunity for individuals with disabilities in public accommodations, employment, transportation, state and local government services and telecommunications.
CONTRACT DOCUMENTS: Contract Agreement. General Conditions, Appendices, Special Provisions, Technical Specifications, Drawings and Plans, Bidding Documents, Exhibits
FHWA: Federal Highway Administration
QRMC: Qualified Routine Maintenance Contractor
MASH: Manual for Assessing Safety Hardware
NCHRP 350: National Cooperative Highway Research Program Report 350
AASHTO: American Association of State Highway and Transportation Officials
TCP: Traffic Control Plan
EA: Each
PSI: Pounds Per Square Inch
GAL: Gallon
LF: Lineal Feet
LS: Lump Sum
SY: Square Yard
TN: Ton
OWNER: City of Sandy Springs
Contractor: The Prime Contractor for the Construction
Project. DOL: U.S. Department of Labor
MUTCD: Manual on Uniform Traffic Control Devices
SCOPE OF SERVICES
The City of Sandy Springs is seeking a qualified contractor to provide all labor, materials, equipment, supervision, and incidentals to complete Project T-7500, Guardrail Replacement and Maintenance. The base contract work includes repairing and replacing guardrail at nine locations shown on the approved construction plans, including removal and installation of Type W beam and Type T beam guardrail, anchors, terminals, and related appurtenances, plus all required posts, offset blocks, hardware, grading, shoulder work, and site restoration. All work must follow the current GDOT Standard Specifications for the Construction of Transportation Systems, as modified by the contract documents and special provisions.
The contract also includes an on-call guardrail repair and replacement component for future locations across the City, with work performed only after written City authorization through a purchase order, work order, or written directive, since locations and quantities are unknown at bid time. Maintenance work is paid using the bid unit prices in Exhibit B, with unit prices for guardrail materials and installation serving as the basis, while traffic control, grading, and other ancillary items may be adjusted on a task order basis to reflect site conditions, market conditions, and current GDOT pay items, subject to City review and approval.
Contractors must be GDOT registered as a Qualified Routine Maintenance Contractor in the Guardrail Maintenance work class or provide documented experience installing new guardrails at previously unguarded locations in compliance with GDOT standards and FHWA accepted crashworthy systems (MASH or NCHRP 350), AASHTO requirements, MUTCD traffic control, and manufacturer instructions, with the most restrictive requirement governing. Materials must meet GDOT Section 859 and come from GDOT certified suppliers unless otherwise approved, and crashworthy components must be FHWA accepted with supporting acceptance letters and installation instructions; field modifications to FHWA accepted systems are prohibited unless approved in writing by the Engineer, and the City does not inspect or verify installations, compliance is the contractor’s responsibility. Special conditions include restricted hours for lane closures (no 6:00 a.m. to 9:00 a.m. and 3:30 p.m. to 7:00 p.m. without written approval), a Traffic Control Plan due at least two weeks before work, and no work on listed holidays unless approved; bids are evaluated on pay item pricing, ability to perform, and experience and references. Bidders are strongly encouraged to independently visit and inspect the project site(s) to fully assess existing conditions and develop an accurate bid proposal. All site locations are identified in the attached plans and drawings.
The selected contractor shall be able to start work within ten (10) calendar days after the “Notice to Proceed” is issued. The time of completion for the project is two hundred seventy days (270) from the date of the “Notice to Proceed.”
Contractor shall not be permitted to work on the following federal holidays, including the day the holiday is observed by the federal government when the holiday falls on a weekend: New Year’s Day, Birthday of Martin Luther King, Jr., Washington’s Birthday (Presidents Day), Memorial Day, Juneteenth National Independence Day, Independence Day, Labor Day, Columbus Day (also recognized as Indigenous Peoples’ Day), Veterans Day, Thanksgiving Day, the Day After Thanksgiving, and Christmas Day.
BIDDING INSTRUCTIONS
Failure to submit the following bid documents may result in the bid being deemed non-responsive and the bid shall be rejected:
City Bid Form City Qualification Signature and Certification Form Bid Schedule Bid Price Certification E-verify Affidavit under O.C.G.A. 13-10-91(b)(1) Addenda Acknowledgment Certification of Sponsor Drug Free Workplace Georgia Security Immigration Compliance Act Affidavit Certificate of Insurance Notice to Contractors Compliance with Electrical Safety Provisions Affidavit verifying Status for City Public Benefit Application Corporate Certificate Sub-Contractors List Signed Contract Business License References Contractor License GDOT Prequalification (GDOT registration as a Qualified Routine Maintenance Contractor (QRMC)) Bid Bond (If Bid Price Exceeds $100,000)
Upon award of contract the following items shall also be submitted:
Performance Bond Payment Bond Certificate of Insurance Signed Contract
BID FORM
(Bidder to sign and return)
TO: PURCHASING MANAGER
CITY OF SANDY SPRINGS
SANDY SPRINGS, GEORGIA 30350
Ladies and Gentlemen:
In compliance with your Invitation To Bid, the undersigned, hereinafter termed the Bidder, proposes to enter into a Contract with the City of Sandy Springs, Georgia, to provide the necessary machinery, tools, apparatus, other means of construction, and all materials and labor specified in the Contract Documents or as necessary to complete the Work in the manner therein specified within the time specified, as therein set forth, for:
ITB 26-040 Guardrail Maintenance and Repair Project
The Bidder has carefully examined and fully understands the Contract, Specifications, and other documents hereto attached, has made a personal examination of the Site of the proposed Work, has satisfied himself as to the actual conditions and requirements of the Work, and hereby proposes and agrees that if his bid is accepted, he will contract with the City of Sandy Springs in full conformance with the Contract Documents.
Unless otherwise directed, all work performed shall be in accordance with the Georgia Department of Transportation Standard Specifications, Construction of Transportation Systems (current edition). All materials used in the process of completion of the work included in the Contract will be furnished from Georgia Department of Transportation certified suppliers only.
It is the intent of this Bid to include all items of construction, and all Work called for in the Specifications, or otherwise a part of the Contract Documents.
In accordance with the foregoing, the undersigned proposes to furnish and construct the items listed in the attached Bid schedule for the unit prices stated.
The Bidder agrees that the cost of any work performed, materials furnished, services provided, or expenses incurred, which are not specifically delineated in the Contract Documents, but which are incidental to the scope, intent, and completion of the Contract, shall be deemed to have been included in the prices bid for the various items scheduled.
The Bidder further proposes and agrees hereby to promptly commence the Work with adequate forces and equipment within ten (10) calendar days from receipt of Notice to Proceed and begin planting procedures within ninety (90) calendar days of the effective date on the Notice to Proceed.
The Bidder shall be responsible for installing and maintaining the “Best Management Practices” (BMP’s) throughout the term of the project.
If this bid shall be accepted by the City of Sandy Springs and the undersigned shall fail to execute a satisfactory contract in the form of said proposed Contract, and give satisfactory Performance and Payment Bonds, or furnish satisfactory proof of carriage of the insurance required within ten days from the date of Notice of Award of the Contract, then the City of Sandy Springs may, at its option, determine that the undersigned abandoned the Contract and there upon this bid shall be null and void, and the sum stipulated in the attached Bid Bond or certified check shall be forfeited to the City of Sandy Springs as liquidated damages.
Bidder acknowledges receipt of the following addenda:
Addendum No. Date Received
Bidder further declares that the full name and resident address of Bidder’s Principal is as follows:
Signed, sealed, and dated this day of
Bidder
Company Name
Seal
Bidder Mailing Address:
By:
Title: _
By:
Title:
QUALIFICATIONS SIGNATURE AND CERTIFICATION
(Bidder to sign and return)
I certify that this offer is made without prior understanding, agreement, or connection with any corporation, firm, or person submitting a proposal for the same materials, supplies, equipment, or services and is in all respects fair and without collusion or fraud. I understand collusive bidding is a violation of State and Federal Law and can result in fines, prison sentences, and civil damage awards. I agree to abide by all conditions of the proposal and certify that I am authorized to sign this proposal for the proposer. I further certify that the provisions of the Official Code of Georgia Annotated, Sections 45-10-20 et. seq., have not been violated and will not be violated in any respect.
Authorized Signature Date_
Print/Type Name_______________________________________________________
Email Address
Print/Type Company Name Here_
REQUEST FOR REFERENCES
INVITATION TO BID # 26-040
Guardrail Maintenance and Repair Project
All references must be from customers for whom your company has provided projects completed in the last five years of similar scope and services as the specifications of
Invitation to Bid #26-040-Guardrail Maintenance and Repair Project
References for: _______________________________________
(Company Name)
1. Company ________________________________________________________________________
Street Address ______________________________________________________________________
City, State & Zip_____ ________________________________________________________________
Contact Person Name_______________________________ Phone_____________________________
Email address________________________________________________________________________
Describe specific job performed and date: ________________________________________________
2. Company_________________________________________________________________________
Street Address _______________________________________________________________________
City, State & Zip ______________________________________________________________________
Contact Person Name________________________________ Phone____________________________
Email address________________________________________________________________________
Describe specific job performed and date: _________________________________________________
3. Company _________________________________________________________________________
Street Address _______________________________________________________________________
City, State & Zip ______________________________________________________________________
Contact Person Name ______________________________ Phone _____________________________
Email address________________________________________________________________________
Describe specific job performed and date: _________________________________________________
EXHIBIT B
BID SCHEDULE – GUARDRAIL MAINTENANCE AND REPAIR
Unit prices listed below shall apply to future maintenance and repair work authorized by the City during the three-year maintenance term.
ITEM
NO
PAY
ITEM DESCRIPTION
ESTIMATED
QUANTITY UNIT
UNIT
PRICE
TOTAL
PRICE
150-
1000 TRAFFIC CONTROL LS
165-
MAINTENANCE OF TEMPORARY SILT FENCE,
TP C 2,348 LF
171-
0030 TEMPORARY SILT FENCE TYPE C 4,692 LF
210-
0100 GRADING COMPLETE LS
441-
0106 6' CONCRETE SIDEWALK 16 SF
441-
0303 TYPE 3 SPILLWAY 3 EA
500-
3200 CLASS B CONCRETE 114 CY
500-
9999 CLASS B WIDENING 10 CY
501-
2000 STRUCTURAL STEEL 3 LS
610-
1055 REM GUARDRAIL 2,604 LF
610-
1075 REM GUARDRAIL ANCH, ALL TYPES 10 EA
611-
3000 RECONSTRUCTION CATCH BASIN 1 EA
611-
5551 RESET SIGN 23 EA
636-
1033 TYPE 2 HEADER CURB 282 LF
641-
1100 GUARDRAIL,TP T 2,187.18 LF
641-
1200 GUARDRAIL, TP W 1,625 LF
641-
5001 GUARDRAIL ANCHORAGE, TP 1 25 EA
641-
GUARDRAIL TERMINAL, TP 12A, 31 IN,
TANGENT, ENERGY-ABSORBING 11 EA
643-
1152 CHAIN LINK FENCE 100 LF
700-
9300 SOD 522 SY
21 PEDESTRIAN RAILING 107 LF
22 CONTENGENCY 1 LS 25,000
TOTAL BID PRICE
*Notes* Unit prices shall remain in effect for the full three-year maintenance term Payment shall be based on actual quantities installed and approved by the Engineer Work may only proceed with written authorization from the City.
BID PRICE CERTIFICATION
In compliance with the attached Specification, the undersigned offers and agrees that if this Bid is accepted, by the City Council within one hundred and twenty (120) days of the date of Bid opening, that he will furnish any or all of the Items upon which Prices are quoted, at the Price set opposite each Item, delivered to the designated point(s) within the time specified in the Bid Schedule.
TOTAL BID PRICE: ______________________________________________________________
TOTAL BID PRICE IN WORDS: _____________________________________________________
COMPANY: ___________________________________________________________________
ADDRESS: ____________________________________________________________________
AUTHORIZED SIGNATURE: _______________________________________________________
EMAIL ADDRESS: _______________________________________________________________
PRINT / TYPE NAME: ____________________________________________________________
SCHEDULE OF EVENTS
EVENT DATE
Advertisement February 19, 2026 Pre-bid Conference February 26, 2026, at 1:00PM EST
Deadline for Written Inquiries March 6, 2026 by 5:00PM EST Submission Due Date March 20, 2026 by 2:00PM EST
Evaluation TBD
CONTRACT
For Guardrail Maintenance and Repair Project
(“Project”)
Between
CITY OF SANDY SPRINGS, GEORGIA
(“City”) and
(“Contractor”)
ITB # 26-040
01977500-2
TABLE OF CONTENTS
ARTICLE I
THE CONTRACT AND THE CONTRACT DOCUMENTS
1.1 The Contract
1.2 The Contract Documents
1.3 Entire Agreement
1.4 Subletting, Assignment, or Transfer
1.5 No Privity with Others
1.6 Intent and Interpretation
1.7 Ownership of Contract Documents
1.8 Hierarchy of Contract Documents
ARTICLE II
THE WORK
2.1 Contractor Responsibility
2.2 “Work” Defined
2.3 Review of Work
2.4 Workday and Restrictions, Suspension and Interruption
ARTICLE III
CONTRACT TIME
3.1 Time and Liquidated Damages
3.2 Substantial Completion
3.3 Time is of the Essence
ARTICLE IV
CONTRACT PRICE
4.1 The Contract Price
ARTICLE V
PAYMENT OF THE CONTRACT PRICES
5.1 Bid Schedule
5.2 Payment Procedure
5.3 Withheld Payment
5.4 Substantial Completion and Punch List
5.5 Final Completion and Payment
ARTICLE VI
THE CITY
6.1 City Responsibility
6.2 City’s Right to Stop Work
6.3 City’s Right to Carry Out the Work
6.4 City's Right to Suspend or Interrupt the Work
ARTICLE VII
THE CONTRACTOR
7.1 Duties with Respect to Documents
7.2 Manner of Performance
7.3 Supervision
7.4 Compliance
7.5 Warranty
7.6 Permits, Inspections, Fees and Licenses
7.7 Supervision
7.8 Schedules
7.9 Contract to be Maintained at Project Site
7.10 Shop Drawings, Product Data and Samples
7.11 Cleaning the Project Site and the Project
7.12 Access to Work
7.13 Indemnity
7.14 Means, Methods, Techniques, Sequences, Procedures and Safety
7.15 Separate Contracts
7.16 Maintenance of Contract Cost Records
ARTICLE VIII
CONTRACT ADMINISTRATION
8.1 Claims by the Contractor
ARTICLE IX
SUBCONTRACTORS
9.1 Definition
9.2 Award of Subcontracts
ARTICLE X
CHANGES IN THE WORK
10.1 Changes Permitted
10.2 Change Order Defined
10.3 Field Order Define
10.4 Changes in the Contract Price
10.5 Effects of Executed Change Order
10.6 Notice to Surety; Consent
ARTICLE XI
UNCOVERING AND CORRECTING WORK
11.1 Uncovering Work
11.2 Correcting Work
11.3 City May Accept Defective or Nonconforming Work
ARTICLE XII
CONTRACT TERMINATION
12.1 Termination by the Contractor
12.2 Termination by the City
ARTICLE XIII
INSURANCE
13.1 Insurance Requirements
ARTICLE XIV
DISPUTES
14.1 Mediation
ARTICLE XV
INDEPENDENT CONTRACTOR
15.1 Relationship between Contractor and City
ARTICLE XVI
COVENANT AGAINST CONTINGENT FEES
16.1 Warranty by Contractor
ARTICLE XVII
MISCELLANEOUS
17.1 Governing Law
17.2 Successors and Assigns
17.3 Surety Bonds
17.4 Notices
EXHIBITS
EXHIBIT A SCOPE OF SERVICES
EXHIBIT B BID SCHEDULE
EXHIBIT C BID PRICE CERTIFICATION
EXHIBIT D NOTICE TO CONTRACTORS - COMPLIANCE WITH TITLE VI OF THE CIVIL RIGHTS ACT
EXHIBIT E CERTIFICATION OF SPONSOR DRUG-FREE WORKPLACE
EXHIBIT F CERTIFICATION OF CONTRACTOR GEORGIA SECURITY AND IMMIGRATION COMPLIANCE
ACT
EXHIBIT G INSURANCE REQUIREMENTS
EXHIBIT H SPECIAL PROVISIONS
EXHIBIT I NOTICE TO CONTRACTORS COMPLIANCE WITH ELECTRICAL SAFETY PROVISIONS
EXHIBIT J AFFIDAVIT VERIFYING STATUS FOR CITY PUBLIC BENEFIT APPLICATION
EXHIBIT K CONTRACTOR AFFIDAVIT UNDER O.C.G.A. § 13-10-91(b)(1)
EXHIBIT L CORPORATE CERTIFICATE
EXHIBIT M ADDENDA
EXHIBIT N SURETY BONDS
EXHIBIT O SUBCONTRACTORS
CONTRACT FOR CONSTRUCTION
THIS AGREEMENT (“the Agreement”) is made effective as of the execution date of the last party signing this Agreement by and between the City of Sandy Springs, a Georgia Municipal Corporation located 1 Galambos Way Sandy Springs, GA 30328 (“City or Owner”) and _____________________ (“Contractor”) a legal entity having a principal office address of _____________________________ and authorized to do business in the State of Georgia under seal for construction of the _______________ (hereinafter referred to as “the Project”);
WHEREAS, the Contractor desires to enter into this Agreement for construction of the Project; and
WHEREAS, the Contractor has represented to the City that it is qualified and experienced to provide such services necessary for construction of the Project; and
WHEREAS, the Contractor has represented that it will comply with all federal, state and local legal requirements imposed on or applicable to the Project.
NOW, THEREFORE, in consideration of the mutual promises and covenants contained herein, it is agreed by and between the Contractor and the City as follows:
ARTICLE I
THE CONTRACT AND THE CONTRACT DOCUMENTS
1.1 The Contract
1.1.1 The Contract between the City and the Contractor, of which this Agreement is a part, consists of the Contract Documents. The Contract shall be effective on the date indicated in the introductory paragraph hereof.
1.2 The Contract Documents
1.2.1 The Contract Documents consist of this Agreement, General Conditions, Special Provisions as attached hereto as EXHIBIT H – SPECIAL PROVISIONS, the Specifications, the Drawings, Bidding Documents, all Change Orders and Field Orders issued hereafter, the base bid made by the Contractor in response to the City’s Invitation for Bid No. 26-040 (“Bid”), and any other amendments hereto executed by the parties hereafter, together with the following (if any):
Documents not enumerated in this Paragraph 1.2 are not Contract Documents and do not form a part of this Contract.
1.3 Entire Agreement
1.3.1 The Contract constitutes the entire and exclusive agreement between the City and the Contractor with reference to the Project. The Contract may be modified only by written Change Order or Field Order issued in accordance herewith. No oral representations or conduct by the Owner or any of its representatives, employees or agents shall be sufficient to modify the terms of the Contract.
1.4 Subletting, Assignment, or Transfer
1.4.1 It is understood by the parties to this Contract that the Work of the Contractor is considered personal by the City. The Contractor agrees not to assign, sublet, or transfer any or all of its interest in this Contract without prior written approval of the City.
1.4.2 The City reserves the right to review all subcontracts prepared in connection with the Contract, and the Contractor agrees that it shall submit to the City proposed subcontract documents together with Subcontractor cost estimates for the City’s review and written concurrence in advance of their execution.
1.4.3 All subcontracts entered into by the Contractor for performance of Work under the Contract shall include or incorporate the provisions set forth in this Contract in their entirety.
1.5 No Privity with Others
1.5.1 Nothing contained in this Contract shall create, or be interpreted to create, privity or any other contractual agreement between the City and any person or entity other than the Contractor.
1.6 Intent and Interpretation
1.6.1 The intent of this Contract is to require complete, correct and timely execution of the Work.
Any Work that may be required, implied or inferred by the Contract Documents, or any one (1) or more of them, as necessary to produce the intended result shall be provided by the Contractor for the Contract Price, as hereinafter defined.
1.6.2 This Contract is intended to be an integral whole and shall be interpreted as internally consistent. What is required by any one (1) Contract Document shall be considered as required by the Contract.
1.6.3 When a word, term or phrase is used in this Contract, it shall be interpreted or construed, first, as defined herein; second, if not defined, according to its generally accepted meaning in the construction industry; and third, if there is no generally accepted meaning in the construction industry, according to its common and customary usage.
1.6.4 The words include, includes, or including, as used in this Contract, shall be deemed to be followed by the phrase, without limitation.
1.6.5 The specification herein of any act, failure, refusal, omission, event, occurrence or condition as constituting a material breach of this Contract shall not imply that any other, non-specified act, failure, refusal, omission, event, occurrence or condition shall be deemed not to constitute a material breach of this Contract.
1.6.6 Words or terms used as nouns in this Contract shall be inclusive of their singular and plural forms, unless the context of their usage clearly requires a contrary meaning.
1.6.7 The Contractor shall have a continuing duty to read, carefully study and compare each of the Contract Documents, the shop drawings and the product data and shall give written notice to the City of any inconsistency, ambiguity, error or omission which the Contractor may discover with respect to these documents before proceeding with the Work or any part thereof. The issuance or the express or implied approval by the City of the Contract Documents, shop drawings or product data shall not relieve the Contractor of the continuing duties imposed hereby, nor shall any such approval be evidence of the Contractor’s compliance with this Contract. THE CITY MAKES NO REPRESENTATION
OR WARRANTY OF ANY NATURE WHATSOEVER TO THE CONTRACTOR CONCERNING THE DOCUMENTS
FOR THE PROJECT, INCLUDING THE DRAWINGS AND SPECIFICATIONS FOR THE PROJECT. By the execution hereof, the Contractor acknowledges and represents that it has received, reviewed and carefully examined such documents, has found them to be complete, accurate, adequate, consistent, coordinated and sufficient for construction, and that the Contractor has not, does not, and will not rely upon any representation or warranties by the City concerning such documents as no such representation or warranties have been or are hereby made.
1.6.8 Neither the organization of any of the Contract Documents into divisions, sections, paragraphs, articles, (or other categories), nor the organization or arrangement of the design, shall control the Contractor in dividing the Work or in establishing the extent or scope of the Work to be performed by Subcontractors.
1.7 Ownership of Contract Documents
1.7.1 The Contractor may be provided, have access to or become aware of the City’s Confidential Information including the City’s strategic plans, employee data, customer data and other technical and business information of the City (collectively referred to as the “Confidential Information”). The term Confidential Information includes the deliverables as well as all information generated by the Contractor that contains, references or is derived from the Confidential Information and the Services including, without limitation, the Contractor’s summaries, analysis, extracts, working papers and notes relating to the Services and the Deliverables (referred to as the “Working Papers”). The Contractor agrees not to disclose the Confidential Information to third parties without the prior written approval of the City and not to make use of the Confidential Information other than as needed to perform the Services. The Contractor further agrees that it will only disclose the Confidential Information to its personnel on a need-to-know basis solely for the performance of the Services and will protect the Confidential Information with the same degree of care that the Contractor uses to protect its own confidential information, but no less than reasonable care or as the various laws may require or impose.
All Confidential Information as well as other documents, data and information provided to the Contractor by the City is and will remain the property of the City to the extent that it was the property of the City at the time it was provided to the Contractor.
All Confidential Information shall be returned to the City by the Contractor within five (5) business days of the completion of the Services under this Contract or termination of the Contract. The Contractor will keep no copies of the Confidential Information except that the Contractor may retain one (1) copy of the Working Papers as required by law, regulation, professional standards or reasonable business practice. If requested by the City, an officer of the Contractor will certify in writing that, to the best of his/her knowledge, information and belief, all Confidential Information and all copies thereof (except for one (1) copy of the Working Papers) have been delivered to the City or destroyed.
The Contract Documents, and each of them, shall remain the property of the City. The Contractor shall have the right to keep one (1) record set of the Contract Documents upon completion of the Project;
provided, however, that in no event shall Contractor use, or permit to be used, any or all of such Contract Documents on other projects without the City’s prior written authorization.
1.8 Hierarchy of Contract Documents
1.8.1 In the event of any conflict, discrepancy, or inconsistency among any of the Contract Documents, the following hierarchy shall control: (a) as between figures given on Drawings and the scaled measurements, the figures shall govern; (b) as between large scale Drawings and small scale Drawings, the large scale shall govern; (c) as between Drawings and Specifications, the requirements of the Specifications shall govern; (d) as between this Agreement and the General Conditions, Special Provisions, the Technical Specifications, the Drawings and Plans, or Bidding Documents ,all Change Orders and Field Orders issued hereafter, the requirements of this Agreement shall govern unless specifically and expressly modified by a Change Order or Amendment to this Agreement approved by the City. As set forth hereinabove, any and all conflicts, discrepancies, or inconsistencies shall be immediately reported to the City in writing by the Contractor. If after application of the above, the conflict, discrepancy, or inconsistency cannot be resolved, the Contractor shall be obligated to perform in accordance with the most stringent requirement and/or provide the greater scope of Work as such resolution.
ARTICLE II
THE WORK
2.1 Contractor Responsibility
2.1.1 The Contractor shall perform all of the Work required, implied or reasonably inferable from, this Contract.
2.2 “Work” Defined
2.2.1 The term “Work” shall mean whatever is required of the Contractor to perform and complete its duties under this Contract, including the following: construction of the whole or a designated part of the Project; furnishing of any required surety bonds and insurance; and the provision or furnishing of all labor, supervision, services, materials, supplies, equipment, fixtures, appliances, facilities, tools, transportation, storage, power, permits, licenses, fuel, heat, light, cooling, and utilities and any other thing or service required of the Contractor to complete this Contract. The Work to be performed by the Contractor is generally described in EXHIBIT A, SCOPE OF SERVICES, attached hereto and incorporated herein.
2.3 Review of Work
2.3.1 Authorized representatives of the City, GDOT, and affected state and federal agencies may at all reasonable times have access to review and inspect the Work, activities and Contractor’s records and data prepared or collected under the terms of the Contract and any amendments thereto, including but not limited to, all reports, drawings, studies, specifications, estimates, maps, and computations, prepared by or for the City.
2.4 Workday and Restrictions, Suspension, and Interruption
2.4.1 Normal workday for the Work shall be from 8:00 A.M. to 5:00 P.M. and the normal work week shall be Monday through Friday. The City will consider extended workdays or work weeks upon written request on a case-by-case basis. The City may restrict work hours in certain locations or at certain times of the day. No work will be allowed on national holidays (i.e., Memorial Day, July 4th, Labor Day, etc.).
ARTICLE III
CONTRACT TIME
3.1 Time and Liquidated Damages
3.1.1 The Contractor shall not proceed to furnish such services, and the City shall not become obligated to pay for same until a written authorization to proceed (“Notice to Proceed”) has been sent to the Contractor from the City. The Contractor shall commence the Work no later than ten (10) days after the effective date of the Notice to Proceed and shall achieve Substantial Completion of the Work no later than 270 calendar days from the date on which the City issues the Notice to Proceed. The Contractor shall achieve Final Completion of the Work, as defined within Section 5.5. no later than twenty-one (21) days after achieving Substantial Completion. This shall constitute the Contract Time.
The Work shall be carried on continuously and expeditiously, it being understood, however, that this Contract may be extended or continued in force by the parties hereto by Change Order as provided herein.
3.1.2 The Contractor shall pay the City the liquidated damages in the amount of $500.00 per day for each and every calendar day of unexcused delay in achieving Substantial Completion beyond the date set forth herein for Substantial Completion of the Work. Any such sums due and payable hereunder by the Contractor shall be payable to the City, not as a penalty, but as liquidated damages representing a reasonable estimate of damages likely to be sustained by the City by reason of such unexcused delay, estimated at or before the time of executing this Contract. When the City reasonably believes that Substantial Completion will be inexcusably delayed, the City shall be entitled, but not required, to withhold from any amounts otherwise due the Contractor an amount then believed by the City to be adequate to recover liquidated damages applicable to such delays. If the Contractor should recovery such delay in achieving Substantial Completion, or any part thereof, for which the City has liquidated damages, the City shall promptly release to the Contractor those funds withheld, but no longer applicable, as liquidated damages.
3.2 Substantial Completion
3.2.1 Substantial Completion shall mean the stage of the Contractor’s performance under the Contract, as determined in the City’s sole and absolute discretion, when the Work is sufficiently complete allowing the newly constructed facilities to be occupied by the City and used for their intended purpose. The City and Contractor may agree to declare portions of the Work substantially complete pursuant to the conditions for issuing a Certificate of Substantial Completion as provided in Article 5, Section 5.4 and allow the City to occupy and use such portions by written agreement.
However, absent such agreement, partial use or occupancy of the Work shall not result in the Work being deemed substantially complete, and such partial use or occupancy shall not be evidence of Substantial Completion.
3.3 Time is of the Essence
3.3.1 The Contractor’s timely performance of the Work, and all limitations of time related thereto as set forth in the Contract Documents are of the essence of this Contract.
ARTICLE IV
CONTRACT PRICE
4.1 The Contract Price
4.1.1 The total Contract amount for the Project (the “Contract Price”) is (BLANK) Dollars and is set forth in detail the bid schedule (“Bid Schedule”) attached hereto as EXHIBIT B, BID SCHEDULE and incorporated herein. The Contract Price shall be certified by the Bid Price Certification (“Bid Price Certification”) attached hereto as EXHIBIT C, BID PRICE CERTIFICATION and incorporated herein.
Payment to the Contractor of the Contract Price pursuant to the Bid Schedule, as may be adjusted by Change Order in accordance with the Contract, shall be full payment for the complete scope of Work provided for in the Contract. The Contract Price shall not be modified except by Change Order as provided in this Contract.
ARTICLE V
PAYMENT OF THE CONTRACT PRICE
5.1 Bid Schedule
5.1.1 The Contractor shall invoice and be paid pursuant to the Bid Schedule contained in the Contract Documents.
5.2 Payment Procedure
5.2.1 The City shall pay the Contract Price to the Contractor as provided below.
5.2.2 Based upon the Contractor’s invoices for payment submitted to the City, the City shall make progress payments to the Contractor on account of the Contract Price.
5.2.3 On or before the 5th day of each month after commencement of the Work, the Contractor shall submit an invoice for Work satisfactorily completed pursuant to the Bid Schedule. The invoice shall be in such form and manner, and with such supporting data and content, as the City may require.
Contractor’s submission of such fully executed Contractor’s Interim Claim Waiver, shall be an express condition precedent to the City’s obligation to pay any invoice submitted by the Contractor under this Subparagraph. Therein, the Contractor may request payment for ninety percent (90%) of that portion of the Contract Price properly allocable to the Work properly provided, including labor, materials and equipment properly incorporated into the Work plus ninety percent (90%) of that portion of the Contract Price properly allocable to materials or equipment properly stored on-site (or elsewhere if approved in advance in writing by the City) for subsequent incorporation into the Work, less the total amount of previous payments received from the City. Payment for stored materials and equipment, whether such materials are stored on or off the Project site, shall be conditioned upon the Contractor’s proof satisfactory to the City, that the City has title to such materials and equipment, that such materials and equipment have been properly stored and secured, and that the Contractor has in effect proper insurance providing for the replacement of such stored materials or equipment in the event of damage or theft. Such invoice shall be signed by the Contractor and shall constitute the Contractor’s representation that the Work has progressed to the level for which payment is requested in accordance with the Contractor’s construction schedule, that the Work has been properly installed or performed in full accordance with this Contract, and that the Contractor knows of no reason why payment should not be made as requested. Thereafter, the City will review the invoice and may also review the Work at the Project Site or elsewhere to determine whether the quantity and quality of the Work is as represented in the invoice and is as required by this Contract.
The City shall make partial payments on account of the Contract Price to the Contractor within thirty
(30) days following receipt of each invoice. The amount of each partial payment shall be the amount approved for payment less such amounts of retainage for up to ten percent (10%) of the Contract Price, if any, otherwise owing by the Contractor to the City or which the City shall have the right to withhold as authorized by this Contract. The City shall not be precluded from the exercise of any of its rights as set forth in Paragraph 5.3 herein below; PROVIDED, HOWEVER, that when fifty (50) percent of the Contract Price, including Change Orders and other additions to the Contract Price, provided for by the Contract Documents is due, and the manner of completion of the Work and its progress are reasonably satisfactory to the City, the City shall withhold no more retainage. At the discretion of the City, and with the approval of the Contractor, the retainage of any Subcontractor may be released separately as the Subcontractor completes its Work. If, however, after discontinuing the retention, the City determines that the Work is unsatisfactory or has fallen behind schedule, retention may be resumed at the previous level. If retention is resumed by the City, the Contractor and Subcontractors shall be entitled to resume withholding retainage accordingly. The rights of the City set forth herein to withhold retainage are in addition to all of the other rights and remedies of the City set forth in this Contract.
5.2.4 The Contractor warrants that upon submittal of an invoice, all Work for which payments have been received from the City shall be free and clear of liens, claims, security interest or other encumbrances in favor of the Contractor or any other person or entity whatsoever.
5.2.5 The Contractor shall promptly pay each Subcontractor out of the amount paid to the Contractor on account of such Subcontractor’s Work, the amount to which such Subcontractor is entitled. In the event the City becomes informed that the Contractor has not paid a Subcontractor as herein provided, the City shall have the right, but not the duty, to issue future checks in payment to the Contractor of amounts otherwise due hereunder naming the Contractor and such Subcontractor as joint payees. Such joint check procedure, if employed by the City, shall create no rights in favor of any person or entity, including the payees named on any joint check, and shall not be deemed to commit the City to repeat the procedure in the future.
5.2.6 No progress payment, nor any use or occupancy of the Project by the City, shall be interpreted to constitute an acceptance of any Work not in strict accordance with this Contract.
5.3 Withheld Payment
5.3.1 The City may refuse to make any payment, may withhold payment of any funds, and, if necessary, may demand the return of some or all of the amounts previously paid to the Contractor, to protect the City from loss because of:
(a) defective Work not remedied by the Contractor or, in the opinion of the City, unlikely to be remedied by the Contractor;
(b) claims of third parties against the City or the City’s property;
(c) failure by the Contractor to pay Subcontractors or others in a prompt and proper fashion;
(d) evidence that the balance of the Work cannot be completed in accordance with the Contract for the unpaid balance of the Contract Price;
(e) evidence that the Work will not be completed in the time required for Substantial
Completion or final completion;
(f) Contractor’s persistent failure to carry out the Work in accordance with the Contract;
(g) damage to the City or a third party to whom the City is, or may be, liable.
In the event that the City makes written demand upon the Contractor for amounts previously paid by the City as contemplated in this Subparagraph 5.3.1, the Contractor shall promptly comply with such demand.
5.4 Substantial Completion and Punch List
5.4.1 When the Contractor believes that the Work is substantially complete, the Contractor shall so notify the City in writing. Upon receipt of Contractor’s notice, the City shall conduct an inspection of the Work to determine whether the Contractor has achieved Substantial Completion. If the City finds that the Contractor has failed to achieve Substantial Completion, the City shall provide Contractor written notice describing the reasons for the City’s decision. In such event, Contractor shall address the matters set forth in the City’s notice and, once fully addressed, again provide notice to the City as provided herein. If the City deems the Work is substantially complete, the City shall prepare and the parties shall execute a Certificate of Substantial Completion affixing the date of Substantial Completion and establishing the obligations of the Contractor and City after such date. The Contractor and the City shall inspect the Work and attach to the Certificate of Substantial Completion a list of items to be completed or corrected (the “Punch List”). The Contractor shall complete all items on the Punch List within twenty-one (21) calendar days from the date of issuance of the Punch List by the City.
5.4.2 Upon the City’s determination that Contractor has achieved Substantial Completion and the issuance of the Certificate of Substantial Completion, including attaching the Punch List, the City shall pay the Contractor an amount sufficient to increase total payments to the Contractor to one hundred percent (100%) of the Contract Price less an amount, to be determined in the sole discretion of the City, equal to two hundred percent (200%) of the reasonable value of the cost to complete the Punch List, to complete any and all incomplete Work, to correct and bringing into conformance any and all defective or nonconforming Work, and to resolve or settle all unsettled claims.
5.5 Final Completion and Payment
5.5.1 When Contractor has completed all items on the Punchlist, including completing all incomplete Work and correcting all defective or nonconforming Work and the Work is in full compliance with the Contract, the Contractor shall provide the City written notice thereof. Upon receipt of Contractor’s notice, the City shall conduct an inspection of the Work to determine whether the Contractor has completed such items. If the City finds that the Contractor has failed to complete such items the City shall provide Contractor written notice describing the reasons for the City’s decision. In such event, Contractor shall address the matters set forth in the City’s notice and, once fully addressed, again provide notice to the City as provided herein. If the City finds the Contractor has completed all items on the Punchlist, including completing all incomplete Work and correcting all defective or nonconforming Work and that the Work is in full compliance with the Contract, the City shall declare Final Completion of the Work. Thereupon, the Contractor will submit its final invoice for the payments withheld as provided in Subparagraph 5.4.2 and the City shall make final payment to the Contractor as provided for herein, provided however, the City may retain liquidated damages as provided in Subparagraph 5.5.2 and a reasonable amount, which shall be determined in its sole and absolute discretion, as may be required to resolve or settle any unsettled claims. Guarantees required by the Contract shall commence on the date of final completion of the Work.
5.5.1.1 If the Contractor fails to achieve Final Completion of the Work within twenty-one (21) days after receiving the Punch List in Subparagraph 5.4.1, the Contractor shall pay the City liquidated damages in the amount of $250.00 per day…