ITB_26_001 Addendum 2 Final.pdf
PDF 281 KB Posted
- Solicitation number
- PE-66098-NONST-2026-000000096
- Issued by
- Fulton County, Georgia
About this file
This is Addendum Number 2 to Invitation to Bid (ITB) 26-001 issued by the City of Sandy Springs, Georgia, for the Path 400 Trail Extension (Windsor Parkway to North of Baroque Circle, Phase II). The project encompasses construction of a 12-foot-wide concrete shared-use path paralleling SR400, including retaining walls, soil nail walls, noise barriers, storm drain infrastructure, and landscape installation. The project contains multiple bid schedule items including field office setup, various classifications of pipe materials, storm drain installations, and MSE (mechanically stabilized earth) wall construction with anti-graffiti coating requirements. Responses are due October 6, 2025, at 1:00 p.m. The anticipated Notice to Proceed (NTP) date is summer 2026, pending GDOT approval, with a project completion timeline of 1,095 days. All work must comply with current GDOT Standard Specifications for Construction of Transportation Systems and Special Provisions, with materials sourced exclusively from GDOT-certified suppliers.
The addendum addresses 29 bidder questions and clarifications regarding specifications, material selections, wall design standards, utility conflicts, and project requirements. Key revisions to the bid schedule include a new line item for Field Engineer's Office (Item 153-1300), quantity changes for 18-inch storm drain pipe Class III (Item 550-5180), and a new line item for 18-inch storm drain pipe Class V (Item 550-5183). The contractor bears responsibility for obtaining Georgia EPD-related permits, following NOI/NOT requirements, completing landscape maintenance per GDOT specifications, and coordinating tie-ins with the adjacent Segment 3 contractor. Performance and payment bonds are required. The city confirmed that landscape architecture services are not included in the construction contract, and prime contractors do not require subcontractor GDOT registration at bid submission, though such approval is mandatory post-award. Supporting documents including retaining wall foundation investigation reports, utility adjustment schedules, and revised bid tables are available via SharePoint link.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum Number 2
Invitation to Bid (“ITB”) 26-001
Path 400 Trail Extension (Windsor Parkway to N of Baroque Circle - Phase II)
COMPLETE THIS ADDENDUM, SIGN and SUBMIT with the ITB
RESPONSE DUE DATE: October 6, 2025, 1:00 p.m.
To All Prospective Offerors: In reference to the ITB listed above, the following answers to questions, additions, deletions, and change are hereby incorporated into the ITB:
**Questions**
Number Question Response
1. Would it be possible for the City to share the soil survey report?
WFIs have been provided in Bonfire for information only.
2. Could the City provide the Utility Adjustment Schedule for our reference?
Yes, see AT&T utility schedule attached.
3. Are plans sheets missing from the set that would the additional 6" concrete trail? The amount shown in the pay item is much more that what is shown on the plans given.
No plan sheets are missing. The 6” concrete trail paving quantity also includes areas of paved shoulder adjacent to the trail.
4. Are there any irrigation requirements for this project?
Irrigation requirements are per GDOT specifications.
5. The sheets for Walls 8, 9, 10, 11 and 13A show a table detailing the minimum lengths of soil reinforcements for given stations along the wall. The table shows a design height with it's associated minim reinforcement length. For design heights that are shorter, can we maintain the same ratio of design height to length, or would the city like the supplier to use the same minimum strip length for all intermediate design heights?
For example, Wall 8 shows a design height of 21.99 feet, with a reinforcement length of 29 feet. This is height to length (B/H) ratio of 1.32.
For a design height within the same region of 14 feet, does the city intend
The walls should be bid as shown in the plans. The successful bidder may provide the owner with alternates for consideration after award.
to still want to use 29 feet or can the designer use 14 x 1.32 = 19 feet.
6. The plans call for a Sierra Drystack form liner finish Pattern #17933. On previous phase of this project, the city allowed the use of the Custom Rock #2208 Travis Drystack pattern.
I assume this pattern can be used for this phase also to maintain consistency.
The walls should be bid as shown in the plans. The successful bidder may provide the owner with alternates for consideration after award.
7. Will the use of precast fascia panels be allowed for the soil nail walls?
The use of the precast facing panels will maintain a constant aesthetic between the MSE walls and the soil nail walls.
Yes.
8. What is the anticipated NTP date for the project?
The City cannot give NTP to the selected contractor until we receive NTP from GDOT. It is estimated that the City will receive NTP from GDOT in summer 2026.
9. Are there any specifications for this project? Or any other specifications for the sound barriers?
Standard GDOT Specs are to be used. Special Provisions are provided in Bonfire.
10. Do the prime general contractors need to have their subcontractors provide a GDOT Number in order to provide a bid for this project?
Prime general contractors do not need their subcontractors to provide a GDOT Number in order to submit a bid for the project. The requirement for subcontractor approval, including GDOT registration, applies only after the project is awarded.
11. Can we get a CAD file for this project for earthwork calc?
A CAD file will be provided to the selected contractor.
12. Does this bid opportunity include Landscape Architecture Services?
(it’s listed).
Landscape Architecture Services are not part of this construction contract.
13. Can you please tell us when tree installation will begin? With days to complete project at 1,095, we need to confirm with its growing season.
Please refer to GDOT specs for appropriate planting dates.
14. Since the GDOT letting is scheduled for September 19th, could the City please extend the due date for this project by one week to allow sufficient time for analysis and an accurate bid?
The City has extended the due date to October 6, 2025.
15. Is the contractor solely responsible for completing this form, or does it also need to be filled out by subcontractors and vendors?
The prime contractor is solely responsible for completing and submitting the forms to GDOT.
Subcontractors and vendors may need to fill in their own details and sign supporting affidavits, but these are routed through the prime, not submitted separately.
16. Construction for Segment 2 (and corresponding cross section data)
Wall 13BB and S-2 barrier full length quantities are included in the SOV (beyond Station 314+00). The ends at STA. 314+00, but there are portions of work shown in the plans that extend beyond this point.
Specifically, Wall 13BB does not end until STA. 314+23.53, and the Type S-2 barrier does not end until STA.
314+67.32. Please advise as to how this discrepancy should be handled contractor will be allowed to work beyond 314+00 and will be required to coordinate with the contractor currently building Segment 3 for the tie-in.
17. What is the anticipated timeline from bid opening to award and Notice to Proceed (NTP) for PATH 400 Segment 2?
Please see answer to 8.
18. May an office trailer/field office be added as a bid item for this project?
Yes, the bid schedule has been adjusted.
19. Do MSE wall faces require anti-graffiti coating?
Yes.
20. Is the GC responsible for post-installation landscape maintenance, If yes, what is the required duration.
Will a dedicated bid item be added for landscape maintenance?
The GC is responsible for following all GDOT specifications related to landscape installation and maintenance.
21 Will the GC be responsible for obtaining Georgia EPD-related permits?
Yes. The contractor will be responsible for filing the NOI/NOT and other documents in accordance with the GSWCC requirements.
22. Have any utility conflicts been identified along the Segment 2 corridor, If yes, will the City provide the Utility Adjustment Schedule
(UAS)?
Yes, see attached.
23. Will the City accept a GRAVIX (precast modular gravity) wall as an alternate to the specified soil nail wall?
The walls should be bid as shown in the plans. The successful bidder may provide the owner with alternates for consideration after award.
24. Note 5 under the Pipe Materials table on sheet 04-001 states that all pipes used under MSE walls, within the MSE wall backfill or within 5 feet of the MSE wall face shall be Class V concrete pipe. Can pay items for Class V RCP please be added to account for where this occurs?
Pay items have been adjusted to reflect the Class V RCP quantity.
25. There is a pay item for construction engineering inspection. Can the City please clarify what is involved with his work?
This item has been removed from the SOV.
26. Can the City please confirm the panel type for the Noise Barrier Walls? The bid item description is cut off, but the specification number 624-0450 indicates they are to be Type C.
The panel type should be Type B.
27. The MSE wall notes indicate that each wall is to have a Special Surface Coating in accordance with Special Provision 999. Can this
Special Provision 836 has been provided.
special provision please be provided?
28. Will Vibration Monitoring be required? If so, can a pay item please be added?
Please refer to contract plans. If vibration monitoring is not mentioned in the contract plans, it is not required.
29. Can the Geotechnical reports please be made available?
WFIs are available on Bonfire for information only.
**Update Bid Schedule**
BID SCHEDULE
Please be advised that the bid table for this project has been updated on Bonfire/Euna. The revisions specifically apply to the following items:
• Item 153-1300 – Field Engineer’s Office, TP 3 (New Line Item)
• Item 550-5180 – Storm Drain Pipe, 18 in, Class III (Quantity Change)
• Item 550-5183 – Storm Drain Pipe, 18 in, Class V (New Line Item)
Vendors must review the updated bid table and ensure their pricing reflects these revisions. Any bids submitted prior to this addendum may be modified and resubmitted before the project’s closing date.
**Additional Documents**
The following link below will provide additional documents for this project that were mentioned in addendum questions above.
Addendum 2 Documents
Here is a complete list of documents in the that link.
1. 0021223 SP 107.23H (Special Provision Section 107—Legal Regulations and Responsibility to the Public)
2. 0021223 SP 836 (Special Provision Section 836—Special Surface Coating for Concrete)
3. 0021223_06-0006 (Summary Quantities)
4. 0021223_06-0007(Summary Quantities)
5. 0021223_06-0011 (Summary Quantities)
6. 0021223_PATH400 Segment 2_Bid Tab (Revised)
7. AT&T Proposed Adjustment Schedule
8. PI 0015023 WFI #5 (Retaining Wall Foundation Investigation Wall 5)
9. PI 0015023 WFI #6A (Retaining Wall Foundation Investigation Wall 6A)
10. PI 0015023_WFI #8 (Retaining Wall Foundation Investigation Wall 8)
11. PI 0015023_WFI #9 (Retaining Wall Foundation Investigation Wall 9)
12. PI 0015023_WFI #10 (Retaining Wall Foundation Investigation Wall 10) https://cityofsandysprings-my.sharepoint.com/:f:/g/personal/reginald_starling_sandyspringsga_gov/EprPABS6n-dKo5e_Nn7MMS0BjdTzwG1r_SG7jcn0L0Qr8Q?e=v5HvYq
13. PI 0015023 Wall #11 (Retaining Wall Foundation Investigation Wall 11)
14. PI 0015023_WFI #12 (Retaining Wall Foundation Investigation Wall 12)
15. PI 0015023_WFI #13 (Retaining Wall Foundation Investigation Wall 13)
16. PI 0015023_WFI #13C (Retaining Wall Foundation Investigation Wall 13C)
17. PI 0015023 WFI #14 (Retaining Wall Foundation Investigation Wall 14)
18. PI 0015023 WFI #15 (Retaining Wall Foundation Investigation Wall 15)
19. PI 0015023 WFI #16 (Retaining Wall Foundation Investigation Wall 16)
20. PI 0015023 WFI #17 & 18 (Retaining Wall Foundation Investigation Wall 17 & 18)
21. PI 0015023 WFI #20 (Retaining Wall Foundation Investigation Wall 20)
I hereby acknowledge receipt of Addendum Number 2 for #26-001 Path 400 Trail Extension (Windsor
Parkway to N of Baroque Circle - Phase II) and have incorporated the changes into my response for the above-mentioned Invitation to Bid.
COMPANY NAME:
CONTACT PERSON:
ADDRESS:
CITY: _________________________________STATE: ___________ ZIP: ________________________
PHONE: ________________ FAX: _______________
EMAIL ADDRESS: ______________________________________
SIGNATURE: ____________________________________________
DATE: ______________________________________