ITB 24_03 _ Curiosity Corner Addendum 2.pdf
PDF 118 KB Posted
- Attached to
- ITB 24-03 Curiosity Corner
- Solicitation number
- PE-66790-NONST-2025-000000011
- Issued by
- Gwinnett County, Georgia
About this file
This document is an Addendum to Invitation to Bid (ITB) 24-03 for the Curiosity Corner project, issued by the City of Peachtree Corners, Georgia. The addendum provides written questions and answers related to the project, including information about required contractor qualifications, site furnishings, material testing responsibilities, limit of disturbance, necessary permits and licenses, tree removal, and parking lot striping. The original ITB 24-03 solicits bids for furnishing all labor, materials, and equipment necessary for the Curiosity Corner project in Peachtree Corners, Georgia. Bids are due by 2:00 PM ET on December 2, 2024, and must be submitted to the City's Department of Public Works.
The addendum clarifies that the contractor must be a Gwinnett County Department of Water Resources approved contractor to complete the utility work, and that the contractor is responsible for all material testing required by the specifications. It also confirms that site furnishings are not included in the contract, and provides details on the project's limit of disturbance, required permits and licenses, and tree removal requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ITB 24_03 _ Curiosity Corner Addendum 1.pdf | ||
| ITB 24_03 _ Curiosity Corner (No Exhibit).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM #2
ISSUE DATE: NOVEMBER 21, 2024
This Addendum shall become and form a part of the RFP for:
ITB 24-03 Curiosity Corner
NOTE: PLEASE REVIEW CAREFULLY. THERE MAY BE CHANGES TO THE INFOMRATION
TO BE PROVIDED. FAILURE TO ADHERE TO ANY CHANGES ADDRESSED IN THIS
ADDENDUM MAY RESULT IN DISQUALIFICATION.
In the event of a conflict between previously released information and the information contained herein, the latter shall control.
NOTE: A signed acknowledgement of this addendum (this page) MUST be attached to your SUBMITTAL for Phase I of the Statements of Qualifications.
Company Name:
Signature:
Printed Name and Title:
City of Peachtree Corners 310 Technology Parkway
Peachtree Corners, GA 30092
This Addendum, including all questions and answers, shall become and form a part of the original RFP package and shall be taken into account when preparing your proposal.
The purpose of this addendum is to present the following changes as well as provide the answers to the written questions received during the question-and-answer period of the RFP Phase as follows:
I. Written Questions and Answers:
Questions Answers
1.
Are the items in the utility plan legend from drawing C-2 included in this contract? If so, does the contractor need a Gwinnett County qualification?
Yes, all items annotated on C-2 Grading and Utility Plan are included in this contract and must be completed by a Gwinnett County Department of Water Resources approved contractor.
2.
Are the site furniture items shown on details 1 and 2 on drawing L-7 included in the contract?
No, site furnishing (dining chair and dining table) is not included in this contract and will be provided by others.
3.
Who is in charge of paying for testing? The awarded contractor is responsible for all material testing required in the specifications.
ITB 24-03 Addendum #2 November 21, 2024
4.
Please define project limit of disturbance, it is different in Erosion Control Plans and Site/Grading Plans.
The limit of disturbance lines displayed on the Erosion Control Plans shall be used as the project limits.
5.
Please confirm the permits and licenses needed per the following notes from page 81 from bid documents: “The contractor shall procure all permits and licenses, pay all charges, taxes and fees, and give all notices necessary and incidental to the due and lawful prosecution of the work”.
The contractor will be given an approved city Land Disturbance Permit, but any additional permits and licenses required to complete the project will be the responsibility of the contractor.
6.
Will the City provide a tree removal plan or confirm what trees must be removed?
The city will not provide a tree removal plan.
Contractors should plan to meet with city officials and flag selected trees to remain in the two areas delineated on sheet ES-1. In all other areas, the contractors should plan to only remove the trees necessary to complete the project, including trees in the way of sidewalks and ramps heading to the road.
7.
Please confirm if the parking lot striping is thermoplastic or paint.
Parking lot striping is thermoplastic.
8.
Please confirm if a drainage system is required for artificial turf or not. If a drainage system is required, please provide details and specifications.
A drainage system is not required for the installation of artificial turf. Artificial turf should be installed according to Detail 3 on sheet L-7.
All other terms & conditions remain unchanged.
End of Addendum #2