This document is an Invitation to Bid (ITB) issued by the Salem Area Mass Transit District (SAMTD) for the replacement of an existing vehicle lift at their Del Webb Facility in Salem, Oregon. SAMTD is soliciting bids to remove and dispose of the current OMER Vega 240/50 parallelogram lift and install a new above ground vehicle lift. The project milestones include a Notice to Proceed to the successful contractor by May 1, 2023, Substantial Completion by July 1, 2023, and Final Contract Completion by August 1, 2023. Bidders are required to submit their bids by March 27, 2023 at 4:00 PM PDT. A non-mandatory pre-bid conference will be held on March 13, 2023.
The bid documents specify the technical requirements for the new lift, including a 50,000 lb minimum lifting capacity, hot-dipped galvanized and/or stainless steel components, and weatherproof electrical connections. Bidders must provide lift literature, warranty information, and training for SAMTD staff. The contract will be awarded to the responsible bidder submitting the lowest responsive bid. There are no specific Disadvantaged Business Enterprise (DBE) requirements, but SAMTD strongly encourages DBE participation. The contract will be funded through federal sources and all applicable Federal Transit Administration (FTA) clauses are included in the bid documents.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SALEM AREA MASS TRANSIT DISTRICT (SAMTD)
Del Webb Steam Bay Lift ITB No. 23-006
SALEM AREA MASS TRANSIT DISTRICT
INVITATION TO BID
ITB 23-006
DEL WEBB STEAM BAY VEHICLE LIFT
Date Issued March 3, 2023
Pre-Bid Conference:
*Non-Mandatory*
March 13, 2023 11:00 AM PST
Crater Lake Conference Room
Requests for Questions Deadline: March 15, 2023 4:00 PM PST
Response to Questions Deadline: March 17, 2023 5:00 PM PDT
Bid Closes & Responses Due: March 27, 2023 4:00 PM PDT
Project Manager: Gregg Thompson, Maintenance Manager
Procurement Contact: Charleen McCurdy, Procurement & Contracts Analyst
Submit Bid To:
Packages must be clearly marked
“ITB 23-006 DEL WEBB STEAM BAY
VEHICLE LIFT”
Salem Area Mass Transit District 555 Court St. NE, Suite 5230 Salem, OR 97301
TABLE OF CONTENTS
ITB 23-006
SECTION NO OF PAGES
1. ITB COVER PAGE
2. TABLE OF CONTENTS ………………………………………….. 1
3. PART 1 – INSTRUCTIONS TO BIDDERS …………………….. 11
4. PART 2 – SCOPE AND SPECIFICATIONS ……………………
DRAWINGS OF CURRENT LIFT………………………………...
5. PART 3 – EXHIBITS 1-12 BID FORMS ………………………… 17
6. PART 3 – EXHIBIT 13 PRICE BID FORM ………………..…..
(ATTACHED SEPARATELY)
PART 3 – EXHIBIT 14 REFERENCES…………………………..
(ATTACHED SEPARATELY)
7. PART 4 - EVALUATION OF BIDS ………………………………. 1
8. EXHIBIT A – FTA CLAUSES…………….………………………. 24
9. EXHIBIT B - SAMPLE CONTRACT ……….…………………… 17
PART 1
INSTRUCTIONS FOR BIDDER
SALEM AREA MASS TRANSIT DISTRICT
INVITATION TO BID (ITB)
ITB No. 23-006
Issue Date: March 3, 2023 Bid Due: March 23, 2023 Time: 4:00 PM PDT
SAMTD OVERVIEW
Salem Area Mass Transit District (SAMTD) is the public transportation agency operating fixed-route, regional express, and paratransit service in the urban growth boundary of the Salem- Keizer area, as well as Marion and Polk counties. SAMTD services include Cherriots Local, Cherriots Regional, Cherriots LIFT (paratransit service), Cherriots Shop and Ride, Travel Training, and Transportation Options, which promotes additional services such as carpool and vanpool matching.
SAMTD operates 64 local buses, 43 paratransit buses (Cherriots LIFT), 15 regional buses (Cherriots Regional), and five shopper shuttles. Most SAMTD services operate seven days a week.
SAMTD Locations:
Administrative Offices General Manager, Finance, Customer Service, Marketing, Human Resources and part of the Operations Division are located at:
555 Court St N.E., Suite 5230 Salem, OR 97301
Operations, Contracted Services, and Maintenance Del Webb Facility 3140 Del Webb Ave.
Salem, OR 97301 The Del Webb facility also includes the parking area for buses not in service.
Keizer Transit Center 5860 Keizer Station Blvd., N.E.
Keizer, OR 97303
SECTION 1: INTRODUCTION
Salem Area Mass Transit District (SAMTD) dba Cherriots is soliciting Bids to provide services to remove and dispose of the current OMER Vega 240/50 parallelogram lift and existing above ground vehicle lift and install a new above ground vehicle lift in the Maintenance Shop located at SAMTD’s Del Webb facility.
Successful Bidder shall be licensed by the State of Oregon to do the work required under this contract.
Successful Bidder shall obtain and maintain in current status all applicable permits and licenses.
For Scope and Specifications for this project, please see PART 2 of this ITB.
SECTION 2: PROJECT MILESTONES
Notice To Proceed to successful contractor - May 1, 2023
Substantial Completion: - July 1, 2023 (Estimate)
Final contract completion – August 1, 2023 (Estimate
SECTION 3: INSTRUCTIONS TO BIDDER
1. A. Bid Submission Requirements
Response shall be submitted in a sealed envelope / container to the following address and clearly marked “ITB 23-006 DEL WEBB STEAM BAY VEHICLE LIFT”.
Bids must be submitted as follows:
1. One (1) original and three (3) copies of the technical response and bid documents in a sealed container. One (1) copy must be unbound for ease of photocopy reproduction.
One (1) copy of the price bid in a separate, sealed envelope marked, “Price Bid.” (See Price Bid Form Exhibit #13).
* See Item #6 below for acceptable alternative methods.
2. One (1) electronic PDF format version of the response and bid documents on a USB flash drive.
3. Digital signatures on forms are permitted.
4. Submit with a cover letter to:
Charleen McCurdy Procurement & Contracts Manager Salem Area Mass Transit District 555 Court St., NE, Suite 5230 Salem, Oregon 97301 procurement@cherriots.org mailto:procurement@cherriots.org
5. In the event of any conflicts between the hard copy and the electronic copy, the hard copy will prevail.
6. COVID-19 Considerations:
An email submission with electronic signatures submitted on or before the bid close date and time will be accepted and considered a timely response to our solicitation.
SAMTD will also accept an electronic formatted version (thumb drive preferred) of the bid documents, which are received at the SAMTD office on or before the bid close date and time, and this submission will also be accepted and considered a timely response to our solicitation.
Additionally, SAMTD will also accept hard copy Bids that are received on or before the bid close date, however an electronic formatted version is also required. Bids delivered via US Mail can continue to be sent to the address identified in the solicitation.
Bids must be received by SAMTD by 4:00 p.m., Pacific Time, March 27, 2023.
B. Accommodation For People With Disabilities - People with disabilities who wish to request special accommodation, (e.g., sign language interpreters, Braille, etc.) need to contact SAMTD seven (7) working days prior to the scheduled bid opening.
C. Exceptions / Modifications To Drawings And Specifications - Bidder may not take exception to, or modify any part of, the Drawings or Specifications.
D. Right of Rejection / Cancellation and Irregularities - SAMTD reserves the right to reject any or all Bids, or part thereof, to accept one or more items of a bid without obligation as to other items. SAMTD reserves the right to cancel this ITB / solicitation at any time without liability prior to execution of a contract by SAMTD if it is in SAMTD’s or the public's best interest and is not liable for any costs the firm incurs while preparing or presenting the bid. All Bids will become part of the public file without obligation to SAMTD. SAMTD enforces the right to wave irregularities anytime through the solicitation process.
E. Late Bids - Bids submitted or received after the date and time indicated herein shall not be accepted without a prior extension of the closing date or time by SAMTD.
Requests for extensions of the bid closing date or time may be requested prior to the deadline for receipt of Bidder questions noted above. Timely requests will be considered, but SAMTD reserves the right to extend the due date or decline to extend the due date at its sole discretion.
F. One Bid; Partial Bids – A Bidder may not submit more than one (1) Bid in response to this solicitation. No partially completed Bids will be accepted and will be rejected if not properly completed based on the solicitation guidelines.
G. Single-Bidder Responsibility - Single-Bidder responsibility is required under this ITB.
Each Bidder responding to this ITB must propose all professional services/goods and provide all materials, equipment, supplies, transportation, freight, special services, and other work described or otherwise required herein for each project task.
H. Withdrawal or Modification of Bids – Bids shall not be modified after the due date and time for Bid submittal. Bids may be withdrawn by Bidder before Bid due date and time as specified within this solicitation.
I. Requests for Clarification or Modification - All requests for clarification or modification of the ITB shall be made in accordance with PART 1, Section 3, subsection 13 of this ITB.
J. Required Forms: If a form does not apply to your business or Bid, please mark the form “Not Applicable.” Sign and date each form. Some forms may require notarization. Failure to complete all forms will result in the Bid being ruled nonresponsive. Nonresponsive Bids will not be evaluated or awarded a contract.
K. Addenda - Modifications to this ITB shall be made only by addenda to the OregonBuys site. Verbal, faxed, or e-mailed instructions, interpretations, and changes shall not serve as official expressions of SAMTD and shall not be binding. All cost adjustments or other changes resulting from said addenda shall be taken into consideration by Bidders and included in their bids. All addenda issued by SAMTD (posted to OregonBuys site) shall be acknowledged by Bidder on the Acknowledgement of Addenda form.
L. Experience and Qualifications (REQUIRED) – Bidder must demonstrate to the satisfaction of SAMTD that they possess the qualifications, experience, skill, licenses, necessary facilities, and financial resources required to perform the contract services in a satisfactory manner and within the required time.
1. Introduction or Cover Letter: Provide a brief introduction of the Bidder, and/or an introduction of all members who may be involved in the contract resulting from this ITB. Describe primary business experience of the Bidder, length of time in business, organizational structure, size, capabilities, financial ability of Bidder to fulfill obligations of resultant contract award, ownership, the location of office(s), telephone number, email address, web-address, and any other information that the Bidder deems pertinent and introductory in nature.
2. Qualifications of Bidder: The Bidder shall describe its knowledge and past project experience relevant to SAMTD’s needs as listed in the Scope and Specifications in PART 2 of this ITB, including the Bidder’s direct experience on projects of similar size, scope and complexity.
M. Ambiguity in Specifications - Bidder shall promptly notify the SAMTD Procurement
Manager at the address listed in PART 1, Section 3, subsection 1.A(4) of this ITB, of any ambiguity, inconsistency, or error that it may discover upon examination of the Bid documents within the time limits for Requests for Clarifications in Section 13.
N. DBE (Disadvantaged Business Enterprise): SAMTD has an overall agency goal of
2.49 percent for the utilization of DBEs using race neutral means. SAMTD strongly encourages and expects Bidder to pursue subcontracting, mentoring, joint venturing, teaming, and partnering opportunities with DBE firms in the ordinary course of its business/teaming strategies. Bidder are encouraged and expected to create a level playing field to the maximum practical extent, consistent with the objectives and requirements of the SAMTD DBE Program, which is based on federal regulations codified at 49 CFR Part 26. The DBE participation goal applies to the total value of the contract including the results of all pre-award negotiations and post-award change orders/modifications. SAMTD’s DBE Program and Policy may be accessed at www.Cherriots.org/en/about-us/procurement.
O. Substitution of Materials: BASE BID MUST BE BASED UPON SPECIFIED MATERIALS. Substitution of materials from those specified must be requested in accordance with the detailed requirements found in the Project Specifications. For the substitutions to be considered the Bid Form must be accompanied by an alternate price and a detailed description, with drawings and manufacturer’s written specifications as may be necessary, on a separate form which fully describes the proposed alternate methods and materials.
P. Contractor’s License Law & Bond Requirements: Bidder shall comply with, and require all of their subcontractors to comply with Federal, State, County, and City contractor’s licensing laws, and be duly registered and licensed thereunder. Bidder shall provide a performance bond and a labor and material payment bond, each in the amount of (100%) of the subcontract price unless otherwise noted in the individual Bid package.
Note: A Performance Bond and a Payment Bond is not required for this solicitation.
Q. Solicitation and Attachments – The Solicitation and any attachment or exhibit to this ITB will be incorporated into and made a part of the resulting Contract. In the event of a conflict between the provisions contained in the body of this ITB, the solicitation, and any attachment or exhibit, the terms in the body of the resulting Contract will control.
R. Waiver of Liens: The Bidder is responsible for the payment of all bills for labor and materials furnished by, or to, their subcontractors and itself. Upon presentation of the billing, subcontractor shall certify that they are submitting such lien waivers for all of their lower tier subcontractors and material suppliers that have furnished services or materials for the previous billing period. A Bond in lieu of Waivers will not be satisfactory.
S. Subcontractor’s Agreement: In submitting this Bid, the Bidder hereby agrees, if awarded a Contract, to enter into and execute SAMTD’s standard form of contract agreement.
T. Value Engineering: Base Bid MUST be based upon specified materials. SAMTD reserves the right to consider value engineering consistent with ORS 279C.340.
U. Protest: Duty to Exhaust Local Procedures. Once the Contractor exhausts SAMTD’s protest procedures, as described in applicable SAMTD Procurement Policy, the Contractor may request review from the FTA. Protests shall only be accepted from participating Bidder and must be submitted in writing and in a timely fashion, in accordance with SAMTD’s formal protest procedures. SAMTD’s formal protest procedures may be requested by contacting SAMTD Procurement by telephone at 503-588-2424.
V. Certification: By submitting its Bid, Bidder certifies that it is in compliance with the
State of Oregon statutory requirements governing registration of corporations and/or http://www.cherriots.org/en/about-us/procurement assumed business names. Further, by submitting its Bid, Bidder certifies that it is, and that its subcontractors are, in compliance with the State of Oregon statutory requirements governing registration of with the Oregon Construction Contractors Board.
2. PREPARATION OF BID
A. Bids must be:
i. Submitted on the Bid forms, or copies of forms, furnished by SAMTD, and
ii. Signed. If the Bid is made by a corporation, it shall be signed by the corporation’s authorized designee.
iii. The address of the Bidder shall be typed or printed on the Bid in the space provided.
B. Organization & Format. Bids shall be typed and submitted on 8.5 by 11 inch paper bound securely. See PART 1, Section 3, subsection 1.A.6 for alternate methods for submitting electronic files.
C. The Bid may require Bidder to submit prices for one or more items, including:
(1) lump sum bid; (2) lump sum Bid alternate prices; (3) unit prices; or (4) any combination of items (1) through (3) above.
D. SAMTD requires proposing on all items (including alternates and unit prices).
Failure to do so may disqualify the bid. If proposing on all items is not required by the specific bid package documents, Bidder should insert the words “NO BID” in the space provided for any item on which no price is to be submitted.
E. Bidder MUST comply with the requirements in the Bid Documents. Modifying the bid forms, conditioning or limiting the bid, or offering to perform work not requested by the Bid Documents may disqualify the bid.
F. Bidder must submit the most recent two (2) years of audited financial statements. This information, along with the proposal documents, will be utilized to provide SAMTD information that will lead to a financial ability to perform determination. Private companies who may not have audited financial statements, can comply with this requirement by providing the most recent two (2) years of Financial statements that may include P&L Statements, Income Statements, Balance Sheets, Tax Returns, and other company information that may help SAMTD make a financial ability to perform a resultant contract determination.
3. BASE BID
The Bidder agrees to hold all pricing for period of one-hundred twenty (120) days from the date of the bid opening.
4. ADDITIVE OR DEDUCTIVE BID ITEMS
The Bidder agrees to hold all alternate and unit prices for one-hundred twenty (120) days from the date of the bid opening.
5. SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK??
By submitting this bid, the Bidder acknowledges that it has taken steps necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost, including but not limited to: (1) conditions bearing upon transportation, handling, and storage of materials; (2) the availability of labor, material, equipment, and roadways;
(3) uncertainties of weather, river stages, tides, ground water, or similar climatic and/or physical conditions that may have impact; (4) the conformation and conditions of the ground; (5) the character of equipment and facilities needed preliminary to and during the work; (6) compliance with the project quality control program; and (7) compliance with the Bidder’s safety plan as approved by SAMTD, and all applicable Occupational Safety and Health Administration (OSHA) regulations for work performed on site.
The Bidder also acknowledges that it has satisfied itself as to character, quality, and quantity of materials or obstacles to be encountered. Any failure of the Bidder to take the actions described and acknowledged in this paragraph will not relieve the Bidder from responsibility for estimating properly the difficulty and cost of successfully performing the work.
6. BID AMOUNT
The Bidder acknowledges that the details of the specifications accurately reflect the Scope of the Work on which the Bidder is submitting its bid. Bidder should base their bid pricing amounts on the following elements:
A. All labor, material, equipment, overhead, and compensation to complete all of the work under each particular heading as shown in the Bid Documents at the time of bid.
B. Travel Costs. Any travel costs associated with the Bid shall be incorporated into the Price Bid. This includes lodging, meals, transportation, and tips. SAMTD shall not pay travel costs.
SAMTD is not subject to taxation; no federal or other taxes (excise, luxury, transportation, sales, etc.) shall be added to bid amount.
7. BID RESULTS
Following the issuance of the Notice of Intent to Award the Contract, SAMTD may provide the following information to interested parties upon request:
A. The number of Bids SAMTD received;
B. The name of the successful Bidder;
and C. The total resulting contract price, including descriptions of items, quantities, and unit prices, if practical.
SAMTD will attempt to give notice under this paragraph promptly after the Notice of Intent to Award the Contract. SAMTD’s failure to give such notice shall not be deemed to affect the validity of the resulting contract.
8. CONTRACT AWARD
A. RESPONSIVENESS OF BID
A bid will be considered responsive if it meets the following requirements:
1. Is received at the proper date and time.
2. Meets the stated requirements of the bid form.
3. Exhibits #1 - #14 under this solicitation are all completed and returned with the bid.
4. Bid is prepared and submitted in accordance with Section 3, 2 “Preparation of Bid”.
5. The Contractor is licensed/registered within the State of Oregon at the time of bid due date and is not banned from proposing by the Bureau of Labor and Industries.
6. The bid is accompanied by a bid guarantee, if required.
7. Complies with the State of Oregon and Federal requirements as applicable.
8. Demonstrated ability to comply with schedule.
9. Demonstrates performance of similar projects relative to size, schedule, etc.
10. Demonstrates the management resources and financial capacity to effect performance of the work.
B. SUCCESSFUL BIDDER
If awarded, the Contract will be awarded to the Responsible Bidder submitting the lowest, Responsive Bid. .
C. BID SELECTION PROCESS
The successful Bidder shall be selected on the basis of having submitted a responsive and responsible bid for this bid package, and meeting the other requirements established in PART 4 and the other requirements of the bid documents.
D. EFFECTIVE DATE OF THE CONTRACT
SAMTD will notify the successful Bidder and provide the successful Bidder with a written Notice of Intent to Award the Contract. The successful Bidder shall return a signed copy of the Contract as well as all other documents required to be signed or provided such as bonds, insurance certificates, etc. The Contract will only become effective when all parties sign the contract and the Bidder provides all other documents required to be signed or provided such as bonds, insurance certificates, etc. Work performed and all costs incurred prior to SAMTD signature shall be the sole responsibility of the Bidder.
E. PAYMENT AND PERFORMANCE BONDS
Not required for this solicitation
F. PROMPT PAY ACT
All Bidders must comply with the applicable Prompt Payment Act provisions, if any, if selected. Failure to do so will be considered a material breach of contract.
9. MINIMUM WAGE AND PREVAILING WAGE REQUIREMENTS
10. APPLICABILITY OF RESULTING CONTRACT
11. BID DOCUMENTS
The following documents form a part of and are included in the Bid Documents:
A. Bid Solicitation Documents Complete.
B. Scope, Drawings, and Specifications for the Project.
C. Project Schedule Milestone Dates.
12. SCHEDULE OF BID PROCEDURES
The anticipated project procurement timetable is as follows for Bid Solicitation ITB 23-
006 DEL WEBB STEAM BAY VEHICLE LIFT:
Date Issued: March 3, 2023 Pre-Bid Conference: March 13, 2023 11:00 AM PST (Pre-Bid Conference is *Non-Mandatory) Requests for Question Deadline:
March 15, 2023 4:00 PM PST
Response to Questions: March 17, 2023 5:00 PM PDT Bid Closes: March 27, 2023 4:00 PM PDT
13. QUESTIONS, CLARIFICATIONS AND CHANGES TO ITB
SAMTD reserves the right to make changes to the ITB. All changes to the ITB, prior to the receipt of Bids, shall be electronically distributed through addendum. Failure to acknowledge receipt of an addendum may cause a bid to be rejected as non-responsive.
Bidder may submit questions, request clarification, or request a change to the ITB by submitting a written request to Charleen McCurdy, Procurement & Contracts Analyst at the address set forth above in PART 1, Section 3, subsection 1.A.(4) or via email procurement@cherriots.org. The request shall specify the provision of the ITB in question, and, if a change is requested, contain an explanation for the requested change. Where applicable, the Bidder is required to provide the value of each proposed modification and a brief explanation as to why the change is requested. Value shall be defined as any cost or savings to SAMTD and the advantage to SAMTD of the proposed change.
Questions, clarification requests, and /or ITB change requests must be received by March 15, 2023 at 4:00 PM Pacific Time. SAMTD will evaluate any question or request submitted, but reserves the right to determine whether to respond or accept the requested change.
Bidder shall not rely on oral or written representations regarding this ITB unless issued in writing as an addendum by the SAMTD Procurement & Contracts Department.
mailto:procurement@cherriots.org
14. PRE-BID CONFERENCE – NON-MANDATORY
A Pre-Bid Conference will be held on March 13, 2023 at 11:00 AM via Teleconference and in-person. Suppliers who are considering proposing for this solicitation are strongly encouraged to attend. Statements made by SAMTD at the Pre-Bid conference are not binding upon SAMTD unless confirmed by written Addendum.
To attend in-person and attend a site walk through:
Salem Area Mass Transit District Del Webb Facility 3140 Del Webb Ave.
Salem, OR 97301
Location: Crater Lake Conference Room
To participate via teleconference:
To access via video:
https://meet.google.com/uoj-ddac-zbj
To access via telephone: (US)
+1 443-671-8519 PIN: 171 790 338#
15. SITE VISITATION & VIEWING
Bidders may view the site areas where work is to be performed.
Bidders may submit requests to view the site where work is to be performed. Viewing may take place between the hours of 9:00AM – 3:00PM, Monday – Friday. Bidder must have an appointment scheduled in advance. If a Bidder arrives to view the site without a prior appointment, SAMTD may not accommodate the request. To schedule an appointment to view the site please contact:
Gregg Thompson, Maintenance Manager ……………….………… 503-361-7562
END OF PART 1
PART 2
SCOPE AND SPECIFICATIONS
It is the intent of these specifications to describe the minimum acceptable requirements for obtaining a new parallelogram lift.
Remove and replace the current OMER Vega 240/50 parallelogram lift with one of similar specifications.
The current lift is flush mounted. (Ground recessed) The recessed dimensions are
32’8”L x 8’7.12””W x 15.5”D.
This lift will be used in a wet, steam rack type of environment.
Vendor will be responsible for any permits or fees.
Vendor will be responsible for the removal and disposal of the current OMER lift.
All drawings for the OMER lift are attached.
Specifications:
The proposed new lift will fit into the current recessed area without modifications or need for construction activities.
The proposed new lift will use existing electrical circuits 480vac/3ph/60hz.
The proposed lift will have:
o Minimum 50,000lb lifting capacity o Components Hot-Dipped Galvanized and/or stainless steel for outdoor or wash-bay use o A panel with a galvanized weather proof cover for the controls.
o All electrical connections weather proof.
All Bidders will provide lift literature for all equipment proposed.
Vendor will commission the lift and provide training to SAMTD staff on the operation of the lift.
Warranty and Training:
Standard 3 year warranty covering parts and labor.
Please describe and provide warranty information on item being offered.
Training shall be provided by vendor
Options:
Under Carriage light kit
Please provide any brochures or specification documents of your bid.
PART 3
BID FORMS
EXHIBITS 1-14
SALEM AREA MASS TRANSIT DISTRICT EXHIBITS
The following items must be included in your bid in order to receive consideration. Failure to complete all forms included in this package may result in your bid being ruled nonresponsive.
Nonresponsive Bids will not be considered for a contract award. Please sign and date each form and/or certification. If a form does not apply to your bid, please mark the form “Not Applicable.” Sign and date each form and/or certification.
Exhibit #1 – Bid Form
Exhibit #2 – Acknowledgement of Addenda to ITB
Exhibit #3 – Non-Collusion Affidavit
Exhibit #4 – Organizational Conflict of Interest
Exhibit #5 - DBE Participation Commitment Statement
Exhibit #6 - DBE Letter of Intent
Exhibit #7 - DBE Affidavit
Exhibit #8 - DBE Unavailable Certification
Exhibit #9 - Contractor’s Representations & Warranties Certification
Exhibit #10 - Federal Debarment & Suspension Certificate
Exhibit #11 - Certification Regarding Lobbying
Exhibit #12 – Buy America Certification
Exhibit #13 – Price Bid Form
Exhibit #14 – References
Bidder Financial Statements (Please Provide)
Bidder Sample Invoice (Please Provide)
EXHIBIT #1
BID FORM
The undersigned (“Bidder”), upon acceptance by SAMTD, agrees to furnish all labor, freight, transportation, materials, equipment, services, supplies, and other work in accordance with the INVITATION TO BID No. 23-006, entitled ”DEL WEBB STEAM BAY VEHICLE LIFT” as issued on March 3, 2023.
BIDDER: The undersigned certifies as follows:
1. That he/she has read and understands all requirements and specifications of the
Request For Quote (RFQ) (including any exhibits also posted); and
2. That he/she agrees to all requirements, specifications, terms, and conditions of the
Solicitation referenced above; and
3. That he/she will furnish the designated item(s) and/or service(s) as Proposed in the Bid; and
4. That he/she certifies under penalty of perjury that Bidder is, to the best of his/her knowledge, not in violation of any Oregon tax law; and
5. That his/her company has been certified as one of the following registered business classifications:
DBE _____ MBE ______ WBE_____ ESB _____ Veteran-Owned _____
Corporation ______ Other, identify: _________________________________
Resident Bidder (Oregon): _____ Yes _____ No
6. Federal Tax I.D. Number: ___D&B (Dun’s) Number: _____________
Firm's Name: ____________________________________________________
Firm's Address: __________________________________________________
Contact Person: _______________________ E-mail: ____________________
Authorized Signature: _________________________ Date: _______________
Telephone Number: ____________________ Fax Number: _______________
Name of Project Manager and Title ____________________________________
7. Accounts Receivable Address, if different from above:
Bidder understands and agrees that, by his/her signature, if awarded the contract for the project, he/she is entering into a contract with SAMTD that incorporates the terms and conditions of the entire Request for Quote package.
Bidder understands that this Bid constitutes a firm offer to SAMTD that cannot be withdrawn for one-hundred twenty (120) calendar days from the date of the deadline for receipt of Bids. If awarded the contract, Bidder agrees to deliver to SAMTD the required insurance certificates within ten (10) calendar days of the Notice of Award.
IMPORTANT: This form must be signed below by an authorized representative of the proposing firm, to authenticate the Bid.
Authorized Signature: ______________________________ Date: _________________
Printed Name: _________________________________________________________
Title: _________________________________________________________________
THIS FORM MUST BE SIGNED AND RETURNED WITH YOUR BID
EXHIBIT #2
ACKNOWLEDGMENT OF ADDENDA
The following form shall be completed and included in the Bid.
Failure to acknowledge receipt of all addenda may cause the Bidder to be considered nonresponsive to the solicitation. Acknowledged receipt of each addendum must be clearly established and included with the Bid.
The undersigned acknowledges receipt of the following addenda to the documents:
Addendum No. Dated
Addendum No. Dated
Addendum No. Dated
Addendum No. Dated
Addendum No. Dated
Addendum No. Dated
Addendum No. Dated
Contractor Name: ___________________________________________
Signature of Authorized Representative: _________________________
Printed Name: __________________________Date:_______________
Title/Position: ______________________________________________
EXHIBIT #3
NON-COLLUSION AFFIDAVIT
I state that I am (the sole owner) (a partner) (an officer) (an agent) of and that I am authorized to make this affidavit on behalf of my firm, and its owners, directors, and officers. I am the person responsible in my firm for the price(s) and the amount of this offer.
I state that:
1. The price(s) and amount of this offer have been arrived at independently and without consultation, communication, or agreement with any other contractor, Bidder, or potential Bidder.
2. That neither the price(s) nor the amount of this Bid, and neither the approximate prices(s) nor approximate amount of this Bid, have been disclosed to any other firm or person who is a Bidder or potential Bidder, and they will not be disclosed before the Bid opening/closing.
3. No attempt has been made or will be made to induce any firm or person to refrain from Proposing on this contract, or to submit a Bid higher than this Bid, or to submit any intentionally high or competitive Bid or other form of complementary Bid.
4. The Bid of my firm is made in good faith and not pursuant to any agreement or discussion with, or inducement from, any firm or person to submit a complementary or other form of competitive Bid.
5. , its affiliates, subsidiaries, officers, directors, and employees are not currently under investigation by any governmental agency and have not in the last four years been convicted of or found liable for any act prohibited by state or federal law in any jurisdiction, involving conspiracy or collusion with respect to Proposing on any public contract.
I state that understands and acknowledges that the above representations are material and important, and will be relied on by Salem Area Mass Transit District in awarding the contract(s) for which this Bid is submitted. I understand and my firm understands that any misstatement in this affidavit is and shall be treated as fraudulent concealment from Salem Area Mass Transit District of the true facts relating to the submission of Bids for this contract.
Signed Date ______________________
Printed Name and Title ______________________________________________
EXHIBIT #4
ORGANIZATIONAL CONFLICT OF INTEREST
AND AVOIDANCE / MITIGATION PLAN
This disclosure statement outlines potential organizational conflicts of interest, either real or apparent, which as a result of activities or relationships with other persons or entities, such person or entity:
1. Is unable or potentially unable to render impartial assistance or advice to Salem Area
Mass Transit District; or
2. Is or might be otherwise impaired in its objectivity in performing the contract work; or
3. Has an unfair competitive advantage.
SECTION I. List potential organizational conflicts of interest. An organizational conflict of interest exists where other activities, relationships, or contracts of a contractor inhibit, affect, or prevent the contractor from rendering impartial assistance or advice to SAMTD;
a contractor's objectivity in performing the contract work is or might be otherwise impaired
(e.g., a contractor assisting with a design might have a financial interest in a product or system that could be utilized in implementing that design); or a contractor has an unfair competitive advantage which might be gained through its involvement in writing, or reviewing the solicitation and contract documents, including the scope or specification except as part of a general industry review.
SECTION II of this disclosure statement describes the management plan for avoiding or neutralizing the potential Organizational Conflicts of Interest as described in SECTION I of this disclosure statement. I acknowledge that Salem Area Mass Transit District may require revisions to the management plan described in SECTION II of this disclosure statement prior to approving it, and that Salem Area Mass Transit District has the right, in its sole discretion, to limit or prohibit my involvement in the Project as a result of the potential conflicts of interest described in SECTION I of this disclosure statement.
SECTION Ia – Name of Person or Firm Potentially Conflicted
SECTION Ib – Current Project Name and Scope of Work
SECTION Ic – Future Project Name and Description of Potential Conflict of Interest
SECTION II - Plan for Managing Potential Conflicts of Interest
Signed _____________________________________ Date: _________________
Printed Name and Title __________________________________________________
DISADVANTAGED BUSINESS ENTERPRISE POLICY STATEMENT
DBE POLICY: It is the policy of the United States Department of Transportation (DOT) and Salem Area Mass Transit District (SAMTD) that minority business enterprises, as defined in 49 CFR 26, shall have an equal opportunity to participate in the performance of contracts financed in whole or part with federal funds under this agreement. Consequently, the DBE requirements of 49 CFR 26 and FTA 4220.1F, as amended, apply to this agreement.
DBE OBLIGATION: SAMTD or its Contractor agrees to ensure that minority business enterprises, as defined in 49 CFR 26, have an equal opportunity to participate in the performance of contracts and subcontracts financed in whole or in part with Federal funds provided under this agreement. SAMTD and its Contractor shall take all necessary and reasonable steps in accordance with 49 CFR 26 to ensure that disadvantaged business enterprises (DBE) have an equal opportunity to compete for and perform contracts. SAMTD and its Contractor shall not discriminate on the basis of race, color, national origin, or sex in the award and performance of DOT-assisted contracts.
DBE APPLICABILITY: This applies to all projects and contracts financed by the Federal Transit Administration (FTA) or through the Oregon Department of Transportation (ODOT) without regard to the funding source. Recipients and Contractors shall conform to all applicable civil rights laws, orders, and regulations, including Section 504 of the Rehabilitation Act of 1973. Recipients and their Contractors shall not discriminate on the basis of race, age, sex, color, religion, national origin, mental or physical handicap, political affiliation, or marital status in the award and performance of ODOT contracts.
DBE CERTIFICATION: SAMTD will accept current certifications by the State of Oregon Office of Minority, Women and Emerging Small Business Enterprise Program (OMWESB). If a completed application for DBE certification has been submitted to the Office of Minority, Women and Emerging Small Business Enterprise Program (OMWESB) as of Bid opening but has not been processed, the District may count the applicant’s participation toward achieving the DBE contract specific goal, assuming that the applicant’s certification application is approved prior to contract award. The DBE directory of certified firms is available on the Internet at:
https://oregon4biz.diversitysoftware.com/FrontEnd/VendorSearchPublic.asp?XID= 6787&TN=oregon4biz
This DBE Policy Statement shall be included in all subcontracts entered into under this contract.
GOOD FAITH EFFORTS: In addition to signing the DBE Participation Commitment Statement contained in the Bid documents, the Bidder who has not achieved the assigned goal on this project shall document the steps taken to obtain participation.
Failure to document and submit good faith efforts when the Bidder has not achieved the assigned goal shall render Bid nonresponsive. Good faith efforts may include the following:
A. Attendance at a pre-bid meeting, if any, scheduled by SAMTD to inform the DBEs of subcontracting opportunities in this contract work;
https://oregon4biz.diversitysoftware.com/FrontEnd/VendorSearchPublic.asp?XID=6787&TN=oregon4biz https://oregon4biz.diversitysoftware.com/FrontEnd/VendorSearchPublic.asp?XID=6787&TN=oregon4biz
B. Advertising in general circulation media, trade association publications, and minority-focus media at least ten (10) days before Bids or Bids are due. If ten (10) days are not available, a shorter reasonable time will be acceptable;
C. Use of the Oregon Department of Consumer & Business Services Certified DBE Directory;
D. Written notification to DBEs that their interest in the contract is solicited;
E. Efforts to select portions of the work proposed to be performed to increase the likelihood of achieving the assigned goal;
F. Efforts to negotiate for specific sub-Bids, including at a minimum:
a. The name, address, or telephone number of each DBE contacted;
b. A description of the information provided regarding the plans and specifications for the portions of the work to be performed;
c. A statement of why additional agreements were not reached;
d. Reasons for rejecting as unqualified any DBE contacted;
G. Efforts to provide assistance in obtaining any necessary bonding or insurance;
H. Efforts to use the service of banks owned and controlled by minorities or women;
I. Efforts to assist the DBE in purchasing materials and supplies; and
J. Any other affirmative action efforts
CONTRACT/SUBCONTRACT APPLICABILITY: DBE Program for Contracts Solicitation language shall require that contractors, including subcontractors, must meet all requirements of the DBE program as a matter of responsiveness.
A. Prompt Payment to Subcontractors: The prime contractor agrees to pay each subcontractor under this prime contract for satisfactory performance of its contract no later than thirty (30) days from the receipt of each payment the prime contractor receives from SAMTD. The prime contractor agrees further to return retainage payments to each subcontractor within thirty (30) days after the subcontractor’s work is satisfactorily completed. Any delay or postponement of payment from the above-referenced timeframe may occur only for good cause following written approval of SAMTD. This clause applies to both DBE and non-DBE subcontracts.
B. Contract Assurance Clause: SAMTD will ensure that the following clause is placed in every DOT-assisted contract and subcontract:
The contractor or subcontractor shall not discriminate on the basis of race, color, national origin, or sex in the performance of this contract. The contractor shall carry out applicable requirements of 49 CFR Part 26 in the award and administration of DOT-assisted contracts. Failure by the contractor to carry out these requirements is a material breach of this contract, which may result in the termination of this contract or such other remedy as the recipient deems appropriate.
EXHIBIT #5
DISADVANTAGED BUSINESS ENTERPRISE (DBE) PARTICIPATION
COMMITMENT STATEMENT
AGENCY GOAL: 2.49%
SAMTD hereby notifies all Bidders that it is the policy of SAMTD to ensure nondiscrimination on the basis of race, color, sex, or national origin in the award and administration of contracts. Bidders are urged to obtain Disadvantaged Business Enterprise (DBE) participation on this project, although there is no specific DBE contract goal for this project. Bidders are encouraged to attend any pre-Bid conferences held to better understand the project and better obtain participation of DBE contractors, as applicable.
DBE GOAL: Bid documents for all Federal Transit Administration-funded projects must contain a DBE policy statement advising Bidders that, as required by the Federal Transit Administration, SAMTD has established an overall DBE goal, and that SAMTD is required to report its DBE participation to FTA each year. As such, SAMTD is required to request information from contractors in order to fulfill its reporting responsibilities.
The Bidder's total DBE goal is the sum of the Bidder's proposed commitment to the goals for disadvantaged and women-owned firms. Bidders will calculate single goal percentages using the Bidder's proposed total dollar amount commitment to each single goal, divided by the Bidder's total amount of Bid dollars. Goals will be calculated to the nearest one-one hundredth (0.01) of a percent.
Bidders must indicate the total DBE goal they propose to achieve. Even if the assigned contract goals are 0 percent, Bidders must fill in all blanks related to the Bidder's contract goals. FAILURE TO DO SO MAY RENDER THE BID
NONRESPONSIVE.
BIDDER`S CONTRACT GOALS:
TOTAL DBE GOAL %
The Bidders shall list all DBE subcontractors and their intended function for each phase of this contract. Monetary amounts shall be included beside each subcontractor that is identified to perform work on this contract. If there is no DBE participation, please note so in the space above.
By signing this statement, the Bidder assures that Good Faith Efforts have been made to meet the goal(s) for the DBE participation specified for this contract, and accepts the DBE Policy Statement on the next page.
Bidder Name: _______________________________________________________
Signature of Authorized Representative: ___________________________________
Printed Name: _____________________________________ Date: ____________
Title/Position: ________________________________________________________
EXHIBIT #6
DBE LETTER OF INTENT
(To be completed by each DBE)
To: __________________________________________________ (Name of Prime Bidder)
The undersigned intends to perform work in connection with the above project as a DBE in the following capacity (check one):
Individual Corporation Partnership Joint Venture
The Disadvantaged Business status of the undersigned is confirmed:
(a) On the reference list of Disadvantaged Business Enterprises dated ____________, or
(b) On the attached Disadvantaged Business Enterprise Identification Statement.
The undersigned is prepared to perform the following work in connection with the above project (specify in detail the particular work items or parts thereof to be performed):
The above work will not be sublet to a non-Disadvantaged Business Enterprise at any tier. The undersigned will enter into a formal agreement for the above work with you, conditioned upon your execution of an agreement with SAMTD.
Date ___________________ ________________________________________
Name of Disadvantaged Business Enterprise
By________________________________________
EXHIBIT #7
DBE AFFIDAVIT
(To be completed by each DBE)
STATE OF _______________________________ (DATE _______________)
COUNTY OF __________________________________
The undersigned being duly sworn, deposes and says that he/she is the (Sole owner, partner, president, treasurer or ________________________ of ______________________________ and certifies that since the date other duly authorized official of a corporation) (Name of DBE) of its certification by the Oregon Department of Transportation (ODOT), *UCP or other *DOT, the certification has not been revoked nor has it expired nor has there been any change in the minority status of _______________________________.
(Name of DBE)
(Signature and Title of Person Making Affidavit)
*Certified DBE’s can be found on http://www.oregon4biz.com/How-We-Can- Help/COBID/
Sworn to before me this _______________ day of _____________________, 20_____.
(Notary Public)
Affix Seal Here:
NOTE: The Bidder must attach the DBE’s most recent certification letter or document to this affidavit.
*Please list other entity __________________________________________________ http://www.oregon4biz.com/How-We-Can-Help/COBID/ http://www.oregon4biz.com/How-We-Can-Help/COBID/
EXHIBIT #8
DBE UNAVAILABLE CERTIFICATION
To be completed by Prime Contractor:
I, ______________________________, the below named agent of ___________________, certify that I have contacted the following Disadvantaged Business Enterprise to obtain a Bid for the following work items.
Certified DBE Contractor
Work Disciplines Sought
To the best of my knowledge and belief, said Disadvantaged Business Enterprise was unavailable for work on this project, or unable to prepare a Bid for the following reason(s):
Signature: ________________________________ Date: _________________
To be completed by DBE:
_____________________________________________ was offered an opportunity to propose (Name of Disadvantaged Business Enterprise) on the above identified work on _____________________ by (Date) (Source)
The above statement is a true and accurate account of why I did not submit a Bid on this project.
(Signature of Disadvantaged Business Enterprise) (Date)
EXHIBIT #9
CONTRACTOR’S REPRESENTATIONS AND WARRANTIES
CERTIFICATION
(State of Oregon)
Contractor hereby represents and warrants to Salem Area Mass Transit District (SAMTD) that:
1. Contractor has the power and authority to enter into and perform this Contract.
2. This Contract, when executed and delivered, is a valid and binding obligation of
Contractor, enforceable in accordance with its terms.
3. Contractor (to the best of Contractor’s knowledge, after due inquiry) has never knowingly or intentionally failed to comply with:
(i) All tax laws of this state, including but not limited to ORS 305.620 and
ORS Chapters 316, 317, and 318;
(ii) Any tax provisions imposed by a political subdivision of this state that applied to Contractor, to Contractor’s property, operations, receipts, or income, or to Contractor’s performance of or compensation for any work performed by Contractor;
(iii) Any tax provisions imposed by a political subdivision of this state that applied to Contractor, or to goods, services, or property, whether tangible or intangible, provided by Contractor; and
(iv) Any rules, regulations, charter provisions, or ordinances that implemented or enforced any of the foregoing tax laws or provisions.
4. Any goods and/or services to be provided to SAMTD, in the performance of Contractor’s obligations under this Contract, shall be provided to SAMTD free and clear of any and all restrictions on or conditions of use, transfer, modification, or assignment, and shall be free and clear of any and all liens, claims, mortgages, security interests, liabilities, charges, and encumbrances of any kind.
Contractor Name: ______________________________________________
Signature of Authorized Representative: ____________________________
Printed Name: ________________________Date:____________________
Title/Position: _________________________________________________
CERTIFICATION REGARDING DEBARMENT, SUSPENSION,
INELIGIBILITY, AND VOLUNTARY EXCLUSION
Instructions for Certification
1. By signing and submitting this Bid or Bid, the prospective contractor is providing the signed certification set out below:
"Certification Regarding Debarment, Suspension, Ineligibility, and Voluntary Exclusion – Lower-Tier Covered Transaction"
(1) The prospective contractor certifies, by submission of this Bid or Bid, that neither it nor its "principals" [as defined at 49 C.F.R. § 29.105(p)] is presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from participation in this transaction by any Federal department or agency.
(2) When the prospective contractor is unable to certify to the statements in this certification, such prospective participant shall attach an explanation to this Bid or Bid.
2. The certification in this clause is a material representation of fact upon which reliance was placed when this transaction was entered into. If it is later determined that the prospective contractor knowingly rendered an erroneous certification, in addition to other remedies available to the Federal Government, Salem Area Mass Transit District (SAMTD) may pursue available remedies, including suspension and/or debarment.
3. The prospective contractor shall provide immediate written notice to SAMTD if at any time the prospective contractor learns that its certification was erroneous when submitted or has become erroneous by reason of changed circumstances.
4. The terms "covered transaction," "debarred," "suspended," "ineligible," "lower-tier covered…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .