This document is an Invitation to Bid (ITB) from the City of Miami Beach, Florida for the Dade Blvd Water Main Replacement and Gravity Sewer project on 19th Street. The project involves completely replacing an approximately 80-year-old 20-inch Ductile Iron Pipe (DIP) water main along Dade Blvd between N Michigan Ave and 23rd St, and replacing an existing 20-inch DIP water main and 8-inch gravity sewer pipe along 19th St between Alton Rd and N Michigan Ave. The bid (ITB No. 2025-487-MP) was issued on August 14, 2025, with a bid submission deadline of September 29, 2025 at 3:00 pm. A pre-bid conference is scheduled for August 28, 2025 at 3:00 pm, and site visits are planned for the same day with specific time slots for different project locations. The total project duration is 300 days for the base bid, with a potential 412 days if the alternate is selected.
The estimated budget is $5,318,661 for the City of Miami Beach portion, with an additional $1,642,999.88 potentially available from Miami Dade County through a Joint Participating Agreement (JPA), contingent on fund approval. The project will be awarded based on the lowest responsive, responsible bidder, considering factors such as the contractor's capacity, skill, performance history, and compliance with local workforce participation goals. Bidders must meet specific minimum qualifications, including being a Florida Certified Licensed Underground Utility and Excavation Contractor or having such a contractor as a subcontractor. The bid requires comprehensive insurance coverage, performance and payment bonds, and compliance with prevailing wage rates. Bidders must also submit detailed documentation of previous project experience, including water main and gravity sewer replacements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Version 2023.2.10
ITB SUMMARY
The purpose of this ITB Summary is to summarize the major terms, conditions, and requirements of the ITB. Bidders shall note that various paragraphs within these bid documents have a box ( ☐ ), which may be checked ( ☒ ). If the box is checked, the language is made a part of the bid documents, and compliance therewith is required of the Bidder; if the box is not checked, the language is not made a part of the bid documents. It is the Bidder's responsibility to become familiar with all terms, conditions, and requirements of the ITB, whether or not they are included in the ITB Summary.
Further, it is the Bidder's responsibility to make note of and account for any revisions to any portion of the ITB Summary that may result from an addendum to the ITB.
SUMMARY
ITEM NO.
ITB INFORMATION & GENERAL REQUIREMENTS
1 ITB No.: 2025-487-MP
2 ITB Title: Dade Blvd Water Main (WM) Replacement - Gravity Sewer and WM on 19th Street
3 Date of Issuance: August 14, 2025
4 Project Description & Scope of Work:
The scope of work for this project includes the complete replacement of the existing 20-inch Ductile Iron Pipe (DIP) water main along Dade Blvd. (between N Michigan Ave and 23rd St) and the replacement of the existing 20-inch DIP water main and the existing 8-inch gravity sewer pipe along 19th St.(between Alton Rd. and N Michigan Ave). The existing water main is approximately eighty years (80) old and the gravity sewer pipe was built in 1925, both were prioritized in the master plans due to the high probability and consequence of failure. City records indicate that both systems have surpassed their useful/design life and have exhibited poor performance, with a history of leaks and structural failures. As part of this project, the City is looking to improve the gravity sewer and water main infrastructure, expand the flow capacity to support anticipated growth and demands, and enhance pressure and flows in the water transmission and distribution systems.
The scope also includes a design alternative to cover the full roadway restoration cost in lieu of area trench restorarion along Dade Blvd. This project alternative was agreed between the City and Miami Dade County through a Joint Participating Agreement (JPA). The JPA will cover the cost for the construction scope that includes the milling,resurfacing and roadway base restoration along Dade Blvd. from 17th Street to 23rd Street. Miami Dade County Commission is to approve and authorize the allocation of the project funds, if available.
Therefore, this project alternative shall only be considered if MDC Commission approves the funds.
The work set forth within the Contract Documents includes the furnishing of all labor, materials, equipment, services, and incidentals necessary to complete the required work described here including all appurtenant work, complete, tested, and ready for operation, including temporary utilities and facilities as required, all surveying work for layout construction and as-builts, all in conformance with these Contract Documents and the City of Miami Beach Public Works Standards https://www.miamibeachfl.gov/city-hall/public-works/manual-standards/
5 Project Site: City of Miami Beach
• Dade Blvd. (between N Michigan Ave and 23rd St)
• 9th St. (between Alton Rd. and N Michigan Ave).
Miami Dade County JPA
• Dade Blvd. (between 17th Street and 23rd St
Estimated Budget:
City of Miami Beach
$5,318,661
Miami Dade County JPA $1,642,999.88 (Contingent upon approval of funds by Miami Dade County)
7 Procurement Contact: Name: Marie Duvivier Telephone: 305-673-7490 ext. 26695 Email: marieduvivier@miamibeachfl.gov
8 Cone of Silence: Bidders are hereby advised that pursuant to Section 2-486 of the City Code, this solicitation is under the Cone of Silence law. Communications regarding this solicitation are to be submitted in writing to the Procurement Contact named herein with a copy to the City Clerk at rafaelgranado@miamibeachfl.gov.
Reference: Section 0400, Solicitation Terms and Conditions
IMPORTANT DATES
9 Due Date & Time for Bid Submittal:
An addendum to the ITB may modify the due date. The Bidder must download all addenda.
The deadline for the submittal of bids is 3:00 pm on Monday, September 29, 2025
Join on your computer or mobile app Join the meeting now
Or call in (audio only) +1 786-636-1480 United States, Miami Phone Conference ID: 153 194 755#
Bidders are cautioned that late bids can not be submitted.
Bidders are fully responsible for assuring that bids are received by the deadline.
https://www.miamibeachfl.gov/city-hall/public-works/manual-standards/ https://www.miamibeachfl.gov/city-hall/public-works/manual-standards/ mailto:arjuyudasto@miamibeachfl.gov mailto:rafaelgranado@miamibeachfl.gov https://teams.microsoft.com/l/meetup-join/19%3ameeting_MmE1ODBjNzctMGFiNC00ZGE3LWI4YWUtODk5NWUxYmE3YTYx%40thread.v2/0?context=%7b%22Tid%22%3a%22551608f9-48f3-4871-808a-a969ec5cf48a%22%2c%22Oid%22%3a%2292707ce1-2de9-4cbe-b5f5-afd5393bcff7%22%7d
10 Pre-Bid Conference:
Pre-Bid Conference will be held.
Pre-Bid Conference is Mandatory.
A Pre-Bid Conference will not be held.
Date: Thursday, August 28, 2025 Time: 3:00 pm
Join on your computer or mobile app Join the meeting now Or call in (audio only) +1 786-636-1480 United States, Miami Phone Conference ID: 712 922 638#
Reference: Section 0100, Sub-section 6, Pre-Bid Interpretations.
11 Site Visit:
Site Visit will be held.
Site Visit is Mandatory.
Site Visit will not be held.
Date: Thursday, August 28, 2025 Location: Please see below for site visit schedule
Location Site visit hours
19th St.(between Alton Rd.
and N Michigan Ave
10:00 am
Dade Blvd. from 17th Street to 23rd Street
10:45 am
12 Last Day for Receipt of Questions:
Monday, September 15, 2025 by 5:00 pm E.T.
Questions will be allowed up to 15 days before the initial deadline for submittal of Bids. Questions must be directed to marieduvivier@miamibeachfl.gov, with a copy sent to the City Clerk rafaelgranado@miamibeachfl.gov.
Reference: Section 0100, Sub-section 6, Pre-Bid Interpretations.
https://teams.microsoft.com/l/meetup-join/19%3ameeting_YmM1OTk4MmQtMjY1NS00OGIxLTg2NjYtNjJkMDFiZTM2ODQw%40thread.v2/0?context=%7b%22Tid%22%3a%22551608f9-48f3-4871-808a-a969ec5cf48a%22%2c%22Oid%22%3a%2292707ce1-2de9-4cbe-b5f5-afd5393bcff7%22%7d mailto:marieduvivier@miamibeachfl.gov mailto:rafaelgranado@miamibeachfl.gov
PROJECT SPECIFIC INFORMATION & REQUIREMENTS
13 Minimum Requirements:
Shall apply.
Shall not apply.
Bids from bidders that do not meet the following Minimum Requirements shall be deemed non-responsive and shall not be considered.
1. Licensing Requirements. Bidder shall be State of Florida Certified Licensed Underground Utility and Excavation Contractor
OR
State of Florida Certified Licensed General Contractor, with a State of Florida Certified Licensed Underground Utility and Excavation Contractor as a subcontractor;
OR
Miami Dade County Registered Licensed General Contractor with a State of Florida Certified Licensed Underground Utility and Excavation Contractor as a subcontractor.
Submittal Requirement: Provide a copy of the licenses.
2. Previous Experience of Bidder (Firm), or its subcontractor. Bidder or subcontractor or its principal(s) must have been awarded a minimum of three (3) projects of similar scope within the last ten
(10) years, two (2) of which must be completed and one (1) may be ongoing. The cumulative experience provided by the submitted references must meet the below-defined criteria as projects of similar scope:
• Water main replacements via open cut methods to include bypass and dewatering, with a construction cost of at least $3 million dollars.
• Gravity sewer via open cut methods cost with a construction cost of at least $300,000.
Submittal Requirement: For each project, submit: 1) Owner Name, 2) Owner Contact Name, Telephone and/or Email, 3) Project Address, 4) Narrative on Scope of Services Provided (the narrative must specify whether the project included water and/or gravity sewer main replacements via open cut (yes/no), dewatering, and bypass), 5) Contract amount and completion date, as applicable.
3. Previous Experience of Bidder (Firm) Lead Project Manager. Bidder’s Lead Project Manager must have completed (with current or previous firm) at least three
(3) projects with similar scope within the last ten (10) years, two (2) of which must be successfully completed and one (1) may be ongoing. Projects of similar scope shall be defined as water and/or sewer main replacements via open cut methods with a construction cost of at least $3.0 million dollars.
Submittal Requirement: For each project, submit: 1) Owner Name, 2) Owner Contact Name, Telephone and/or Email, 3) Project Address, 4) Narrative on Scope of Services Provided (the narrative must specify whether the project included water and/or gravity sewer main replacements via open cut (yes/no), dewatering,
4. Previous Experience of Bidder (Firm) Superintendent Bidder’s Superintendent must have completed (with current or previous firm) at least three
(3) projects with similar scope within the last ten (10) years, two (2) of which must be successfully completed and one (1) may be ongoing.
Projects of similar scope shall be defined as water and/or sewer main replacements via open cut methods with a construction cost of at least $3.0 million dollars.
Submittal Requirement: For each project, submit: 1) Owner Name, 2) Owner Contact Name, Telephone and/or Email, 3) Project Address, 4) Narrative on Scope of Services Provided (the narrative must specify whether the project included water and/or gravity sewer main replacements via open cut (yes/no), dewatering, Reference: Section 0200.
14 Bid Bond Requirements:
If the requirement applies, a bid bond that is in compliance with Section 0100 must submitted.
Reference: Appendix B Bid Bond Form
Section 0100, Sub-section 8, Bid Bond.
15 Insurance:
If the requirement applies, Bidder agrees it shall fully comply with the insurance requirements in Appendix J.
Compliance with the insurance requirements shall not relieve the Contractor of its liability and obligation under this section or any other section of the agreement.
16 Contract Price:
Lump sum pricing shall apply.
Unit pricing.
As indicated, contract pricing shall be based on lump sum or unit pricing in accordance with Section 0400, Terms and Conditions of the Contract. The award shall be made in accordance with Section 0100, Instructions to Bidders subsection 10, Method of Award.
17 Alternates:
Included.
Not Included.
In determining the lowest bid, the City may consider the total base bid cost or the cost of the total base bid plus any selected alternates (as applicable). The consideration of any bid alternate (if applicable) shall be solely at the City's discretion.
If applicable, bid alternates will be detailed in the Bid Price Form, Appendix B. Determination of the award (including whether bid alternates will be included in the award) shall be made in accordance with Section 0100, Instructions to Bidders subsection 10, Method of Award.
18 Contract Time & Schedule:
Dade Blvd Water Main (Water Main) Replacement - Gravity Sewer and WM on 19th Street Days for Substantial Completion: 270 days Days for Final Completion: 30 days Total Project Duration: 300 days
WITH ALTERNATE: Dade Blvd Water Main (Water Main) Replacement - Gravity Sewer and WM on 19th Street with Alternate Days for Substantial Completion: 382 days Days for Final Completion: 30 days Total project Duration: 412 days
Project Scheduling Software Required:
Bar Chart Computerized CPM using Primavera "P6" software Modified CPM Microsoft Project
Reference: Section 0400, Terms and Conditions of the Contract.
19 Liquidated Damages:
Failure to achieve Substantial Completion: $3,813.00/day
Failure to achieve Final Completion: $3,813.00/day
Reference: Section 0400, Terms and Conditions of the Contract.
20 Minimum % of Self-Work Requirement:
Minimum % of the work Contractor will self-perform with its forces: 20 %
See Section 0400, Terms and Conditions of the Contract.
21 Performance & Payment Bond Requirements:
See Section 0400, Terms and Conditions of the Contract.
Formal Solicitations Terms and Conditions for Goods and Services
AND
General Conditions for Construction Contracts
22 Davis-Bacon Wage Rates:
If the requirement applies, Bidder agrees that it and its sub-contractors shall pay laborers and mechanics employed under the Contract no less than the prevailing wage rate, and fringe benefit payments to be used in implementation of this article shall be those last published by the United States Department of Labor in the Federal Register prior to the date of issuance of the ITB.
23 Local Workforce Participation:
Applicable to contracts in excess of $1,500,000. If the requirement applies, the Bidder agrees that it and its subcontractors shall make its good-faith, reasonable efforts to promote employment opportunities for Miami-Dade County residents by seeking to achieve a project goal of having thirty percent (30%) of all construction labor hours performed by Miami-Dade County residents. The Contractor shall also make its best reasonable efforts to promote employment opportunities for Miami Beach residents.
Refer to Section 0100, Sub-section 9, Prevailing Wage Rates & Local Workforce Participation and City Code Sec. 31-40. - Local workforce participation goals and reporting requirements for city construction contracts.
24 Prevailing Wage Rates: Applicable to contracts in excess of $1,500,000. If the requirement applies, Bidder agrees it, and its subcontractors shall pay laborers and mechanics employed under the Contract no less than the prevailing wage rate, and fringe benefit payments to be used in implementation of this article shall be those last published by the United States Department of Labor in the Federal Register prior to the date of issuance of the ITB.
Refer to Section 0100, Sub-section 9, Prevailing Wage Rates & Local Workforce Participation and City Code Sec. 31-27. - Establishment of minimum wages for city construction contracts.
25 Certified Payroll Reporting Requirement:
Pursuant to City Code Section 31-32, the Awarded Contractor must submit certified payroll records along with each payment application to allow the City to verify the wage rates paid to construction workers performing work on city projects.
All certified payroll records submitted to the City shall, at a minimum, include the name, address or zip code, labor classification, hours worked, and hourly base rate paid for each laborer, mechanic, and apprentice employed by any contractor or subcontractor on the work covered by the city construction contract.
https://library.municode.com/fl/miami_beach/codes/code_of_ordinances?nodeId=SPAGEOR_CH31PU_ARTIIILOWOPAGORERECOCO_S31-40LOWOPAGORERECOCO https://library.municode.com/fl/miami_beach/codes/code_of_ordinances?nodeId=SPAGEOR_CH31PU_ARTIICOCOINWABE_S31-27ESMIWA
26 Required Permits:
PERMITS: The CONTRACTOR shall obtain and pay for any permits that may be required for execution of the work, including but not limited to:
1. City of Miami Beach Building and Zoning Department.
2. City of Miami Beach Public Works Department
3. United States Army Corp of Engineers, if required.
4. Florida Department of Environmental Protection
(FDEP), if required.
5. South Florida Water Management District, if required.
6. Miami-Dade Department of Environmental Resources
Management (DERM), if required.
7. Miami-Dade Water and Sewer (WASD), if required.
8. If required, Miami Dade County Transportation and
Public Works: Traffic Signals and Signs Division, and
DTPW.
27 Trench Safety Act Requirements
Reference: Section 0100, Sub-section 12, Florida Trench Safety Act.
28 Art in Public Places:
This Project is subject to the Art in Public Places ("AiPP") provisions as set forth in Sections 82-561 through 82-612 of the City of Miami Beach Code, as managed by the City of Miami Beach Tourism and Culture Department. The Project or Developer, as applicable, shall transmit 2% or as amended of the Project costs for all development on City land to Art in Public Places, Tourism, and Culture Department for the implementation of the AiPP program. The Project or Developer is required to work collaboratively with the Tourism and Culture Department on the implementation of the AiPP program, including construction project coordination as required by the project, pursuant to the requirements of said program.
29 Consultant: AECOM 2 Alhambra Plaza, Suite 900 Coral Gables, Florida 33134
30 Participating Agency/Grantor:
Miami Dade County, if alternate is awarded.
SUBMITTAL REQUIREMENTS
30 Submittal Location: Bids will be submitted ELECTRONICALLY ONLY through Bidnet Direct (Government Bids Opportunities and RFP | BidNet Direct
31 Submittal Format & Requirements:
Bids are to be submitted ELECTRONICALLY ONLY, contain all information, and organized in accordance with Section 0300, including:
TAB 1: CERTIFICATION, QUESTIONNAIRE &
REQUIREMENTS AFFIDAVIT
Submit responses to Certification, Questionnaire & Requirements Affidavit (Appendix A, uploaded separately to Bidnet Direct).
TAB 2: MINIMUM QUALIFICATIONS AND
SUBMITTAL REQUIREMENTS
Submit evidence, as specifically requested in the ITB Summary, of compliance with each minimum requirement(s) of this ITB. Bidders that do not comply, or for whom the City cannot verify compliance, shall be deemed non-responsive, and its bid shall not be considered.
TAB 3: BID PRICE FORM & BID BOND
The following documents shall be submitted by the deadline for the submittal of bids:
1. Bid Price Form. (Appendix B).
2. Bid Bond Form (see Section 0100, Sub-section 8). If the requirement applies, the bid bond is a required document that shall be submitted on or before the deadline for bids.
FAILURE TO SUBMIT THE MOST
RECENTLY COMPLETED 1)
CERTIFICATION, QUESTIONNAIRE &
REQUIREMENTS AFFIDAVIT (2) BID
PRICE FORM AND 3) BID BOND BY
THE DEADLINE FOR SUBMITTAL OF
BIDS SHALL RESULT IN THE BID
BEING DEEMED NOT RESPONSIVE
AND NOT BEING FURTHER
CONSIDERED.
3. Schedule of Values (Appendix D).
MUST BE SUBMITTED WITH THE BID
OR WITHIN THREE (3) DAYS OF
REQUEST BY THE CITY.
https://www.bidnetdirect.com/
TAB 4: OTHER BID FORMS
Submit other forms if required in the ITB Summary, including but not limited to:
1. Local Workforce Participation Program Responsible Contractor Affidavit Form (Appendix E). If the ITB Summary indicates a Local Workforce Participation Program is applicable, then this form must be submitted.
2. Trench Safety Certification Form (Appendix F). If the ITB Summary indicates a Trench Safety Act is applicable, then this form must be submitted.
1.
TABLE OF CONTENTS
SOLICITATION SECTIONS:
0100 ......................................................................................... INSTRUCTIONS TO BIDDERS
0200 ........................................................................................... MINIMUM QUALIFICATIONS
0300 ............................................................................................... BID SUBMITTAL FORMAT
0400 .............................................................. TERMS & CONDITIONS (Under separate cover)
APPENDICES:
APPENDIX A ................ CERTIFICATION, QUESTIONNAIRE & REQUIREMENTS AFFIDAVIT
APPENDIX B ................................................................................................. BID PRICE FORM
APPENDIX C ................................................................................................. BID BOND FORM
APPENDIX D ....................................................................................... SCHEDULE OF VALUES
APPENDIX E .................. PREVAILING WAGES AND LOCAL WORKFORCE PARTICIPATION
APPENDIX F .......................................................... TRENCH SAFETY CERTIFICATION FORM
APPENDIX G ................................................................................................ CONTRACT FORM
APPENDIX H .................................................................... LIST OF PLANS & SPECIFICATIONS
APPENDIX I ........................................................................................... POST AWARD FORMS
APPENDIX J .............................................................................. INSURANCE REQUIREMENTS
SECTION 0100 – INSTRUCTIONS TO BIDDERS:
1. General. This Invitation to Bid (ITB) is issued by the City of Miami Beach, Florida (the "City"), as the means for prospective Bidders to submit their qualifications and bid (the "Bid") to the City for the City's consideration as an option in achieving the required scope of services and requirements as noted herein. All documents released in connection with this solicitation, including all appendixes and addenda, whether included herein or released under separate cover, comprise the solicitation and are complementary to one another and together establish the complete terms, conditions, and obligations of the Bidders and, subsequently, the successful Bidder(s) (the "contractor[s]") if this ITB results in an award.
The City utilizes Bidnet Direct (Government Bids Opportunities and RFP | BidNet Direct) for automatic notification of competitive solicitation opportunities and document fulfillment, including the issuance of any addendum to this ITB. Any prospective Bidder who has received this ITB by any means other than through Bidnet Direct must register immediately with Bidnet Direct to ensure it receives any addendum issued to this ITB. Failure to receive an addendum may result in disqualification of the proposal submitted.
2. Background and Scope of Work. The Project is described more fully in the Invitation to Bid Summary (and any exhibits referenced therein).
3. Abbreviations and Symbols. The abbreviations used throughout the Contract Documents are defined in the Technical Specifications. The symbols used in the Plans are defined therein.
4. Examination of Contract Documents and Site. It is the responsibility of each Bidder, before submitting a Bid, to:
a. Examine the Contract Documents thoroughly.
b. Visit the site or structure to become familiar with conditions that may affect costs, progress, performance, or furnishing of the Work.
c. Take into account federal, state, and local (City and Miami-Dade County) laws, regulations, permits, and ordinances that may affect costs, progress, performance, furnishing of the Work, or award.
d. Study and carefully correlate Bidder's observations with the Contract Documents.
e. Carefully review the Contract Documents and notify the City of all conflicts, errors, or discrepancies in the Contract Documents of which Bidder knows or reasonably should have known.
The submission of a Bid shall constitute an incontrovertible representation by Bidder that Bidder has complied with the above requirements and that, without exception, the Bid is premised upon performing and furnishing the Work required by the Contract Documents and that the Contract Documents are sufficient in scope and detail to indicate and convey an understanding of all terms and conditions for performance and furnishing of the Work.
5. Location of Work. This Scope of Work shall be completed at the Project Site/Location of the
Work specified in the Invitation to Bid Summary (the "Project Site").
6. Pre-Bid Interpretations. Oral information or responses to questions received by prospective
Bidders are not binding on the City. They will be without legal effect, including any information received at the pre-submittal meeting or site visit(s). The City, through Addenda, will issue https://www.bidnetdirect.com/ interpretations or written addenda clarifications considered necessary by the City in response to questions. Only questions answered by written addenda will be binding and may supersede terms noted in this solicitation. Addenda will be released through Bidnet Direct.
Any prospective bidder who has received this ITB by any means other than through Bidnet Direct must register immediately with Bidnet Direct to ensure it receives any addendum issued to this ITB. Failure to receive an addendum may result in disqualification of the bid submittal. Written questions should be received no later than the date outlined in the ITB SUMMARY section. Written questions should be received no less than fifteen (15) calendar days prior to the date of the opening of Bids. There shall be no obligation on the part of the City or the City's Procurement Director to respond to questions received less than fifteen (15) calendar days prior to bid opening.
7. Electronic Form of Bid. All bids must be made upon the blank Bid/Tender Form included herein and must give the price in strict accordance with the instructions thereon. The bid must be signed and acknowledged by the Bidder in accordance with Section 0300 and must be received on or before the deadline for the submittal of bids. Late bids will not be accepted and will not be considered. It is the Bidder's responsibility to account for any possible delay.
8. Bid Bond. If the Invitation to Bid Summary specifies that a bid bond is required, the Bidder shall submit, BY THE DEADLINE FOR SUBMITTAL OF BIDS, a bid bond, in the manner prescribed herein, in the amount of 5% of the total base bid amount, payable to City of Miami Beach, Florida, as guarantee of good faith on the part of the Bidder that, if awarded, it will enter into a contract within 30 days of notification of award. Bid bonds must be issued by a surety company authorized to conduct business in the State of Florida and carry a rating of B+ or better, as listed in the A.M. Best or equivalent rating guide.
a. Acceptable Forms of Bid Bonds. Electronic, electronic copy, paper (original or certified hard copy), or cash/check bid bonds are acceptable in the following forms only:
1. Electronic Bid Bond. Bidder may submit an electronic bid bond, provided by
Surety2000.com (verified by an eleven-digit code generated by the Surety2000 system) and provided by the Bidder with the bid. The instructions for obtaining a bid bond through Surety2000 are below.
1. Register with Surety2000 by visiting www.surety2000.com. If you have previously registered with Surety2000, you will not need to register again.
2. Verify that your Surety Broker is registered with Surety2000. If they are not, direct them to visit www.surety2000.com to register.
3. Provide your Surety Broker with the bond details for the proposal you want to bid on.
4. Once your Surety Broker has confirmed the execution of the electronic Bond, log into www.surety2000.com to digitally sign the Bond and receive the eleven-digit bond number.
5. Enter this number where indicated in the bid proposal submission.
The option to submit an electronic bid bond is provided solely for the convenience of the Bidder. The Bidder is solely responsible for ensuring that the City receives an electronic bid in the manner and by the time and date prescribed herein. The City is not responsible for any issues, technical or otherwise, relating to the use of the Surety 2000 system by a bidder. For questions regarding the Surety 2000 system, contact 1- 800-660-3263 or help@surety2000.com.
Or http://www.surety2000.com/ mailto:help@surety2000.com
2. Electronic Copy Bid Bond. Bidders may submit an electronic copy of the bid bond through Bidnet Direct, which the City must receive on or before the deadline for the submittal of bids. Failure to submit an electronic copy of the bid bond through Bidnet Direct or bid bonds received after the deadline for submittal of bids will not be acceptable and shall render the bid submittal non-responsive. The City may require the original bid bond to be submitted within three (3) days from request.
3. Paper Bid Bond. Bidder may submit an original or certified hard-copy (paper) bid bond, which the City must receive on or before the deadline for submittal of bids. Failure to submit an original or certified hard-copy (paper) bid bond or bid bonds received after the deadline for submittal of bids will not be acceptable and shall render the bid submittal non-responsive. The original or certified hard copy (paper) must be mailed to the address below by the deadline for the submittal of bids.
Attn: Procurement Department City of Miami Beach City Clerk's Office 1700 Convention Center Dr., 1st Floor Miami Beach, 33139 – 1st Floor
4. Certified or Cashier's Check. Bidder may submit a certified check or cashier's check issued by any national or state bank (United States) payable to the City of Miami Beach, Florida.
A SCANNED OR PDF COPY OR A PERSONAL CHECK OR COMPANY
CHECK OF A BIDDER SHALL NOT BE DEEMED A VALID BID BID BOND
AND SHALL NOT BE ACCEPTABLE. FAILURE TO SUBMIT A BID BOND
IN ONE OF THE ACCEPTABLE FORMS STATED ABOVE SHALL RENDER
BID NON-RESPONSIVE.
b. Forfeiture of Bid Bond. The bid bond of the successful Bidder shall be forfeited to the City of Miami Beach as liquidated damages, not as a penalty, for the cost and expense incurred should said Bidder fail to execute the Contract, provide the required Performance Bond, Payment Bond (recorded by Miami Dade County) and Certificate(s) of Insurance, within ten (10) calendar days after the Bidder's receipt of the Contract for execution, or failure to comply with any other requirements set forth herein. Bid bonds of the unsuccessful Bidders will be returned after the successful Bidder is awarded.
9. Prevailing Wage Rates & Local Workforce Participation. See ITB Bid Summary to determine if prevailing wages and local workforce participation are a requirement of this ITB.
If required, Chapter 31, Articles II and III, of the Code of City of Miami Beach requires that the rate of wages and fringe benefits, or cash equivalent, for all laborers, mechanics and apprentices employed by any contractor or subcontractor on the work covered by the Contract, shall not be less than the prevailing rate of wages and fringe benefit payments or cash equivalence for similar skills or classifications of work, as established by the Federal
Register last published by the United States Department of Labor prior to the date of issuance of this solicitation. Additionally, the Contractor will make its best reasonable efforts to promote employment opportunities for Miami-Dade County residents by seeking to achieve a project goal of having thirty percent (30%) of all construction labor hours performed by Miami-Dade County residents. The Contractor shall also make its best reasonable efforts to promote employment opportunities for Miami Beach residents. Refer to Appendix D for additional information, the submittal requirements for these programs, and the applicable prevailing wage table for the project.
10. Method of Award. On the Bid Price Form (Appendix A), the Bidder must state its Total Base Bid, which includes the cost of the base project scope requirements (inclusive of all terms, conditions, specifications, plans, and any other requirement) and the Grand Total Bid, which includes the Total Base Bid plus permit and trench safety indemnification allowances.
The Bid Price Form (Appendix A) may also include Additive Alternates, which add certain additional scope elements, and Deductive Alternates, which reduce certain scope elements. The City may consider additive or deductive bid alternates to achieve the maximum project scope within the available budget.
When bids are below the stated budget, the City may consider including one or more Additive Alternate, in the order of priority stated, in determining the lowest responsive, responsible Bidder. When bids are above the stated budget, the City may consider including one or more Deductive Alternate, in the order of priority stated, in determining the lowest responsive, responsible Bidder.
The responsive, responsible Bidder submitting the lowest sum of the Grand Total Bid plus any alternates selected by the City shall be considered the lowest responsive, responsible Bidder. When the Grand Total Bid plus any alternates selected is equal to or less than the amount established in section 2-366 of the City Code for formal bids shall be awarded by the City Manager, or designee, to the lowest responsive and responsible Bidder meeting all terms, conditions, and specifications of the ITB.
When the Grand Total Bid plus any alternates selected is in excess of the amount established in section 2-366 of the City Code for formal bids shall be awarded by the City Commission to the lowest responsive and responsible Bidder meeting all terms, conditions, and specifications of the ITB.
In addition to price, the following factors, pursuant to Section 2-369 of the City Code, shall be considered:
• The ability, capacity, and skill of the Bidder to perform the Contract.
• Whether the Bidder can perform the Contract within the time specified, without delay or interference.
• The character, integrity, reputation, judgment, experience, and efficiency of the Bidder.
• The quality of performance of previous contracts.
• The previous and existing compliance by the Bidder with laws and ordinances relating to the Contract.
The City Commission may consider the City Manager's recommendation(s) and may approve or reject the City Manager's recommendation(s). The City Commission may also reject all bids received.
The approval of the City Manager's recommendation by the City Commission shall not constitute a binding contract between the City and the selected Bidder(s). A binding contract will exist upon the complete execution and delivery of the City's Contract.
11. Contract Price. The Contract Price consists of the total base bid amount and the owner's contingency (to be used solely by the City at its sole discretion for the purpose described in that Contract Documents). The Contract Price, exclusive of the Owner's Contingency, includes, without limitation, all costs for all labor, materials, equipment, fixtures, freight, field supervision, supervisory expenses, project vehicles, field office and equipment, postage and delivery, safety and first aid, telephone, transportation of employees, parking, insurance, taxes, preparation and maintenance of the construction schedule and the preparation of as-built and shop drawings, as well as Contractor's overhead and profit required for completion of all the Work in accordance with the requirements of the Contract Documents, including work reasonably inferable therefrom, even if such items of Work are not specifically or expressly identified as part of a line item in the Bid Price Form.
12. Florida Trench Safety Act. If the work involves trench excavations that will exceed a depth of 5 feet, the requirements of Florida Statutes, Chapter 553, Part III, Trench Safety Act, will be in effect. The Bidder, by virtue of submitting a bid, certifies that such Act will be complied with during the execution of the work. The Bidder acknowledges that the total bid price includes all costs for complying with the Florida Trench Safety Act. The Trench Safety Certification Form can be found in Appendix E. If the ITB Summary indicates a Trench Safety Act is applicable, then this form must be submitted.
13. E-Verify. As a contractor, you are obligated to comply with the provisions of Section 448.095, Fla. Stat., "Employment Eligibility." Therefore, you shall utilize the U.S. Department of Homeland Security's E-Verify system to verify the employment eligibility of all new employees hired by the Contractor during the term of the Contract and shall expressly require any subcontractors performing work or providing services pursuant to the Contract to utilize the U.S. Department of Homeland Security's E-Verify system to verify the employment eligibility of all new employees hired by the subcontractor during the Contract term.
14. BIDNET DIRECT. The Procurement Department utilizes Bidnet Direct, as its electronic bidding (e-Bid) platform. If you would like to be notified of available competitive solicitations released by the City, you must register through Bidnet Direct, www.bidnetdirect.com/florida/cityofmiamibeach. Registration is easy and will only take a few minutes. For detailed instructions on registering and submitting electronic bids, visit https://www.miamibeachfl.gov/city-hall/procurement/for-approval-how-to-become-a-vendor/.
If you have any questions regarding this system or registration, please visit the link above or contact Bidnet Direct at support@Bidnet.com or 1-800-835-4603 option 2.
15. How to Manage or Create a Vendor Profile on Vendor Self-Service (VSS). In addition to registering with Bidnet Direct, the City encourages vendors to register with our online Vendor Self-Service web page, allowing City vendors to easily update contacts, attachments (W-9), and commodity information. The VSS webpage http://www.bidnetdirect.com/florida/cityofmiamibeach https://www.miamibeachfl.gov/city-hall/procurement/for-approval-how-to-become-a-vendor/ mailto:support@Bidnet.com https://selfservice.miamibeachfl.gov/vss/Vendors/default.aspx will also provide purchase orders and payment information.
Should you have any questions, please submit them to vendorsupport@miamibeachfl.gov.
16. Supplier Diversity. The City has established a registry of LGBT-owned businesses, as certified by the National LGBT Chamber of Commerce (NGLCC), and small and disadvantaged businesses, as certified by Miami-Dade County. See authorizing resolutions here.
If your company is certified by NGLCC as an LGBT-owned business or as a small or disadvantaged business by Miami-Dade County, click on the link below to be added to the City's supplier registry (Vendor Self-Service) and bid system (Bidnet Direct). These are two different systems, and you must register for both.
Click to see acceptable certification and to register: https://www.miamibeachfl.gov/city-hall/procurement/how-to-become-a-vendor/.
https://selfservice.miamibeachfl.gov/vss/Vendors/default.aspx mailto:vendorsupport@miamibeachfl.gov https://www.miamibeachfl.gov/city-hall/procurement/procurement-related-ordinance-and-procedures/ https://www.miamibeachfl.gov/city-hall/procurement/how-to-become-a-vendor/ https://www.miamibeachfl.gov/city-hall/procurement/how-to-become-a-vendor/
SECTION 0200 – MINIMUM QUALIFICATIONS AND REQUIREMENTS
The Minimum Eligibility Requirements for this solicitation are listed in the ITB Bid Summary.
Bidders that fail to comply with minimum requirements shall be deemed non-responsive and shall not have its bid considered.
Rest of page left blank intentionally.
SECTION 0300 – ELECTRONIC BID SUBMITTAL FORMAT
1. ELECTRONIC RESPONSES (ONLY). Bids must be submitted electronically through Bidnet Direct on or before the date and time indicated. Hard copy proposals or proposals received through email or facsimile are not acceptable and will be rejected.
A bidder may submit a modified bid to replace all or any portion of a previously submitted bid until the deadline for bid submittals. The City will only consider the latest version of the bid.
Electronic bid submissions may require the uploading of attachments. All documents should be attached as separate files in accordance with the instructions included in Section 4 below. Attachments containing embedded documents or proprietary file extensions are prohibited. It is the Bidder's responsibility to ensure that its bid, including all attachments, is uploaded successfully.
Only bid submittals received and time stamped by Bidnet Direct prior to the bid submittal deadline shall be accepted as submitted in a timely manner. Late bids cannot be submitted and will not be accepted. Bidders are cautioned to allow sufficient time for the submittal of bids and uploading of attachments. Any technical issues must be submitted to Bidnet Direct by contacting (1-800-835-4603, option 2, or support@bidnet.com). The City cannot assist with technical issues regarding submittals and will in no way be responsible for delays caused by any technical or other issue.
It is the sole responsibility of each Bidder to ensure its proposal is successfully submitted in Bidnet Direct prior to the deadline for bid submittals.
2. REQUIRED DOCUMENTS. Failure to submit the following requirements shall result in a determination of non-responsiveness. Non-responsive bids will not be considered.
a. Certification, Questionnaire & Requirements Affidavit (Appendix A, uploaded separately to Bidnet Direct). .
b. Bid Price Form (Appendix B)
c. Bid Bond (Appendix C) If the ITB Summary indicates a bid bond is required, then a fully executed bid bond must be submitted by the deadline for submittal of bids)
d. Schedule of Values (Appendix D) Shall be submitted with the bid or within three (3) days of request from the City.
3. OMITTED INFORMATION. The City reserves the right to request any documentation omitted, with the exception of the required documents set forth in section 2 above, which must be submitted at the time of bid. Bid Submittals received without the Bid Price Form or Bid Bond (if applicable) or with an incomplete Bid Price Form or Bid Bond (if applicable) shall be deemed non-responsive. Bidder must submit any other omitted documentation within three (3) business days upon request from the City, or the bid may be deemed non-responsive. Non-responsive bid packages will receive no further consideration.
4. ELECTRONIC PROPOSAL FORMAT. In order to maintain comparability, facilitate the review process, and assist in the review of bid submittals, it is strongly recommended that bids be organized and tabbed in accordance with the tabs and sections specified below.
The electronic submittal should be tabbed as enumerated below and contain a table of contents with page references. The electronic proposal shall be submitted through the "Documents" tab in Bidnet Direct.
TAB 1: CERTIFICATION, QUESTIONNAIRE & REQUIREMENTS AFFIDAVIT
Submit responses to Certification, Questionnaire & Requirements Affidavit (uploaded separately to Bidnet Direct). Failure to complete and submit the Certification, Questionnaire & Requirements Affidavit (Appendix A, uploaded separately to Bidnet Direct), with the bid and by the deadline for submittals shall render the bid non-responsive. Non-responsive bids will not be considered.
TAB 2: MINIMUM QUALIFICATIONS AND SUBMITTAL REQUIREMENTS
Submit evidence, as specifically requested in the ITB Summary, of compliance with each minimum requirement(s) of this ITB. Bidders that do not comply, or for whom the City cannot verify compliance, shall be deemed non-responsive, and its bid shall not be considered.
TAB 3: BID PRICE FORM & BID BOND
The following documents shall be submitted with the bid by the deadline for submittal of bids:
1. Bid Price Form (Appendix B)
2. Bid Bond Form (see Section 0100, Sub-section 8). If the requirement applies, the bid bond is a required document that shall be submitted on or before the deadline for bids.
FAILURE TO SUBMIT THE MOST RECENTLY COMPLETED
1) BID PRICE FORM AND 2) BID BOND BY THE DEADLINE
FOR SUBMITTAL OF BIDS SHALL RESULT IN THE BID
BEING DEEMED NOT RESPONSIVE AND NOT BEING
FURTHER CONSIDERED.
3. Schedule of Values (Appendix D)
MUST BE SUBMITTED WITH THE BID OR WITHIN THREE
(3) DAYS OF REQUEST BY THE CITY.
TAB 3: OTHER BID FORMS
Submit any other form requested on the ITB Summary, including but not limited to:
1. Local Workforce Participation Program Responsible Contractor Affidavit Form (Appendix E) If ITB Summary indicates a Local Workforce Participation Program is applicable, then this form must be submitted).
2. Trench Safety Certification Form (Appendix F) If the ITB Summary indicates a Trench Safety Act is applicable, then this form must be submitted.
0400 – TERMS AND CONDITIONS
The following documents identify terms and conditions that, together with the ITB, inclusive of all appendixes and addenda, whether included herein or released under separate cover, comprise the solicitation and the Contract and are complementary to one another and together establish the complete terms, conditions, and obligations of the Bidder and, subsequently, the awarded Contractor.
1. FORMAL SOLICITATIONS TERMS & CONDITIONS - GOODS AND SERVICES. By virtue of submitting a bid in response to this ITB, Bidder agrees to be bound by and in compliance with the Solicitation Terms and Conditions (dated 10.27.2022, or as amended until the bid due date), incorporated herein, located at:
https://www.miamibeachfl.gov/city-hall/procurement/standard-terms-and-conditions/
2. GENERAL CONDITIONS FOR CONSTRUCTION CONTRACTS. By virtue of submitting a bid in response to this ITB, Bidder agrees that all work shall be bound by and in compliance with the General Conditions for Construction Contracts (dated 4/13/20,or as amended until the bid due date), incorporated herein, located at:
APPENDIX A
Certification, Questionnaire &
Requirements Affidavits
(UPLOADED AS A SEPARATE ATTACHMENT)
APPENDIX B
Bid Price Form
MUST BE SUBMITTED WITH THE BID. FAILURE TO DO SO WILL
RENDER THE BID NON-RESPONSIVE.
Bid Price Form
FAILURE TO SUBMIT THIS BID PRICE FORM FULLY COMPLETED ON OR BEFORE
THE DUE DATE FOR BIDS SHALL RENDER THE BID NON-RESPONSIVE, AND THE
BIDDER SHALL RECEIVE NO FURTHER CONSIDERATION.
The TOTAL BASE BID amount includes the all-inclusive total cost for the work specified in this bid, consisting of furnishing all materials, labor, equipment, shoring, supervision, mobilization, demobilization, overhead and profit, insurance, permits, and taxes to complete the work to the full intent as shown or indicated in the contract documents. The City will not accept any revision to the total base bid sum, divisions, line item totals, or add alternates after the deadline for receipt of bids.
In the event of a discrepancy between the sum of the items in the schedule of values and the total base bid, the Bidder agrees that the total base bid shall govern. In the absence of a numerical value for any item or division, the City shall interpret it as no bid for the division, which may disqualify the Bidder.
The allowance items that have been delineated below shall be used only at the City's discretion, as needed. In the event that an allowance is not used in its entirety, any remaining balance shall be reflected in a deductive change order.
TOTAL BASE BID
TOTAL BASE BID AMOUNT $
1 Indemnification of City $ 25.00
Permit Allowance $100,000.00
Police Officer Allowance $120,000.00
GRAND TOTAL
(TOTAL BASE BID AMOUNT + INDEMNIFICATION OF CITY + PERMIT ALLOWANCE +
POLICE OFFICER ALLOWANCE) $
1See Section 0100, Sub-section 12.
ADDITIVE ALTERNATE
Selection of additive alternates, if any, will be made pursuant to Section 0100, No. 10 Method of Award.
TOTAL ADDITIVE ALTERNATE BASE BID
TOTAL ADDITIVE ALTERNATE BASE BID AMOUNT $
End of Bid Price Form.
APPENDIX C
BID BOND FORM
Only applicable if checked in the Invitation to Bid Summary
BID BOND
KNOW ALL MEN BY THESE PRESENTS, that we, _________________________ as Principal, hereinafter referred to as Contractor, and __________________________ as Surety, are held and firmly bound unto the City of Miami Beach, Florida, as a municipal corporation of the State of Florida, hereinafter called the City, in the sum of five percent (5%) of the Contractor's Total Base Bid amount of $_________________________ lawful money of the United States of America, for the payment of which well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors, and assigns, jointly and severally by these presents.
WHEREAS, the Contractor contemplates submitting, or has submitted, a Bid to the City for the furnishing of all labor, materials, equipment, machinery, tools, apparatus, means of transportation for, and the performance of the Work covered in the Bid Documents which include the Project Manual, the detailed Plans and Specifications, and any Addenda, for the following solicitation.
Bid No.:____________________________
Title: ______________________________
WHEREAS, it was a condition precedent to the submission of said Bid that a cashier's check, certified check, or Bid Bond in the amount of five percent (5%) of the Total Base Bid be submitted with said Bid as a guarantee that the Contractor would if awarded the Contract, enter into a written Contract with the City for the performance of said Contract, within ten (10) consecutive calendar days after notice having been given of the Award of the Contract.
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH that if the Contractor, within ten (10) consecutive calendar days after notice of such acceptance, enters into a written Contract with the City and furnishes the Performance and Payment Bonds, satisfactory to the City, each in an amount equal to one hundred percent (100%) of the Contract Price, and provides all required Certificates of Insurance, then this obligation shall be void; otherwise the sum herein stated shall be due and payable to the City of Miami Beach and the Surety herein agrees to pay said sum immediately, upon demand of the City, in good and lawful money of the United States of America, as liquidated damages for failure thereof of said Contractor.
BID BOND
IN WITNESS WHEREOF, the said Principal and the said Surety have duly executed this Bond, the ______ day of ______________, 20____.
PRINCIPAL:
(Contractor Name)
Signature
Print Name (Principal)
Title
SURETY:
(Surety Name)
Attorney-in-Fact (Print Name)
Signature
(Power of Attorney must be attached.)
APPENDIX D
SCHEDULE OF VALUES
MUST BE SUBMITTED WITH THE BID OR WITHIN THREE (3)
DAYS OF REQUEST BY THE CITY.
SCHEDULE OF VALUES
Bidders should fully complete the Schedule of Values to include quantities, units of measure, unit pricing, and totals. The cost of any item(s) of work not covered by a specific contract unit price shall be included in the contract unit price to which the item(s) is most applicable. Both unit price and extended total prices must be stated in units of quantity specified in the bidding specifications. Bidder agrees that any unit price listed in the Bid is to be multiplied by the stated quantity requirements in order to arrive at the total.
Item Description Quantity U / M Unit Cost
Total (Quantity_X_Unit_Cost)
For performing preparatory work and operations in mobilizing for beginning the work of the Project, but excluding materials and permit costs, both of which are paid under other payment items, the aggregate sum of:
1 LS $ $
For…