Page 1 of 72ORDER NUMBER:

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

1. REQUISITION NUMBER PAGE 1 OF

2. CONTRACT NO. 3. AWARD/EFFECTIVE

DATE

4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE

DATE

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME b. TELEPHONE NUMBER (No collect calls)

8. OFFER DUE DATE/

LOCAL TIME

9. ISSUED BY

13b. RATING

14. METHOD OF SOLICITATION

CODE

15. DELIVER TO 16. ADMINISTERED BY CODE

18a. PAYMENT WILL BE MADE BY CODE17a. CONTRACTOR/

OFFEROR

CODE

FACILITY

CODE

CODE

TELEPHONE NO.

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN

OFFER

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK

BELOW IS CHECKED

RFQ IFB RFP

SEE ADDENDUM

19.

ITEM NO.

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

(Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED

29. AWARD OF CONTRACT: REF. OFFER

DATED . . YOUR OFFER ON SOLICITATION

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR

30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED

31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA - FAR (48 CFR) 53.212

10. THIS ACQUISITION IS UNRESTRICTED OR

NAICS:

SIZE STANDARD:

13a. THIS CONTRACT IS A

RATED ORDER UNDER

DPAS (15 CFR 700)

SET ASIDE: % FOR:

11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

12. DISCOUNT TERMS

ARE ARE NOT ATTACHED

ARE ARE NOT ATTACHED

27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA

Coll. No.

8 (A)

EDWOSB

WOMEN-OWNED SMALL BUSINESS

(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

HUBZONE SMALL

BUSINESS

SMALL BUSINESS

Page 2 of 72ORDER NUMBER:

Page 3 of 72ORDER NUMBER:

Page 4 of 72ORDER NUMBER:

SECTION B

SUPPLIES OR SERVICES AND PRICES/COSTS

Item No. SUPPLIES OR SERVICE Quantity U/M UNIT PRICE AMOUNT IN US$ Delivery Date

Page 5 of 72ORDER NUMBER:

Page 6 of 72ORDER NUMBER:

Page 7 of 72ORDER NUMBER:

Page 8 of 72ORDER NUMBER:

Page 9 of 72ORDER NUMBER:

Page 10 of 72ORDER NUMBER:

Page 11 of 72ORDER NUMBER:

Page 12 of 72ORDER NUMBER:

Page 13 of 72ORDER NUMBER:

Page 14 of 72ORDER NUMBER:

Page 15 of 72ORDER NUMBER:

Page 16 of 72ORDER NUMBER:

Page 17 of 72ORDER NUMBER:

Page 18 of 72ORDER NUMBER:

Page 19 of 72ORDER NUMBER:

Page 20 of 72ORDER NUMBER:

Page 21 of 72ORDER NUMBER:

Page 22 of 72ORDER NUMBER:

Page 23 of 72ORDER NUMBER:

Page 24 of 72ORDER NUMBER:

Page 25 of 72ORDER NUMBER:

Page 26 of 72ORDER NUMBER:

Page 27 of 72ORDER NUMBER:

Page 28 of 72ORDER NUMBER:

Page 29 of 72ORDER NUMBER:

Page 30 of 72ORDER NUMBER:

Page 31 of 72ORDER NUMBER:

Page 32 of 72ORDER NUMBER:

Page 33 of 72ORDER NUMBER:

Page 34 of 72ORDER NUMBER:

Page 35 of 72ORDER NUMBER:

Page 36 of 72ORDER NUMBER:

Page 37 of 72ORDER NUMBER:

Page 38 of 72ORDER NUMBER:

Page 39 of 72ORDER NUMBER:

Page 40 of 72ORDER NUMBER:

Page 41 of 72ORDER NUMBER:

Page 42 of 72ORDER NUMBER:

Page 43 of 72ORDER NUMBER:

Page 44 of 72ORDER NUMBER:

Page 45 of 72ORDER NUMBER:

Page 46 of 72ORDER NUMBER:

Page 47 of 72ORDER NUMBER:

Page 48 of 72ORDER NUMBER:

Page 49 of 72ORDER NUMBER:

Page 50 of 72ORDER NUMBER:

Page 51 of 72ORDER NUMBER:

Page 52 of 72ORDER NUMBER:

Page 53 of 72ORDER NUMBER:

Page 54 of 72ORDER NUMBER:

Page 55 of 72ORDER NUMBER:

Page 56 of 72ORDER NUMBER:

Page 57 of 72ORDER NUMBER:

Page 58 of 72ORDER NUMBER:

Page 59 of 72ORDER NUMBER:

Page 60 of 72ORDER NUMBER:

Page 61 of 72ORDER NUMBER:

Page 62 of 72ORDER NUMBER:

Page 63 of 72ORDER NUMBER:

Page 64 of 72ORDER NUMBER:

Page 65 of 72ORDER NUMBER:

Page 66 of 72ORDER NUMBER:

Page 67 of 72ORDER NUMBER:

Page 68 of 72ORDER NUMBER:

Page 69 of 72ORDER NUMBER:

Page 70 of 72ORDER NUMBER:

Page 71 of 72ORDER NUMBER:

Page 72 of 72ORDER NUMBER:

Page of

ORDER NUMBER:

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

1. REQUISITION NUMBER

PAGE 1 OF

2. CONTRACT NO.

3. AWARD/EFFECTIVE

DATE

4. ORDER NUMBER

5. SOLICITATION NUMBER

6. SOLICITATION ISSUE

DATE

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

b. TELEPHONE NUMBER (No collect calls)

8. OFFER DUE DATE/

LOCAL TIME

9. ISSUED BY

13b. RATING

14. METHOD OF SOLICITATION

CODE

15. DELIVER TO

16. ADMINISTERED BY

CODE

18a. PAYMENT WILL BE MADE BY

CODE

17a. CONTRACTOR/

OFFEROR

CODE

FACILITY

CODE

CODE

TELEPHONE NO.

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN

OFFER

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK

BELOW IS CHECKED

RFQ

IFB

RFP

SEE ADDENDUM

19.

ITEM NO.

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

(Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA

26. TOTAL AWARD AMOUNT (For Govt. Use Only)

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED

29. AWARD OF CONTRACT: REF. OFFER

DATED . . YOUR OFFER ON SOLICITATION

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR 30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) 31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA - FAR (48 CFR) 53.212

10. THIS ACQUISITION IS

UNRESTRICTED OR

NAICS:

SIZE STANDARD:

13a. THIS CONTRACT IS A

RATED ORDER UNDER

DPAS (15 CFR 700)

SET ASIDE:

% FOR:

11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

12. DISCOUNT TERMS

ARE

ARE NOT ATTACHED

ARE

ARE NOT ATTACHED

27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA 27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA \\iaimain\apps1\Pam_Ward\Logos\Pointer.jpg Right Arrow Pointing to Call the Contact Point for this Solicitation/Contract/Order 8 (A)

EDWOSB

SMALL BUSINESS

WOMEN-OWNED SMALL BUSINESS

(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

SMALL BUSINESS

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

HUBZONE SMALL

BUSINESS

SMALL BUSINESS

SMALL BUSINESS

Page of Printing C:\FORMFLOW\FORMS\SF\S1449_3.FRP BarbMWilliams

SECTION B

SUPPLIES OR SERVICES AND PRICES/COSTS

Item No. SUPPLIES OR SERVICE Quantity U/M UNIT PRICE AMOUNT IN US$ Delivery Date

LV_TITLE: Request for Quotation
CurrentSheet:
SheetCount:
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
20. SCHEDULE OF SUPPLIES/ SERVICES: 1620000056
1. REQUISITION NUMBER:
PAGE 1 OF:
2. CONTRACT NUMBER:
4. ORDER NUMBER:
5. SOLICITATION NUMBER: ISO195-22
31b. NAME OF CONTRACTING OFFICER (Type or print): Jason Morgan
31b. NAME OF CONTRACTING OFFICER (Type or print): Jason Morgan
7. FOR SOLICITATION INFORMATION CALL: b. TELEPHONE NUMBER (No collect calls):
15. DELIVER TO CODE: COCO
15. DELIVER TO CODE: COCO
% For : 100
12. DISCOUNT TERMS:
13b. RATING:
15. DELIVER TO:
17a. CONTRACTOR/ OFFEROR CODE: 321000101
17a. CONTRACTOR/ OFFEROR CODE: 321000101
17a. CONTRACTOR/ OFFEROR CODE: 321000101
17a. CONTRACTOR/ OFFEROR: Misc

400 First Street NW Washington DC 20534

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER:
18a. PAYMENT WILL BE MADE BY:
19. ITEM NUMBER. Line 1 of 8.:
20. SCHEDULE OF SUPPLIES/ SERVICES: See Section B
21. QUANTITY:
22. UNIT:
23. UNIT PRICE:
19. ITEM NUMBER. Line 2 of 8.:
20. SCHEDULE OF SUPPLIES/ SERVICES:
21. QUANTITY:
22. UNIT:
23. UNIT PRICE:
19. ITEM NUMBER. Line 3 of 8.:
21. QUANTITY:
22. UNIT:
23. UNIT PRICE:
19. ITEM NUMBER. Line 4 of 8.:
20. SCHEDULE OF SUPPLIES/ SERVICES: ISO195-22
20. SCHEDULE OF SUPPLIES/ SERVICES: ISO195-22
21. QUANTITY:
22. UNIT:
23. UNIT PRICE:
19. ITEM NUMBER. Line 5 of 8.:
20. SCHEDULE OF SUPPLIES/ SERVICES:
21. QUANTITY:
22. UNIT:
23. UNIT PRICE:
19. ITEM NUMBER. Line 6 of 8.:
21. QUANTITY:
22. UNIT:
23. UNIT PRICE:
19. ITEM NUMBER. Line 7 of 8.:
20. SCHEDULE OF SUPPLIES/ SERVICES:
20. SCHEDULE OF SUPPLIES/ SERVICES:
21. QUANTITY:
22. UNIT:
23. UNIT PRICE:
19. ITEM NUMBER. Line 8 of 8.:
20. SCHEDULE OF SUPPLIES/ SERVICES:
21. QUANTITY:
22. UNIT:
23. UNIT PRICE:
25. ACCOUNTING AND APPROPRIATION DATA:
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED. INITIALS :

29. AWARD OF CONTRACT: REFERENCE OFFER:
DATE. YOUR OFFER ON SOLICITATION

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS.:

30b. NAME OF SIGNER (Type or print):
30b. TITLE OF SIGNER (Type or print):
10. THIS ACQUISITION IS UNRESTRICTED: 0
10. THIS ACQUISITION IS SET ASIDE:: 1
11. DELIVERY FOR FOB DESTINATION UNLESS BLOCK IS MARKED SEE SCHEDULE: X
13a. THIS CONTRACT IS A RATED ORDER UNDER DPAS (15 CFR 700): 0
14. METHOD OF SOLICITATION RFQ: 0
10. THIS ACQUISITION IS NAICS:: 236220
14. METHOD OF SOLICITATION IFB:
14. METHOD OF SOLICITATION RFP: 1
18a. PAYMENT WILL BE MADE BY CODE:
17a. CONTRACTOR/ OFFEROR TELEPHONE NUMBER:
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA: 0
29. AWARD OF CONTRACT :
27a. ARE ATTACHED: 0
29. AWARD OF CONTRACT DATE Enter 2 digit month, 2 digit day and 4 digit year.:
30c. DATE SIGNED. Enter 2 digit month, 2 digit day and 4 digit year.:
6. SOLICITATION ISSUE DATE. Enter 2 digit month, 2 digit day and 4 digit year.: 2022-08-01
8. OFFER DUE DATE Enter 2 digit month, 2 digit day and 4 digit year.: 2022-09-12
8. OFFER LOCAL TIME: 2:00 PM
9. ISSUED BY: UNICOR, FPI CENTRAL OFFICE

400 1ST ST NW

WASHINGTON DC 20534-0004

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK IS CHECKED SEE ADDENDUM:
26. TOTAL AWARD AMOUNT (FOR GOVT. USE ONLY): 0.00
26. TOTAL AWARD AMOUNT (FOR GOVT. USE ONLY): 0.00
26. TOTAL AWARD AMOUNT (FOR GOVT. USE ONLY): 0.00
26. TOTAL AWARD AMOUNT (FOR GOVT. USE ONLY): 0.00
26. TOTAL AWARD AMOUNT (FOR GOVT. USE ONLY): 0.00
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN

OFFER :

31A. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) :
10. THIS ACQUISITION IS SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS: 0
10. THIS ACQUISITION IS HUBZONE SMALL BUSINESS: 0
27a. ARE ATTACHED:
6. SOLICITATION ISSUE DATE. Enter 2 digit month, 2 digit day and 4 digit year.: 2022-08-01
10. THIS ACQUISITION IS SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS: 0
10. THIS ACQUISITION IS HUBZONE SMALL BUSINESS: 1
10. THIS ACQUISITION IS HUBZONE SMALL BUSINESS: 0
10. THIS ACQUISITION IS HUBZONE SMALL BUSINESS: 0
23. UNIT PRICE:
23. UNIT PRICE:
23. UNIT PRICE:
23. UNIT PRICE:
23. UNIT PRICE:
23. UNIT PRICE:
23. UNIT PRICE:
23. UNIT PRICE:
27a. ARE ATTACHED: 0
10. THIS ACQUISITION IS NAICS:: 39.5 M Ann Rece
LV_TERMS_OF_DELIV: Terms:
INCO1:
INCO2:
LV_TARGET_VALUE_CHAR:
TDLINE: Demo:
TDLINE: To include removal and disposal of asbestos containing material,
TDLINE: carpeting, and vinyl tile floor.
TDLINE: Construction:
TDLINE: To include patching and painting walls, install epoxy flooring, adding
TDLINE: a telecommunication room, breakroom and HVAC modifications.
TDLINE: Utilities:
TDLINE: To include disconnecting NMCI, RDT<(>&<)>E, phone, and electrical
TDLINE: connections, adding a new power panel, circuits and power drops, make
TDLINE: power poles connections, install new NMCI / RDT<(>&<)>E drops, new phone
TDLINE: drops
TDLINE: Other Direct Costs:
TDLINE: To include general, administrative, management and incidentals
TDLINE: Section A: Optional Form 308 or SF33
TDLINE: Section B: Supplies or Services Pricing or Cost (Line Items)
TDLINE: 1. The following information pertains to the SF1442, Solicitation,
TDLINE: Offer, and Award:
TDLINE: OMB Clearance Number 1103-0018
TDLINE: Block 8: Emailed, Hand carried or Overnight Express to:
TDLINE: UNICOR, FPI
TDLINE: ATTN: Jason Morgan, UNICOR Contracting Officer<(>,<)>
TDLINE: 3301 LEESTOWN RD<(>,<)>
TDLINE: LEXINGTON, KY 40511
TDLINE: 859-255-6812 EXT 3002
TDLINE: Block 17: LUMP SUM (ENTER THE AMOUNT IN SECTION B.
TDLINE: Block 24, and 27, See Section H.
TDLINE: GENERAL INTENTION: It is the intent of this solicitation to result in a
TDLINE: Firm Fixed Price, Construction Type Contract for a project at the Naval
TDLINE: Service Warfare Center (NSWC Crane) Building 41-1st floor acquisition
TDLINE: office renovation, 2nd and 3rd floor modifications as outlined in the
TDLINE: attached Statement of Work.
TDLINE: The solicitation is 100% set aside for small business. The North
TDLINE: American Industrial Classification System (NAICS) Code applicable to
TDLINE: this project is 236220, commercial and institutional buildings and
TDLINE: related structure construction.
TDLINE: Contract Line Item: Offerors shall enter unit price and amount for
TDLINE: contract line item.
TDLINE: QUESTIONS WILL ONLY be accepted in writing and WILL NOT BE ACCEPTED
TDLINE: AFTER 08/24/2022 at 10:00 AM EST. Responses to questions and site visit
TDLINE: sign in sheet will be posted via www.sam.gov
TDLINE: NO PHONE CALLS PLEASE.
TDLINE: Proposal due date is 09/12/2022,at 2:00 PM EST. Late offers will not be
TDLINE: accepted.
TDLINE: QUESTIONS PERTAINING TO THIS SOLICITATION WILL ONLY BE ADDRESSED IN
TDLINE: WRITING VIA EMAIL TO:jason.Morgan2@USDOJ.GOV
TDLINE: THE NAICS CODE FOR THIS PROJECT IS: 236220 COMMERCIAL AND INSTITUTIONAL
TDLINE: BUILDING CONSTRUCTION
TDLINE: SITE VISIT IS MANDATORY.
TDLINE: Mandatory Site visit has been scheduled for 08/18/2022, at 11:00 AM EST.
TDLINE: Participants will meet at Building 41 on 1st floor Room 127 B, 2nd floor
TDLINE: Rooms 211, 212, 214, 215 and 3rd floor Room 355 for Naval Surface
TDLINE: Warfare Center (NSWC Crane), JXY.
TDLINE: The Contractor shall inspect the site where services are to be
TDLINE: performed. This site review shall satisfy the Contractor's need to
TDLINE: identify all general and local conditions that may affect the cost of
TDLINE: the contract. Failure to inspect the site will not constitute grounds
TDLINE: for claims after contract award. UP to two (2) people per company may
TDLINE: attend.
TDLINE: Mandatory attendance is required for award. Company Name, Name of
TDLINE: attendees, and phone number for attendees must be submitted with
TDLINE: completed SECNAV Form for Base Access to Jason.Morgan2@USDOJ.GOV by
TDLINE: 08/16/2022, at 10:00 AM EST.
TDLINE: NOTE: If you have clearance to access the base - you are still required
TDLINE: to submit your names for the site visit by the deadline of 08/16/2022,
TDLINE: at 10:00 AM EST. in order to attend the site visit.
TDLINE: Physical access to the Government’s facility at Naval Support Activity
TDLINE: (NSA), Crane shall be through the use of the Defense Biometric
TDLINE: Identification System (DBIDS) and associated data processing/information
TDLINE: services for purposes of protecting U.S./Coalition/allied
TDLINE: government/national security areas of responsibility and information.
TDLINE: The contractor shall obtain employee personal identity verification
TDLINE: credentialing (badge) by submitting to the NSA Crane Visitor Center, 103
TDLINE: Furlong St, Crane, IN 47522, form SECNAV 5512/1 (APR 2014), for each
TDLINE: contractor employee. Upon Base Registrar authorization of form 5512/1
TDLINE: the contractor shall submit form NSA Crane 5512/47 DBIDS Badge
TDLINE: Application Record to the NSWC Crane Security Division (812)-854-1213.
TDLINE: The Contractor shall retrieve badges of employed personnel upon
TDLINE: separation. A background check will be conducted as part of the process
TDLINE: and two forms of identification are required. A visitor's pass will be
TDLINE: provided if the background check is cleared. Please allow an
TDLINE: significant time (1-2 hours) for the entire process.
TDLINE: PROJECT MUST BE COMPLETED BY 03/31/2023
TDLINE: THE FOLLOWING INFORMATION IS REQUIRED TO BE COMPLETED BY THE OFFEROR:
TDLINE: VENDOR'S Unique Entity Identifier:___________________________
TDLINE: VENDOR'S POINT OF CONTACT: _____________________________________
TDLINE: VENDOR'S TELEPHONE & FAX NUMBER: ______________________________
TDLINE: VENDOR'S EMAIL ADDRESS: ________________________________________
TDLINE: VENDOR'S BUSINESS SIZE (i.e. SMALL,LARGE,ETC.): ________________
TDLINE: By submission of an offer, the offeror acknowledges the requirement that
TDLINE: a prospective awardee shall be registered in the SAM database (System
TDLINE: Award Management) prior to award, during performance and through final
TDLINE: payment of any contract resulting from this solicitation.
TDLINE: _______________________________________________ signature
TDLINE: ,,,,,,,,,,,,
TDLINE: Demo:
TDLINE: To include removal and disposal of asbestos containing material,
TDLINE: carpeting, and vinyl tile floor.
TDLINE: Construction:
TDLINE: To include patching and painting walls, install epoxy flooring, adding
TDLINE: a telecommunication room, breakroom and HVAC modifications.
TDLINE: Utilities:
TDLINE: To include disconnecting NMCI, RDT<(>&<)>E, phone, and electrical
TDLINE: connections, adding a new power panel, circuits and power drops, make
TDLINE: power poles connections, install new NMCI / RDT<(>&<)>E drops, new phone
TDLINE: drops
TDLINE: Other Direct Costs:
TDLINE: To include general, administrative, management and incidentals
TDLINE: Section C: Description, Spec & SOW
TDLINE: Building 41-1st floor acquisition office renovation, 2nd and 3rd floor
TDLINE: modification
TDLINE: 1.0 SCOPE
TDLINE: The scope of this project is to renovate Building 41 on 1st floor Room
TDLINE: 127 B, 2nd floor Rooms 211, 212, 214, 215 and 3rd floor Room 355 for
TDLINE: Naval Surface Warfare Center (NSWC Crane), JXY. Project consists of
TDLINE: removal and disposal of asbestos containing material, patch and paint
TDLINE: walls, remove and replace carpets and cove base, remove vinyl tile
TDLINE: floor, scarify existing floor, apply new epoxy flooring, disconnect
TDLINE: NMCI, RDT<(>&<)>E, phone and electrical from all existing cubicles, add
TDLINE: new power panel, circuits and power drops, power poles connections,
TDLINE: install new NMCI / RDT<(>&<)>E drops, new phone drops, build new
TDLINE: enclosed telecommunication room, new breakroom and HVAC modifications.
TDLINE: These renovations are required to improve the workspace area and
TDLINE: building conditions.
TDLINE: 2.0,,Acronym Table Refer to Attachment 01 for details
TDLINE: 3.0,,APPLICABLE DOCUMENTS Refer to Attachment 02 for details
TDLINE: The following documents of the revision or issue in effect at the date
TDLINE: of award, form a part of this SOW for reference. In the event of
TDLINE: conflict between the documents referenced herein and the contents of
TDLINE: this SOW, the contents of this SOW shall prevail.
TDLINE: 4.0 PERFORMANCE REQUIREMENTS
TDLINE: The Contractor shall furnish the required material, equipment and labor
TDLINE: to renovate Building 41 on 1st floor Room 127 B, 2nd floor Rooms 211,
TDLINE: 212, 214, 215 and 3rd floor Room 355. The Contractor shall utilize new
TDLINE: material; no postconsumer or recovered material will be authorized for
TDLINE: use. The Contractor shall adhere to all State and Federal building
TDLINE: codes.
TDLINE: 4.1 REQUIREMENTS
TDLINE: The scope of this project will be performed on first, second and third
TDLINE: floors of B-41.
TDLINE: 4.1.1 Room 127B
TDLINE: A) Demolition: There is an approximated 150 linear feet (LF) of existing
TDLINE: cove base and 599 square feet (SF) of existing carpet that shall be
TDLINE: removed and discarded. There is no asbestos containing material
TDLINE: identified.
TDLINE: B) Electrical: The Contractor shall disconnect electrical connections
TDLINE: from the existing cubicles. The Contractor shall provide all electrical
TDLINE: components required to supply power for the new cubicle and printer
TDLINE: station. Power pole (1EA) and 20A, 120V circuit breakers (1EA) shall be
TDLINE: installed.
TDLINE: C) Flooring: New 24”x 24” tufted nylon carpet tiles (approximately 67
TDLINE: SY) shall be installed. Transition strips shall be installed in the
TDLINE: doorways as appropriate (2 EA). Flooring shall be prepared as per
TDLINE: manufacturers requirements prior to the new carpet installation. The
TDLINE: Contractor shall install new 4” vinyl base cove (approximately 150 LF).
TDLINE: The Contractor shall provide carpet tile, cove base and transition
TDLINE: strips samples (neutral colors, blues and greys) for selection after
TDLINE: award. (CDRL A016)
TDLINE: D) Walls: All holes within the walls of Room 127B shall be patched or
TDLINE: filled. The Contractor shall apply 2 coats
TDLINE: (rolled) of new high quality paint (approximately 1,350 SF). New paint
TDLINE: color shall be “Rising Tide”, Valspar, 4008-
TDLINE: 3A. Reference Rooms 356 & 357 for the paint color. Contractor shall
TDLINE: provide paint color samples for selection after
TDLINE: award. (CDRL A016)
TDLINE: E) NMCI/ RDT<(>&<)>E and Phone: All NMCI, RDT<(>&<)>E and phone
TDLINE: connections shall be disconnected from the existing
TDLINE: cubicles, pulled back to the communication room and removed from the
TDLINE: patch panel (approximately 6 EA). The
TDLINE: Contractor shall install new drops for NMCI (1EA), RDT<(>&<)>E Cat 6
TDLINE: (1EA) and Phone (1EA) for the new cubicle.
TDLINE: The new drops shall be installed and punched down back in the
TDLINE: appropriate communication room.
TDLINE: F) See Figure #1 and Figure #4.
TDLINE: 4.1.2 Rooms 211, 212, 214 and 215
TDLINE: A) Demolition: Existing cove base (approximately 1,000 LF) and existing
TDLINE: VCT (approximately 8,404 SF) in Rooms 211, 212 and 215 shall be removed
TDLINE: and discarded. All floors in Rooms 211, 212 and 215 shall be scarified
TDLINE: (approximately 8,404 SF). There is no asbestos containing material
TDLINE: identified.
TDLINE: B) Electrical: The Contractor shall provide all electrical components
TDLINE: required to supply power for the new cubicles, new kiosks, existing
TDLINE: cubicles, existing kiosks, new modular collaboration room, new modular
TDLINE: conference room, new break room area and new person call/meeting office
TDLINE: added to the space in Room 211, Room 212 and Room 215.The Contractor
TDLINE: shall disconnect existing cubicle and kiosk power poles (approximately
TDLINE: 12 EA) and connect new cubicle and kiosk power poles (approximately 14
TDLINE: EA). The Contractor shall install 1-pole, 20A,120V circuit breakers
TDLINE: (approximately 4 EA) , #12 AWG THHN/THWN solid copper conductor
TDLINE: (approximately 500c), ¾” EMT hangers (approximately 15 EA), ¾” EMT SS
TDLINE: insulated connectors (approximately 10 EA), 3/4” EMT SS couplings
TDLINE: (approximately 10 EA), ¾” EMT conduit (approximately 100 LF) and
TDLINE: receptacle 15A duplex w/accessories and branch circuit (approximately 12
TDLINE: EA), A new power feed 120VAC, 20A (1EA) shall be installed to serve a
TDLINE: 120VAC-24VDC transformer to serve the VAV controller in the New Modular
TDLINE: Collaboration Room (Room 212).
TDLINE: C) HVAC: The Contractor shall provide HVAC improvements to exceed
TDLINE: cooling and airflow available in the New Modular Collaboration Room
TDLINE: (Room 212). New VAV box 600 CFM (1 EA) including HW coils, damper,
TDLINE: actuator and thermostat shall be installed to supply the room. VAV box
TDLINE: shall be located above the ceiling on the third floor due to the ceiling
TDLINE: space above the second floor being too tight.
TDLINE: Use round duct, steel, galvanized, 10” diameter, 26 ga from VAV box to
TDLINE: diffuser branches (approximately 25 LF). Fire dampers
TDLINE: shall be used where ducts pass through the floors (2 EA). Duct access
TDLINE: doors are needed to allow fire dampers inspection and maintenance (2
TDLINE: EA). DDC Programming shall be installed with at least four points each
TDLINE: VAV (Space temp, VAV discharge temp, VAV flow rate and HW valve
TDLINE: position). Install controls wiring for the DDC Controller. Install a
TDLINE: temperature sensor (1EA). Install a ball valve with actuator (1EA).
TDLINE: Install a TAB for air (VAV box, supply diffusers, return grilles) (1EA)
TDLINE: and a TAB for water side (HW coils) (1EA). Install HW piping extended
TDLINE: from the existing HW loop (approximately 10 LF). All HW piping shall
TDLINE: have insulation (approximately 10 LF). Diffuser, 4 way cone, 24” x 24”,
TDLINE: shall be installed at ceiling level (1EA). Install round duct, steel,
TDLINE: galvanized, 8” diameter, 26 ga for diffuser branches (approximately 13
TDLINE: LF). Use insulated (1” thick) flexible duct 14” diameter for diffuser
TDLINE: runouts (approximately 10 LF). Return grill, eggcrate, 24” x 24” shall
TDLINE: be installed at ceiling level (1EA). Install round duct, steel,
TDLINE: galvanized, 8” diameter, 26 ga from return grill back to plenum
TDLINE: (approximately 12 LF). All ductwork shall have insulation (approximately
TDLINE: 50 SF).
TDLINE: D) Flooring: The Contractor shall apply new epoxy flooring of Seal Krete
TDLINE: 1000, Rust-Oleum in Rooms 211, 212 and 215 (approximately 8,404 SF).
TDLINE: Flooring shall be prepared as per manufacturers requirements prior to
TDLINE: apply new epoxy flooring. Transition strips shall be installed in the
TDLINE: doorways as appropriate (approximately 10 EA). New 4” vinyl base cove
TDLINE: (approximately 1,000 LF) shall be installed in Rooms 211, 212 and 215.
TDLINE: The Contractor shall provide samples for colors and style of cove base,
TDLINE: new epoxy color and flake broadcast and transition strips (neutral
TDLINE: colors, blues and greys) for selection after award. (CDRL A016)
TDLINE: E) Walls: All holes within the walls of Rooms 211, 212, 214 and 215 and
TDLINE: surrounding hallways shall be patched orfilled (approximately 12,000
TDLINE: SF). The Contractor shall apply 3 coats (rolled) of new high quality
TDLINE: paint in Rooms 211, 212, 214 and 215 and surrounding hallways
TDLINE: (approximately 12,000 SF). New paint color shall be “Rising Tide”<(>,<)>
TDLINE: Valspar, 4008-3A. Reference Rooms 356 & 357 for the paint color.
TDLINE: Contractor shall provide paint color samples for
TDLINE: selection after award. (CDRL A016)
TDLINE: F) NMCI, RDT<(>&<)>E and Phone: All NMCI, RDT<(>&<)>E and Phone
TDLINE: connections shall be disconnected from the existing
TDLINE: cubicles and kiosks, pulled back to the communication room and removed
TDLINE: from the patch panel (approximately 6
TDLINE: EA). The Contractor shall install new drops for NMCI (approximately 83
TDLINE: EA), RDT<(>&<)>E Cat 6 (approximately 83 EA)
TDLINE: and Phone drops (approximately 77 EA) to accommodate 21 net seats in
TDLINE: Rooms 211, 212 and 215. Kiosks will not
TDLINE: require phone drops. The Contractor shall install new NMCI, RDT<(>&<)>E
TDLINE: and Phone wall jacks CAT 6 on the Modular
TDLINE: Collaboration Room (1 EA), Modular Conference Room (1 EA) and Person
TDLINE: Call/Meeting Office (1 EA).
TDLINE: The new drops shall be installed and punched down back in the
TDLINE: appropriate communication room.
TDLINE: G) Breakroom: 13’-2” of new base cabinets with Formica countertop and
TDLINE: cabinet door and drawer pulls shall be
TDLINE: provided and installed. 5’ of new upper wall cabinets shall be provided
TDLINE: and installed to include 1 microwave shelve<(>,<)>
TDLINE: cabinet doors and drawer pulls. Figure #5 and Figure #6. Contractor
TDLINE: shall provide cabinet and Formica countertop
TDLINE: samples for selection after award. (CDRL A016)
TDLINE: H) Cabinetry for Storage Area: 9’-6” of new base cabinets with Formica
TDLINE: countertop and cabinet door and drawer
TDLINE: pulls shall be provided and installed. Figure #5 and Figure #7.
TDLINE: Contractor shall provide cabinet and Formica
TDLINE: countertop samples for selection after award. (CDRL A016)
TDLINE: I) See Figure #2, Figure #5, Figure #6 and Figure #7.
TDLINE: 4.1.3 Room 355
TDLINE: A) Demolition: Existing cove base (approximately 700 LF) and existing
TDLINE: carpet (approximately 12,086 SF) in Room 355 shall be removed and
TDLINE: discarded. The Contractor shall remove and dispose approximated 12,086
TDLINE: SF of asbestos containing material identified on tan carpet mastic with
TDLINE: black mastic under the existing carpet. The carpet shall also be abated
TDLINE: since it is considered contaminated with asbestos floor mastic (floor
TDLINE: mastic is partially adhered to the carpet).
TDLINE: B) Electrical: The Contractor shall provide all electrical components
TDLINE: required to supply power for the new cubicles, new kiosks, existing
TDLINE: cubicles, existing kiosks, new modular collaboration room, new modular
TDLINE: conference room, new break room area and new person call/meeting office
TDLINE: added to the space in Room 355A and to serve HVAC system in the New
TDLINE: Modular Conference Room. The Contractor shall disconnect approximately
TDLINE: 25 EA of existing cubicle power poles and connect approximately 25 EA
TDLINE: new cubicle power poles. The Contractor shall install 1-pole, 20A,120V
TDLINE: circuit breakers (approximately 56 EA), 3-pole, 90A. 480V circuit
TDLINE: breaker (1 EA), 225A main breaker 120/208V 3P-4W panel board (1 EA),
TDLINE: 3-phase 480V pri-120/208V Sec 75 KVA dry-type transformer (1EA), 3-pole,
TDLINE: 480 V, 100A enclosed circuit breaker (1 EA), 2-1/2” EMT conduit (
TDLINE: approximately 150 LF), 2-1/2” EMT SS coupling ( approximately 15 EA), 3”
TDLINE: EMT SS insulated connector (approximately 2 EA), 2-1/2” EMT 90 elbow
TDLINE: (approximately 3 EA), 2-1/2” EMT hanger (approximately 23 EA), #4/0 AWG
TDLINE: THHN/THWN stranded copper conductor (approximately 680 C), ), #3 AWG
TDLINE: THHN/THWN stranded copper conductor (approximately 170 C), ¾” EMT
TDLINE: conduit (approximately 675 LF), ¾” EMT SS coupling (approximately 68
TDLINE: EA), ¾” EMT SS Insulated connector (approximately 80 EA), ¾” EMT hanger
TDLINE: (approximately 75 EA), #12 AWG THHN/THWN solid copper conductor
TDLINE: (approximately 3,000 C) and Receptacle 15A duplex w/accessories and
TDLINE: branch circuits (approximately 25 EA) . The Contractor shall utilize as
TDLINE: many of the existing circuits as possible to feed the new cubicles.
TDLINE: Contractor shall rewire new cubicles and workstations to 3 cubicles per
TDLINE: circuit. New power for cubicle area shall be fed from new power poles
TDLINE: from the suspended ceiling. All new circuits shall be ran above the
TDLINE: suspended ceiling.
TDLINE: A new power feed 120VAC, 20A (1EA) shall be installed to serve a
TDLINE: 120VAC-24VDC transformer to serve the VAV controller in the New Modular
TDLINE: Conference Room.
TDLINE: A 225A main breaker 120/208V 3P-4W panel board and its components to
TDLINE: supply power to the new cubicles and kiosks shall be located in a wall
TDLINE: of the new enclosed telecommunication room face outward into the open
TDLINE: office area. This panel board shall supply power to the mini-split HVAC
TDLINE: unit for the new enclosed telecommunication room. All wiring shall ran
TDLINE: from indoor mini-split HVAC unit to outdoor unit and wiring to outdoor
TDLINE: unit from the new panel board.
TDLINE: C) HVAC: The Contractor shall provide HVAC improvements to exceed
TDLINE: cooling and airflow available in the New Modular Conference Room. VAV
TDLINE: box 1250 CFM (1 EA) including HW coils, damper, actuator and thermostat
TDLINE: shall be installed to supply the room. Use round duct, steel,
TDLINE: galvanized, 16” diameter, 24 ga from VAV box to diffuser branches
TDLINE: (approximately 25 LF). DDC Programming shall be installed with at least
TDLINE: four points each VAV (Space temp, VAV discharge temp, VAV flow rate and
TDLINE: HW valve position). Install controls wiring for the DDC Controller.
TDLINE: Install a temperature sensor (1EA). Install a ball valve with actuator
TDLINE: (1EA). Install a TAB for air (VAV box, supply diffusers, return
TDLINE: grilles) (1EA) and a TAB for water side (HW coils) (1EA). Install HW
TDLINE: piping extended from the existing HW loop (approximately 10 LF). All HW
TDLINE: piping shall have insulation (approximately 10 LF). Diffusers, 4 way
TDLINE: cone, 24” x 24”, shall be installed at ceiling level (2 EA). Install
TDLINE: round duct, steel, galvanized, 12” diameter, 26 ga for diffuser branches
TDLINE: (approximately 13 LF). Use insulated (1” thick) flexible duct 14”
TDLINE: diameter for diffuser runouts (approximately 10 LF). Return grill,
TDLINE: eggcrate, 24” x 24” shall be installed at ceiling level (1EA). Install
TDLINE: round duct, steel, galvanized, 12” diameter, 26 ga from return grill
TDLINE: back to plenum (approximately 12 LF). All ductwork shall have insulation
TDLINE: (approximately 50 SF).
TDLINE: D) Flooring: New 24”x 24” tufted nylon carpet tiles (approximately 1,343
TDLINE: SY) shall be installed. Flooring shall be prepared as per manufacturers
TDLINE: requirements prior to the new carpet installation. Transition strips
TDLINE: shall be installed in the doorways as appropriate (approximately 18 EA).
TDLINE: The Contractor shall install new 4” vinyl cove base (approximately 700
TDLINE: LF). The Contractor shall provide carpet tile, cove base and transition
TDLINE: strips samples (neutral colors, blues and greys) for selection after
TDLINE: award. (CDRL A016)
TDLINE: E) NMCI/ RDT<(>&<)>E and Phone: All NMCI, RDT<(>&<)>E and phone
TDLINE: connections shall be disconnected from the existing cubicles, pulled
TDLINE: back to the communication room and removed from the patch panel
TDLINE: (approximately 127 EA). The Contractor shall install new drops for NMCI
TDLINE: (approximately 146 EA), RDT<(>&<)>E Cat6 (approximately 146 EA) and
TDLINE: Phone (approximately 146 EA) to accommodate 19 net seats in Room 355A.
TDLINE: Kiosks will not require phone and RDT<(>&<)>E drops. The Contractor
TDLINE: shall install new NMCI (approximately 4 EA), RDT<(>&<)>E Cat 6
TDLINE: (approximately 4EA) and Phone (approximately 4 EA) on Conference Rooms
TDLINE: (approximately 4 EA) and Person Call/Meeting Office (1 EA). The new
TDLINE: drops shall be installed and punched down back in the new enclosed
TDLINE: telecommunication room.
TDLINE: F) Enclosed Telecommunication Room:
TDLINE: The Contractor shall construct a new enclosed telecommunication room to
TDLINE: accommodate new network and phone equipment. Figure # 8.The Contractor
TDLINE: shall comply with the Unified Facilities Criteria (UFC) 3- 580-1
TDLINE: TELECOMMUNICATIONS INTERIOR INFRASTRUCTURE PLANNING AND DESIGN
TDLINE: (1-JUNE-2016).
TDLINE: F.1 Architectural
TDLINE: •,,Construct 3-5/8”metal stud walls.
TDLINE: •,,Install 5/8” drywall (Hang, tape, and finish).
TDLINE: •,,Paint all new walls 2 coats eggshell white color.
TDLINE: •,,Install a painted 3’-0” x 7’-0” hollow metal entry door with
TDLINE: appropriate ADA lock and hardware with knock down metal jamb.
TDLINE: •,,Provide and install new 4’ x 6’ x ¾” thick sheet of plywood fire
TDLINE: rated for the new phone equipment.
TDLINE: •,,The telecommunication room shall be enclosed up to the existing
TDLINE: ceiling.
TDLINE: •,,Existing sprinklers shall be aligned on the interior of the
TDLINE: telecommunication room.
TDLINE: •,,Existing lights shall be aligned on the interior of the
TDLINE: telecommunication room.
TDLINE: •,,Existing concrete floor shall be cleaned and finished to accommodate
TDLINE: the new network and phone equipment.
TDLINE: F.2 HVAC
TDLINE: The Contractor shall install an indoor wall mounted ductless mini split
TDLINE: system, 6000 BTU. Refrigerant piping
TDLINE: shall go through roof to outdoor unit. A condensate pump shall be
TDLINE: installed from indoor wall unit to the nearest
TDLINE: drain. An outdoor unit shall be mounted on roof in and wind baffles
TDLINE: around outdoor unit.
TDLINE: F.3 Electrical
TDLINE: The Contractor shall provide all electrical components required to
TDLINE: supply power to three cabinets to be utilized for
TDLINE: NMCI, RDT<(>&<)>E and Phone and to supply power to the mini-split HVAC
TDLINE: unit. The Contractor shall install a standard
TDLINE: quad receptacle outlet in each of the three cabinets. The Contractor
TDLINE: shall install a 100A panel to be utilized only for
TDLINE: the three cabinets. The Contractor shall install a new 225A electrical
TDLINE: panel to supply power to the workstations and
TDLINE: the mini-split HVAC unit as indicated in Section 3.1.3. Room 355. The
TDLINE: Contractor shall install a stand-alone light
TDLINE: switch to isolate the lighting in the telecommunication room versus the
TDLINE: lightings in the rest of Room 355. A 4”
TDLINE: diameter EMT conduit shall be install on top of each of the three
TDLINE: cabinets in the data closet. Each conduit shall
TDLINE: terminate just above the ceiling and shall serve as a path for data
TDLINE: cables to run from the ceiling area down into the
TDLINE: cabinets.
TDLINE: G) See Figure #3 and Figure # 8.
TDLINE: The following requirements listed, but not limited to, are not
TDLINE: applicable to this project:
TDLINE: A),,New FF<(>&<)>E, existing cubes and existing kiosks will be provided
TDLINE: and installed by others and are not part of this Contract.
TDLINE: B),,Existing FF<(>&<)>E will be disassembling by others and are not part
TDLINE: of this Contract.
TDLINE: Additional Notes:
TDLINE: A),,Contractor shall provide a Weekly Production Reports every Monday
TDLINE: (CDRL A006).
TDLINE: B),,Contractor shall clean the worksite at the end of each work day. The
TDLINE: Contractor shall dispose of any scrap material and clean any spills that
TDLINE: may occur.
TDLINE: C),,Contractor shall supply Operation and Maintenance (O<(>&<)>M)
TDLINE: manuals (CDRL A007) and as-built drawings for all equipment installed.
TDLINE: D),,Contractor shall provide training for all systems installed.
TDLINE: E),,Contractor shall provide a complete Bill of Materials (BOM) before
TDLINE: material is purchased for approval by RTA (CDRL A016).
TDLINE: F),,Contractor shall disconnect all NMCI, RDT<(>&<)>E, Phone and
TDLINE: Electrical connections prior existing FF<(>&<)>E being
TDLINE: disassembled.
TDLINE: G),,Contractor shall connect all NMCI, RDT<(>&<)>E, Phone and Electrical
TDLINE: after new FF<(>&<)>E and existing cubes and existing kiosks being
TDLINE: installed.
TDLINE: H),,The Contractor shall provide to the COR all Networking and Phone
TDLINE: testing results after cables being installed. (CDRL A006)
TDLINE: I),,The Contractor shall submit to the COR a Visual Clearance Form,
TDLINE: worker personal air monitoring results, clearance air monitoring
TDLINE: results, and asbestos waste manifest after asbestos abatement
TDLINE: being completed. (CDRL A015)
TDLINE: J),,The Contractor shall provide access to all personnel working on
TDLINE: Rooms 213, 214, and 218 during renovations.
TDLINE: K),,The Contractor shall coordinate with the RTA and Building 41 POC to
TDLINE: get access to Room 214.
TDLINE: L),,The Contractor shall provide 5 percent (%) of total square yards of
TDLINE: each carpet type, pattern, and color for future maintenance. The extra
TDLINE: carpets shall be wrapped and clearly labeled with manufacturer’s name,
TDLINE: brand name, size and project related information including project name
TDLINE: and room number. (CDRL A016).
TDLINE: 4.2 Installation Access
TDLINE: Physical access to the Government’s facility at Naval Support Activity
TDLINE: (NSA), Crane shall be through the use of the Defense Biometric
TDLINE: Identification System (DBIDS) and associated data processing/information
TDLINE: services for purposes of protecting U.S./Coalition/allied
TDLINE: government/national security areas of responsibility and information.
TDLINE: The contractor shall obtain employee personal identity verification
TDLINE: credentialing (badge) by submitting to the NSA Crane Visitor Center, 103
TDLINE: Furlong St, Crane, IN 47522, form SECNAV 5512/1 (APR 2014), for each
TDLINE: contractor employee. Upon Base Registrar authorization of form 5512/1
TDLINE: the contractor shall submit form NSA Crane 5512/47 DBIDS Badge
TDLINE: Application Record to the NSWC Crane Security Division (812)-854-1213.
TDLINE: The Contractor shall retrieve badges of employed personnel upon
TDLINE: separation. Each employee shall affix their badge on their person above
TDLINE: the waste at all times while on the Activity. Badges may only be
TDLINE: removed for safety reasons and must be reaffixed when work is completed.
TDLINE: DBIDS information can be found at the following website:
TDLINE: http://dbids.dmdc.mil/
TDLINE: For Contract employees or subcontractors requiring infrequent access to
TDLINE: the Activity, one day temporary passes MAY be authorized. Requests for
TDLINE: temporary passes shall be submitted to the COR at least 2 working days
TDLINE: prior to the requested base access day.
TDLINE: Be advised that the DBIDS process and temporary pass process both
TDLINE: involve a background check. Persons with a Felony conviction in the
TDLINE: last 10 years will not be issued badges or passes.
TDLINE: Individuals supporting these efforts shall comply with the latest
TDLINE: security regulations applicable to the government facility/installation.
TDLINE: a.,,Depending on the facility/installation regulations, contractor
TDLINE: personnel shall present a proper form of identification(s) and vehicle
TDLINE: proof of insurance or vehicle rental agreement.
TDLINE: b.,,All contractor persons engaged in work while on government property
TDLINE: shall be subject to inspection of their vehicles at any time by the
TDLINE: government, and shall report any known or suspected security
TDLINE: violations to the local host Security Department.
TDLINE: Failure to obtain entry approval will not affect the contract price or
TDLINE: the time of completion.
TDLINE: 4.3 Program Management
TDLINE: The Contractor shall comply with the manufacturer’s recommendations in
TDLINE: installation of all materials and equipment. The Contractor shall be
TDLINE: responsible for field verification of actual conditions prior to
TDLINE: commencement of work. The Contractor shall be responsible for quality
TDLINE: control of all work that is performed via this task order. The
TDLINE: Contractor is responsible for compliance with the U.S. Army Corps of
TDLINE: Engineers Safety and Health Requirements Manual, EM 385-1-1, and shall
TDLINE: maintain a safe working environment at all times during the performance
TDLINE: of this task order. Although this document is intended to identify all
TDLINE: significant features of work to be accomplished in the performance of
TDLINE: this task order, it should not be considered absolutely inclusive of all
TDLINE: minor tasks required for completion of the major work described herein.
TDLINE: 4.3.1 Design and Construction Quality Control (QC) Plan
TDLINE: The Contractor shall establish and maintain a Quality Control program
TDLINE: that is administered by a Design and Construction Quality Control
TDLINE: organization, using Quality Control (Design and Construction) Plans,
TDLINE: (CDRL A004) Commissioning Plans and Reports, meetings, a Coordination
TDLINE: and Mutual Understanding Meeting, three phases of control, submittal
TDLINE: review and approval, testing, completion inspections, and QC
TDLINE: certifications, Inspections in accordance with Section 01 45 35.05 20
TDLINE: SPECIAL INSPECTIONS FOR DESIGN-BUILD or Section 01 45 35.05 10 SPECIAL
TDLINE: INSPECTIONS FOR DESIGN-BID-BUILD and documentation necessary to provide
TDLINE: design, materials, equipment, workmanship, fabrication, construction and
TDLINE: operations which comply with the requirements of this contract. The QC
TDLINE: program must cover on-site and off-site work. (CDRL A006) No
TDLINE: construction work or testing may be performed unless the Contractor’s QC
TDLINE: Manager is on the work site.
TDLINE: 4.3.2 Inspection Benchmarks
TDLINE: A) Periodic quality/ safety checks at Government determined frequency.
TDLINE: B) NMCI, RDT<(>&<)>E, Phone and electrical disconnections (Existing
TDLINE: cubicles and kiosks ready to be disassembled and removed from the
TDLINE: workplace)
TDLINE: C) Pre-carpeting installation (Existing vinyl composite tiles (VCT),
TDLINE: existing carpet removed, asbestos containing material removed and
TDLINE: concrete surface flooring completion prior to install new carpet)
TDLINE: D) Pre-painting (Walls patched or filled prior to apply paint)
TDLINE: E) Inspect floor preparation (prior to epoxy installation)
TDLINE: F) NMCI, RDT<(>&<)>E, Phone and electrical connections (After new FF
TDLINE: <(>&<)>E and existing FF<(>&<)>E being installed)
TDLINE: G) Pre-Final
TDLINE: The Government and QC Manager will perform this inspection to verify
TDLINE: that the facility is complete and ready to be occupied. A Government
TDLINE: "Pre-Final Punch List" will be documented by the QC Manager as a result
TDLINE: of this inspection. The QC Manager will ensure that all items on this
TDLINE: list are corrected prior to notifying the Government that a "Final"
TDLINE: inspection with the Client can be scheduled. Any items noted on the
TDLINE: "Pre-Final" inspection must be corrected in a timely manner and be
TDLINE: accomplished before the contract completion date for the work or any
TDLINE: particular increment thereof, if the project is divided into increments
TDLINE: by separate completion dates.
TDLINE: H) Final (At completion)
TDLINE: Notify the COR at least 5 working days prior to the date a final
TDLINE: acceptance inspection can be held. State within the notice that all
TDLINE: items previously identified on the pre-final punch list will be
TDLINE: corrected and acceptable, along with any other unfinished Contract work,
TDLINE: by the date of the final acceptance inspection. The Contractor must be
TDLINE: represented by the QC Manager, the Project Superintendent, and others
TDLINE: deemed necessary. Attendees for the Government may include the PCO, COR,
TDLINE: Construction Management personnel, and personnel representing the
TDLINE: Client.
TDLINE: 4.4 Safety and Health
TDLINE: 4.4.1 Activity Hazard Analysis (AHA)
TDLINE: Before beginning each activity, task, or Definable Feature of Work
TDLINE: (DFOW) involving a type of work presenting hazards not experienced in
TDLINE: previous project operations, or where a new work crew or subcontractor
TDLINE: is to perform the work, the Contractor(s) performing that work activity
TDLINE: must prepare an AHA. Format the AHA in accordance with EM 385-1-1,
TDLINE: Section 1 or as directed by the KO. Submit the AHA for review within 10
TDLINE: working days after the PAK meeting. (CDRL A002) The Government
TDLINE: reserves the right to require the Contractor to revise and resubmit the
TDLINE: AHA if it fails to effectively identify the work sequences, specific
TDLINE: anticipated hazards, site conditions, equipment, materials, personnel
TDLINE: and the control measures to be implemented.
TDLINE: 4.4.2 Standard Lift Plan (SLP)
TDLINE: Plan lifts to avoid situations where the operator cannot maintain safe
TDLINE: control of the lift. Prepare a written SLP in accordance with EM
TDLINE: 385-1-1, Section 16.A.03, and using Form 16-2 for every lift or series
TDLINE: of lifts (if duty cycle or routine lifts are being performed). Submit

This is the start of the file's text. The full file is on GovTribe.