This document is an Addendum 1 to Contract Documents issued by ABHA|BSA+A, LLC for the Indian River School District's Sussex Central High School Weight Room Equipment project (Contract #IRD25049-EQUIP). The addendum, dated July 24, 2025, provides clarifications and responses to bidder questions submitted by Elitefts regarding equipment specifications. Specifically, the addendum confirms the quantity of 10 for Soft Plyo sets and provides details for a ½" rubber rollout runway flooring measuring 4'-0" wide by 80'-0" long, totaling 320 square feet of flooring.
The addendum does not introduce modifications to drawings or specifications and serves primarily to address potential bidder uncertainties through the attached RFI (Request for Information) Log. The document instructs bidders to acknowledge receipt of the addendum on their bid form, with a warning that failure to do so may result in disqualification. No pricing, funding sources, or additional contract terms are modified in this addendum beyond the clarification of equipment and flooring details for the weight room equipment procurement.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| IRD25049-EQUIP-appA.pdf | ||
| IRD25049-EQUIP-itb.pdf | ||
| IRD25049-EQUIP-appB.xlsx | XLSX spreadsheet | |
| IRD25049-EQUIP-appC.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ABHA | BSA+A, LLC.
1621 North Lincoln Street Wilmington, DE
302.658.6426 fax 658.8431
ADDENDUM to
CONTRACT
DOCUMENTS
Date: JULY 24, 2025
To: All Bidders
From: Maureen Rozanski, ABHA|BSA+A
Copies: All Bidders
William J. Dooley, IRSD
Project Name: Sussex Central High School – Weight Room Equipment
Contract Number: IRD25049-EQUIP
Subject: ADDENDUM 1
NOTICE:
Attention is called to the following item(s), effective as of the date above, which shall be added to, deleted from, or changed in the contract documents dated JULY 16, 2025 and any previously issued addenda, thereby incorporating these items into the contract documents.
Attach this Addendum to the project manual for this project. Work or materials not specifically mentioned herein are to be as described in the main body of the specifications and as shown on the drawings. Bidders shall acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may subject the bidder to disqualification.
The following clarification, changes and/or additions shall by this reference be incorporated into the contract documents as though fully set forth therein.
ADDENDUM 1 PAGE 2
A. GENERAL
Item No.
Item
A-1 Please see RFI Log for bidder questions and responses.
B. BIDDER QUESTIONS & CLARIFICATIONS – REFER TO ATTACHED Q&A LOG
C. MODIFICATIONS TO DRAWINGS
Description:
C-1 N/A
D. MODIFICATIONS TO SPECIFICATIONS
Description:
D-1 N/A
E. ATTACHMENTS
Items Date RFI Log July 24, 2025
END OF ADDENDUM 1
BIDDER RFI LOG
Project Name: Sussex Central High School - Weight Room Equipment Contract #: IRD25049-EQUIP Indian River School District
Submission Format
Date Bidder Question Assignee Addendum # Item # Answer
Email 7/22/25 Elitefts On the attached equipment list. On line 65 (Soft Plyo set), the quantity says 10. Is this correct?
ABHA|BSA+A 1 A Yes.
Email 7/23/25 Elitefts Is there a spec for line 73, Rollout Runway Flooring install ?
ABHA|BSA+A 1 B
Provide a ½” rubber flooring measuring 4’- 0” W x 80’-0”L
Email 7/23/25 Elitefts Total Square footage of the Rollout Runway Flooring install ?
ABHA|BSA+A 1 C Total square footage is 320 SF
ANSWERRFI
| IRSD SCHS - Weight Room Equipment - Addendum #01 |
| Bidder RFI Log - SCHS Weight Room Equipment |
| Bidder RFI Register |