About this file
This is a comprehensive bid document for the Regional Drought Resiliency Project: Intertie-1, issued by the City of Santa Cruz Water Department in collaboration with the Scotts Valley Water District. The project involves constructing approximately 8,000 linear feet of 12-inch diameter bi-directional intertie pipeline and a new pump station to facilitate water supply transfers between the two water districts during wet and dry seasons. The bid is limited to five prequalified contractors: Anderson Pacific Engineering Construction, Monterey Peninsula Engineering, Mountain Cascade, Pacific Underground Construction, and Specialty Construction Inc. Sealed bids will be received through the City's e-procurement portal until July 9, 2024, at 3:00 PM, with a mandatory pre-bid conference scheduled for June 25, 2024. The project has a contract time of 510 calendar days, with an estimated total bid price range of $6.3 to $7.7 million.
The project will be funded through the Department of Water Resources' Urban and Multibenefit Drought Relief Grant, supplemented by capital improvement budgets from the City of Santa Cruz and Scotts Valley Water District. Bidders are required to comply with local hiring requirements, with a goal of employing qualified individuals who are residents of Santa Cruz County. The project also mandates compliance with prevailing wage regulations, California Air Resources Board requirements, and Department of Industrial Relations registration. Contractors must be registered with the DIR and maintain appropriate licensing, with the prime contractor required to self-perform at least 50% of the work. Bid security of 10% is required, and the contract will be awarded to the lowest responsive and responsible bidder.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Intertie_1_EXHIBITS_5.30.24.pdf | ||
| Intertie_1_PLANS_5.30.24.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WATER DEPARTMENT
INVITATION FOR BID,
PLANS AND SPECIFICATIONS, AND BIDDING AND CONTRACT REQUIREMENTS
FOR
INTERTIE 1: SANTA CRUZ-SCOTTS VALLEY
CWO #2023-003
SANTA CRUZ CITY COUNCIL
Fred Keeley, Mayor
Renee Golder, Vice Mayor
Sandy Brown
Sonja Brunner
Shebreh Kalantari-Johnson
Scott Newsome
Martine Watkins
Matt Huffaker, City Manager
Bonnie Bush, City Clerk Administrator
Anthony P. Condotti, City Attorney
Heidi Luckenbach, Water Department Director
Bids Opening July 9th, 2024, 3:00PM
Submit Bids to: https://procurement.opengov.com/portal/santacruzca
Closing time to receive bids will be according to the OpenGov portal time clock
Isidro Rivera, RCE No. C72965, Exp. 12/31/2024 Deputy Water Director/Engineering Manager
Exp. 12/31/2024 https://procurement.opengov.com/portal/santacruzca
Regional Drought Resiliency Project – Intertie 00 01 07 - 2 Seals and Signatures
James Bowland, PE, Kennedy Jenks Civil License No. C66400 License Expiration Date: 6/30/24
The seal and signature to the left applies to the following Specifications divisions and sections of this Bidding Document:
Division 02
02 40 00 Division 31
31 00 00 31 10 00 Division 32
32 12 16 Division 33
33 14 00 33 46 10
Kevin Castillo, PE, Kennedy Jenks Civil License No. C95673 License Expiration Date: 3/31/24
The seal and signature to the left applies to the following Specifications divisions and sections of this Bidding Document:
Division 03
03 10 00
03 15 00
03 20 00
03 30 00
03 30 50
03 30 60
03 33 00
03 35 00
03 60 00
03 93 50 Division 04
04 22 00 Division 05
05 09 00 05 50 00 Division 06
06 10 00 06 17 80
Division 33
33 05 63
Brittany A. Mahoney, AIA, Kennedy Jenks Architect License No. C39288 License Expiration Date: 2/28/25
The seal and signature to the left applies to the following Specifications divisions and sections of this Bidding Document:
Division 07
07 10 00
07 21 00
07 32 16
07 62 00
07 72 00
07 92 00 Division 08
08 11 13
08 71 00
08 91 00
Division 09
09 91 99 09 96 23 Division 10
10 00 00 10 40 00
Regional Drought Resiliency Project – Intertie 00 01 07 - 3 Seals and Signatures
Donald L. Ervin, PE, CDT, Kennedy/Jenks Civil License No. C50633 License Expiration Date: 9/30/25
The seal and signature to the left applies to the following Specifications divisions and sections of this Bidding Document:
Division 09 09 96 00
Edward J. Pascua, PE, Kennedy Jenks Mechanical License No. M32213 License Expiration Date: 9/30/24
Division 11
11 00 00
Division 23
23 00 00
Division 43
43 23 02
Sandy Schuler, PE, Kennedy Jenks Electrical License No. E15453 License Expiration Date: 6/30/25
Division 26
26 01 26
26 05 00
26 05 10
26 05 19
26 05 20
26 05 26
26 05 33
26 05 43
26 05 73
26 09 00
26 22 00
26 24 13
26 24 16
26 24 19
26 27 26
26 29 23
26 35 33
26 35 54
26 43 00
25 50 00
Regional Drought Resiliency Project – Intertie 00 01 07 - 4 Seals and Signatures
Paul E. Post, PE, Kennedy Jenks Electrical License No. E17119 License Expiration Date: 9/30/25
Division 40
40 50 57
40 60 00
40 63 00
40 63 00A
40 67 00
40 71 00
40 73 00
Engineer’s seal and signature does not apply to the documents that comprise Division 00 – Bidding and Contracting Requirements.
It is a violation of applicable laws and regulations governing professional licensing and registration for any person, unless acting under the direction of the licensed and registered design professional(s) indicated above, to alter in any way the Specifications in this Bidding Document.
END OF SECTION
Regional Drought Resiliency Project – Intertie 00 01 10 - 1 Table of Contents
SECTION 00 01 10
TABLE OF CONTENTS
DIVISION 00 – BIDDING AND CONTRACTING REQUIREMENTS
Section Number Section Title
00 01 07 Seals and Signatures
00 01 10 Table of Contents
00 11 13 Advertisement for Bids
00 21 13 Instructions to Bidders
00 41 13 Bid Form
00 43 13 Bid Security Form
00 43 33 Proposed Suppliers Form
00 43 36 Proposed Subcontractors Form
00 43 38 Good Faith Effort Statement for Local Hire
00 45 19 Non-Collusion Declaration
00 45 46.1 Anti-Lobbying Certification
00 45 46.2 Iran Contracting Certification
00 45 46.6 Good Neighbor Commitment
00 45 46.11 Russian Sanctions Compliance
00 52 13 Agreement
00 54 63 Escrow Agreement in Lieu of Retainage
00 61 13.13 Performance Bond
00 61 13.16 Payment Bond
00 61 19 Maintenance Bond
00 62 91 Division of Apprenticeship Standards Form 140
00 62 92 Request for Dispatch of an Apprentice
00 72 13 General Conditions
00 73 01 Supplementary Conditions
Regional Drought Resiliency Project – Intertie 00 01 10 - 2 Table of Contents
DIVISION 01 – GENERAL SPECIFICATIONS
Section Number Section Title
01 11 13 Summary of Work
01 14 00 Work Restrictions
01 14 33 Works in Right-of-Way
01 19 00 Structural Design Requirements
01 22 00 Measurement and Payment
01 24 13 Value Engineering
01 25 00 Structural Design Requirements
01 26 00 Contract Modification Procedures
01 29 73 Schedule of Values
01 29 76 Progress Payment Procedures
01 31 19 Project Meetings
01 32 00 Construction Progress Documentation
01 32 16 Construction Progress Schedule
01 32 26 Construction Progress Reporting
01 32 33 Photographic Documentation
01 32 34 Video Monitoring and Documentation
01 33 00 Submittal Procedures
01 35 23 Owner Safety Requirements
01 35 23.1 COVID 19 Safety Requirements
01 35 43 Environmental Procedures
01 41 26 Stormwater Pollution Prevention Plan and Permit
01 42 00 References
01 43 05 Quality Assurance and Quality Control Requirements
01 45 33 Code-Required Special Inspections and Procedures
01 50 00 Temporary Facilities and Controls
01 55 26 Traffic Control
01 61 00 Common Product Requirements
01 62 00 Product Options
01 65 00 Product Delivery Requirements
01 66 00 Product Storage and Handling Requirements
01 71 23 Field Engineering
01 74 00 Cleaning and Waste Management
01 77 00 Closeout Procedures
01 78 23 Operation and Maintenance Data
01 78 36 Warranties
01 78 39 Project Record Documents
01 78 43 Spare Parts
01 79 00 Demonstration and Training
Regional Drought Resiliency Project – Intertie 00 01 10 - 3 Table of Contents
DIVISON 02-49 – TECHNICAL SPECIFICATIONS
Section Number Section Title
Division 2 – Existing Conditions
02 40 00 Demolition
Division 3 – Concrete
03 10 00 Concrete Formwork and Formwork Accessories
03 15 00 Concrete Joints and Accessories
03 20 00 Concrete Reinforcement and Reinforcement Supports
03 30 00 Concrete Mixtures, Handling, Placing, and Constructing
03 30 50 Hot Weather Concreting
03 30 60 Cold Weather Concreting
03 33 00 Concrete Curing and Protection
03 35 00 Concrete Finishing
03 60 00 Grouts
03 93 50 Repair of Defective Concrete
Division 4 – Masonry
04 22 00 Concrete Unit Masonry
Division 5 – Metals
05 09 00 Concrete and Masonry Anchors
05 50 00 Metal Fabrication (Miscellaneous Metal)
Division 6 – Woods, Plastics, and Composites
06 10 00 Rough Carpentry
06 17 80 Metal Plate Connected Wood Trusses
Division 7 – Thermal and Moisture Protection
07 10 00 Water Repellent Sealer
07 21 00 Insulation
07 32 16 Cement Tile Shingles
07 62 00 Flashing and Sheet Metal
07 72 00 Roof Accessories
07 92 00 Joint Sealants
Division 8 – Openings
08 11 13 Hollow Metal Work
08 71 00 Finish Hardware
08 91 00 Louvers
Division 9 – Finishes
09 91 00 Painting
09 96 00 High Performance Coatings
09 96 23 Graffiti Resistant Coating
Division 10 – Specialties
10 00 00 Building Specialties
10 40 00 Identifying Devices
Division 11 – Equipment
11 00 00 General Equipment and Mechanical Requirements
Regional Drought Resiliency Project – Intertie 00 01 10 - 4 Table of Contents
Division 23 – Heating, Ventilating, and Air Conditioning Equipment
23 00 00 Heating, Ventilating, and Air Conditioning Equipment
Division 26 – Electrical
26 01 26 Electrical Tests
26 05 00 General Electrical Requirements
26 05 10 Electric Motor Drives
26 05 19 Low Voltage Wire Cables
26 05 20 Signal Cable
26 05 26 Electrical Grounding
26 05 33 Electrical Raceway Systems
26 05 43 Underground Electrical Work
26 05 73 Power System Studies
26 09 00 Control Devices
26 22 00 Dry Type Transformers
26 24 13 Switchboards
26 24 16 Panelboards
26 24 19 Motor Control Center
26 27 26 Wiring Devices
26 29 23 Variable Frequency Drives (VFD)
26 35 33 Harmonic Filters
26 35 54 Uninterruptible Power Supply (UPS) 1.5 KVA and Smaller
26 43 00 Surge Protective Devices
26 50 00 Lighting
Division 31 – Earthwork
31 00 00 Earthwork
31 10 00 Site Preparation
Division 32 – Exterior Improvements
32 12 16 Paving and Surfacing
32 92 19 Seeding
Division 33 – Utilities
33 05 63 Precast Concrete Utility Vaults and Access Hatches
33 14 00 Water System Piping and Accessories
33 46 10 Stormwater Bioretention Facility
Division 40 – Process Interconnections
40 05 57 Electric Valve Actuators
40 60 00 Instrumentation and Controls, General Requirements
40 63 00 Programmable Logic Controller
40 63 00A Process Control Narratives
40 67 00 Panels
40 71 00 Flow Measurement
40 73 00 Pressure Measurement
Division 43 – Process Gas and Liquid Handling, Purification and Storage Equipment
43 23 02 Centrifugal Pumps
Regional Drought Resiliency Project – Intertie 00 01 10 - 5 Table of Contents
PLANS AND DRAWINGS (BOUND SEPARATELY)
Attachment 1 Contract Drawings
EXHIBITS
Exhibit Number Exhibit Title
Exhibit A General Construction Permit
Exhibit B-1 Santa Cruz Water Rights Environmental Impact Report and Intertie 1
Addendum
Exhibit B-2 Applicable Measures from the Mitigation Monitoring and Reporting
Program
Exhibit C Temporary Access Easement – Yates Property
Exhibit D Functional Acceptance Testing Form
Exhibit E City Safety Policies
Exhibit F-1 Pressure Testing
Exhibit F-2 Disinfection Procedure
Exhibit G-2 Division of Apprenticeship Standards (DAS) Form 140
Exhibit G-3 DAS Form 142
Exhibit H Tree Protection Plan
Exhibit I-1 2013 Geotechnical Investigation - Boring Logs
Exhibit I-2 2023 Geotechnical Investigation - Boring Logs
Exhibit J PG&E Trench Package
Exhibit K-1 Draft County Encroachment Permit
Exhibit K-2 Draft Caltrans Encroachment Permit
Exhibit L-1 City Water Meter Policy
Exhibit L-2 SVWD Water Meter Policy
Exhibit X-1 Application for Payment
Exhibit X-2 Santa Cruz Local Hire Residency Compliance Form
Exhibit X-3 Field Order Form
Exhibit X-4 Change Order Form
Exhibit X-5 Certificate of Substantial Completion
Exhibit X-6 Notice of Completion
Exhibit X-7 Non-Disclosure Agreement
Exhibit X-8 System Outage Form
Exhibit Y Good Neighbor Commitment, Section 00 45 46.6 (to be Agreement
Exhibit)
Exhibit Z Contract Price Exhibit, Section 00 41 13 (to be Agreement Exhibit)
Regional Drought Resiliency Project – Intertie 00 01 10 - 6 Table of Contents
This page intentionally left blank.
Regional Drought Resiliency Project – Intertie 00 11 13 - 1 Advertisement for Bids
SECTION 00 11 13
ADVERTISEMENT FOR BIDS
NOTICE IS HEREBY GIVEN that the City of Santa Cruz, California, invites sealed Bids for the following
Project:
Regional Drought Resiliency Project – Intertie 1: Santa Cruz –Scotts Valley CWO # 2023-003
Sealed bids for the construction of the Project will be received through the City’s e‐procurement portal located at https://procurement.opengov.com/portal/santacruzca until Tuesday, July 9th, 2024 at 3:00 PM local time. At that time the Bids received will be publicly opened and read.
Bids will be received for a single prime contract for approximately 8,000 LF of new 12-inch-diameter bi-directional intertie pipeline and pump station between the City and Scotts Valley Water District (SVWD) distribution systems to facilitate transfers of water supply during wet seasons, and from SVWD to the City during dry seasons or drought years. The pipeline will run from the City’s Pasatiempo (Kite Hill) Tanks, along Firehouse Lane to Sims Road, and then along La Madrona Drive to the north to the City of Scotts
Valley where a new pump station would be constructed. This pump station will be a single-story building with an outdoor paved area surrounded by security fencing. The Project will also include installation of appurtenances that are required for pipeline operation, monitoring, and maintenance, including the line valves, air release valves, isolation valves, sample stations, and hydrants.
The Engineer’s estimate anticipates that the total bid price will be $6.3 – $7.7 million and the Contract
Time for the completion of all the Work of the Project is 510 calendar days. The proposed Work is generally described as follows:
1. Installation of approximately 8,000 LF of 12” diameter of conventional, trenched PVC pipeline along or near Firehouse Ln. to Sims Rd. to La Madrona Dr
2. Construction of a pump station.
3. Removal and trimming of trees along the pipeline alignment.
4. Restoration of constructed areas including paving, seeding, and erosion control.
5. Some areas will remain unpaved in the area between Kite Hill Tanks and Sims Rd.
Due to the specialized nature and complexity of the construction, General Contractors proposing to bid this Project have been selected through a formal prequalification process. Only Bids received from
General Contractors who are listed below and attend the mandatory pre-bid meeting, as described below, will be accepted. The General Contractor must self-perform a minimum of 50% of the Project work based on Project cost.
1. Anderson Pacific Engineering Construction, Inc.
2. Monterey Peninsula Engineering
3. Mountain Cascade, Inc.
4. Pacific Underground Construction, Inc.
5. Specialty Construction Inc.
Bidding Documents, as defined in the General Conditions, may be downloaded, without charge, from the designated website (indicated below). Prospective Bidders are urged to register with the designated website as a Bidding Documents holder, even if Bidding Documents are obtained from a plan room or source other than the designated website or City in either electronic or paper format. The designated website will be updated periodically with Addenda, lists of registered holders of the Bidding Documents, reports, and other https://procurement.opengov.com/portal/santacruzca
Regional Drought Resiliency Project – Intertie 00 11 13 - 2 Advertisement for Bids information relevant to submitting a Bid for the Project. All official notifications, Addenda, and other
Bidding Documents will be offered only through the designated website. Neither City, Program Manager, Construction manager, nor Engineer will be responsible for Bidding Documents, including Addenda, if any, obtained from sources other than the designated website or the City. Those downloading the Bidding
Documents from any other source assume responsibility and risk for completeness of those Bidding
Documents.
All Bidders shall verify if the City has issued any Addenda for this Project via the designated website. It is the Bidder’s responsibility to ensure that all requirements of Addenda are inserted in the bid. Bidders are required to register for an account via the City e‐Procurement Portal hosted by Open.Gov to receive written addenda to the solicitation. Once the Bidder has completed registration, they will receive addenda notifications to their email by clicking “Follow” on this project. Ultimately, it is the sole responsibility of each bidder to periodically check the site for any addenda at the designated website below.
The designated website is: https://procurement.opengov.com/portal/santacruzca
Paper Bidding Documents may be examined, by appointment only, at the City of Santa Cruz Water
Department, 212 Locust Street, Suite C, Santa Cruz, CA 95060 (“Issuing Office”). Contact Taylor Kihoi, Senior Professional Engineer, TKihoi@santacruzca.gov to schedule an appointment.
A mandatory pre-bid conference will be held at the time, date, and location indicated in Article 4 of the Instructions to Bidders. All Prospective Bidders must sign in on the City-provided sign-in sheet at this conference to be eligible to bid for the Project. Bids for this Project will not be accepted from
Bidders that did not attend and sign in to the mandatory pre-bid conference.
The Contract will be awarded to the lowest responsible responsive bidder. The City reserves the right to reject any or all Bids, including for any minor irregularities or defects. The City may reject a Bid if the
City determines that any of the bid prices are materially unbalanced to the potential detriment of the City.
Each bid shall be accompanied by one of the following forms of Bidder’s security: cash, certified or cashier’s check drawn upon a responsible bank, or Bid Bond executed by an admitted surety insurer, made payable to the City of Santa Cruz. The Bidder’s security shall be in an amount equal to at least ten percent (10%) of the total bid price, and shall be conditioned to be forfeited to the City in the event that the Bidder, if their bid is accepted, does not execute the Contract for the Project and provide the required bonds, certificates of insurance, and endorsements as required. A bid will not be considered unless one of the approved forms of Bidder’s security is enclosed with it.
Bidders and their proposed subcontractors shall hold such licenses as may be required by the laws of the
State of California for the performance of the Project, as specified in the Contract Documents. Bidders bidding as the Prime Contractor shall possess a valid California Contractor’s General Engineering
License “A” at the time of contract bid and throughout the contract term until Notice of Final Acceptance has been issued. The Contractor will also be required to ensure that all subcontractors working on this
Project are holding valid licenses suitable for their trade throughout the contract term until Notice of Final
Acceptance has been issued. Failure to possess the specified license at the time the bid is submitted shall render the bid non-responsive.
The successful Contractor awarded a contract from this solicitation will be required to obtain and maintain a City of Santa Cruz Business Tax Certificate until completion of the Work. For additional information and licensing requirements, view the City’s Business Licenses and Permits webpage or call the Revenue and Taxation division at 831/420-5070.
Regional Drought Resiliency Project – Intertie 00 11 13 - 3 Advertisement for Bids
The Project will be financed through the Department of Water Resources’ Urban and Multibenefit
Drought Relief Grant, and the City’s and Scotts Valley Water District’s capital improvement budget.
Contractual requirements of the funding-financing entity are set forth in Supplemental Conditions 00 73
01.
The General Contractor and all Subcontractors must make good faith efforts to hire qualified individuals who are residents of Santa Cruz County as required by Santa Cruz Municipal Code (SCMC) Chapter
3.10, and to employ apprentices who are enrolled and participate in a viable apprenticeship program approved by the Division of Apprenticeship Standards.
This Project is subject to compliance monitoring and enforcement by the DIR pursuant to the California
Labor Code section 1771.4. No General Contractor or subcontractor may be listed on a bid proposal for a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5 (with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)).
No contractor or subcontractor may be awarded a contract for public work on a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5.
Pursuant to the provisions of California Labor Code Section 6707, each Bid submitted in response to this
Invitation to Bid shall contain, as a separate bid item, adequate sheeting, shoring, and bracing, or equivalent method, for the protection of life or limb in trenches and open excavation, exceeding five feet, which shall conform to applicable safety orders. Neither this requirement, nor any payment by City for this separate bid item, shall be construed to impose tort liability on City, or its employees or agents, for any injury or damage caused by failure of any excavation or protective equipment or methods.
Progress payments are subject to 5% retention withholding until thirty five (35) calendar days after recording the notice of completion. Pursuant to California Public Contract Code Section 22300, for monies earned by the General Contractor and withheld by the City to ensure the performance of the
Contract. The General Contractor, may, at its option, choose to substitute securities meeting the requirements of California Public Contract Code Section 22300, or have the retained, earned monies deposited in an escrow account at a federal or state chartered bank.
Bidder shall verify compliance with California Air Resources Board (CARB) requirement for certificate of reported compliance regarding in-use off-road diesel-fueled fleets regulation as stated in California
Code of Regulations, Title 13 § 2449 et seq.
For all further requirements regarding Bid submittal, qualifications, procedures, and contract award, refer to the Instructions to Bidders that are included in the Bidding Documents.
Technical questions and requests for information related to this Invitation for Bids should be directed to the City designated website above. All questions shall be in writing and received a minimum of 5 business days prior to the bid opening date.
Regional Drought Resiliency Project – Intertie 00 21 13 - 1 Instructions to Bidders
SECTION 00 21 13
INSTRUCTIONS TO BIDDERS
These Instructions to Bidders establish the basic procedures and requirements for preparing and submitting a Bid, evaluation of Bids and criteria for award of the Contract, and requirements for the signing of the Contract.
TABLE OF ARTICLES
ARTICLE 1— Defined Terms
ARTICLE 2— Bidding Documents
ARTICLE 3— Qualifications of Bidders
ARTICLE 4— Pre-Bid Conference
ARTICLE 5— Site and Other Areas
ARTICLE 6— Bidder’s Representations and Responsibilities
ARTICLE 7— Interpretations and Addenda
ARTICLE 8— Bid Security
ARTICLE 9— Substitutes and “Or-Equals” During Bidding
ARTICLE 10— Subcontractors and Suppliers
ARTICLE 11— Preparation of Bid
ARTICLE 12— Submittal of Bid
ARTICLE 13— Withdrawal of Bids
ARTICLE 14— Bids to remain Subject to Acceptance
ARTICLE 15— Evaluation of Bids and Basis for Award
ARTICLE 16— Contract Bonds and Evidence of Insurance
ARTICLE 17— Notice of Award and Signing of Contract
ARTICLE 18— Security Deposit Option in Lieu of Retention
ARTICLE 1— DEFINED TERMS
1.01 Defined terms, indicated in these Instructions to Bidders with initial capital letters, are as set forth in the General Conditions and Supplementary Conditions, available at the
Designated Website indicated on the Advertisement for Bids. Proper nouns and the titles of documents and statutes are also indicated with initial capital letters. Additional defined terms used in the Bidding Requirements have the meaning set forth below:
A. Designated Website – The website designated by the Issuing Office for obtaining Bidding
Documents, Addenda, and all official notifications and where to register as a holder of the Bidding Documents. The identity of the Designated Website is indicated in the
Advertisement for Bids.
Regional Drought Resiliency Project – Intertie 00 21 13 - 2 Instructions to Bidders
B. Issuing Office—The office from which the Bidding Documents are issued. The identity of the Issuing Office is indicated in the Advertisement for Bids.
ARTICLE 2— BIDDING DOCUMENTS
2.01 Obtaining Bidding Documents
A. The City’s Standard Specifications, together with the Project’s Bidding Documents, may be obtained at the Designated Website or address indicated on the Advertisement for
Bids.
2.02 Obtain and Use Complete Bidding Documents
A. Bidder shall obtain a complete set of the Bidding Requirements and proposed Contract
Documents (together, the Bidding Documents). See the Agreement for a list of the
Contract Documents. It is Bidder’s responsibility to determine that it is using a complete set of documents in the preparation of a Bid. Bidder assumes sole responsibility for errors or misinterpretations resulting from the use of incomplete documents, by Bidder itself or by its prospective Subcontractors and Suppliers.
2.03 Restrictions on Use of Bidding Documents
A. Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding
Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for
Bidding Documents holders to print documents solely for their use, and the use of their prospective Subcontractors and Suppliers, provided the plan holder pays all costs associated with printing or reproduction. Printed documents may not be re-sold under any circumstances.
2.04 Bidding Documents Website
A. City has established a Designated Website as indicated in the Advertisement for Bids.
City requires that Bidder register as a Bidding Documents holder with the Issuing Office at such website, and obtain a complete set of the Bidding Documents from such website.
Bidders may rely that sets of Bidding Documents obtained from the Designated Website are complete, unless an omission is blatant. The Designated Website will be updated with any Addenda, lists of registered holders of the Bidding Documents, reports, and other information relevant to submitting a Bid for the Project. All official notifications, Addenda, and other Bidding Documents will be offered only through the Designated
Website.
2.05 Bidding Documents Obtained from Issuing Office
A. Bidder obtaining Bidding Documents from the Issuing Office shall also register as a
Bidding Documents holder on the Designated Website.
2.06 Plan Rooms
A. Plan rooms (including construction information subscription services, and electronic and virtual plan rooms) may distribute the Bidding Documents or make them available for examination. Those prospective bidders that obtain an electronic (digital) copy of the
Bidding Documents from a plan room are encouraged to register as plan holders from the
Bidding Documents Website or Issuing Office. City is not responsible for omissions in
Bidding Documents or other documents obtained from plan rooms, or for a Bidder’s failure to obtain Addenda from a plan room.
Regional Drought Resiliency Project – Intertie 00 21 13 - 3 Instructions to Bidders
2.07 Electronic Documents
A. When the Bidding Requirements indicate that electronic (digital) copies of the Bidding
Documents are available, such documents will be made available to the Bidders as
Electronic Documents in the manner specified.
1. Bidding Documents will be provided in Adobe PDF (Portable Document Format)
(.pdf) files readable by edition of Adobe Reader or Adobe Acrobat current at the time the Bidding Documents are issued. Other software capable of opening and displaying
.pdf files may also properly display the Bidding Documents issued as Electronic
Documents. It is the intent of the Engineer and City that such Electronic Documents are to be exactly representative of the paper copies of the Bidding Documents.
However, because the City cannot totally control the transmission and receipt of
Electronic Documents nor Bidders’ and the Contractor’s means of reproduction of such documents, the City cannot and do not guarantee that Electronic Documents and reproductions prepared from those versions are identical in every manner to the paper copies.
B. Unless otherwise stated in the Bidding Documents, the Bidder may use and rely upon complete sets of Electronic Documents of the Bidding Documents, described in
Paragraph 2.07.A above, obtained via the City’s Designated Website. However, Bidder assumes all risks associated with differences arising from transmission/receipt of
Electronic Documents versions of Bidding Documents and reproductions prepared from those versions and, further, assumes all risks, costs, and responsibility associated with use of the Electronic Documents versions to derive information that is not explicitly contained in printed paper versions of the documents, and for Bidder’s reliance upon such derived information.
ARTICLE 3— QUALIFICATIONS OF BIDDERS
3.01 Bidder’s Qualification
A. Competency of Bidder:
1. As required by Title 5, Chapter 5.04 of the City of Santa Cruz Municipal Code, the
Contractor and Subcontractors must obtain and maintain a current City of Santa Cruz
Business License for the duration of the Work. Proof of application(s) and payment of Business License(s) shall be required prior to Work beginning.
2. Bidder shall be licensed under the applicable provisions of the Business and
Professions Code of the State of California to do the Work contemplated in the
Project.
3. No General Contractor or subcontractor may be listed on a bid proposal for a public works project unless registered with the Department of Industrial Relations as stated in Paragraph 3.02 of this Article.
B. Bidder shall be skilled and regularly engaged in the general class or type of work called for under the Project.
C. It is the City’s intent to award the Contract to a Bidder that furnishes satisfactory evidence that Bidder has the requisite experience, resources, and ability and that Bidder has sufficient capital and facilities, or can demonstrate to City’s satisfaction that Bidder has prompt access to construction equipment and facilities, to enable Bidder to prosecute the Work in accordance with the Contract Documents (including the Contract Times established therein).
Regional Drought Resiliency Project – Intertie 00 21 13 - 4 Instructions to Bidders
1. Bidder must have been prequalified by the City pursuant to the Request for
Qualifications. The City reserves its right to adjust, suspend, or rescind the prequalification rating previously given based on subsequently learned information.
Further while it is the intent of the prequalification process to assist City in determining Bidder responsibility prior to bid and to aid City in selecting the lowest responsible bidder, neither the fact of prequalification, nor any prequalification rating, will preclude City from a post-bid consideration and determination of whether a Bidder has the quality, fitness, capacity, and experience to satisfactorily perform the
Work, and has demonstrated the requisite trustworthiness.
D. To determine the degree of responsibility to be credited to a Bidder, any relevant evidence will be considered that the Bidder, or personnel guaranteed to be employed in responsible charge of the Work, has satisfactorily performed other projects similar in scope, type of work, and complexity at similar rates of progress required for the Project.
3.02 DIR Registration
A. No prospective Contractor or prospective Subcontractor may be indicated in a submitted
Bid, for public works, unless registered with the California Department of Industrial
Relations (DIR) pursuant to California Labor Code Section 1725.5. A prospective
Contractor and Subcontractor is not qualified to bid on, be listed in the Bid, or enter into any contract for public work in California unless currently registered and qualified to perform public work pursuant to Labor Code Section 1725.5. By submitting its Bid to the
City, Bidder is certifying that Bidder itself is listed by the DIR, and Bidder has verified that all Subcontractors to be employed on the Project, if Bidder is awarded the Contract, are registered with the DIR in compliance with Labor Code Sections 1771.1 and 1725.5, and Contractor shall submit proof of registration to the City with the Bid.
B. Bidder’s or Contractor’s inadvertent error in listing a Subcontractor, whether prospective or under a subcontract with Contractor, who is not registered pursuant to Labor Code
Section 1725.5 in response to the Advertisement for Bids shall not be grounds for filing a bid protest or grounds for considering the Bid nonresponsive, provided that one or more of the following apply: (1) the Subcontractor is registered prior to Bid opening; (2) within twenty-four hours after the Bid opening, the prospective Subcontractor is registered and has paid the penalty registration fee specified in Labor Code Section 1725.5; or (3) the
Subcontractor is replaced by another registered Subcontractor pursuant to Public Contract
Code Section 4107.
3.03 Further Evaluations
A. No requirement in this Article 3 to submit information will prejudice the right of City to seek additional pertinent information regarding Bidder’s qualifications.
ARTICLE 4— PRE-BID CONFERENCE
4.01 Pre-Bid Conference
A. A mandatory pre-bid conference is scheduled for 1:30 PM local time, on Tuesday, June 25th, 2024. The pre-bid conference will be virtual and a meeting link will be provided through the OpenGov e-procurement portal. The purpose of this conference is to give prospective Bidders the opportunity to familiarize themselves with the City’s requirements for bidding. Pose questions to the City, Program Manager, Construction Manager, and Engineer, and review the scope of the Work.
B. All Prospective Bidders must ‘sign in’ on the City-provided sign-in sheet at this conference to be eligible to bid for the Project.
Regional Drought Resiliency Project – Intertie 00 21 13 - 5 Instructions to Bidders
C. Attendees must adhere to all applicable rules and protocols issued by the local and state
Public Health Departments and the Centers for Disease Control and Prevention in response to the COVID-19 pandemic. Failure to comply with such guidelines may result in an attendee being precluded from attending the meeting and/or site tour.
D. Photos and videotaping will be allowed.
E. Personal Protective Equipment Required for Site Visit
1. To visit the Site, each attendee of the pre-bid conference must bring and wear to the site visit the following: (1) sturdy, closed-toed shoes and (2) reflective safety vest for high visibility in traffic areas and (3) face coverings, as required by the applicable public health guidelines. Attendees without the required equipment will not be allowed on the tour.
2. City, Construction Manager, or Engineer will not have extra protective equipment available.
F. An optional tour of the accessible areas of the Work will be conducted by representatives of City and Engineer. Time and date will be arranged during the pre-bid conference.
4.02 Interpretations and Oral Statements at Pre-Bid Conference
A. Information presented at the pre-bid conference does not alter the Contract Documents.
City (via Designated Website) will issue any necessary Addenda to make any changes to the Bidding Documents that result from discussions at the pre-bid conference.
Information presented, and statements made at the pre-bid conference will not be binding or legally effective unless incorporated in an Addendum.
4.03 Non-Attendance of Mandatory Pre-Bid Conference
A. Bids will be accepted only from Bidders who attend the pre-bid conference.
B. Bidders arriving at the pre-bid conference more than 10 minutes after the scheduled start-time will not be admitted to the mandatory pre-bid conference.
C. Bidders must attend the entire pre-bid conference.
ARTICLE 5— SITE AND OTHER AREAS
5.01 Examination of Site
A. Contractor will not be entitled to a change in the Contract Price or Contract Times, nor any associated payment, because of error on Bidder’s part or of Bidder’s negligence or failure to acquaint itself with the existing conditions, limitations, or features of the Site or requirements of the Bidding Documents; or by reason of any estimate, tests, or representations of any officer, employee or agent of the City or the City’s representatives and consultants. Bidder is advised to read and understand the Bidder’s representations in the Bid Form, which are repeated as the Contractor’s representations in the Agreement.
B. Where investigation of subsurface conditions has been made by City regarding design of foundation(s) or other subsurface Work, Bidders should inspect the records of the City as to such investigation, including examination of samples and drill cores, if any. Refer to
Paragraph 5.02 of these Instructions to Bidders and to the Supplementary Conditions for identification of reports and drawings of existing physical and subsurface conditions at the Site. The General Conditions and Supplementary Conditions set forth the extent, if any, to which Bidders and Contractor may rely on such data.
Regional Drought Resiliency Project – Intertie 00 21 13 - 6 Instructions to Bidders
C. Investigations by City or City’s consultants of subsurface conditions are made for the purpose of design, and the City assumes no responsibility whatsoever in regard to the sufficiency of test borings or other information for Bidder’s purposes for pricing or
Contractor’s purposes for means, methods, procedures, and sequences of construction.
City and City’s consultants make no representation that subsurface data available and investigations performed by the City or City’s consultants are adequate for Contractor’s purposes for construction.
D. Making such information available to prospective Bidders is not to be construed in any way as a waiver of the provisions of the first paragraph of this provision.
E. Records of such preliminary investigations as may have been made by the City may be inspected at the City of Santa Cruz Water Department, Engineering Office, 212 Locust
Street, Suite C, Santa Cruz CA 95060, during regular business hours, Mondays through
Fridays (City holidays excluded). or by appointment. Email Taylor Kihoi, PE, Senior
Professional Engineer, TKihoi@santacruzca.gov to schedule.
5.02 Supplemental Information Available to Bidders
A. Subsurface and Physical Conditions; Hazardous Environmental Conditions
1. The supplementary information identifies the following regarding existing conditions at or adjacent to the Site:
a. Those reports of explorations and tests of subsurface conditions at or adjacent to the Site that contain Technical Data.
b. Those drawings known to City of existing physical conditions at or adjacent to the Site, including those drawings depicting existing surface or subsurface structures at or adjacent to the Site (except Underground Facilities), that contain
Technical Data.
c. Reports and drawings known to City relating to Hazardous Environmental
Conditions (if any) that have been identified at or adjacent to the Site.
d. Technical Data contained in such reports and drawings.
2. City will make a copy of the report referenced above available to any Bidder on request. This report is not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the
General Conditions, has been identified and established in the Supplementary
Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.
B. Underground Facilities: Underground Facilities are shown or indicated on the Drawings, pursuant to Paragraph 5.05 of the General Conditions, and not in the drawings referred to in Paragraph 5.02.A of these Instructions to Bidders. Information and data regarding the presence or location of Underground Facilities are not intended to be categorized, identified, or defined as Technical Data.
5.03 Other Site-Related Documents
A. Other reports, drawings, and information (if any) about the Site that do not constitute
Technical Data are Supplementary Information. Such documents are not part of the
Contract Documents. Bidders and Contractor are not entitled to rely on reports, drawings, or information furnished by City, Construction Manager (if applicable), or Engineer (if applicable) that are not Technical Data.
mailto:TKihoi@santacruzca.gov
Regional Drought Resiliency Project – Intertie 00 21 13 - 7 Instructions to Bidders
B. Such information is available at the Issuing Office and may be posted on the Designated
Website.
5.04 Site Visit and Testing by Bidders
A. Bidder is required to visit the Site and conduct a thorough visual examination of the Site and adjacent areas before submitting its bid. During the visit the Bidder must not disturb any ongoing operations at the Site.
B. A visit to the Site will be conducted immediately following the pre-bid conference.
C. Bidders visiting the Site are required to arrange their own transportation to the Site.
D. All access to the Site other than during the scheduled Site visit/tour indicated above, must be coordinated in advance by contacting Water Engineering (831) 420-5210 and scheduled at least 10 business days prior to the bid opening date. Bidder must conduct the required Site visit during normal working hours. Refer to Paragraph 4.01.B of these
Instructions to Bidders regarding requirements for personal protective equipment required for all personnel visiting the Site.
E. Bidder is not required to conduct any subsurface testing, or exhaustive investigations of
Site conditions.
F. On request, and to the extent City has control over the Site, and schedule permitting, the
City will provide Bidder general access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. City will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on City’s authority regarding the Site. Bidder is responsible for establishing access needed to reach specific selected test sites.
G. Bidder must comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by City or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.
H. Bidder must fill all holes and clean up and restore the Site to its former condition upon completion of such pre-Bid explorations, investigations, tests, and studies.
5.05 Site Safety
A. Site visits and work at the Site are governed by the safety requirements as stated in the
General Conditions, Section 00 72 13.
B. Bidder should recognize that the means and methods of construction preceding the onset of the COVID-19 pandemic, and the ways of doing business, have been, at least for the foreseeable future, materially impacted and changed. These impacts and changes concern and relate to social distancing, ability to have commerce perform at the pace it previously performed, how labor can interact, the implementation of increased safety measures, and a myriad of other impacts to construction operations. Heightened and increased measures to protect persons from illness, and the adoption and implementation of many new and increased safety practices, will make the performance of construction work different and more challenging. It is the intent of the City, by including Section 01 35 23.1, Novel
Coronavirus (COVID-19) Safety Requirements, to alert all Bidders for all aspects of this
Project, that they include in their Bids all known and reasonably estimated costs and
Regional Drought Resiliency Project – Intertie 00 21 13 - 8 Instructions to Bidders impacts to the ability to obtain goods and materials required, as well as labor to perform the Work.
5.06 Other Work at the Site
A. Reference is made to Paragraph 1.09, Cooperation with Other Work Forces, in Section
01 11 13 – Summary of Work, for the identification of the general nature of other work of which City is aware (if any) that is to be performed at the Site by City, contractors retained by City, or others (such as utilities and transportation facility owners) and relates to the Work contemplated by these Bidding Documents. If City is party to a written contract for such other work, then on request, City will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential information, if any.
ARTICLE 6— BIDDER’S REPRESENTATIONS AND RESPONSIBILITIES
6.01 Bidder’s Responsibilities and Representations
A. Bidder shall examine carefully the Site and the Bidding Documents. The submission of a
Bid will be conclusive evidence that Bidder has investigated and is fully aware of the conditions and difficulties to be encountered, of the character, quality and quantities of
Work to be performed, and of the requirements of the Bidding Documents as to the nature and location of the Work, the general and local conditions at and adjacent to the
Site, particularly those bearing upon transportation, disposal, handling and storage of material, availability of labor, water, electric power, roads and uncertainties of weather, and environmental and physical conditions at and adjacent to the Site; the conformation and conditions of the ground, the character and quality and quantity of surface and subsurface materials, facilities, and structures, including groundwater, to be encountered;
the character of equipment and facilities needed preliminary to, and during the, prosecution of the Work; and all other matters which can in any way affect the Work or the cost thereof under this Contract. Any failure by the Contractor to acquaint themselves with all available information concerning these conditions will not relieve Bidder from responsibility for estimating properly the difficulty or cost of successfully performing the
Work.
B. Also refer to Bidder’s representations set forth in the Bid Form.
6.02 Bidder Certifications
A. The following certifications shall be included with the Bid:
1. CARB Requirement for Certificate of Reported Compliance (Section 00 45 46.10) required by Cal Code Regs., Title 13 § 2449 et seq.;
2. Anti-Lobbying Certification form (Section 00 45 46.1) required by section 1352, title
31, United States Code;
3. Iran Contracting Act Certification form (Section 00 45 46.2) required by Public
Contract Code section 2200 et seq;
6.03 Other Attachments to the Bid
A. In addition to the certifications listed in Paragraph 6.02 above, other documents shall be submitted with the Bid as stated in Article 2 of the Bid Form, Section 00 41 13.
Regional Drought Resiliency Project – Intertie 00 21 13 - 9 Instructions to Bidders
ARTICLE 7— INTERPRETATIONS AND ADDENDA
7.01 Interpretations
A. If there is any doubt as to the true meaning of any part of the Bidding Documents, or the proposed Contract Documents, or if discrepancies in, or omissions from, the Bidding
Documents are found, Bidder shall submit written request for interpretation or clarification to the contact person indicated in Paragraph 7.02 of these Instructions to
Bidders.
B. Interpretations and clarifications, if any, will be issued in the form of one or more
Addenda. Otherwise, in evaluating the intended Work and preparing its Bid, Bidder shall consider that any discrepancies or conflict in the Bidding Documents shall be governed by the Precedence of Documents provision, Paragraph 6.02 of the Agreement, Section 00
52 13.
7.02 Contact for Interpretations of the Bidding Documents
A. Questions regarding interpretation of the Specifications or Drawings or any other portion of the Bidding Documents or Addenda thereto shall be submitted in writing or by email to Taylor Kihoi, P.E. TKihoi@santacruzca.gov
B. No interpretation of the meaning of the Specifications, Drawings, or other Bidding
Documents will be made orally. Only interpretations made via Addendum will be binding.
7.03 Addenda
A. Addenda may be issued by the Issuing Office prior to the deadline established for the receipt and opening of Bids. Addenda become part of the Bidding Documents. The additions or changes contained in such Addenda shall be considered by Bidders in preparation of the Bid. Addenda will be posted only on the Designated Website. A copy of each Addendum shall be attached to the Bid submitted by the Bidder.
B. Neither City, Issuing Office, nor Engineer is responsible for distributing Addenda to any entity interested in the bidding of the Project unless such entity has registered as a
Bidding Document holder with the Designated Website.
C. To be considered for interpretations or clarifications made via Addendum, Bidder requests for clarifications or interpretations must be received by the person designated in
Paragraph 7.02 hereof not later than five (5) days prior to the deadline for receipt of the
Bids , as indicated in the Advertisement for Bids.
D. Issuing Office will endeavor to post Addenda to the Designated Website by three days prior to the deadline established in the Bidding Documents for receipt of the Bids.
However, City and Issuing Office reserve the right to issue Addenda that, in the sole opinion of the City, do not constitute major changes (except possibly for delays in the deadline for receipt of Bids) closer to the deadline for receipt of Bids.
ARTICLE 8— BID SECURITY
8.01 Required Form and Amount of Bid Security
A. Each Bid shall be submitted accompanied by bid security in the form of one of the following: (1) a certified check, (2) cashier's check or (3) bid bond executed by surety
(surety to comply with the qualifications requirements set forth in Paragraph 6.01 of the
General Conditions).Checks shall be made payable to the City of Santa Cruz and bid bonds shall indicate the City of Santa Cruz as obliged. The bid security must be in an mailto:TKihoi@santacruzca.gov
Regional Drought Resiliency Project – Intertie 00 21 13 - 10 Instructions to Bidders amount of not less than 10 percent of the Bidder’s maximum Bid price, including alternates (if any). A Bid will be rejected if not accompanied by acceptable bid security.
8.02 Default of Successful Bidder
A. The bid security of the apparent Successful Bidder will be retained until City awards the
Agreement to such Bidder, and such Bidder has signed the Agreement, furnished the required bonds, and met the other conditions of the Notice of Award, whereupon the bid security will be released. If the Successful Bidder fails to sign and deliver the Agreement and furnish the required bonds within the time indicated in Paragraph 17.02.C of these
Instructions to Bidders, City may consider Bidder to be in default, annul the Notice of
Award, and the bid security of that Bidder will be forfeited, to the extent of City’s damages (including not less than the difference between: (1) the amount of the Contract as awarded to…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .