Insurance_Requirements_from_Risk_-_INTERANL_USE_ONLY.pdf

PDF 310 KB Posted

Attached to
7th St N, 50th Ave N and Vicinity Storm Drainage Improvements Part 1 (Project No. 19045-110)
Solicitation number
IFB- 25 - 289
Issued by
Pinellas County, Florida

About this file

This document is an email chain between City of St. Petersburg staff regarding insurance requirements for the 7th Street North, 50th Avenue North Storm Drainage Improvements project (Project No. 19045-110). The project is a crucial infrastructure initiative aimed at addressing flooding issues in the southeastern Pinellas County area within the Basin M Watershed. Specifically, the project will improve stormwater conveyance by constructing a new drainage system along 7th Street North and 50th Avenue North that directs drainage north to the 54th Avenue Canal. The estimated construction value is $6,300,000, and the project will be solicited as a Construction Manager at Risk procurement method.

The insurance requirements for the project, as determined by Aleksey Morozov from Risk Management, include standard Commercial General Liability, Commercial Auto Insurance, and Workers Compensation Insurance. Additional specifications note that the project will be performed near a navigable waterway, the City has a consultant involved, and there are no expected pollutants or contaminants. The insurance requirements have been reviewed and confirmed as adequate for the project's scope, with no significant changes needed from the initial requirements established in June. The project team includes David Ojeda (Senior Capital Projects Coordinator), Roger T. Johnson (Engineering Design Manager), and Christy Carlton (Capital Improvements Assistant).

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

From: Aleksey Morozov To: David Ojeda Cc: Roger T. Johnson; Tina M. Dineen Subject: RE: 19045-110 _ 7th Street No, 50th Ave N Storm Drainage Improvements Date: Tuesday, October 22, 2024 2:15:45 PM Attachments: image001.gif

Hello, Based on our conversation I don’t see a reason to change the requirements we outlined back in June.

Unless there is a significant change in scope, cost, or things like cranes are going to be brought in for this upgrade, what we have in there is adequate for a project of this scope.

Thank you, Aleksey Morozov CRM CIC CWC-FL CCA Risk Management Analyst, Human Resources City of St. Petersburg 727-893-7314 / Fax 727-892-5570 aleksey.morozov@stpete.org

From: David Ojeda <David.ojeda@stpete.org> Sent: Tuesday, October 22, 2024 2:02 PM To: Aleksey Morozov <aleksey.morozov@stpete.org> Cc: Roger T. Johnson <Roger.Johnson@stpete.org>; Tina M. Dineen <tina.dineen@stpete.org> Subject: RE:19045-110 _ 7th Street No, 50th Ave N Storm Drainage Improvements

Hey Alek, Hope you've dodged the recent wild weather.

We're kicking things back off with the 7th Street drainage project and I wanted to touch base about the insurance requirements you sent over last time. Everything on our end is the same as before—could you give a quick look to make sure all those details are still good? Let me know if something needs tweaking.

Best, David Ojeda Senior Capital Projects Coordinator Engineering & Capital Improvements City of St. Petersburg Phone: 727-893-7308 David.Ojeda@stpete.org mailto:Aleksey.Morozov@stpete.org mailto:David.ojeda@stpete.org mailto:Roger.Johnson@stpete.org mailto:Tina.Dineen@stpete.org mailto:aleksey.morozov@stpete.org mailto:David.Ojeda@stpete.org

From: Aleksey Morozov <aleksey.morozov@stpete.org> Sent: Friday, June 14, 2024 2:58 PM To: Christy B. Carlton <Christy.Carlton@stpete.org> Cc: Fatima Sohrabi <sfsohrab@stpete.org>; David Ojeda <David.ojeda@stpete.org>; Roger T.

Johnson <Roger.Johnson@stpete.org> Subject: RE: 19045-110 _ 7th Street No, 50th Ave N Storm Drainage Improvements

Aleksey Morozov CRM CIC CWC-FL CCA Risk Management Analyst, Human Resources City of St. Petersburg 727-893-7314 / Fax 727-892-5570 aleksey.morozov@stpete.org

From: Christy B. Carlton <Christy.Carlton@stpete.org> Sent: Friday, June 14, 2024 12:03 PM To: Aleksey Morozov <aleksey.morozov@stpete.org> Cc: Fatima Sohrabi <sfsohrab@stpete.org>; David Ojeda <David.ojeda@stpete.org>; Roger T.

Johnson <Roger.Johnson@stpete.org> Subject: RE: 19045-110 _ 7th Street No, 50th Ave N Storm Drainage Improvements

Good afternoon Alex, Thank you for the information below. This project will be solicited as a Construction Manager at Risk and will need the completed Exhibit B (draft attached). Sorry for any confusion!

Thanks, Christy Carlton Capital Improvements Assistant Engineering and Capital Improvements City of St. Petersburg

(727) 893-7270 christy.carlton@stpete.org

From: Aleksey Morozov <aleksey.morozov@stpete.org> Sent: Thursday, June 13, 2024 12:42 PM To: Roger T. Johnson <Roger.Johnson@stpete.org> Cc: Fatima Sohrabi <sfsohrab@stpete.org>; Christy B. Carlton <Christy.Carlton@stpete.org>; David Ojeda <David.ojeda@stpete.org> Subject: RE: 19045-110 _ 7th Street No, 50th Ave N Storm Drainage Improvements

Engineering & Capital Improvements Department Contract Standards

Type Of Insurance Yes No mailto:aleksey.morozov@stpete.org mailto:Christy.Carlton@stpete.org mailto:sfsohrab@stpete.org mailto:David.ojeda@stpete.org mailto:Roger.Johnson@stpete.org mailto:aleksey.morozov@stpete.org mailto:Christy.Carlton@stpete.org mailto:aleksey.morozov@stpete.org mailto:sfsohrab@stpete.org mailto:David.ojeda@stpete.org mailto:Roger.Johnson@stpete.org mailto:christy.carlton@stpete.org mailto:aleksey.morozov@stpete.org mailto:Roger.Johnson@stpete.org mailto:sfsohrab@stpete.org mailto:Christy.Carlton@stpete.org

Commercial General Liability ☒ ☐ Commercial Auto Insurance ☒ ☐ Workers Compensation Insurance ☒ ☐ US Longshore and Harbor Worker's Act Insurance ☒ ☐ Builders Risk Insurance ☐ ☒ Pollution/Environmental Liability Insurance ☐ ☒ Professional Liability Insurance ☐ ☒

Aleksey Morozov CRM CIC CWC-FL CCA Risk Management Analyst, Human Resources City of St. Petersburg 727-893-7314 / Fax 727-892-5570 aleksey.morozov@stpete.org

From: Roger T. Johnson <Roger.Johnson@stpete.org> Sent: Tuesday, June 11, 2024 1:33 PM To: Aleksey Morozov <aleksey.morozov@stpete.org> Cc: Fatima Sohrabi <sfsohrab@stpete.org>; Christy B. Carlton <Christy.Carlton@stpete.org>; David Ojeda <David.ojeda@stpete.org> Subject: 19045-110 _ 7th Street No, 50th Ave N Storm Drainage Improvements

Good day, We are preparing to proceed with the bidding phase for the above-captioned project. Please provide us with the insurance requirements, based on the project scope detailed below.

The City of St. Petersburg is undertaking a crucial infrastructure project aimed at addressing flooding issues in the southeastern Pinellas County area, within the Basin M Watershed. This project focuses on improving stormwater conveyance along 7th Street North and 50th Avenue North with the construction of a new stormwater drainage system that directs drainage north to the 54th Avenue Canal.

Estimated Construction Value:

$6,300.000.00

Engineer of Record:

City - NO mailto:aleksey.morozov@stpete.org mailto:Roger.Johnson@stpete.org mailto:aleksey.morozov@stpete.org mailto:sfsohrab@stpete.org mailto:Christy.Carlton@stpete.org

City’s Consultant - YES

Are there any expected pollutants or contaminants? NO

Is the work to be performed on or near navigable a waterway? YES

Engineering & Capital Improvements Department Contract Standards Type Of Insurance Yes No

Commercial General Liability (standard) ☒ ☐ Commercial Auto Insurance (standard) ☒ ☐ Workers Compensation Insurance (standard) ☒ ☐ US Longshore and Harbor Worker's Act Insurance ☐ ☐ Builders Risk Insurance ☐ ☐ Pollution/Environmental Liability Insurance ☐ ☐ Professional Liability Insurance ☐ ☐

Thank you, Roger T. Johnson, P.E.

Engineering Design Manager City of St. Petersburg Office.727.892.5380 Mobile.727.922.3981