This document comprises instructions for completing Subcontractor/Subconsultant Schedules 1-4, issued by Palm Beach County, Florida, pursuant to Emergency Ordinance 2025-014 (effective June 3, 2025). The instructions govern how respondents must complete required Office of Economic and Business Opportunity (OEBO) schedules when bidding on solicitations with Small Business Enterprise (SBE) goals and when submitting payment requests following contract award. Prime contractors must submit Schedule 1 with their bid or proposal, detailing company information and identifying all subcontractors and subconsultants, including their SBE certification status and the percentage or dollar amount of work each will perform. Schedule 2 must accompany the bid for each subcontractor or subconsultant listed on Schedule 1, specifying the detailed work to be performed and corresponding dollar amounts or percentages, with separate schedules required for second and third-tier subcontractors. Following contract award, prime contractors must submit Schedule 3 with each payment request, listing subcontractor names, contracted amounts, change orders, amounts drawn, and payment status. Schedule 3(a) applies exclusively to professional services contracts and requires primes to indicate the percentage of work performed with their own workforce and payments made to date for themselves and sub-consultants.
Schedule 4, supplied as a fillable PDF form, documents actual payments made to each subcontractor or subconsultant, with separate schedules required for each subcontractor and each payment request involving disbursements. The prime contractor obtains vendor codes for subcontractors through the OEBO website and is responsible for entering subcontractor information, payment amounts, work order numbers, payment dates, and vendor codes. Subcontractors or subconsultants must verify the accuracy of submitted information through signature and notarization, either in printed or electronically signed format. If a subcontractor indicates that a portion of payment will be disbursed to lower-tier subcontractors, an additional Schedule 2 must be submitted. All schedules require proper execution with signatures and dates from authorized individuals. The prime contractor bears responsibility for ensuring responsive bid submissions and accurate documentation of all subcontracting activity throughout the contract term.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 26-0214-RC - ALUMINUM SIGN BLANKS, PURCHASE AND DELIVERY OF, TERM CONTRACT .pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rev.: 6.17.2025, pursuant to Emergency Ordinance 2025-014, approved on June 3, 2025
INSTRUCTIONS ON COMPLETING
SUBCONTRACTOR/SUBCONSULTANT SCHEDULES 1 – 4*
Respondents must complete and correctly execute the required OEBO Schedules when responding to a solicitation and submitting payment requests after contract award. As long as there is a required API goal, Schedules 1 and 2 must be submitted with all bids or proposals from subcontractors and subconsultants in order to be considered responsive to the solicitation. Following award of the contract, Schedules 3, 3(a), and 4 must be sent along with requests for payment or invoices.
Important Points to Remember
A. Schedule 1 must be completed by the Prime Contractor and submitted with their bid or proposal.
1. All Prime Contractors/Consultants must fully complete Section "A" of this form, regardless of their certification status (Small Business Enterprise (SBE) or Non-SBE).Include the company name, address, contact person, and information, as well as the dollar amount or percentage of work that the prime is responsible for completing.
2. Section “B” of this form must list all Subcontractor(s)/Subconsultant(s) to be utilized on this project. Please check the appropriate box if the Subcontractor(s)/subconsultant(s) is certified as a PBC-OEBO SBE, or if they are Non-SBE.
3. At the very bottom of the Schedule, write down the total bid amount or percentage of work that will be completed by SBE.
4. The Prime or authorized individual must print, sign and date the form.
B. Schedule 2 must be properly executed and submitted with the bid/proposal for all subcontractors/subconsultants listed on Schedule 1.
1. Specify in detail the work to be performed or material supplied, along with the dollar amount or percentage of work for each item and corresponding line item number(s), when available.
2. If there is a portion of the work that will not be performed by the subcontractor/subconsultant, a separate, properly executed Schedule 2 must be submitted for all 2nd and 3rd tier Subcontractors/subconsultants. The original subcontractor/subconsultant must indicate that information in the “red box” located in the middle of the form.
3. All subcontractors/subconsultants must print, sign, and date the form.
C. Schedule 3 is completed by the Prime and submitted with each payment request made to Palm Beach County.
1. In the subcontracting Information section, list the Name(s) of each subcontractor on the project and the total contracted amount for each subcontractor.
2. As the project proceeds, complete each column under the subcontracting Information section accordingly to show, approved change orders, revised contract amounts, amounts drawn this pay period, amounts drawn to date, amounts paid to date and the starting date of the subcontractors.
3. In the Subcontractor Category section, check the appropriate category the represents the type of certification each subcontractor has with Palm Beach County.
4. The Schedule 3 must be signed by the Prime’s designated individual and must include the person's title.
D. Schedule 3(a) is used for professional services contracts only. This Schedule is completed by the Prime and submitted with each payment request made to Palm Beach County.
1. The Prime must complete all of the necessary information, which includes the project name, CSA name and number, contract amounts (original and amended, if applicable), and the Pay Application number.
Rev.: 6.17.2025, pursuant to Emergency Ordinance 2025-014, approved on June 3, 2025
2. The Prime must indicate the percentage of work performed with their own workforce and the amount paid to date.
3. In the “Sub-Consultants” section of the Schedule, the Prime must list the firms’ name and their contract amount. The date when that sub begins their work, the amount paid to date, when applicable, and the percentage of work they have completed by the date of the payment request.
4. The Schedule 3(a) must be signed by the Prime’s designated individual and must include the person's title.
E. Schedule 4 is supplied in a fillable PDF form that allows the Prime to enter the requested information, which is then submitted by the Prime to reflect actual payments made to each subcontractor/subconsultant.
1. The Prime is not to request signature from a Subcontractor/subconsultant unless it has made payment to the Subcontractor/subconsultant.
2. A separate Schedule 4 is required for each Subcontractor/sub consultant.
3. A separate Schedule 4 is required for each contract and payment request in which a disbursement has been made to a subcontractor or sub consultant.
4. A fillable pdf Schedule 4 will be emailed to the prime contractor by the user department. The user department will pre-fill the spaces on the form that pertain to the Department number, project number, and Prime contractor’s vendor code.
5. The Prime will type in the Subcontractor/sub consultant name, payment amount, work order number, if applicable, payment date, and Subcontractor/sub consultant vendor code in the fillable form fields.
Subcontractor/sub consultant vendor codes can be found through the OEBO website at Error!
Hyperlink reference not valid..
6. The Prime will either print the form for the Subcontractor/subconsultant to sign and have notarized, or send the form electronically for digital signature and notarization, if possible, verifying that the information is correct. The Subcontractor/subconsultant must provide information as to whether a portion of the payment received will be disbursed to another Subcontractors/sub consultant. If the Subcontractor/subconsultants indicates that a portion of their payment will be disbursed to 2nd or 3rd tier sub, a separate Schedule 2 must be submitted for the Subcontractor/sub consultant listed.
7. The original completed Schedule 4 is submitted to Palm Beach County with the Prime's payment request documents.
http://www.pbcgov.com/osba/vendordirectory.htm http://www.pbcgov.com/osba/vendordirectory.htm
| INSTRUCTIONS ON COMPLETING |
| SUBCONTRACTOR/SUBCONSULTANT SCHEDULES 1 – 4* |
| Important Points to Remember |
File details come from the government source that posted it. Updated .